Texas 2011 82nd Regular

Texas House Bill HB1390 Comm Sub / Bill

                    82R17798 PMO-F
 By: Deshotel, Bohac H.B. No. 1390
 Substitute the following for H.B. No. 1390:
 By:  Quintanilla C.S.H.B. No. 1390


 A BILL TO BE ENTITLED
 AN ACT
 relating to retainage under certain construction contracts.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  Section 53.053(e), Property Code, is amended to
 read as follows:
 (e)  A claim for retainage accrues on the last day of the
 month in which all work called for by the contract between the owner
 and the original contractor has been completed, finally settled,
 terminated, or abandoned.
 SECTION 2.  Section 53.056(d), Property Code, is amended to
 read as follows:
 (d)  Except as provided by Section 53.057, to [To] authorize
 the owner to withhold funds under Subchapter D, the notice to the
 owner must state that if the claim remains unpaid, the owner may be
 personally liable and the owner's property may be subjected to a
 lien unless:
 (1)  the owner withholds payments from the contractor
 for payment of the claim; or
 (2)  the claim is otherwise paid or settled.
 SECTION 3.  Section 53.057, Property Code, is amended to
 read as follows:
 Sec. 53.057.  DERIVATIVE CLAIMANT: NOTICE FOR [CONTRACTUAL]
 RETAINAGE CLAIM.  (a)  For the portion of a retainage claim not in
 excess of the amount of the required retainage under Section
 53.101, a [A] claimant may give notice under this section instead of
 or in addition to notice under Section 53.056 or 53.252 if the
 claimant is to labor, furnish labor or materials, or specially
 fabricate materials, or has labored, furnished labor or materials,
 or specially fabricated materials, under an agreement with an
 original contractor or a subcontractor providing for retainage.
 (b)  The claimant must give notice that the claimant may have
 a lien claim for retainage to the owner or reputed owner [notice of
 the retainage agreement] not later than the earliest of:
 (1)  the 15th day of the second month following the date
 the claimant completed the work required under the claimant's
 contract with the original contractor or subcontractor;
 (2)  the 25th day after the date the work under the
 original contract is completed, provided that the owner, if
 required, gave notice under Section 53.106 or 53.108 to the
 claimant;
 (3)  the 25th day after the date the original contract
 is terminated, provided that the owner, if required, gave notice
 under Section 53.107 to the claimant; or
 (4)  the 25th day after the date the original
 contractor abandons performance under the original contract,
 provided that the owner, if required, gave notice under Section
 53.107 to the claimant [the delivery of materials or the
 performance of labor by the claimant that first occurs after the
 claimant has agreed to the contractual retainage. If the agreement
 is with a subcontractor, the claimant must also give notice within
 that time to the original contractor].
 (c)  [The notice must contain:
 [(1)  the sum to be retained;
 [(2)  the due date or dates, if known; and
 [(3)     a general indication of the nature of the
 agreement.
 [(d)]  The notice must be sent by registered or certified
 mail to the last known business or residence address of the owner or
 reputed owner or the original contractor, as applicable.
 (d) [(e)]  If a claimant gives notice under this section [and
 Section 53.055 or, if the claim relates to a residential
 construction project, under this section and Section 53.252], the
 claimant is not required to give any other notice as to the
 retainage before the date the notice under Section 53.055 is
 required.
 SECTION 4.  Section 53.081(c), Property Code, is amended to
 read as follows:
 (c)  If notice is sent under Section 53.057, the owner may
 withhold funds immediately on receipt of the notice.  The owner may
 withhold funds by retaining funds under Subchapter E for the period
 required by Section 53.082 [a copy of the claimant's affidavit
 prepared in accordance with Sections 53.052 through 53.055].
 SECTION 5.  Section 53.103, Property Code, is amended to
 read as follows:
 Sec. 53.103.  LIEN ON RETAINED FUNDS. A claimant has a lien
 on the retained funds if the claimant:
 (1)  sends the notices required by this chapter in the
 time and manner required; and
 (2)  files an affidavit claiming a lien not later than
 the [30th day after the] earlier of [the date]:
 (A)  the 60th day after the earliest of:
 (i)  the date the work under the original
 contract is completed, provided that the owner, if required, gave
 notice under Section 53.106 or 53.108 to the claimant;
 (ii)  the date the original contract is
 terminated, provided that the owner, if required, gave notice under
 Section 53.107 to the claimant; or
 (iii)  the date the original contractor
 abandons performance under the original contract, provided that the
 owner, if required, gave notice under Section 53.107 to the
 claimant; or
 (B)  the last day of the period provided under
 Section 53.052 [work is completed;
 [(B)  the original contract is terminated; or
 [(C)     the original contractor abandons
 performance under the original contract].
 SECTION 6.  Section 53.106, Property Code, is amended to
 read as follows:
 Sec. 53.106.  AFFIDAVIT OF COMPLETION. (a)  An owner may
 file with the county clerk of the county in which the property is
 located an affidavit of completion. The affidavit must contain:
 (1)  the name and address of the owner;
 (2)  the name and address of the original contractor;
 (3)  a description, legally sufficient for
 identification, of the real property on which the improvements are
 located;
 (4)  a description of the improvements furnished under
 the original contract;
 (5)  a statement that the improvements under the
 original contract have been completed and the date of completion;
 and
 (6)  a conspicuous statement that a claimant may not
 have a lien on retained funds unless the claimant:
 (A)  complies with the notice requirement under
 Section 53.057 not later than the earlier of:
 (i)  the 15th day of the second month
 following the date the claimant completed the work required under
 the claimant's contract with the original contractor or
 subcontractor; or
 (ii)  the 25th day after the date the work
 under the original contract is completed; and
 (B)  files an [the] affidavit claiming a lien not
 later than the 60th [30th] day after the date the work under the
 original contract is completed [of completion].
 (b)  A copy of the affidavit must be sent by certified or
 registered mail to the original contractor not later than the date
 the affidavit is filed and to each claimant who sends a notice of
 lien liability to the owner under Section 53.056, 53.057, 53.058,
 53.252, or 53.253 not later than the date the affidavit is filed or
 the fifth [10th] day after the date the owner receives the notice of
 lien liability, whichever is later.
 (c)  A copy of the affidavit must also be sent to each person
 who furnishes labor or materials for the property and who furnishes
 the owner with a written request for the copy. The owner must
 furnish the copy to the person not later than the date the affidavit
 is filed or the fifth [10th] day after the date the request is
 received, whichever is later.
 (d)  Except as provided by this subsection, an affidavit
 filed under this section on or before the fifth [10th] day after the
 date of completion of the improvements is prima facie evidence of
 the date the work under the original contract is completed for
 purposes of this subchapter and Section 53.057. If the affidavit is
 filed after the fifth [10th] day after the date of completion, the
 date of completion for purposes of this subchapter and Section
 53.057 is the date the affidavit is filed. This subsection does not
 apply to a person to whom the affidavit was not sent as required by
 this section.
 SECTION 7.  Sections 53.107(a), (b), (c), and (d), Property
 Code, are amended to read as follows:
 (a)  Not later than the fifth [10th] day after the date an
 original contract is terminated or the original contractor abandons
 performance under the original contract, the owner shall give
 notice to each subcontractor who, before the date of termination or
 abandonment, has:
 (1)  given notice to the owner as provided by Section
 53.056, 53.057, or 53.058; or
 (2)  sent to the owner by certified or registered mail a
 written request for notice of termination or abandonment.
 (b)  The notice must contain:
 (1)  the name and address of the owner;
 (2)  the name and address of the original contractor;
 (3)  a description, legally sufficient for
 identification, of the real property on which the improvements are
 located;
 (4)  a general description of the improvements agreed
 to be furnished under the original contract;
 (5)  a statement that the original contract has been
 terminated or that performance under the contract has been
 abandoned;
 (6)  the date of the termination or abandonment; and
 (7)  a conspicuous statement that a claimant may not
 have a lien on the retained funds unless the claimant:
 (A)  complies with the notice requirement in
 Section 53.057 not later than the earlier of:
 (i)  the 15th day of the second month
 following the date the claimant completed the work required under
 the claimant's contract with the original contractor or
 subcontractor; or
 (ii)  the 25th day after the date the
 original contract is terminated or abandoned; and
 (B)  files an affidavit claiming a lien not later
 than the 60th [30th] day after the date of the termination or
 abandonment.
 (c)  A notice sent in compliance with this section on or
 before the fifth [10th] day after the date of termination or
 abandonment is prima facie evidence of the date the original
 contract was terminated or work was abandoned for purposes of this
 subchapter.
 (d)  A subcontractor to whom an owner fails to send notice
 under this section is not required to comply with Section 53.057 to
 claim retainage and may claim a lien by filing a lien affidavit as
 prescribed by Section 53.052 [who fails to file a lien affidavit in
 the time prescribed by Section 53.103(2) has a lien to the extent
 authorized under this subchapter if:
 [(1)     the subcontractor otherwise complies with this
 chapter; and
 [(2)     the owner did not provide the subcontractor
 notice as required by this section].
 SECTION 8.  Subchapter E, Chapter 53, Property Code, is
 amended by adding Section 53.108 to read as follows:
 Sec. 53.108.  NOTICE OF COMPLETION TO SECURE RETAINAGE
 CLAIM. (a)  Not later than the fifth day after the date of
 completion, an owner shall send by certified mail, return receipt
 requested, or registered mail a notice of completion to:
 (1)  the original contractor;
 (2)  any person who provides a notice under Section
 53.056, 53.057, 53.058, 53.252, or 53.253; and
 (3)  any person who furnished labor or provided
 materials for the improvement and requests a copy of the notice of
 completion.
 (b)  The notice must contain:
 (1)  the name and address of the owner;
 (2)  the name and address of the original contractor;
 (3)  a description, legally sufficient for
 identification, of the real property on which the improvements are
 located;
 (4)  a description of the improvements furnished under
 the original contract;
 (5)  a statement that the improvements under the
 original contract have been completed; and
 (6)  the date of completion.
 (c)  A notice sent in compliance with this section is prima
 facie evidence under Sections 53.053(e) and 53.057 of the date the
 work under the original contract was completed.
 (d)  An owner who sends a copy of an affidavit of completion
 as prescribed by Section 53.106 satisfies the requirements of this
 section.
 (e)  A person described by Subsection (a) to whom an owner
 fails to send notice under this section is not required to comply
 with Section 53.057 to claim contractual retainage and may claim a
 lien by filing a lien affidavit as prescribed by Section 53.052.
 SECTION 9.  Sections 53.159(a), (b), and (e), Property Code,
 are amended to read as follows:
 (a)  An owner, on written request, shall furnish the
 following information within a reasonable time, but not later than
 the 10th day after the date the request is received, to any person
 furnishing labor or materials for the project:
 (1)  a description of the real property being improved
 legally sufficient to identify it;
 (2)  whether there is a surety bond and if so, the name
 and last known address of the surety and a copy of the bond; [and]
 (3)  whether there are any prior recorded liens or
 security interests on the real property being improved and if so,
 the name and address of the person having the lien or security
 interest; and
 (4)  the date on which the original contract for the
 project was executed.
 (b)  An original contractor, on written request by a person
 who furnished work under the original contract, shall furnish to
 the person the following information within a reasonable time, but
 not later than the 10th day after the date the request is received:
 (1)  the name and last known address of the person to
 whom the original contractor furnished labor or materials for the
 construction project; [and]
 (2)  whether the original contractor has furnished or
 has been furnished a payment bond for any of the work on the
 construction project and if so, the name and last known address of
 the surety and a copy of the bond; and
 (3)  the date on which the original contract for the
 project was executed.
 (e)  If a person from whom information is requested does not
 have a direct contractual relationship on the project with the
 person requesting the information, the person from whom information
 is requested, other than a claimant requested to furnish
 information under Subsection (d), may require payment of the actual
 costs, not to exceed $25, in furnishing the requested information.
 A subcontractor who does not receive information requested under
 Subsection (a)(4) within the period prescribed by Subsection (a) is
 not required to comply with Section 53.057 and may perfect a lien
 for retainage by filing a lien affidavit under Section 53.052.
 SECTION 10.  Section 53.160(b), Property Code, is amended to
 read as follows:
 (b)  The grounds for objecting to the validity or
 enforceability of the claim or lien for purposes of the motion are
 limited to the following:
 (1)  notice of claim was not furnished to the owner or
 original contractor as required by Section 53.056, 53.057, 53.058,
 53.252, or 53.253;
 (2)  an affidavit claiming a lien failed to comply with
 Section 53.054 or was not filed as required by Section 53.052;
 (3)  notice of the filed affidavit was not furnished to
 the owner or original contractor as required by Section 53.055;
 (4)  the deadlines for perfecting a lien claim for
 retainage under this chapter have expired and the owner complied
 with the requirements of Section 53.101 and paid the retainage and
 all other funds owed to the original contractor before:
 (A)  the claimant perfected the lien claim; and
 (B)  the owner received a notice of the claim as
 required by this chapter;
 (5)  all funds subject to the notice of a claim to the
 owner and a notice regarding the [perfection of a claim against the
 statutory] retainage have been deposited in the registry of the
 court and the owner has no additional liability to the claimant;
 (6)  when the lien affidavit was filed on homestead
 property:
 (A)  no contract was executed or filed as required
 by Section 53.254;
 (B)  the affidavit claiming a lien failed to
 contain the notice as required by Section 53.254; or
 (C)  the notice of the claim failed to include the
 statement required by Section 53.254; and
 (7)  the claimant executed a valid and enforceable
 waiver or release of the claim or lien claimed in the affidavit.
 SECTION 11.  Chapter 53, Property Code, as amended by this
 Act, applies only to a lien claim for labor or materials furnished
 under a subcontract where the original contract was entered into on
 or after the effective date of this Act.  A lien claim for labor or
 materials furnished under a subcontract where the original contract
 was entered into before the effective date of this Act is governed
 by the law in effect immediately before the effective date of this
 Act, and that law is continued in effect for that purpose.
 SECTION 12.  This Act takes effect September 1, 2011.