Rhode Island 2025 2025 Regular Session

Rhode Island Senate Bill S0981 Introduced / Bill

Filed 04/16/2025

                     
 
 
 
2025 -- S 0981 
======== 
LC002703 
======== 
S T A T E O F R H O D E I S L A N D 
IN GENERAL ASSEMBLY 
JANUARY SESSION, A.D. 2025 
____________ 
 
A N   A C T 
RELATING TO STATE AFFAIRS AND GOVERNMENT -- ENERGY FACILITY SITING 
ACT 
Introduced By: Senators Zurier, and Britto 
Date Introduced: April 16, 2025 
Referred To: Senate Housing & Municipal Government 
 
 
It is enacted by the General Assembly as follows: 
SECTION 1. Section 42-98-1.1 of the General Laws in Chapter 42-98 entitled "Energy 1 
Facility Siting Act" is hereby amended to read as follows: 2 
42-98-1.1. Capital city underground utility initiative. 3 
(a) Legislative Findings 4 
(1) In 2004, the cities of Providence and East Providence exercised their rights under this 5 
section as it was originally enacted in 2004, to forego receipt of a customer credit owed to The 6 
Narragansett Electric Company’s (“company”) electric customers residing in those communities, 7 
opting instead to use those communities’ allocated share of the customer credit to fund a portion of 8 
the cost of constructing the “Underground Alignment” of a portion of the E-183 115 kilovolt 9 
electric transmission line as defined in the Settlement Agreement approved by the Board on May 10 
28, 2004 in Docket No. SB-2003-01. 11 
(2) The Settlement Agreement approved by the Board in Docket No. SB-2003-01 provided, 12 
in part, that the parties to the Settlement Agreement would work to reach an agreement on a route 13 
for the Underground Alignment while the Rhode Island attorney general would work to secure 14 
funding for construction of the Underground Alignment. The Settlement Agreement provided 15 
further that if the Underground Alignment was found not to be feasible for reasons including cost 16 
or constructability, other identified alignments of the relevant portion of the E-183 electric 17 
transmission line would be considered in order of preference. 18   
 
 
LC002703 - Page 2 of 5 
(3) On January 17, 2018, the Board issued an Order determining that the Underground 1 
Alignment and the “Bridge Alignment North,” as defined in the Settlement Agreement, were not 2 
feasible, and approving construction of the “Bridge Alignment South,” as defined in the Settlement 3 
Agreement. 4 
(4) Following appellate review pursuant to § 42-98-12, on June 17, 2022, in Case No. 2018-5 
40-M.P., the Supreme Court of Rhode Island upheld the Board’s January 17, 2018 Order. 6 
(5) Due to the foregoing events and decisions, as of 2025, no portion of the E-183 7 
transmission line has been constructed underground and no part of the customer credit referred to 8 
in subsection (a)(1) of this section has been returned to electric customers in the cities of Providence 9 
and East Providence. 10 
(6) The customer credit that arose from the company’s base distribution rate case in 2004, 11 
which the cities of Providence and East Providence did not accept on behalf of their ratepayers, has 12 
been segregated and has accrued interest for the benefit of Providence and East Providence electric 13 
distribution customers. 14 
(7) The cities of Providence and East Providence desire to have portions of the E-183 15 
electric transmission line located underground and require legislative authorization for funding 16 
mechanisms to pay the incremental cost, over and above the estimated cost of the Bridge Alignment 17 
South, of the burial of portions of the E-183 electric transmission line along the southern shore of 18 
Fox and India Points that are south of Interstate 195 and in East Providence on the east side of the 19 
Seekonk River (the “Bridge Alignment South – Hybrid”). 20 
(b) The public utilities commission shall permit the city of Providence or and the city of 21 
East Providence, upon petition by a duly authorized representative of such municipality, to forego 22 
some or apply all of the respective municipality’s pro rata share of the refund accruing to the 23 
ratepayers of the respective municipality as computed under section 11(c) of the 3rd Third 24 
Amended Settlement Agreement in Docket No. 2930; provided, however, that the city council of 25 
each petitioning ratifies such action by passage of a resolution. 26 
(b) The public utilities commission shall permit, upon petition by the attorney general, for 27 
the use of up to two million dollars ($2,000,000) from Narragansett Electric Company’s Storm 28 
Contingency Fund for purposes of under grounding that portion of the E-183 transmission line 29 
under consideration in Energy Facility Siting Board Docket 2003-01. 30 
(c) Narragansett Electric Company shall be required to apply to the regional grid operator 31 
or its successor organization for approval to charge New England regional network service 32 
customers for the capital costs associated with the construction of Phase II overhead configuration 33 
labeled the “North Bridge Alignment” as defined by the Settlement Agreement that was approved 34   
 
 
LC002703 - Page 3 of 5 
by the Energy Facility Siting Board in Docket 2003-1. 1 
(d) The Narragansett Electric Company (“company”) shall be authorized to proceed with 2 
the construction of the underground alignment of the E-183 line referenced in the Settlement 3 
Agreement that was approved by the Energy Facility Siting Board in Docket 2003-01 4 
(“Underground alignment”), including the acquisition of any property rights needed to implement 5 
the underground alignment, plus accrued interest, toward the incremental cost of constructing the 6 
Bridge Alignment South - Hybrid.  7 
(c) Notwithstanding the Supreme Court’s June 17, 2022 affirmation of the Board’s January 8 
17, 2018 Order, the Board shall have jurisdiction to consider a modification to the license to include 9 
burial of a portion of the E-183 electric transmission line without having to consider whether the 10 
requirements of §§ 42-98-11(b)(1) and (b)(2) have been met. Following approval by the Board of 11 
a modified license, the company shall be authorized to proceed with the construction of the 12 
modification which will include consideration of the Bridge Alignment South- Hybrid, subject to 13 
the passage of resolutions by both city councils of the cities of Providence and East Providence 14 
agreeing that any incremental costs above existing funding made available pursuant to subsection 15 
(b) of this section may be included in electric rates of electric customers in those cities. Such 16 
resolutions must be delivered to the public utilities commission no later than July 1, 2009. 17 
Notwithstanding the terms of the Settlement, to 2026. To the extent the actual costs for the 18 
underground alignment Bridge Alignment South - Hybrid exceed the funding obtained for the 19 
project pursuant to this section and from federal and any other sources, the company is authorized 20 
to include the incremental costs above those funding levels in its distribution rate base and reflect 21 
the revenue requirement, including interest, any resulting tax adjustments, and billing system 22 
modification costs in rates charged to the electric distribution customers within the cities of 23 
Providence and East Providence in a manner approved by the public utilities commission, subject 24 
to the timely passage and delivery of the resolution specified above. Such rate adjustment shall be 25 
made within six (6) months from project completion, applying the same ratemaking principles as 26 
ordinarily applied to distribution capital projects when they are allowed in its distribution rate base 27 
by the public utilities commission. After completion of the underground alignment, the public 28 
utilities commission shall conduct a review of costs incurred to construct the underground 29 
alignment in order to verify that the company’s calculation and implementation of rates are in 30 
compliance with this section; provided, further, the auditor general shall perform a performance 31 
audit of state costs. billed as a per kilowatt hour charge designed to recover the full incremental 32 
cost of the Bridge Alignment South – Hybrid, including interest, any resulting tax adjustments, 33 
and billing system modification costs, over a period not less than three (3) years subject to 34   
 
 
LC002703 - Page 4 of 5 
reconciliation of the final cost compared to billed revenues. The incremental costs of 1 
undergrounding net of the customer credit referenced in subsection (b) of this section will be 2 
allocated to each city based on the actual cost of the underground portions in each respective city. 3 
The company shall book the revenues collected through the rate adjustment for such incremental 4 
underground construction costs as contribution in aid of construction in the appropriate 5 
transmission accounts.  6 
(d) If the cities of Providence and East Providence obtain any other source of funding that 7 
can be used to offset the cost of burial of the E-183 electric transmission line, that source of funding 8 
shall offset the amount of the rate adjustment charged to the electric ratepayers in the cities of 9 
Providence and/or East Providence under subsection (c) of this section as defined by the source of 10 
funding. 11 
(e) If the underground alignment goes forward, the company shall retain such portions of 12 
the properties acquired to implement the underground alignment as may be necessary and prudent, 13 
and shall transfer any remaining portions of said properties to the redevelopment authority of the 14 
city in which the property is located after the completion of the project, at the city’s request and at 15 
no additional cost to the city conditions precedent to the construction of the Bridge Alignment 16 
South - Hybrid are satisfied, the cities of Providence and East Providence shall acquire and convey 17 
to the company, at no cost to the company, all property rights needed in the company’s reasonable 18 
judgment for the construction, operation, and maintenance of the relevant segment of E-183. Any 19 
easements no longer being used by the company for utility purposes after the underground 20 
alignment Bridge Alignment South-Hybrid is completed also shall be transferred to the city in 21 
which such property is located after the completion of the project, at the city’s request and at no 22 
additional cost to the city. If there is any dispute about the extent to which property or easements 23 
are needed and therefore should not be transferred, the public utilities commission shall decide the 24 
issue upon petition by the affected city. 25 
SECTION 2. This act shall take effect upon passage. 26 
======== 
LC002703 
========  
 
 
LC002703 - Page 5 of 5 
EXPLANATION 
BY THE LEGISLATIVE COUNCIL 
OF 
A N   A C T 
RELATING TO STATE AFFAIRS AND GOVERNMENT -- ENERGY FACILITY SITING 
ACT 
***
This act would allow for measures to advance the undergrounding of certain utility cables 1 
and to have the same funded through utility rate increases to the cities of Providence and East 2 
Providence. 3 
This act would take effect upon passage. 4 
======== 
LC002703 
========