Florida 2025 2025 Regular Session

Florida Senate Bill S0492 Analysis / Analysis

Filed 03/11/2025

                    The Florida Senate 
BILL ANALYSIS AND FISCAL IMPACT STATEMENT 
(This document is based on the provisions contained in the legislation as of the latest date listed below.) 
Prepared By: The Professional Staff of the Committee on Environment and Natural Resources  
 
BILL: SB 492 
INTRODUCER:  Senator McClain 
SUBJECT:  Mitigation Banking 
DATE: March 10, 2025 
 
 ANALYST STAFF DIRECTOR  REFERENCE  	ACTION 
1. Barriero Rogers EN Favorable 
2.     AEG   
3.     FP  
 
I. Summary: 
SB 492 provides a standardized schedule for releasing mitigation credits and removes the 
requirement that the Department of Environmental Protection (DEP) and water management 
districts determine the credit release schedule on a case-by-case basis pursuant to statutorily 
enumerated factors.  The bill provides that credits must be released as follows: 
• 30 percent upon recording a conservation easement and establishing financial assurances (or 
100 percent for preservation-only banks). 
• 30 percent after completing initial construction activities. 
• 20 percent upon meeting interim performance criteria. 
• 20 percent upon meeting final success criteria. 
 
Additionally, the bill allows freshwater wetland creation credits to be released earlier, after initial 
construction success criteria are met.   
 
The bill also allows project applicants to use mitigation credits from outside a mitigation service 
area when an insufficient number or type of credits are available within the impacted area. DEP 
or a water management district must verify the lack of appropriate credits within the regional 
watershed before approving credits outside the service area. The bill provides that the following 
multipliers would apply to credits outside the service area: 
• 1.5 multiplier if credits are from an adjacent regional watershed. 
• An additional 0.5 multiplier for each watershed beyond the adjacent one.  
• An additional 0.75 multiplier for use of out-of-kind mitigation which does not match the 
impacted wetland or surface water type. 
 
The bill also requires mitigation banks to submit annual reports detailing the number and type of 
available credits for sale. DEP and water management districts must compile these reports and 
provide an annual assessment of the state’s mitigation banking system to the Legislature. 
REVISED:   BILL: SB 492   	Page 2 
 
II. Present Situation: 
Environmental Resource Permits (ERP) 
Part IV of chapter 373, F.S., and chapter 62-330 of the Florida Administrative Code regulate the 
statewide ERP program, which governs the construction, alteration, operation, maintenance, 
repair, abandonment, and removal of stormwater management systems, dams, impoundments, 
reservoirs, appurtenant works, and other works such as docks, piers, structures, dredging, and 
filling located in, on, or over wetlands or other surface waters.
1
 ERP applications are processed 
by either the Department of Environmental Protection (DEP) or one of Florida’s five water 
management districts.
2
 
 
Permit applicants must demonstrate that the regulated activity will not be harmful to the water 
resources or will not be inconsistent with the overall objectives of the water management 
district.
3
 Applicants must provide reasonable assurance that state water quality standards will not 
be violated and that the proposed activity is not contrary to the public interest.
4
 If a proposed 
activity significantly degrades or is within an Outstanding Florida Water,
5
 the applicant must 
provide reasonable assurance that the proposed activity will be clearly in the public interest.
6
 In 
determining whether an activity is contrary to the public interest or clearly in the public interest, 
the water management district or DEP must consider and balance the following criteria: 
• Whether the activity will adversely affect the public health, safety, or welfare or the property 
of others; 
• Whether the activity will adversely affect the conservation of fish and wildlife, including 
endangered or threatened species, or their habitats; 
• Whether the activity will adversely affect navigation or the flow of water or cause harmful 
erosion or shoaling; 
• Whether the activity will adversely affect the fishing or recreational values or marine 
productivity in the vicinity of the activity; 
• Whether the activity will be of a temporary or permanent nature; 
• Whether the activity will adversely affect or will enhance significant historical and 
archaeological resources; and 
• The current condition and relative value of functions being performed by areas affected by 
the proposed activity.
7
 
 
If the applicant is unable to otherwise meet this criteria, DEP or the governing board of a water 
management district, in deciding to grant or deny a permit, must consider measures proposed by 
 
1
 Fla. Admin. Code R. 62-330.010(2). 
2
 DEP, Environmental Resource Permitting Coordination, Assistance, Portals, https://floridadep.gov/water/submerged-lands-
environmental-resources-coordination/content/environmental-resource-
permitting#:~:text=The%20Environmental%20Resource%20Permit%20(ERP,alteration%20of%20surface%20water%20flow
s (last visited Mar. 5, 2025). 
3
 Section 373.414(1), F.S. 
4
 Id. 
5
 An Outstanding Florida Water is a water designated worthy of special protection because of its natural attributes. DEP, 
Outstanding Florida Waters, https://floridadep.gov/dear/water-quality-standards/content/outstanding-florida-waters (last 
visited Feb. 7, 2025); see Fla. Admin. Code R. 62-302.700(2) and (9). 
6
 Section 373.414(1), F.S. 
7
 Section 373.414(1)(a), F.S.  BILL: SB 492   	Page 3 
 
or acceptable to the applicant to mitigate adverse effects of the regulated activity.
8
 Such 
measures may include onsite mitigation, offsite mitigation, offsite regional mitigation, and the 
purchase of mitigation credits from mitigation banks.
9
  
 
In deciding whether to grant or deny a permit for an activity that affects surface waters or 
wetlands, DEP or the water management district must consider the cumulative impacts of: 
• The proposed activity;  
• Other projects that already exist, are under construction, or have applied for permits or 
formal wetland or surface water determinations;  
• Activities related to developments of regional impact
10
 which are under review, approved, or 
vested, or other activities regulated under Part IV of chapter 373, F.S., which may reasonably 
be expected to be located within surface waters or wetlands in the same drainage basin based 
upon a local government’s comprehensive plans.
11
  
 
These cumulative impacts must be evaluated within the same drainage basin as the proposed 
activity.
12
  
 
Overview of Mitigation Banking 
Mitigation banking is a practice in which an environmental enhancement and preservation 
project is conducted by a public agency or private entity to provide mitigation for unavoidable 
wetland impacts within a defined mitigation service area.
13
 Mitigation banks are alternative to 
permittee-responsible mitigation.
14
 Permittee-responsible mitigation refers to mitigation 
undertaken by the permittee to provide compensatory mitigation for which the permittee retains 
full responsibility.
15
  
 
In mitigation banking, the bank is the site itself, and the currency sold by the banker to the 
impact permittee is a credit, representing the wetland ecological value equivalent to the complete 
restoration of one acre.
16
 Creation of a mitigation bank in Florida typically requires both a permit 
from DEP or a water management district and federal approval of a mitigation bank instrument 
from several agencies led by the U.S. Army Corps of Engineers (USACE), in a joint state/federal 
interagency review team.
17
 Requirements for mitigation bank permits differ between mitigation 
 
8
 Section 373.414(1)(b), F.S. 
9
 Id. 
10
 “Development of regional impact” means any development that, because of its character, magnitude, or location, would 
have a substantial effect upon the health, safety, or welfare of citizens of more than one county. Section 380.06(1), F.S. 
11
 Section 373.414(8)(a), F.S. 
12
 Id. 
13
 DEP, Mitigation and Mitigation Banking, https://floridadep.gov/water/submerged-lands-environmental-resources-
coordination/content/mitigation-and-mitigation-banking (last visited Feb. 17, 2025). “Mitigation service area” means the 
geographic area within which mitigation credits from a mitigation bank may be used to offset adverse impacts of activities 
regulated under this part. Section 373.403(21), F.S. 
14
 Section 373.4135(1)(b), F.S. 
15
 EPA, Mechanisms for Providing Compensatory Mitigation under CWA Section 404, https://www.epa.gov/cwa-
404/mechanisms-providing-compensatory-mitigation-under-cwa-section-404 (last visited Feb. 17, 2025). 
16
 DEP, Mitigation and Mitigation Banking, https://floridadep.gov/water/submerged-lands-environmental-resources-
coordination/content/mitigation-and-mitigation-banking (last visited Feb. 17, 2025). 
17
 DEP, Mitigation Banking Rule and Procedure Synopsis, https://floridadep.gov/water/submerged-lands-environmental-
resources-coordination/content/mitigation-banking-rule-and (last visited Feb. 17, 2025).  BILL: SB 492   	Page 4 
 
bank instruments issued by USACE and state permits issued by DEP or water management 
districts.  
 
The Uniform Mitigation Assessment Method (UMAM) was established as a way to determine 
the amount of mitigation needed to offset adverse impacts to wetlands and other surface waters 
and to award and deduct mitigation bank credits.
18
 UMAM provides a standardized procedure for 
assessing the ecological functions provided by wetlands and other surface waters, the amount 
that those functions are reduced by a proposed impact, and the amount of mitigation necessary to 
offset that loss.
19
 UMAM evaluates functions through consideration of an ecological 
community’s current condition, hydrologic connection, uniqueness, location, fish and wildlife 
utilization, and mitigation risk.
20
 This standardized methodology is also used to determine the 
degree of improvement in ecological value of proposed mitigation bank activities.
21
 
 
State Mitigation Banking Regulations 
To obtain a mitigation bank permit, the applicant must provide reasonable assurance that the 
mitigation bank will:  
• Improve ecological conditions of the regional watershed;  
• Provide viable and sustainable ecological and hydrological functions for the proposed 
mitigation service area;  
• Be effectively managed in perpetuity;  
• Not destroy areas with high ecological value;  
• Achieve mitigation success; and  
• Be adjacent to lands that will not adversely affect the long-term viability of the mitigation 
bank due to unsuitable land uses or conditions.
22 
 
 
The applicant must also provide reasonable assurances that:  
• Any surface water management system that will be constructed, altered, operated, 
maintained, abandoned, or removed within a mitigation bank will meet ERP requirements 
and related rules;  
• The applicant has sufficient legal or equitable interest in the property to ensure perpetual 
protection and management of the land within a mitigation bank; and  
• The applicant can meet the financial responsibility requirements prescribed for mitigation 
banks.
23 
 
 
 
 
18
 See section 373.414(18), F.S. 
19
 DEP, The Uniform Mitigation Assessment Method (UMAM), https://floridadep.gov/water/submerged-lands-environmental-
resources-coordination/content/uniform-mitigation-assessment (last visited Feb. 17, 2025). 
20
 Id. 
21
 Id. 
22
 Section 373.4136(1), F.S.  
23
 Id.; Fla. Admin. Code R. 62-342.400.  BILL: SB 492   	Page 5 
 
Mitigation Bank Credits 
After evaluating the permit application, the permitting agency awards mitigation credits to a 
proposed mitigation bank or phase of such mitigation bank.
24
 The number of credits awarded is 
based on the degree of improvement in ecological value expected to result from the 
establishment and operation of the mitigation bank as determined using a functional assessment 
methodology.
25
 In determining the degree of improvement in ecological value, specific factors 
must be evaluated, including, among other things, the ecological and hydrological relationship 
between wetlands and uplands in the mitigation bank and the proximity of the mitigation bank to 
areas with regionally significant ecological resources or habitats, and the extent to which the 
mitigation bank provides habitat for fish and wildlife.
26
 
 
After awarding mitigation credits to a mitigation bank, the permitting agency establishes a 
schedule for the release of those credits in the mitigation bank permit.
27
 A mitigation credit that 
has been released may be sold or used to offset adverse impacts from a regulated activity.
28
 A 
portion of the mitigation credits can be released for sale or use prior to meeting all the 
performance criteria specified in the mitigation bank permit.
29
 However, the permitting agency 
will only release the full amount of awarded credits after all success criteria are met.
30
 
 
The permitting agency determines the number of credits and schedule for release based on the 
performance criteria for the mitigation bank and the success criteria for each mitigation 
activity.
31
 The release schedule for a specific mitigation bank or phase thereof is related to the 
actions required to implement the bank, such as site protection, site preparation, earthwork, 
removal of wastes, planting, removal or control of nuisance and exotic species, installation of 
structures, and annual monitoring and management requirements for success. In determining the 
specific release schedule for a bank, the permitting agency must consider, at a minimum, the 
following factors: 
• Whether the mitigation consists solely of preservation or includes other types of mitigation. 
• The length of time anticipated to be required before a determination of success can be 
achieved. 
• The ecological value to be gained from each action required to implement the bank. 
• The financial expenditure required for each action to implement the bank.
32
 
 
However, no credit can be released for freshwater wetland creation until the success criteria 
included in the mitigation bank permit are met.
33
 
 
24
 Section 373.4136(4), F.S., An entity establishing and operating a mitigation bank may apply to modify the mitigation bank 
permit to seek the award of additional mitigation credits if the mitigation bank results in an additional increase in ecological 
value over the value contemplated at the time of the original permit issuance, or the most recent modification thereto 
involving the number of credits awarded. Id. 
25
 Id. 
26
 Section 373.4136(4), F.S. 
27
 Section 373.4136(5), F.S. 
28
 Id. 
29
 Section 373.4136(5)(a), F.S. 
30
 Id. 
31
 Section 373.4136(5)(b), F.S. 
32
 Section 373.4136(5)(b), F.S. 
33
 Section 373.4136(5)(c), F.S.  BILL: SB 492   	Page 6 
 
Mitigation Service Area 
During the permitting of a mitigation bank, the permitting agency (DEP or a water management 
district) determines the mitigation service area, which is the geographic region within which the 
bank could reasonably be expected to offset impacts.
34
 In determining the boundaries of the 
mitigation service area, the permitting agency must consider the characteristics, size, and 
location of the mitigation bank and, at a minimum, the extent to which the mitigation bank: 
• Contributes to a regional integrated ecological network; 
• Will significantly enhance the water quality or restoration of an offsite receiving water body 
that is designated as an Outstanding Florida Water, a Wild and Scenic River, an aquatic 
preserve, a water body designated in a plan approved pursuant to the Surface Water 
Improvement and Management Act, or a nationally designated estuarine preserve; 
• Will provide for the long-term viability of endangered or threatened species or species of 
special concern; 
• Is consistent with the objectives of a regional management plan adopted or endorsed by the 
department or water management districts; and 
• Can reasonably be expected to offset specific types of wetland impacts within a specific 
geographic area. A mitigation bank need not offset all expected impacts within its service 
area.
35
 
 
DEP and water management districts use regional watersheds to guide the establishment of 
mitigation service areas.
36
 A mitigation service area may extend beyond the regional watershed 
in which the bank is located into all or part of other regional watersheds when the mitigation 
bank has the ability to offset adverse impacts outside that regional watershed.
37
 Similarly, a 
mitigation service area may be smaller than the regional watershed in which the mitigation bank 
is located when adverse impacts throughout the regional watershed cannot reasonably be 
expected to be offset by the mitigation bank because of local ecological or hydrological 
conditions.
38
 
 
In general, mitigation credits may only be used to offset adverse impacts in the mitigation service 
area.
39
 However, if certain requirements are met, the following projects may be eligible to use a 
mitigation bank regardless of whether they are located within the mitigation service area: 
• Projects with adverse impacts partially located within the mitigation service area. 
• Linear projects, such as roadways, transmission lines, distribution lines, pipelines, railways, 
or certain seaports. 
• Projects with total adverse impacts of less than one acre in size.
40
 
 
 
34
 DEP, Mitigation Banking Rule and Procedure Synopsis, https://floridadep.gov/water/submerged-lands-environmental-
resources-coordination/content/mitigation-banking-rule-and (last visited Feb. 13, 2025); section 373.4136(6), F.S. 
35
 Id. 
36
 Section 373.4136(6)(b), F.S. Regional watersheds within each water management district are specifically delineated in 
DEP rules. See Fla. Admin. Code R. 62-342.200(9). 
37
 Section 373.4136(6)(b), F.S. 
38
 Id. 
39
 Section 373.4136(6), F.S. 
40
 Section 373.4136(6)(d), F.S.  BILL: SB 492   	Page 7 
 
Federal Mitigation Banking Regulations  
For projects requiring a federal permit, a USACE district engineer determines the mitigation to 
be required in a mitigation bank permit based on what is practicable and capable of 
compensating for the aquatic resource functions that will be lost as a result of the permitted 
activity.
41
 When evaluating options for mitigation, USACE considers the type and location 
options in the following order (commonly referred to as the mitigation preference hierarchy): 
• Mitigation bank credits; 
• In-lieu fee program credits;
42
 
• Permittee-responsible mitigation under a watershed approach;
43
 
• Permittee-responsible mitigation through on-site and in-kind
44
 mitigation; or 
• Permittee-responsible mitigation through off-site and/or out-of-kind
45
 mitigation.
46
 
 
In general, the required mitigation should be located within the same watershed as the impact site 
and where it is most likely to successfully replace lost functions and services, taking into account 
watershed scale features as aquatic habitat diversity, habitat connectivity, relationships to 
hydrologic sources, trends in land use, ecological benefits, and compatibility with adjacent land 
uses.
47
 When compensating for impacts to marine resources, the location of the mitigation site 
should be chosen to replace lost functions and services within the same marine ecological system 
(e.g., reef complex, littoral drift cell).
48
 Compensation for impacts to aquatic resources in coastal 
watersheds should also be located in a coastal watershed where practicable.
49
  
 
Mitigation Bank Credits  
When permitted impacts are located within the service area of an approved mitigation bank, and 
the bank has the appropriate number and resource type of credits available, the permittee’s 
compensatory mitigation requirements may be met by securing those credits from a mitigation 
bank.
50
 An approved instrument (including an approved mitigation plan and appropriate real 
estate and financial assurances) must be in place before credits can be used to compensate for 
 
41
 33 C.F.R. 332.3(a)(1). 
42
 An in-lieu fee program is a program involving the restoration, establishment, enhancement, and/or preservation of aquatic 
resources through funds paid to a governmental or non-profit natural resources management entity to satisfy compensatory 
mitigation requirements for DA permits. Similar to a mitigation bank, an in-lieu fee program sells compensatory mitigation 
credits to permittees whose obligation to provide compensatory mitigation is then transferred to the in-lieu program sponsor. 
However, the rules governing the operation and use of in-lieu fee programs are somewhat different from the rules governing 
operation and use of mitigation banks. 33 C.F.R. 332.2. 
43
 Permittee-responsible mitigation means an aquatic resource restoration, establishment, enhancement, and/or preservation 
activity undertaken by the permittee (or an authorized agent or contractor) to provide compensatory mitigation for which the 
permittee retains full responsibility. 33 C.F.R. 332.2. 
44
 In-kind means a resource of a similar structural and functional type to the impacted resource. 33 C.F.R. 332.2. 
45
 Out-of-kind means a resource of a different structural and functional type from the impacted resource. 33 C.F.R. 332.2. 
46
 See 33 C.F.R. 332.3(b). 
47
 33 C.F.R. 332.3(b)(1). 
48
 Id. 
49
 Id. 
50
 33 C.F.R. 332.3(b)(1).  BILL: SB 492   	Page 8 
 
authorized impacts.
51
 Mitigation bank credits are not released until specific milestones associated 
with the mitigation bank site’s protection and development are achieved.
52
 
 
If USACE determines that mitigation is necessary to offset unavoidable impacts to aquatic 
resources, the amount of required mitigation must be, to the extent practicable, sufficient to 
replace lost aquatic resource functions.
53
 USACE requires a mitigation ratio greater than one-to-
one where necessary to account for (1) the distance between the affected aquatic resource and the 
compensation site, (2) the method of mitigation (e.g., preservation), (3) the likelihood of success, 
(4) differences between the functions lost at the impact site and the functions expected to be 
produced by the mitigation project, (5) temporal losses of aquatic resource functions, and/or (5) 
the difficulty of restoring or establishing the desired aquatic resource type and functions.
54
  
 
Mitigation Service Area 
Under federal law, the mitigation service area is the watershed, ecoregion,
55
 physiographic 
province, or other geographic area within which the mitigation bank is authorized to provide 
compensatory mitigation required by USACE permits.
56
 The service area must be appropriately 
sized to ensure that the aquatic resources provided will effectively compensate for adverse 
environmental impacts across the entire service area.
57
 For example, in urban areas, a U.S. 
Geological Survey 8-digit hydrologic unit code (HUC)
58
 watershed or a smaller watershed may 
be an appropriate service area.
59
 In rural areas, several contiguous 8-digit HUCs or a 6-digit 
HUC watershed may be an appropriate service area.
60
 Delineation of the service area must also 
consider any locally-developed standards and criteria that may be applicable.
61
 The economic 
viability of the mitigation bank may also be considered in determining the size of the service 
area.
62
 
 
 
51
 33 C.F.R. 332.3(b)(2). 
52
 Id. 
53
 33 C.F.R. 332.3(f)(1). 
54
 33 C.F.R. 332.3(f)(2). 
55
 Ecoregions are areas where ecosystems (and the type, quality, and quantity of environmental resources) are generally 
similar. A Roman numeral classification scheme has been adopted for different hierarchical levels of ecoregions, ranging 
from general regions to more detailed: Level I - 12 ecoregions in the continental U.S.; Level II - 25 ecoregions in the 
continental U.S.; Level III -105 ecoregions in the continental U.S.; Level IV - 967 ecoregions in the conterminous U.S. EPA, 
Ecoregions, https://www.epa.gov/eco-research/ecoregions (last visited Feb. 14, 2025). 
56
 33 C.F.R. 332.8(d)(6)(ii)(A). 
57
 Id. 
58
 “HUC” means the hydrologic cataloging unit assigned to a geographic area representing a surface watershed drainage basin. 
Each unit is assigned a two- to 12-digit number that uniquely identifies each of the six levels of classification within six two-
digit fields. United States Geological Survey (USGS), Hydrologic Unit Codes (HUCs) Explained , 
https://nas.er.usgs.gov/hucs.aspx (last visited Mar. 3, 2025). Eight-digit HUCs are used for large watersheds known as 
subbasins; 10-digit HUCs divide the large subbasins into watersheds; and 12-digit HUCs divide watersheds into subwatersheds 
that capture local tributary systems. EPA, Hydrologic Unit Codes: HUC 4, HUC 8, and HUC 12, available at 
https://enviroatlas.epa.gov/enviroatlas/datafactsheets/pdf/Supplemental/HUC.pdf; DEP, About the Florida National 
Hydrography Dataset, https://floridadep.gov/dear/watershed-services-program/content/about-florida-national-hydrography-
dataset (last visited Mar. 3, 2025). 
59
 33 C.F.R. 332.8(d)(6)(ii)(A). 
60
 Id. 
61
 Id. 
62
 Id.  BILL: SB 492   	Page 9 
 
USACE Proximity Factor Tool 
USACE developed a proximity factor tool that may be used when there are insufficient 
mitigation credits within the approved mitigation bank service area. The tool is used to assess the 
number of credits required for any compensatory mitigation proposed outside of approved 
mitigation bank service areas.
63
 The proximity factor is based on ratio multipliers for multiple 
variables.
64
 The tool is only applied when USACE has determined that mitigation outside of the 
approved mitigation service area is the most environmentally preferable mitigation option.
65
 
 
The proximity factor tool applies the following multipliers: 
• No multiplier if the impact site is outside of a mitigation bank service area boundary, but 
within the same 8-digit HUC that contains the mitigation bank location. 
• 1.5 multiplier if the impact site is outside of a mitigation bank service area boundary and one 
8-digit HUC away from the mitigation bank service area boundary. 
• 0.25 multiplier for each additional 8-digit HUC away from the mitigation bank location. 
• 0.75 multiplier if mitigation entails out-kind replacement (there is no multiplier if the 
mitigation entails in-kind replacement). 
• 0.25 multiplier if mitigation occurs within a different EPA Level IV Ecoregion.
66
 
 
The sum of the applicable multipliers provides the proximity factor.
67
 The resulting proximity 
factor is then multiplied by the number of credits required by USACE to compensate for 
unavoidable adverse effects to aquatic resources (e.g., via application of an approved functional 
assessment such as UMAM).
68
 USACE has the discretion to consider and approve use of the 
proximity factor tool on a case-by-case basis.
69
 
 
Mitigation should be performed within the same 6-digit HUC.
70
 When assessing the location of 
the mitigation site relative to the impact site, the calculation starts at the 8-digit HUC that 
contains the mitigation bank site.
71
 
III. Effect of Proposed Changes: 
Section 1 amends s. 373.4136, F.S., regarding the establishment and operation of mitigation 
banks. Currently, the Department of Environmental Protection (DEP) and water management 
districts are authorized to set the schedule for releasing mitigation credits to each mitigation bank 
 
63
 USACE, Standard Operating Procedure—Assessing a Proximity Factor for Compensatory Mitigation Required to Offset 
Unavoidable Impacts to Waters of the United States, 1 (2023), available at 
https://usace.contentdm.oclc.org/utils/getfile/collection/p16021coll15/id/1998.  
64
 Id. 
65
 Id. at 3. 
66
 Id. 
67
 USACE, Standard Operating Procedure—Assessing a Proximity Factor for Compensatory Mitigation Required to Offset 
Unavoidable Impacts to Waters of the United States at 1, 4, available at 
https://usace.contentdm.oclc.org/utils/getfile/collection/p16021coll15/id/1998. 
68
 Id. 
69
 Id. at 5. 
70
 Id. at 5. 
71
 Id.  BILL: SB 492   	Page 10 
 
on a case-by-case basis based on the performance criteria for the mitigation bank, the success 
criteria for each mitigation activity, and other enumerated factors.
72
  
 
The bill requires DEP and water management districts to adhere to the following credit release 
schedule: 
• 30 percent of awarded credits for the recording of the conservation easement and 
establishment of financial assurances required by the mitigation bank permit, or 100 percent 
in the case of a preservation-only bank. 
• 30 percent of awarded credits following completion of initial construction activities as 
established by the mitigation bank permit. 
• 20 percent of awarded credits upon meeting interim performance criteria established by the 
mitigation bank permit, in increments as monitoring indicates success. 
• 20 percent of awarded credits upon meeting final success criteria established by the 
mitigation bank permit 
 
Currently, credits cannot be released for freshwater wetland creation until the success criteria 
included in the mitigation bank permit are met. The bill allows these types of credits to be 
released sooner, after the success criteria for initial construction activities are met. 
 
The bill provides that once a mitigation bank service area has been established by DEP or a 
water management district, such service area must be considered to have met the cumulative 
impact requirements of s. 373.414(8)(a), F.S.,
73
 for impacts permitted within any regional 
watershed included in the mitigation bank service area. 
 
Currently, only certain projects can use credits from a mitigation bank outside the mitigation 
service area.
74
 The bill expands this provision to provide that any project that meets the 
requirements set forth in the bill may use credits from a mitigation bank outside the mitigation 
service area to offset impacts resulting from such projects or activities. 
 
The bill provides that, when the requirements of s. 373.414(1)(a), F.S.,
75
 are met and an 
insufficient number or type of credits have been released within the mitigation bank service area 
in which the impacts associated with a proposed project are located, the project applicant may 
use credits released from a mitigation bank outside such mitigation service area to offset impacts. 
 
72
 Section 373.4136(5)(b), F.S. The factors include (1) whether the mitigation consists solely of preservation or includes other 
types of mitigation; (2) the length of time anticipated to be required before a determination of success can be achieved; (3) 
the ecological value to be gained from each action required to implement the bank; and (4) the financial expenditure required 
for each action to implement the bank. Id. 
73
 Section 373.414(8)(a), F.S., provides that, in deciding whether to grant a permit for an activity that affects surface waters 
or wetlands, the permitting agency must consider the cumulative impacts of (1) the proposed activity; (2) other projects that 
already exist, are under construction, or have applied for permits or formal wetland or surface water determinations; and (3) 
activities related to developments of regional impact  which are under review, approved, or vested, or other activities 
regulated under Part IV of chapter 373, F.S., which may reasonably be expected to be located within surface waters or 
wetlands in the same drainage basin based upon a local government’s comprehensive plans. 
74
 This includes (1) projects with adverse impacts partially located within the mitigation service area; (2) linear projects, such 
as roadways, transmission lines, distribution lines, pipelines, railways, or seaports; and (3) projects with total adverse impacts 
of less than one acre in size. Section 373.4136(6)(d), F.S. 
75
 Section 373.414(1)(a), F.S., delineates the balancing test DEP or water management districts must use to determine 
whether an ERP activity is not contrary to the public interest or clearly in the public interest.  BILL: SB 492   	Page 11 
 
The project applicant may only use out-of-service area credits once DEP or a water management 
district verifies that mitigation banks within the regional watershed where the adverse impacts 
are located lack the appropriate credit type to offset impacts associated with the proposed 
project.  
 
The bill provides that, if the number of released credits within a mitigation service area only 
partially offsets the impacts associated with a proposed project in that mitigation service area, the 
project applicant may use out-of-service area credits to account for the difference between the 
released credits available in the mitigation bank service area and the credits required to offset the 
impacts associated with the proposed project. The bill requires DEP and water management 
districts to follow the following guidelines to apply a proximity factor to determine adequate 
compensatory mitigation by using the following process: 
• A multiplier may not be applied for use of out-of-service area credits located within the same 
regional watershed as the proposed impacts. 
• A 1.5 multiplier must be applied for use of out-of-service area credits located within a 
regional watershed immediately adjacent to the regional watershed in which the proposed 
impacts are located. 
• When credits are not available in the regional watershed immediately adjacent to the regional 
watershed in which the proposed impacts are located, an additional 0.50 multiplier must be 
applied for each additional regional watershed away from the regional watershed 
immediately adjacent to the regional watershed in which the proposed impacts are located. 
• An additional 0.75 multiplier must be applied if the mitigation used to offset impacts entails 
an out-of-kind replacement which does not replace the same type of wetland or surface water 
impacted. 
 
The bill provides that the use of these multipliers meets the requirements for addressing 
cumulative impacts. 
 
The bill provides that, once a project applicant requests to use credits from a mitigation bank 
outside the mitigation service area in which the proposed impacts will occur, DEP or the water 
management district must contact all mitigation banks within a mitigation service area 
encompassing the location of the proposed impacts within three business days after the request 
from the project applicant and request an accounting of available credits, which may not include 
credits reserved for other project applicants. The mitigation banks contacted must provide such 
accounting within five business days after the request.  
 
Upon receipt of the accounting from the mitigation banks, DEP or the water management district 
must determine if sufficient credits exist to offset impacts associated with the proposed project 
and notify the project applicant of such determination. The applicant may rely on the 
determination for a period of one year after such determination. 
 
The bill requires each mitigation bank to submit an annual report to DEP or the applicable water 
management district with an accounting of the number and type of credits that the mitigation 
bank has available for sale, but the report may not include names of parties for which credits 
have been reserved, if any, or the contract price paid for such credits. DEP and each water 
management district must compile such annual reports and provide an annual assessment of the 
health of the state’s mitigation banking system to the Legislature.  BILL: SB 492   	Page 12 
 
Section 2 reenacts s. 373.403(19), F.S., regarding mitigation and enforcement, for the purpose of 
incorporating the amendment the bill makes to s. 373.4136, F.S. 
 
Section 3 reenacts several subsections of s. 373.4135, F.S., regarding mitigation banks and 
offsite regional mitigation, for the purpose of incorporating the amendment the bill makes to s. 
373.4136, F.S. 
 
Section 4 reenacts s. 373.41365, F.S., regarding adoption and modification of rules to ensure 
financial assurances for long-term management of mitigation, for the purpose of incorporating 
the amendment the bill makes to s. 373.4136, F.S. 
 
Section 5 reenacts s. 373.414(1)(b), F.S., regarding additional criteria for activities in surface 
waters and wetlands, for the purpose of incorporating the amendment the bill makes to s. 
373.4136, F.S. 
 
Section 6 provides an effective date of July 1, 2025. 
IV. Constitutional Issues: 
A. Municipality/County Mandates Restrictions: 
None. 
B. Public Records/Open Meetings Issues: 
None. 
C. Trust Funds Restrictions: 
None. 
D. State Tax or Fee Increases: 
None. 
E. Other Constitutional Issues: 
None. 
V. Fiscal Impact Statement: 
A. Tax/Fee Issues: 
None. 
B. Private Sector Impact: 
Indeterminate.  BILL: SB 492   	Page 13 
 
C. Government Sector Impact: 
None. 
VI. Technical Deficiencies: 
On line 71, the bill provides that “preservation-only” banks will receive 100 percent of awarded 
credits for the recording of the conservation easement and establishment of financial assurances. 
However, the bill does not define “preservation-only” bank, and the meaning of this term is 
unclear. 
 
On lines 134-137, the bill adds language regarding compliance with project-level cumulative 
impact assessments in a section of law that outlines the requirements for establishing mitigation 
bank service areas. The language may be more appropriately placed within s. 373.414, F.S., 
where project-level cumulative impacts are addressed. Specifically, s. 373.474(8)(b), F.S., 
already has language that states, “If an applicant proposes mitigation within the same drainage 
basin as the adverse impacts to be mitigated, and if the mitigation offsets these adverse impacts, 
the governing board and department shall consider the regulated activity to meet the cumulative 
impact requirements of paragraph (a). However, this paragraph may not be construed to prohibit 
mitigation outside the drainage basin which offsets the adverse impacts within the drainage 
basin.” If that concept needs clarification, s. 373.414(8)(b), F.S., would be the appropriate place 
to make that change. 
 
On lines 153-158, the bill provides that project applicants may use credits from a mitigation bank 
outside the service area “when the requirements of s. 373.414(1)(a), F.S., are met.”
76
 However, if 
the criteria in this section of law are met, an applicant would not be required to consider 
mitigation measures such as a mitigation bank.
77
 Moreover, it is unclear what is meant by 
“requirements” here and on line 151, as the cited provisions to do not clearly establish 
“requirements” that must be satisfied. 
 
Regarding lines 140-152, existing law in s. 373.4136(6)(d), F.S., limits the use of mitigation 
bank credits outside the bank’s service area to three specific types of projects. The bill amends 
this provision by adding a fourth category—projects that use the proximity factor multiplier 
established in this bill. It also removes the language specifying that the activities listed are the 
only types of activities that can be mitigated outside of the mitigation services area. With the 
changes in the bill, there is nothing linking paragraph (6)(d) with an authorization that the 
mitigation can occur outside the service area. Paragraph (6)(e) could be read to function 
independently and be the only method for credits to be offered outside of the service area. If that 
is the intent, then (6)(d) could be deleted.   
VII. Related Issues: 
The proximity factor multipliers in the bill are based on regional watersheds, whereas the federal 
proximity factor uses 8-digit hydrologic unit code (HUC) and EPA ecoregions. Additionally, the 
 
76
 Section 373.414(1)(a), F.S., delineates the balancing test criteria DEP or water management districts must use to determine 
whether an ERP activity is not contrary to the public interest or clearly in the public interest. 
77
 Section 373.414(1)(b), F.S.  BILL: SB 492   	Page 14 
 
federal proximity factor provides that mitigation should be performed within the same 6-digit 
HUC, while the bill does not include such a requirement and would allow the use of credits from 
a mitigation bank regardless of how far it is from the impact site. These differences may affect 
the consistency and effectiveness of mitigation efforts and create challenges for permittees who 
must obtain both state and federal permits. 
 
Additionally, the bill’s three- and five-day deadlines for contacting mitigation banks and 
confirming credit availability may be difficult to meet due to potential administrative constraints 
and the time required to verify and report accurate credit accounting. 
VIII. Statutes Affected: 
This bill substantially amends the following sections of the Florida Statutes: 373.4136, 373.403, 
373.4135, 373.41365, and 373.414. 
IX. Additional Information: 
A. Committee Substitute – Statement of Changes: 
(Summarizing differences between the Committee Substitute and the prior version of the bill.) 
None. 
B. Amendments: 
None. 
This Senate Bill Analysis does not reflect the intent or official position of the bill’s introducer or the Florida Senate.