Hawaii 2025 2025 Regular Session

Hawaii House Bill HB592 Introduced / Bill

Filed 01/17/2025

                    HOUSE OF REPRESENTATIVES   H.B. NO.   592     THIRTY-THIRD LEGISLATURE, 2025         STATE OF HAWAII                                A BILL FOR AN ACT     relating to capital improvement projects for the benefit of THE Thirty-first REPRESENTATIVE DISTRICT.     BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:   

HOUSE OF REPRESENTATIVES H.B. NO. 592
THIRTY-THIRD LEGISLATURE, 2025
STATE OF HAWAII

HOUSE OF REPRESENTATIVES

H.B. NO.

592

THIRTY-THIRD LEGISLATURE, 2025

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

relating to capital improvement projects for the benefit of THE Thirty-first REPRESENTATIVE DISTRICT.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 

      SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $43,100,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2025-2026 for the purpose of capital improvement projects for the thirty-first representative district, as follows: 1.   Admiral Arthur W. Radford high school      Design and construction for campus-wide electrical upgrades.      Design                         $500,000      Construction                 $2,500,000           Total funding                     $3,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 2.   Admiral Arthur W. Radford high school      Design and construction for the replacement of five portable classrooms.      Design                         $500,000      Construction                 $2,500,000           Total funding                     $3,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 3.   Admiral Arthur W. Radford high school      Plans, design, construction, and equipment and appurtenances for artificial turf for the practice field and baseball field areas.      Plans                          $300,000      Design                         $400,000      Construction                 $9,000,000      Equipment                      $400,000           Total funding                    $10,100,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 4.   Moanalua elementary school      Construction for multi-purpose innovation center construction completion.      Construction                 $2,900,000           Total funding                     $2,900,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 5.   Moanalua high school      Design, construction, and equipment and appurtenances for weight room and athletic training room construction.      Design                       $3,000,000      Construction                $16,000,000      Equipment                    $1,000,000           Total funding                    $20,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 6.   Moanalua middle school      Plans, design, construction, and equipment and appurtenances for planned campus-wide electrical upgrades.      Plans                           $50,000      Design                         $150,000      Construction                 $1,200,000      Equipment                      $100,000           Total funding                     $1,500,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 7.   Salt Lake elementary school      Plans, design, construction, and equipment and appurtenances for air conditioning installation in classrooms F-4, F-5, F-6, and F-7.      Plans                          $200,000      Design                         $300,000      Construction                   $600,000      Equipment                    $1,500,000           Total funding                     $2,600,000      The sum appropriated for this capital improvement project shall be expended by the department of education.      SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2028, shall lapse as of that date.      SECTION 3.  This Act shall take effect on July 1, 2025.      INTRODUCED BY:   _____________________________              

     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $43,100,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2025-2026 for the purpose of capital improvement projects for the thirty-first representative district, as follows:

1.   Admiral Arthur W. Radford high school

     Design and construction for campus-wide electrical upgrades.

     Design                         $500,000

     Construction                 $2,500,000

          Total funding                     $3,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

2.   Admiral Arthur W. Radford high school

     Design and construction for the replacement of five portable classrooms.

     Design                         $500,000

     Construction                 $2,500,000

          Total funding                     $3,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

3.   Admiral Arthur W. Radford high school

     Plans, design, construction, and equipment and appurtenances for artificial turf for the practice field and baseball field areas.

     Plans                          $300,000

     Design                         $400,000

     Construction                 $9,000,000

     Equipment                      $400,000

          Total funding                    $10,100,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

4.   Moanalua elementary school

     Construction for multi-purpose innovation center construction completion.

     Construction                 $2,900,000

          Total funding                     $2,900,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

5.   Moanalua high school

     Design, construction, and equipment and appurtenances for weight room and athletic training room construction.

     Design                       $3,000,000

     Construction                $16,000,000

     Equipment                    $1,000,000

          Total funding                    $20,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

6.   Moanalua middle school

     Plans, design, construction, and equipment and appurtenances for planned campus-wide electrical upgrades.

     Plans                           $50,000

     Design                         $150,000

     Construction                 $1,200,000

     Equipment                      $100,000

          Total funding                     $1,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

7.   Salt Lake elementary school

     Plans, design, construction, and equipment and appurtenances for air conditioning installation in classrooms F-4, F-5, F-6, and F-7.

     Plans                          $200,000

     Design                         $300,000

     Construction                   $600,000

     Equipment                    $1,500,000

          Total funding                     $2,600,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

     SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2028, shall lapse as of that date.

     SECTION 3.  This Act shall take effect on July 1, 2025.

 

INTRODUCED BY: _____________________________

INTRODUCED BY:

_____________________________

 

 

         Report Title: CIP; Thirty-first Representative District; Appropriation   Description: Appropriates funds for capital improvement projects in the thirty-first representative district.       The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent. 

 

 

 

Report Title:

CIP; Thirty-first Representative District; Appropriation

 

Description:

Appropriates funds for capital improvement projects in the thirty-first representative district.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.