ENGROSSED SENATE 
BILL NO. 1520 	By: Murdock of the Senate 
 
  and 
 
  West (Kevin) of the House 
 
 
 
 
An Act relating to public buildings; amending 61 O.S. 
2021, Section 226, which relates to retainage 
provisions in certain contracts; specifying the 
retainage amount for specific contracts; and 
providing an effective date. 
 
 
 
BE IT ENACTED BY THE PEOPLE OF THE STATE OF OKLAHOMA: 
SECTION 1.     AMENDATORY     61 O.S. 2021, Section 226, is 
amended to read as follows: 
Section 226. A.  A construction contract may include a 
provision for the retainage of a portion of payment due.  Such 
retainage is not to exceed five percent (5%) of the amount of the 
payment due.  If a construction contract is subject t o a bond 
pursuant to this titl e and when the work of the contractor has been 
determined by the holder to be at least fifty percent (50%) 
complete, and with respect to t he balance of the work to be 
performed by the contractor, the retainage amount shall be two and 
one-half percent (2.5%) of the original contract amount. 
B.  A subcontract shall include a provision for the retainage of 
a portion of payment due.  Such retain age shall not exceed five 
percent (5%) of the amount of the payment due.  If a construct ion   
 
ENGR. S. B. NO. 1520 	Page 2  1 
2 
3 
4 
5 
6 
7 
8 
9 
10 
11 
12 
13 
14 
15 
16 
17 
18 
19 
20 
21 
22 
23 
24 
  
subcontract is subject to a bond pursuant to this title and when the 
work of the subcontractor has been determined by the holder to be at 
least fifty percent (50%) complete, and with respect to the balance 
of the work to be performed by the subcontract or, the retainage 
amount shall be two and one-half percent (2.5%) of the original 
subcontract amount. 
C.  No later than twenty -one (21) calendar days after a 
certificate of substantial completion is issued for the project or 
separate usable phase of the pr oject and upon adequate perfor mance 
of the prime contractor and with approval of any applicable surety, 
retainage shall be released by the owner to the prime contractor 
less an amount no greater than one hundr ed fifty percent (150%) of 
the estimated costs to correct any incomplete or d efective work as 
identified, itemized, and attached to the certificate of substantial 
completion.  All remaining funds shall be released a s each 
deficiency is satisfactorily compl eted.  The prime contractor shall 
release within ten (10) calendar days of re ceipt the share of those 
funds that have been withheld from other entities.  All other 
entities shall release within seven (7) calendar da ys of receipt the 
share of those funds th at have been withheld from other entities. 
SECTION 2.  This act shall become effective November 1, 2022.   
 
ENGR. S. B. NO. 1520 	Page 3  1 
2 
3 
4 
5 
6 
7 
8 
9 
10 
11 
12 
13 
14 
15 
16 
17 
18 
19 
20 
21 
22 
23 
24 
  
Passed the Senate the 14th day of March, 2022. 
 
 
  