Montana 2025 2025 Regular Session

Montana Senate Bill SB301 Amended / Bill

                     - 2025 
69th Legislature 2025 	SB0301.2
- 1 - Authorized Print Version – SB 301 
1 SENATE BILL NO. 301
2 INTRODUCED BY D. ZOLNIKOV
3
4 A BILL FOR AN ACT ENTITLED: “AN ACT GENERALLY REVISING UTILITY LINES AND FACILITIES LAWS; 
5 ALLOWING THE COMMISSION TO GRANT A PUBLIC UTILITY A CERTIFICATE OF PUBLIC 
6 CONVENIENCE AND NECESSITY FOR ELECTRIC TRANSMISSION FACILITY CONSTRUCTION; 
7 ESTABLISHING OPTIONAL RATEMAKING PROCEDURES AND TIMELINES; PROVIDING RULEMAKING 
8 AUTHORITY; PROVIDING DEFINITIONS; AND PROVIDING AN IMMEDIATE EFFECTIVE DATE.”
9
10 WHEREAS, advanced transmission technology offers multiple advantages, including increased 
11 capacity on existing transmission infrastructure, significantly reduced wildfire risk, and improved grid reliability, 
12 and is a cost-effective solution to Montana's current congestion and curtailments of transmission pathways; and
13 WHEREAS, the intention of this legislation is to expedite the necessary and overdue transmission 
14 upgrades needed to serve the ever-increasing demand of power; and 
15
16 WHEREAS, the Public Service Commission has the decisionmaking authority to determine the balance 
17 between modernizing the grid to increase reliability and identifying what costs are reasonable or unreasonable 
18 to ensure ratepayer affordability.
19
20 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MONTANA:
21
22 NEW SECTION. Section 1.  As used IN [sections 1 through 3], unless the context clearly 
23 indicates otherwise, the following definitions apply:
24 (1) "Advanced transmission technology" means a technology that increases the capacity, 
25 efficiency, and reliability of an existing or new transmission facility, as defined in 42 U.S.C. 16422. For the 
26 purposes of [sections 1 through 3], the term applies to the following technology:
27 (a) underground cables;
28 (b) advanced conductor technology, such as advanced composite conductors, high temperature   - 2025 
69th Legislature 2025 	SB0301.2
- 2 - Authorized Print Version – SB 301 
1 low-sag conductors, and fiber optic temperature sensing conductors;
2 (c) high-capacity ceramic electric wire, connectors, and insulators;
3 (d) high-voltage direct-current technology;
4 (e) flexible alternate-current transmission systems;
5
6 (f) energy storage devices, such as pumped storage hydropower, compressed air, 
7 superconducting magnetic energy storage, flywheels, and batteries;
8
9 (g) distributed generation, such as photovoltaic solar cells, fuel cells, and microturbines;
10 (h) (F) enhanced power device monitoring;
11 (i) direct system-state sensors;
12 (j) (G) power electronics and related software, including real-time monitoring and analytical software; 
13 and
14 (k) (H) any other technologies the commission considers appropriate.
15 (2) "Certificate of public convenience and necessity" means a written authorization to operate 
16 issued by the commission for constructing an electric transmission facility.
17 (3) "Department" means the department of environmental quality provided for in 2-15-3501.
18 (4) "Transmission facility" means those facilities that are controlled or operated by a utility and 
19 used to provide transmission services as determined by the federal energy regulatory commission and the 
20 public service commission. The term includes advanced transmission technology.
21
22 NEW SECTION. Section 2. 
23 (1) A public utility, as defined in 69-3-101, or any other entity required to 
24 submit a certification application to the department pursuant to Title 75, chapter 20, may request a certificate of 
25 public convenience and necessity from the commission prior to commencing actual construction work on an 
26 electric transmission facility that is rated higher than 69 kilovolts.
27 (2) A UTILITY MAY REQUEST A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FROM THE 
28 PURSUANT TO SUBSECTION (1).THE UTILITY  THE COMMISSION IN WRITING THAT IT SEEKS   - 2025 
69th Legislature 2025 	SB0301.2
- 3 - Authorized Print Version – SB 301 
1 CERTIFICATE. IF THE UTILITY NOTIFIES THE COMMISSION PURSUANT TO THIS SUBSECTION, THE DEPARTMENT MAY 
2 SUBSECTIONS 75-20-301(1)(A), (1)(D)(III), AND (1)(F).
3 (2) (3) (a) Upon receiving a request from a public utility or entity, the commission shall determine 
4 within 270 300 days whether the construction of the proposed transmission facility is in the public interest and 
5 may grant or deny the certificate of public convenience and necessity.
6 (b) In making a determination, the commission may consider:
7 (i) the need for the proposed transmission facility to ensure reliable service for customers;
8 (ii) the ability of the proposed transmission facility to improve customer access to reliable and cost-
9 effective electric generation or storage facilities;
10 (iii) the anticipated costs and benefits of the proposed facility;
11 (iv) the use of advanced transmission technology; and
12 (v) any other factors deemed appropriate by the commission.
13 (3) (4) A commission-approved certificate of public convenience and necessity may satisfy the 
14 requirements set forth in 75-20-301(1)(a), (1)(d), AND (1)(f), and (2) when the department considers siting 
15 applications for proposed transmission facilities.
16 (4) (5) The commission shall adopt rules for the implementation of this section.
17 (6) NT75, CHAPTER 20.
18
19 NEW SECTION. SECTION 3. PPROVAL OF TRANSMISSION AND RELATED FACILITIES. (1) A PUBLIC UTILITY 
20, 
21[SECTION 2].
22 (2) Within 45 days of a utility's application, the commission shall determine if the application is 
23 adequate and in compliance with the commission's minimum filing requirements. If the commission determines 
24 the application is inadequate, it shall explain the deficiencies.
25 (3) The commission shall issue an order within 90 days after receiving an application for 
26 transmission lines and related facilities, unless the commission determines that extraordinary circumstances 
27 warrant additional time.
28 (4) Subject to [section 2(2)] and after the applicant meets the remaining requirements of Title 75,   - 2025 
69th Legislature 2025 	SB0301.2
- 4 - Authorized Print Version – SB 301 
1 chapter 20, the commission may:
2 (a) approve or deny, in whole or in part:
3 (i) an application for approval of transmission lines and facilities; and
4 (ii) cost recovery for costs not prudently incurred; and
5 (b) consider all relevant information until the administrative record in the proceeding is closed for 
6 the commission's evaluation of an application.
7
8
9 NEW SECTION. Section 3.  Electric transmission optional ratemaking procedures -- 
10 .. (1) A public utility operating electric transmission facilities that are part of a bulk electric system 
11 subject to regulation by the federal energy regulatory commission and whose rates are set by the federal 
12 energy regulatory commission using a formula rate process is eligible for optional ratemaking procedures as 
13 described in this section.
14
15 (2) An eligible public utility may establish the optional ratemaking procedures in a general rate 
16 filing pursuant to Title 69, chapter 3, part 3. If the public utility is eligible and the proposed optional ratemaking 
17 procedures are consistent with this section, the commission may ap prove optional ratemaking procedures that 
18 include the following elements:
19
20 (a) The revenues and costs associated with providing electric transmission service must be 
21 unbundled from the revenues and costs associated with providing all other services. Cost recovery and savings 
22 from advanced transmission technology compared to legacy transmission technology must be considered over 
23 the expected life of the transmission line.
24
25 (b) The rates associated with the provisions of electric transmission service m ust be set annually 
26 using forecasted revenues and costs expected over a 12-month perio d, including forecasted revenues the 
27 public utility anticipates it will collect from the provisions of the federal energy regulatory commission 
28 jurisdictional transmission services during that same period.  - 2025 
69th Legislature 2025 	SB0301.2
- 5 - Authorized Print Version – SB 301 
1
2 (c) (i) At the conclusion of each forecasted 12-month period, a public utility shall make a filing to 
3 adjust for a recovery that is above or below the actual, prudently incurred costs and for any revenues the public 
4 utility receives from providing federal energy regulatory commission jurisdictional services.
5
6 (ii) If the federal energy regulatory commission grants the recovery of costs in the rate base during 
7 construction, the public utility may seek similar treatment of these costs through the optional ratemaking 
8 procedures described in this section.
9 (3) Following the initial implementation of unbundled electric transmission rates and optional 
10 ratemaking procedures, the commission shall:
11
12 (a) authorize the public utility to change the rates it charges that are associated with its provision of 
13 electric transmission service on a schedule comparable to the schedule the public utility uses to change its 
14 federal energy regulatory commission formula rates ; and
15
16 (b) authorize a change in the rates associated with the provision of electric transmission service 
17 that is set to go into effect no later than 30 days from the date of filing on an interim basis ..
18
19 (4) A filing to change rates pursuant to this section must comply with the Montana Administrative 
20 Procedure Act, Title 2, chapter 4, part 6.
21 (5) The commission may adopt rules for the implementation of this section."
22
23 NEW SECTION. Section 4.  [Sections 1 through 3] are intended to be 
24 codified as an integral part of Title 69, chapter 4, part 1, and the provisions of Title 69, chapter 4, part 1, apply 
25 to [sections 1 through 3].
26
27 NEW SECTION. Section 5.  [This act] is effective on passage and approval.
28 - END -