New Jersey 2024 2024-2025 Regular Session

New Jersey Assembly Bill A5267 Comm Sub / Analysis

                    ASSEMBLY TELECOMMUNICATIONS AND UTILITIES 
COMMITTEE 
 
STATEMENT TO  
 
ASSEMBLY, No. 5267  
 
with committee amendments 
 
STATE OF NEW JERSEY 
 
DATED:  MARCH 20, 2025 
 
 The Assembly Telecommunications and Utilities Committee 
reports favorably and with committee amendments Assembly Bill No. 
5267.  
 As amended and reported, the Board of Public Utilities (board) is 
required to establish a program to procure and provide incentive 
awards for the development of transmission-scale energy storage 
systems with a reasonable likelihood of successful and timely 
completion. The board is required to solicit applications for the 
program in an initial Tranche 1.  As outlined in the bill, the board is 
permitted to procure additional tranches by either continuing under 
the same program as Tranche 1 or implementing a successor 
program.  
 Under the bill, “transmission-scale energy storage system” 
means an energy storage system, with an installed capacity of at 
least 5 megawatts of alternating current (MW AC), that is 
interconnected with the PJM Transmission Network and situated 
inside a Transmission Zone in New Jersey or is otherwise located in 
New Jersey and qualified to provide energy, capacity, or ancillary 
services in the wholesale markets established by PJM 
Interconnection, L.L.C. (PJM).  
 
Tranche 1 Procurement 
 The bill requires the board to solicit Tranche 1 applications for 
eligible projects whose collective installed capacity totals at least 
500 MW AC.   
 Under the bill, the Tranche 1 application period is to begin no 
later than January 15, 2026, regardless of the publication status of 
the rules and regulations to be issued pursuant to the bill, and is to 
end within 60 days of the date on which the application period 
began.  Within 60 days of the closure of the Tranche 1 application 
period, the board is to evaluate and select eligible projects to 
receive an award.  The board is to finalize and approve all incentive 
awards for Tranche 1 by no later than April 1, 2026.    2 
 
 To qualify for a Tranche 1 incentive award, a transmission-scale 
energy storage system is required to:  (1) not participate in any 
other energy storage program, except for the New Jersey Energy 
Storage Incentive Program (NJ SIP) to the extent that the energy 
storage program established by the bill may be incorporated into the 
NJ SIP; (2) have an anticipated commercial operations date of no 
later than December 31, 2030, unless the board permits an 
exception; (3) have entered the PJM interconnection process and, at 
the time of application for Tranche 1, have a fully-executed 
Generation Interconnection Agreement through PJM, have a 
completed Surplus Interconnection Study through PJM, or have 
notified PJM of intent to transfer existing Capacity Interconnection 
Rights associated with a deactivating generation station; and (4) 
meet any other eligibility criteria set by the board.  
 A Tranche 1 application is required to include certain 
information and a fee, as provided in the bill.  
 At its discretion, the board may instruct an applicant on curing 
minor defects in a Tranche 1 application.  The board is required to 
evaluate each application based on the bid prices of the requested 
incentives, using certain criteria to guide its evaluation as outlined 
in the bill.  The bill permits the board to place an eligible project 
that does not receive an incentive award for Tranche 1 on a waiting 
list and consider the eligible project for an incentive award during a 
subsequent tranche or successor program.  
 
Tranche 1 Incentives 
 Under the bill, by no later than December 31, 2026, the board is 
required to approve:  (1) incentive awards totaling a collective 
minimum of $60 million in annual payments for eligible projects in 
Tranche 1, which projects are to total a collective minimum of 500 
MW AC; or (2) incentive awards for eligible projects that 
collectively have an installed capacity totaling at least 1,000 MW 
AC.  The board is permitted to approve all 1,000 MW in incentives 
in Tranche 1 or through awards in Tranche 1 and subsequent 
tranches, provided that incentives in subsequent tranches are 
awarded by no later than December 31, 2026.  An incentive award 
is to be conditioned upon a developer’s compliance with the board 
order determining the incentive award and with any conditions the 
board requires.  
 
Tranche 1 Board Orders 
 The bill outlines certain requirements for a board order issuing 
an incentive award to an eligible project, including that the board 
order is required to:  (1) define the eligible project receiving an 
incentive award and the eligible project’s installed capacity; (2) 
define the incentive award, including a payment schedule for the 
10- to 20-year award period of the incentive award, which term is to  3 
 
commence no earlier than the commercial operations date of an 
eligible project, and during which term an eligible project is to 
receive an annual incentive award on each anniversary of the first 
payment date; (3) determine the amount of funding to be allocated 
for payment of the incentive award beginning in the fiscal year in 
which the eligible project commences commercial operations; (4) 
include a participation fee as the board is permitted to require from 
the developer; (5) require, for an eligible project awarded an 
incentive, a pre-development security not to exceed $100,000 per 
megawatt and not to exceed in total $10,000,000; (6) outline the 
conditions under which the board may, in the event of a developer’s 
failure to operate an eligible project by the deadline stated in the 
board order or to meet deadlines included in the board order, revoke 
an incentive award or retain some or all of the pre-development 
security; (7) provide that receipt of an incentive award for an 
eligible project is to be contingent on achievement of baseline 
performance requirements, including, but not limited to, availability 
for dispatch in a minimum number of hours per year, as determined 
by the board. The board is permitted to use the PJM Equivalent 
Forced Outage Rate or another metric deemed appropriate by the 
board to measure energy storage availability.  The board order is to 
require that the developer report data for this purpose at regular 
intervals and is to provide for a reduction of an incentive award in 
proportion to the number of hours of required availability that is 
unmet by the eligible project; and (8) require that a developer 
provide additional information to the board during the term of the 
incentive award, as the board may require. The board may set 
additional requirements at its discretion, including, but not limited 
to, a requirement that the developer report major development and 
construction milestones to the board, maintain financial security 
throughout the term of the incentive award, or any other 
requirement the board determines necessary to ensure continued 
progress and operational viability of an eligible project.  
 
Future Procurement 
 If the board elects to extend the procurement of transmission-
scale energy storage through additional tranches, the board is 
permitted either to continue the program under which Tranche 1 
was conducted or to establish a successor program, as outlined in 
the bill.   
 If the board administers subsequent tranches under the same 
program as Tranche 1, the board is required to do so in a similar 
manner to how it administered Tranche 1, modifying as appropriate 
for each subsequent tranche:  (1) the amount of megawatts to be 
solicited; (2) the application requirements or eligibility criteria; (3) 
the timeline for an eligible project, including, but not limited to,  4 
 
application deadlines or the contract term; and (4) any other 
administrative modification the board deems appropriate.  
 If the board establishes a successor program, the board is to 
administer the successor program by adopting rules and regulations 
that implement the NJ SIP, provided that the final version of the NJ 
SIP complies with the requirements of the bill. The board is 
permitted to continue any rule, regulation, or policy used to 
administer Tranche 1 as the board determines necessary and 
appropriate to administer a successor program.   
 
Incentive Award Funding Mechanisms 
 The bill requires the board to fund incentive awards issued for 
Tranche 1, any subsequent tranches issued under the same program 
as Tranche 1, and a successor program through: (1) the societal 
benefits charge; (2) the “Global Warming Solutions Fund”; and (3) 
alternative sources of funding that are available to the board.  
Beginning in Fiscal Year 2028, the board is required to annually 
appropriate and allocate sufficient monies from these sources to 
fully fund incentive awards issued for Tranche 1 for eligible 
projects totaling a collective minimum of 500 MW AC. The 
funding mechanism of an incentive award issued for Tranche 1, or 
for any subsequent tranches issued under the same program as 
Tranche 1, is not to be changed without the consent of the 
developer.  
 
COMMITTEE AMENDMENTS : 
 The committee amended the bill to:   
 (1)  define “accredited capacity,” “base residual auction,” “energy 
storage capacity,” “Generation Interconnection Agreement,” “NJ SIP,” 
and “unforced capacity”; 
 (2)  clarify that the definition of “energy storage” means, in 
relevant part, a device that is capable of absorbing energy from a 
generation resource located behind the same point of interconnection 
as the device, rather than from a Distributed Energy Resource; 
 (3)  clarify that “energy storage program” includes, among other 
programs, NJ SIP, rather than NJ SIP’s replacement or successor in its 
final form; 
 (4)  change the award period of an incentive award from 15 years 
to 10-20 years; 
 (5)  clarify that the fixed series of annual payments that constitute 
an incentive award are to be based on the maximum useable installed 
capacity or the energy storage capacity of an eligible project, which 
energy storage capacity is to be measured in dollars-per-megawatt-
hour; 
 (6)  require incentive awards to be subject to any conditions 
imposed by the board, including, but not limited to, satisfactory up-
time performance metrics;  5 
 
 (7)  revise the definition of “transmission-scale energy storage 
program”; 
 (8)  remove the requirement for the board to conduct a ratepayer 
impact report prior to extending the procurement of transmission-scale 
energy storage in subsequent tranches or in a successor program; 
 (9)  permit an eligible project to participate in NJ SIP, to the extent 
that the energy storage program established by the bill is incorporated 
into NJ SIP; 
 (10)  require an eligible project to have entered, rather than 
completed, the PJM interconnection process; 
 (11)  require an eligible project to have a fully-executed 
Generation Interconnection Agreement through PJM, rather than a 
draft or fully-executed Large Generator Interconnection Agreement 
through PJM; have completed a Surplus Interconnection Study through 
PJM, rather than a System Impact Study or equivalent study; or have 
notified PJM of intent to transfer existing Capacity Interconnection 
Rights associated with a deactivating generation station; 
 (12)  remove the requirement for an eligible project to demonstrate 
evidence reasonably satisfactory to the board that the applicant 
controls all rights of way to the proposed point of interconnection; 
 (13)  remove the requirement for an eligible project to submit as-
built drawings of a transmission-scale energy storage system 
comprised of new equipment in its application for an incentive award; 
 (14)  clarify that an eligible project is to submit, in its application 
for an incentive award, evidence reasonably satisfactory to the board 
that the applicant has submitted all interconnection applications and 
initial application fees, rather than fees in general, that may be 
necessary to obtain permission from the appropriate electric public 
utility or grid operator to operate the transmission-scale energy storage 
system; 
 (15)  require an eligible project to adhere to any safety 
requirements, standards, or measures that the board deems appropriate 
in addition to nationally recognized minimum safety requirements; 
 (16)  require the board to evaluate an application for an incentive 
award based on the bid prices of the requested incentives instead of 
requiring the board to establish a scoring system to review an 
application; 
 (17)  permit the board, in its evaluation of an application for an 
incentive award, to compare bid prices based on the measure of the 
capacity of a transmission-scale energy storage system by the lesser of 
its installed capacity or its energy storage capacity divided by four 
hours or based on the expected accredited capacity of a transmission-
scale energy storage system; 
 (18)  permit the board, in its evaluation of an application for an 
incentive award, to consider project maturity, likelihood of success, 
and whether the installed capacity of the project has the associated  6 
 
Capacity Interconnection Rights through PJM, in addition to other 
factors outlined in the bill; 
 (19)  provides goal of either $60 million or 1,000 MW by 
December 31, 2026 in Tranche 1 and subsequent tranches; 
 (20)  clarify provisions concerning funding of incentive awards; 
 (21)  clarify that a board order issuing an incentive award in 
Tranche 1 or subsequent tranches is to allocate funding for the award 
beginning in the fiscal year in which the eligible project commences 
operations, rather than in the fiscal year beginning on July 1, 2028; 
 (22)  permit the board to require a participation fee from the 
developer of an eligible project; 
 (23)  require an eligible project to be available for dispatch in a 
minimum number of hours per year, as determined by the board, in 
order to receive an incentive award; 
 (24)  remove the requirement for the board to develop application 
requirements and eligibility criteria for Tranche 1 within 120 days of 
the bill’s effective date; 
 (25)  require the board to begin accepting applications for Tranche 
1 by no later than January 15, 2026 and to stop accepting applications 
for Tranche 1 within 60 days of the date on which the application 
period began; 
 (26)  require the board to evaluate and select projects to receive an 
award within 60 days of the closure of the Tranche 1 application 
period; 
 (27)  require the board to finalize and approve all incentive awards 
for Tranche 1 by no later than April 1, 2026; 
 (28)  remove the requirement for the board to allow an applicant to 
submit an early application for Tranche 1; 
 (29)  permit the board to establish a successor program by adopting 
rules and regulations to implement NJ SIP, provided that NJ SIP is 
consistent with the requirements of the bill, if the board determines 
that it requires additional energy storage to meet energy storage goals 
under current law; 
 (30)  remove the requirement that the successor program be funded 
through base rate recovery; 
 (31)  require an incentive award for energy storage procurement to 
be funded through revenues generated by the societal benefits charge, 
the “Global Warming Solutions Fund,” and other sources of funding 
available to the board; 
 (32)  require the board to appropriate and allocate sufficient 
monies from funding sources outlined in the bill, rather than a 
minimum of $60 million from the societal benefits charge, to fully 
fund the incentive awards issued by the board in Tranche 1; 
 (33)  remove the requirement that rules and regulations issued in 
Tranche 1 be similar to the board’s rules concerning Grid Supply 
projects for NJ SIP;  7 
 
 (34)  require the board to publish a notice of proposal containing 
certain proposed rules within 90 days of the bill’s effective date; 
 (35)  permit the board to adopt rules and regulations implementing 
NJ SIP as the successor program outlined by the bill in the same 
rulemaking proceeding in which the board proposes and adopts certain 
other rules and regulations outlined in the bill; 
 (36)  provide that the board is to allocate sufficient funding from 
the societal benefits charge to cover the remaining cost of fully 
funding incentive award payments, after accounting for funding 
allocated to this purpose from other sources; and 
 (37)  make technical corrections to the bill.