Prior law (R.S. 38:2211) defined terms used in the public bid law.
New law retains prior law definition of the terms "bidding documents", "change order
outside the scope of the contract", "change order within the scope of the contract",
"contractor", "emergency", "licensed design professional", "Louisiana resident contractor",
and "negotiate"; adds definitions for the terms "alternate" and "probable construction costs";
amends the definition of "change order".
New law adds definition of "alternate" to mean an item on the bid form that may increase
or decrease either the quantity of work or change the type of work within the scope of the
project, materials, or equipment specified in the bidding documents, or both.
New law amends definition of "change order" to mean any contract modification that
includes an alteration, deviation, addition, or omission as to a preexisting public work
contract, which authorizes an adjustment in the contract price, contract time, or an addition,
deletion, or revision of work.
New law adds definition of "probable construction costs" to mean the estimate for the cost
of the project as designed that is determined by the public entity or the designer.
Prior law (R.S. 38:2212) required that public work, including labor and materials, exceeding
$150,000 undertaken by a public entity to be advertised and let by written contract to the
lowest responsible bidder who bids according to the contract, plans, and specifications.
New law substitutes the term "bidding documents" for the phrase "contract, plans, and
specifications" wherever it occurs in prior law.
Prior law required the office of facility planning and control to develop a bid form necessary
to obtain information and to implement use of such form to bid for public works projects
through promulgation of rules and regulations in accord with the APA.  Required the bid
form request only information necessary to determine the low bidder and certain listed
information: Bid Security or Bid Bond, Acknowledgment of Addenda, Base Bid, Alternates,
Signature of Bidder, Name, Title, and Address of Bidder, Name of Firm or Joint Venture,
Corporate Resolution, and Louisiana Contractors License Number, and on public works
projects that use unit prices, a section to set forth such prices, provided such unit prices shall
not be used to construct building projects, unless the unit is incorporated into the base bid.
New law retains prior law but allows written evidence of authority for the person signing the
bid, requires a description of each unit on bid forms that use unit prices, and prohibits use
of unit prices on building projects unless the unit prices and their extensions are incorporated
into the base bid or alternates.
New law requires all public entities to use the Louisiana Uniform Bid Form promulgated by
the office.
Prior law required the low bidder to furnish within 10 days of bid opening other
documentation and information required including but not limited to the low bidder's
attestations pursuant to R.S. 38:2212.10 (E-verify) and 2227 (certain criminal convictions).
New law retains prior law and authorizes the apparent low bidder to submit such information
and documentation any time prior to expiration of the 10-day period.
New law requires a public entity to declare non-responsive an apparent low bidder who fails
to submit information required by bidding documents in 10 days; authorizes a public entity
to award the bid to the next lowest bidder and to afford such bidder 10 days to furnish
required information; and authorizes a public entity to continue such process until the public
entity either determines the low bidder or rejects all bids.
New law retains prior law that requires the public entity shall not waive or alter the 10-day
period except for the governing authority of any publicly owned commercial aviation airport,
the Sewerage and Water Board of New Orleans, the Regional Transit Authority, and all
agencies of the city of New Orleans, including but not limited to the New Orleans Aviation
Board shall require information and documentation from the two lowest bidders three days
after bid opening. The two apparent low bidders may submit such information or
documentation at any time prior to the expiration of the three day period. If the two apparent low bidders do not submit the proper information or documentation as required by the
bidding documents within the three day period, such bidders shall be declared non-
responsive, and from that date, award may be made to the next lowest bidder, and afford that
bidder not less than three days to submit the required information or documentation, and the
process may continue until either a low bidder is determined or all bids are rejected.
New law clarifies the exception in prior law for EBR Parish public works projects that
requires all bidders on public works to submit all bid documents required by statute or by
the La. Administrative Code to the governing authority of EBR Parish prior to the opening
of all bids relative to a contract for public works.  New law deletes prior law that excepts
DOTD from its requirements.
New law reorganizes but retains prior law that requires a bidder on a public works project
conducted by the New Orleans Sewerage and Water Board to include Acknowledgment of
Addenda to the bid form and to attach the addenda if pricing information is contained therein
and the addenda requires its attachment.
Prior law required a bidder who submits a bid to the division of administration or the state
of Louisiana to submit evidence of authority of the person who signs the bid for public
works.  New law expands prior law to apply to any public entity.  Adds that such evidence
shall be written.
Prior law required delivery of each bid by the bidder or his agent either by hand delivery,
electronic delivery, or registered or certified mail with return receipt requested, except that
registered or certified mail with return receipt requested delivery do not apply to municipal
and parochial governing authorities. Required written receipt of hand delivered bids to the
deliverer. Prohibited a public entity from accepting a bid on days recognized as holidays by
the U.S. Postal Service.
New law removes exception applicable to municipal and parochial governing authorities in
prior law for delivery of bids by registered and certified mail.
New law retains but moves prior law (R.S. 38:2212(A)(1)(c)(ii)) to new law (R.S.
38:2225(C)) that requires DOTD and the office of facility planning and control to keep on
file a list of all states with a bid preference.
New law provides that for the purpose of interpretation of the base bid total and alternates,
when applicable, written words govern if a conflict exists between words and numerals.
Provides that if public works require unit prices and if a discrepancy exists between the base
bid total and the sum of the extended prices, the unit price bid governs.
Prior law defined the term "contract limit" as equal to the sum of $150,000, including labor,
materials, and equipment as per the rates in the latest edition of the Associated Equipments
Dealers Rate Book and administrative overhead not to exceed 15% except that the contract
limit is $50,000 per project for the Department of Public Safety and Corrections (DPSC)
when it intends to use inmates as labor for projects on the grounds of prisons and
correctional institutions for the calendar year 1982, and provided that such contract limit
increases for each succeeding calendar year, increases such contract limit by a factor equal
to 3% per year for each of the next 10 calendar years (1983-1993).
New law requires, beginning Feb. 1, 2015, and annually on Feb. 1 of each subsequent year,
the office of facility planning and control within the division of administration to adjust the
"contract limit" by an amount not to exceed the annual percentage increase in the Consumer
Price Index in the preceding year and to publish the new contract limit for public works
contracts in the Louisiana Register in January of each year.
New law increases the contract limit for such DPSC projects to $75,000 and removes
provision for 3% per year increases.
New law deletes prior law that authorizes the Bossier Parish Police Jury to undertake a
public works project with its own employees; sets its contract limit at $130,000; authorizes
the police jury to adjust the contract limit annually by an amount not to exceed the annual
percentage increase in the Consumer Price Index in the preceding year; and requires the
police jury to publish the new contract limit for public works contracts in its official journal
in February of each year. New law retains prior law that provides an annual limit of $1,000,000, including labor,
materials, and equipment, per the latest edition of the Associated Equipment Distributors
Rental Rate Book, and administrative overhead not to exceed 15%, for public work, which
is not publicly bid, to restore or rehabilitate a non-federally maintained levee, including
mitigation on public lands owned by the state or a political subdivision provided such work
is undertaken by the public entity with its own resources and employees, or the resources and
employees of another public entity through a cooperative endeavor or other agreement.
Provides that these provisions expire December 31, 2018.
New law retain prior law that requires public entities to furnish at least one complete set of
bid documents to prime bidders who request bid documents and who are properly licensed
by the Louisiana State Licensing Board for Contractors. Authorizes public entities to require
a deposit for bid documents but requires the total deposit, including handling fees and other
costs, not to exceed twice the actual cost of reproduction. Provides that a deposit on the first
set of documents is fully refundable upon return of the documents no later than 10 days after
receipt of bids. Provides for refund of deposit less actual reproduction cost on other sets of
documents upon return no later than 10 days after receipt of bids. Authorizes public entities
that itself prepares and distributes contract documents to charge a fee not to exceed its actual
reproduction cost in lieu of a deposit.
New law requires prime bidders to obtain an original set of bidding documents from the
public entity or the design professional who prepared such documents.  Either the public
entity or the design professional may choose the method and service of plan distribution.
Authorizes the public entity to distribute bidding documents in the manner it chooses when
the public entity utilizes an electronic bid submittal system. Provides public entity has sole
discretion to authorize its design professional of record to choose an electronic bid submittal
system. Requires the public entity or its design professional to maintain a list of all prime
bidders for addenda distribution.
New law deletes prior law that authorized the Sewerage and Water Board of New Orleans
to charge a fee, in lieu of a deposit, for paper documents when it prepares and distributes
electronic contract documents itself.
New law retains prior law that requires public entities to provide contractors a uniform and
secure electronic interactive system for submittal of bids as an additional bidding option.
Requires public entities that provide such system to follow the standards for receipt of
electronic bids adopted by the office of the governor, division of administration, and the
office of information technology as provided in LAC 4:XV.701.
New law allows a public entity at its sole discretion to authorize its design professional of
record to choose an electronic bid system.
New law deletes prior law requiring acceptance of electronic bids for all purchases requiring
competitive bidding.
New law retains prior law that exempts public entities currently without available high-speed
Internet access from providing for electronic bidding until such time such access becomes
available.
New law retains prior law that exempts any parish with a police jury form of government
and a population less than 20,000 from electronic bidding.
New law retains prior law that exempts any other public entity from electronic bidding
without securing and expending additional funding.
New law retains prior law that gives public entities the option to require submittal of
electronic bids on any competitive bid let out for public bid.
New law retains prior law that requires public entities to include all bidding documents on
the electronic website accepting electronic bids.
New law retains prior law that authorizes a bid specification to contemplate a fixed
escalation or de-escalation according to the U.S. Bureau of Labor Statistic's Consumer Price
Index but substitutes the Producer Price Index for the Wholesale Price Index. Provides that
bids based on specifications that are subject to such an escalation index are legal and valid. New law adds that such an escalation index is valid for any item of a public work at the
public entity's discretion.
New law retains prior law that requires the advertisement for public work to be published
once a week for three different weeks in a newspaper in the locality, requires the first
advertisement to appear at least 25 days before opening of bids, and authorizes
advertisement by electronic media available to the general public in addition to such
newspaper advertisement.
New law retains prior law that prohibits the first publication of the advertisement on a
Saturday, Sunday, or legal holiday, and requires all bidding documents to be available on
the day of first advertisement and until 24 hours before the bid opening date.
New law revises prior law that prohibits advertisement of the project if the designer's
estimate is more than the funds budgeted by the public entity for the projects and requires
the designer's estimate to be read aloud upon opening bids.  New law requires the public
entity to provide or to obtain from the project designer an estimate of probable construction
costs prior to advertisement for bids. Prohibits advertisement of a public work unless funds
that meet or exceed the estimate of probable construction costs have been budgeted by the
public entity for the project. Requires the estimate of probable construction costs to be made
available either by electronic posting or by announcing it aloud at bid opening. Provides that
any and all bidders' information shall be available upon request, either no sooner than 14
days following the bid opening or after the recommendation of award by the public entity
or the design professional, whichever occurs first, and the requester shall pay reasonable
reproduction costs. Requires all bid information to be available upon request 72 hours
following opening of bids.
New law retains prior law that requires the date, place, and time of a required pre-bid
conference to be advertised in the advertisement notice.  New law requires pre-bid
conference information to be contained in all three advertisements for bid.
New law requires all prospective bidders to be present at the beginning of the pre-bid
conference and to remain in attendance for the duration of the conference and prohibits any
prospective bidder who fails to attend the conference or remain for the duration from
submitting a bid for the project. New law removes limited application to the orphan well
plug and abandonment program within the Louisiana Dept. of Natural Resources.
New law retains prior law that prohibits no more than three alternates in bidding documents
and requires acceptance of alternates in the order listed on the bid form.  Requires
determination of the low bidder on the basis of the sum of the base bid and any alternates
accepted but gives the public entity the right to accept alternates in any order that does affect
determination of the low bidder.
New law retains prior law that restricts the use of allowances to minor items and limits them
to hardware, face brick, landscaping, electric light fixtures, and carpeting.  Adds
miscellaneous steel, tile, wallpaper and other exterior finishes, fixtures and furnishings to
list of allowances. Prohibits use of allowances to control selection of a subcontractor or
supplier.
New law retains prior law that prohibits a construction manager or any other third-party
consultant employed by a public entity to manage a construction project as a general
contractor or to act in the role of the general contractor to oversee, direct, or coordinate
individual trade contractors on behalf of the public entity, or to accept bids or itself bid on
the public work or components of the public work with respect to which the manager or
consultant is employed or contracted to manage or consult.  New law retains exception in
Prior law for initial construction of a hospital, medical facility, or both, constructed by the
Orleans Hospital Service District.
New law deletes prior law that requires construction contracts to be opened in a public
meeting, that all subcontractors bidding the project be invited to the meeting, and that the
general contractor list subcontractors in the bid documents.
New law retains prior law that requires public works contracts to contain provisions for
change orders within the scope of the contract and for change order to be in writing. New law provides option for change orders in electronic format and requires execution of
the change order by the contractor and the public entity or its design representative.
New law requires the public entity to pay the contractor for work performed by change order
not later than 60 days after the date the public entity receives an approved application for
payment for completion of the work performed in the change order.
New law retains prior law that requires any change order outside the scope of the contract
in excess of the contract limit to be let for public bid as provided by law.
New law retains prior law that authorizes a public entity to either negotiate or let for public
bid a change order less than the contract limit. Provides for negotiated change orders to be
fully documented and itemized as to costs.  Prohibits deviation in unit prices contained in
an initial contract in a negotiated change order.
New law retains prior law that requires public works estimated to cost in excess of $150,000
to be advertised and let by contract to the lowest responsible bidder.  New law requires
public works to be let to the lowest responsible and responsive bidder.
New law retains prior law that authorizes public works estimated to cost less than $150,000
to be undertaken by the public entity with its own employees.
New law retains prior law that authorizes a public entity to issue a bid addendum and to
extend the bid period for up to 30 days without readvertising. Requires completion of
transmittal of a copy of any addendum issued within 24 hours of its issuance and delivery
by either facsimile transmission, email, other electronic means, or by hand provided the
prime bidder has supplied the facsimile transmission number or email address to the public
entity by the public entity to all prime bidders who have requested bidding documents.
Requires postponement of the bid opening by at least seven days if an addendum cannot be
transmitted by facsimile transmission, email, or other electronic means, or otherwise effected
by hand delivery.
New law adds authority to issue addendum by overnight delivery using a nationally
recognized carrier.
New law retains prior law that prohibits issuance of any addenda modifyi ng the bidding
document within 72 hours prior to the advertised time for the opening of bids, excluding
Saturdays, Sundays, and any other legal holidays, but authorizes issuance of an addendum
due to necessity with such period and requires extension of the time to open bids for at least
seven days but not more than 21 working days without the requirement to readvertise.
Requires the addendum to state the revised time and date to open bids.
New law retains prior law that provides competitive bidding requirements do not apply in
cases of public emergency where the public entity certifies such emergency and publishes
notice of such public emergency within 10 days in its official journal or in cases of extreme
public emergency.  Requires the president of the police jury, the president of the parish
council, the mayor of the municipality, or a person to act on behalf of the governing
authority of any other political subdivision to declare the existence of an extreme public
emergency and to publish same in the official journal within 10 days or as soon as
practicable thereafter.
New law retains prior law that authorizes the office of facility planning and control to
address damage caused by hurricanes Katrina and Rita by public advertisement in the
official journal of the locality of the project and the state's official journal and to take public
bids in a minimum of 10 days after advertisement.  Prohibits negotiation of such projects
except when no bids are received. Requires competitive bidding negotiations with no fewer
than two contractors. Requires written determination and findings to support decision for
every negotiated contract under prior law. Requires the public entity to take telephone or
other oral offers, to obtain written confirmation of an accepted offer and to include such
confirmation in the contract case file. Requires the public entity to establish a record that
contains, as a minimum, the following information for each offer: a description of the work
to be performed, the name and address of each offeror quoting, and the performance time
and terms of each offer.  Requires to record and include in the contract file the rejection of
any quotations that are lower than the accepted quotation. Requires retention of such records
for a minimum of six years after the purchase or completion of the public work. New law deletes prior law that authorized EBR Parish to assist LSU through use of the
parish's own employees to undertake a project to enclose approximately 500 feet of
Corporation Canal that runs adjacent to the University Laboratory School on the Baton
Rouge campus, which project has been funded as an emergency through appropriation of
funds by the Interim Emergency Board to LSU.
New law retains prior law that authorizes a publicly owned utility to undertake a public
works project, other than construction of a building, for the contract limit ( $150,000) or less
by either of the following methods: entry into contracts with or without public bid; use of
the employees of the public entity owning the utility.  New law provides that such publicly
owned utility be recognized by the Louisiana Public Service Commission.
New law retains prior law that prohibits ownership or operation of a manufacturing plant for
construction materials by a public entity.  New law adds manufacturing facilities and
production of construction materials to such prohibition.  New law deletes provisions that
excluded any such facilities owned or operated prior to Sept. 11, 1981, from such
prohibition.
New law retains prior law that authorizes a public entity to use its regular maintenance
employees for labor necessary in the maintenance, construction, or extension of publicly
owned and operated electric public utilities.  Authorizes public entities to use their regular
maintenance employees to construct or extend all other public utilities when the cost of the
work per project does not exceed $100,000, including labor and materials.  New law
increases the contract limit for such projects to $150,000.
New law retains prior law that requires all purchases of materials or supplies exceeding the
contract limit ($150,000) to be let by public bid as provided by law.
New law retains prior law that authorizes a public entity to specify a particular brand, make,
or manufacturer for a project let to public bid and requires specification to include the model
or catalog number.
New law retains prior law that requires bidding documents to state clearly that the
specification of the name of a certain brand, make, manufacturer, or definite specification
is used only to denote the quality standard of product desired, to convey to prospective
bidders the general style, type, character, and quality of product desired, does not restrict
bidders to the specific brand, make, manufacturer, or specification named, and that
equivalent products are acceptable.  Requires a professionally employed architect or
engineer to determine what is considered an equivalent product on any and all projects in
which he has been legally employed to perform his professional services.
New law retains prior law that authorizes a public entity to enter into maintenance contracts
for the repair and maintenance of water storage tanks owned, controlled, or operated by a
public entity for a fixed annual fee provided such contracts extend for a duration of not less
than two years, include a nonappropriation clause, and are not considered a debt of the
public entity.  New law changes prior law from water storage tanks to public facilities.  New
law retains prior law that provides that such maintenance contracts are not considered a
public works contract.
New law retains prior law that prohibits division or separation of any public work project
into smaller projects to avoid the requirement that public work be advertised and let by
contract to the lowest responsible bidder.  New law changes phrase lowest responsible bidder
to lowest responsible and responsive bidder.
New law retains prior law that makes it inapplicable to labor necessary for the maintenance
of public works built and completed.
New law retains prior law that makes it inapplicable to volunteer citizen labor used for the
construction of a project funded by the Louisiana Community Development Block Grant
Louisiana Small Town Environment Program and provides that the value of donated
volunteer service shall not be used as a component of any bid if such public work is bid to
determine the lowest responsible bid. New law changes phrase lowest responsible bidder
to lowest responsible and responsive bidder.
New law retains prior law that requires a public entity to give written notice that includes
all reasons and an opportunity for a hearing to any bidder who it proposes to disqualify on the grounds that such bidder is not a responsible bidder prior to such disqualification.  New
law requires the informal hearing to be conducted prior to award of the public work.  New
law further requires the hearing to be conducted by the public entity not later than five
business days after the date of the notice of disqualification of such bidder and requires the
public entity to issue a ruling in writing and deliver same to the affected bidder not later than
five business days after the date of the informal hearing.
New law prohibits award of the contract for the public work by the public entity prior to the
expiration of at least five working days after the date of issuance of the decision by the
hearing official and requires the hearing official to issue a ruling in writing and deliver it to
the affected bidder in the manner agreed upon by such official and the bidder.
New law excepts DOTD from its provisions on disqualification of bidders.
New law retains prior law that prohibits a public entity from entering into a contract for the
purpose of public works with a contractor who then finances the project. Provides that under
no circumstances shall the agreement of a contractor to finance a public works project be
used in any way to avoid the requirement that public work be advertised and let by contract
to the lowest responsible bidder.
New law deletes prior law that authorized a public entity to include bid selection provisions
in bid documents relative to participation in a mentor-protégé program.
New law retains prior law that provides that it shall not apply to purchases of materials and
supplies by contractors awarded public works contracts by a public entity; or to
subcontractors of such contractors, who have been appointed or designated agents for the
purchase of materials and supplies to be incorporated into a public work pursuant to a
contract properly bid when acting pursuant to said appointment or designation.  New law
changes phrase lowest responsible bidder to lowest responsible and responsive bidder.
Prior law (R.S. 38:2212.5) authorized the division of administration to prequalify bidders
for historic restoration projects funded by the state except for construction or repair of roads
and bridges and contractors providing materials and supplies for such construction.  Requires
the division to promulgate rules and regulations. Defined historic restoration projects to
mean repairs, renovations, or reconstruction of state-owned structures included or eligible
for inclusion on the National Register of Historic Places.  Further provided for renovation
of the LSU Student Union on the Baton Rouge campus. Required that only prequalified
bidders may submit bids on designated historic projects.  Required award of contracts for
historic projects to the prequalified bidder submitting the lowest responsible bid. Requires
contract for renovation of the LSU Student Union may be for overhead and profit or lump
sum. Required submission of such contract to the Joint Legislative Committee on the Budget
for review and approval.
New law requires award of a historic restoration project to the prequalified bidder who
submits the lowest responsible and responsive bid.
New law removes prior law applicable to the LSU Student Union.
Prior law (R.S. 38:2212.10) provided, generally, that a private employer shall not bid on or
otherwise contract with a public entity for a contract for public work unless the private
employer verifies in a sworn affidavit attesting to both of the following:
(1)The private employer is registered and participates in a status verification system to
verify that all employees are legal citizens of the U.S. or are legal aliens.
(2)The private employer must continue, during the term of the contract, to utilize a
status verification system to verify the legal status of all new employees.
New law changes prior law to require that private employers verify new employees.
Prior law provided that its provisions shall no longer apply if the status verification system
expires and extensions are no longer approved by the federal government.
New law retains prior law and requires the executive director of the LWC to provide written
notice to Louisiana State Law Institute if the status verification expires and is not extended. Prior law (R.S. 38:2215) provided for the time period to hold bids and to issue a work order
to commence work on a public works project. Required the state or any state agency upon
receipt of bids to award a public works contract to the lowest responsible bidder or to reject
all bids within 30 calendar days of receipt of bids. Required a political subdivision to award
a contract within 45 calendar days of receipt of bids. Required the contractor and the public
entity to execute the public works contract not later than 45 days from the public entity's
acceptance of the lowest responsible bid if the low bidder has timely provided all necessary
documents within 10 days of the opening of bids and no bid challenge has been submitted
to the public entity.  Required issuance of a notice to proceed within 30 days of execution
of the contract. Authorized an extension of time to issue the notice to proceed upon mutual
consent of both parties. Provided that these provisions do not apply to contracts financed
by bonds that must be sold after opening of bids, to contracts financed in whole or in part
by federal or other funds not readily available at the time of bid opening, or to contracts that
require a poll of the legislature before funds are available. Required such time exceptions
to be mentioned in the bidding documents and the advertisement for bids.
New law changes prior law to uniformly require any public entity, which includes the state,
a state agency, and a political subdivision, to execute a contract not later than 60 days after
the date of the public entity's award of a public works contract to the lowest responsible and
responsive bidder or to reject all bids, if the lowest responsible and responsive bidder has
timely provided all documents required by R.S. 38:2212, and no injunction or temporary
restraining order is in effect.
New law requires the public entity to issue the contractor a notice to proceed with the project
or work order not later than 30 calendar days following the date of execution of the contract
by both parties, whichever is execution date is later, provided that the parties may agree to
extend the time to issue a notice to proceed upon mutual written consent of both contractor
and public entity.
Prior law (R.S. 38:2225) required granting the same percentage preference the state of
domicile of a nonresident contractor provides to a Louisiana resident contractor over such
nonresident contractor bidding on a Louisiana public work. Prohibited local preference
laws. Prohibits granting a preference to any local contractor or subcontractor over other
Louisiana resident contractors.  Prohibited waiver of provisions by any public entity.
New law retains but relocates prior law (R.S. 38:2212(A)(1)(c)(ii)) that requires the Dept.
of Transportation and the office of facility planning and control to keep on file a list of all
states with a bid preference.
Prior law (R.S. 38:2241.1) required a public entity to record acceptance of a written contract
for public works in the office of the recorder of mortgages in the parish where the work has
been done upon substantial completion. Authorized a public entity that does not record such
acceptance to require the contractor to record such acceptance upon written recommendation
of the public entity's architect or engineer. Authorized the architect or engineer to make
such recommendation within 30 days of completion of the project. Defined "substantial
completion" to mean the finishing of construction, in accordance with the contract
documents as modified by any change orders agreed to by the parties, when the public entity
can use or occupy the public works or use or occupy the specified area of the public works
for the use for which it was intended. Provided that such recordation of acceptance upon
substantial completion shall be effective as an acceptance for all purposes under law.
New law requires the public entity to record project acceptance not later than 30 days after
completion or substantial completion of the project.  Requires the contractor to file
acceptance within 45 calendar days after completion or substantial completion of the project
for those public entities that do not record an acceptance only upon written recommendation
of the architect or engineer of the public entity made not later than 30 calendar days after the
date of completion or substantial completion of the project.
Effective August 1, 2014.
(Amends R.S. 38:2211(A)(1), (2), (3), (4), (5), (6), (7), (8), and (9), 2212, 2212.5,
2212.10(C)(1) and (G), 2215, 2225, and 2241.1)