Louisiana 2022 2022 Regular Session

Louisiana Senate Bill SB423 Comm Sub / Analysis

                    RÉSUMÉ DIGEST
ACT 424 (SB 423) 2022 Regular Session	Foil
Existing law provides that a supplier of particular products for public works may seek prior
approval for brand products other than those specified in the contract documents within
seven working days prior to bid opening.
New law retains existing law and adds a potential supplier may, but is not required to, submit
a particular product for prior approval other than a product specified in the contract
documents, no later than seven working days prior to the opening of bids.
Existing law requires the prime design professional furnish written approval or denial of the
product submitted within three days, exclusive of holidays and weekends, after submission.
New law retains existing law and further provides if the prime design professional does not
respond within the allotted time period, the submitted product shall be considered approved.
Effective August 1, 2022.
(Amends R.S. 38:2295(C)(1))