The original instrument and the following digest, which constitutes no part of the legislative instrument, were prepared by Archana Cadge. DIGEST SB 423 Original 2022 Regular Session Foil Present law provides that a supplier of particular products for public works may seek prior approval for brand products other than those specified in the contract document within seven working days, prior to bid opening. Proposed law retains present law and clarifies that prior approval is not required. Present law provides the prime design professional shall furnish written approval or denial of the product submitted within three days, exclusive of holidays and weekends, after submission. Proposed law retains present law and further provides if the prime design professional does not respond within the allotted time period, the submitted product shall be considered approved. Proposed law provides for technical corrections. Effective August 1, 2022. (Amends R.S. 38:2295(C)(1))