Overview 
Considers the notice for mechanics' liens to be complete if all statutory elements are present. 
History 
Statute defines the preliminary twenty-day notice to mean one or more written notices from 
a claimant that are given before recording a mechanic's lien and that are required by law to 
be given. Every person furnishing labor, professional services, materials, machinery, fixtures 
or tools and otherwise may claim a lien must serve the owner, original contractor, any 
construction lender and the person with whom the claimant contracted for the purchase of 
the services or items with a twenty-day notice as prescribed in statute.  Statute outlines the 
pertinent content of the notice that must be given no later than twenty days after the 
claimant first furnishes the aforementioned services and/or items (A.R.S. § 33-992.01). 
Provisions 
1. States that a notice required by statute for mechanics' liens that contains all statutory 
elements is not defective due to the failure to use bold type or font size at least as large 
as otherwise on the notice document, or both.  (Sec. 1) 
2. Makes a technical change.  (Sec. 1) 