Arizona 2023 2023 Regular Session

Arizona House Bill HB2449 Comm Sub / Analysis

Filed 04/05/2023

                    Assigned to TAT & APPROP 	AS PASSED BY COMMITTEE 
 
 
 
 
ARIZONA STATE SENATE 
Fifty-Sixth Legislature, First Regular Session 
 
AMENDED 
FACT SHEET FOR H.B. 2449 
 
appropriation; Pinal East-West Corridor 
Purpose 
Appropriates a total of $369,700,000 from the state General Fund (state GF) in FY 2024 to 
the Arizona Department of Transportation (ADOT), including $9,700,000 to distribute to Pinal 
County for the engineering and design of the West Pinal Parkway East-West Corridor and 
$360,000,000 to widen the Interstate 10 (I-10) between Chandler and Casa Grande. 
Background 
ADOT is responsible for the design and construction of state public transportation systems 
and the maintenance and operation of state highways in Arizona (A.R.S. § 28-332). ADOT may 
contract and do all things necessary to secure the full benefits available to Arizona for 
transportation purposes under federal law. ADOT may cooperate with: 1) federal, state and local 
government agencies; 2) Indian tribes; 3) private and public organizations; and 4) private 
individuals. ADOT may exchange federal monies with local governments in order to receive local 
monies and may include additional federal monies in the exchange to offset the matching costs 
required of local governments (A.R.S. § 28-334).  
H.B. 2449 appropriates a total of $369,700,000 from the state GF in FY 2024 to ADOT, 
including $9,700,000 for the West Pinal Parkway East-West Corridor and $360,000,000 to widen 
the I-10. 
Provisions 
1. Appropriates $9,700,000 from the state GF in FY 2024 to ADOT to distribute to Pinal County 
for the engineering and design of the West Pinal Parkway East-West Corridor. 
2. Appropriates $3,600,000 from the state GF in FY 2024 to ADOT to widen the I-10 between 
Chandler and Casa Grande. 
3. Requires ADOT to use the $360,000,000 appropriation for construction-related activities.  
4. Requires ADOT to draw down federal matching monies for the I-10 project unless the 
acceptance of the federal monies is conditioned on the design and construction of a bicycle 
path or pedestrian walkway as a component of the project. 
5. Exempts the $360,000,000 appropriation from lapsing. 
6. Becomes effective on the general effective date.  FACT SHEET – Amended  
H.B. 2449 
Page 2 
 
 
Amendments Adopted by the Appropriations Committee 
1. Adds a $360,000,000 appropriation to widen the I-10 between Chandler and Casa Grande. 
2. Requires ADOT to:  
a) use the $360,000,000 appropriation for construction-related activities; and  
b) draw down federal matching monies for the I-10 project unless the monies are conditioned 
on the design and construction of a bicycle path or pedestrian walkway. 
3. Exempts the $360,000,000 appropriation from lapsing. 
House Action 	Senate Action 
TI 2/1/23 DP 11-0-0-0 TAT 3/27/23 DP 6-0-1 
APPROP 2/15/23 DP 15-0-0-0 APPROP 4/4/23 DPA 7-3-0 
3
rd
 Read 2/28/23  31-29-0  
Prepared by Senate Research 
April 5, 2023 
KJA/sr