Texas 2021 87th Regular

Texas House Bill HB1505 Introduced / Bill

Filed 03/03/2021

                    87R8812 BRG-F
 By: Paddie H.B. No. 1505


 A BILL TO BE ENTITLED
 AN ACT
 relating to attachments for broadband service on utility poles
 owned by an electric cooperative.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  The heading to Chapter 252, Utilities Code, is
 amended to read as follows:
 CHAPTER 252. CABLE ATTACHMENTS TO ELECTRIC COOPERATIVE'S
 DISTRIBUTION POLES
 SECTION 2.  Title 5, Utilities Code, is amended by adding
 Chapter 253 to read as follows:
 CHAPTER 253. BROADBAND ATTACHMENTS TO ELECTRIC COOPERATIVE'S
 DISTRIBUTION POLES
 SUBCHAPTER A. GENERAL PROVISIONS
 Sec. 253.0001.  DEFINITIONS. In this chapter:
 (1)  "Broadband provider" means an entity that provides
 broadband service either directly or through an affiliate that uses
 the entity's communications facilities, regardless of whether the
 entity:
 (A)  provides additional services in addition to
 broadband service; or
 (B)  uses its facilities in whole or in part to
 provide broadband service.
 (2)  "Broadband service" means Internet service with
 the capability of providing:
 (A)  a download speed of 25 megabits per second or
 faster; and
 (B)  an upload speed of three megabits per second
 or faster.
 (3)  "Communications space" means the lower usable
 space on a pole that is typically reserved for low-voltage
 communications equipment.
 (4)  "Large order application" means an application
 submitted by a broadband provider under this subchapter requesting
 access to attach pole attachments to a number of poles:
 (A)  that exceeds the lesser of 300 poles or a
 number equal to 0.5 percent of the electric cooperative's poles;
 and
 (B)  that is not more than the lesser of 3,000
 poles or a number equal to five percent of the electric
 cooperative's poles.
 (5)  "Pole" has the meaning assigned by Section
 252.001.
 (6)  "Pole attachment" means an affixture of cables,
 strands, wires, and associated equipment used in the provision of a
 broadband provider's services attached to a pole directly or
 indirectly or placed in a right-of-way owned or controlled by an
 electric cooperative.
 (7)  "Simple make-ready activities" means work to
 accommodate a new pole attachment on a pole and includes work where
 existing attachments in the communications space are moved without
 any reasonable expectation of:
 (A)  service outage or facility damage;
 (B)  a need to splice an existing communications
 attachment; or
 (C)  a need to relocate an existing wireless
 attachment.
 Sec. 253.0002.  APPLICABILITY AND CONSTRUCTION OF CHAPTER.
 (a)  This chapter applies to a pole attachment affixed by a
 broadband provider to a pole owned and controlled by an electric
 cooperative. This chapter does not apply to a pole attachment
 regulated by the Federal Communications Commission under 47 U.S.C.
 Section 224.
 (b)  This chapter does not abrogate or affect a right or
 obligation of a party to a pole attachment contract entered into by
 a broadband provider and an electric cooperative before September
 1, 2021.
 (c)  A broadband provider that attaches a pole attachment to
 a pole owned by an electric cooperative under the terms of this
 chapter is subject to Sections 252.006, 252.007, and 252.008 in the
 same manner as if the broadband provider were a cable operator.
 (d)  This chapter does not limit a right of a party to a pole
 attachment contract to request modification, amendment, or renewal
 of such contract to conform it to the provisions of this chapter.
 Sec. 253.0003.  NO STATE CERTIFICATION; NO REGULATORY
 AUTHORITY.  (a)  This chapter does not constitute state
 certification under 47 U.S.C. Section 224. If a court determines
 that this chapter constitutes certification under that section,
 this chapter is not enforceable and has no effect.
 (b)  This chapter may not be construed to subject an electric
 cooperative to regulation by the Federal Communications Commission
 under 47 U.S.C. Section 224.
 (c)  This chapter does not authorize a department, agency, or
 political subdivision of this state to exercise enforcement or
 regulatory authority over attachments to electric cooperative
 poles.
 Sec. 253.0004.  CONSTRUCTION OF TERMS AND PHRASES.
 Technical terms and phrases in this chapter, other than those
 defined by Section 253.0001, shall be construed using the term's or
 phrase's usual and customary meanings in the electric and broadband
 industries.
 Sec. 253.0005.  COST-BASED NON-RECURRING CHARGES.
 Non-recurring charges authorized by this chapter must be
 cost-based.
 SUBCHAPTER B. APPLICATION FOR ACCESS TO POLES
 Sec. 253.0101.  APPLICATION FOR POLE ACCESS. (a)  A
 broadband provider may not access a pole owned by an electric
 cooperative for the purpose of placing a pole attachment unless the
 provider applies for that access in accordance with this
 subchapter.
 (b)  An electric cooperative shall:
 (1)  establish a timeline for a broadband provider to
 apply for and obtain access to poles for placing a pole attachment
 under this chapter; and
 (2)  make available an explanation of the information
 reasonably required for an application for access to poles for
 placing a pole attachment under this chapter to be considered
 complete.
 Sec. 253.0102.  REVIEW OF APPLICATION FOR COMPLETENESS. (a)
 An electric cooperative shall review an application for
 completeness before the cooperative reviews the application on the
 merits.
 (b)  An electric cooperative shall notify an applicant
 whether an application is complete not later than:
 (1)  the 10th business day after the date the
 cooperative receives the application;
 (2)  the 25th business day after the date the
 cooperative receives a large order application;
 (3)  the fifth business day after the date the
 cooperative receives a resubmitted application; or
 (4)  the 20th business day after the date the
 cooperative receives a resubmitted large order application.
 Sec. 253.0103.  TREATMENT OF MULTIPLE APPLICATIONS BY SAME
 APPLICANT. For purposes of this chapter, an electric cooperative
 may treat as a single application for pole access an application the
 cooperative receives from the same applicant before the 31st day
 after the cooperative receives that applicant's most recent
 previous application.
 Sec. 253.0104.  GRANT OR DENIAL OF APPLICATION. (a)  Except
 as provided by Sections 253.0204 and 253.0302, an electric
 cooperative shall grant or deny an application for pole access
 under this chapter and provide to the applicant a survey of the
 poles affected by the application not later than:
 (1)  the 45th day after the date the cooperative
 receives a complete application; or
 (2)  the 60th day after the date the cooperative
 receives a complete large order application.
 (b)  An electric cooperative may deny an application for
 access to a pole under this chapter if:
 (1)  generally applicable safety, reliability, or
 engineering requirements established for the protection of public
 health, safety, or welfare prevent granting access; or
 (2)  the pole lacks sufficient capacity.
 (c)  Notwithstanding Subsection (b)(1), an electric
 cooperative may not deny access to a pole if the capacity, safety,
 reliability, or engineering consideration may be remedied by
 rearranging, expanding, replacing, or otherwise safely
 reengineering the pole or pole attachments through make-ready
 activities.
 (d)  An electric cooperative's denial of an application to
 access a pole under this chapter must:
 (1)  be specific;
 (2)  include all relevant evidence and information that
 supports the denial; and
 (3)  explain how the evidence and information relate to
 the denial.
 Sec. 253.0105.  DEADLINES NOT APPLICABLE TO CERTAIN
 APPLICATIONS. (a)  An electric cooperative is not required to meet
 the deadlines under this subchapter for an application for pole
 access to place pole attachments on more than 3,000 poles or more
 than 5 percent of the electric cooperative's poles.
 (b)  An electric cooperative may not act under Subsection (a)
 to delay an application unreasonably and shall negotiate in good
 faith with the applicant regarding the time required to fulfill the
 cooperative's duties.
 SUBCHAPTER C. MAKE-READY ACTIVITIES
 Sec. 253.0201.  DEADLINES FOR MAKE-READY ACTIVITIES.  (a)
 Not later than the 15th day after the date an electric cooperative
 grants an application, the electric cooperative shall provide to
 the broadband provider a detailed and itemized estimate of the
 expected costs of all necessary make-ready activities.
 (b)  An electric cooperative shall complete all make-ready
 activities in the communications space and send a detailed,
 itemized final invoice to the broadband provider not later than:
 (1)  the 30th day after the date the electric
 cooperative receives payment of the estimated make-ready cost from
 the broadband provider; or
 (2)  for a large order application, the 75th day after
 the date the electric cooperative receives payment of the estimated
 make-ready cost from the broadband provider.
 (c)  An electric cooperative shall complete all make-ready
 activities above the communications space, including pole
 replacements, and send a detailed, itemized final invoice to the
 broadband provider not later than:
 (1)  the 90th day after the date the electric
 cooperative receives payment of the estimated make-ready cost from
 the broadband provider; or
 (2)  for a large order application, the 135th day after
 the date the electric cooperative receives payment of the estimated
 make-ready cost from the broadband provider.
 Sec. 253.0202.  EXTENSION OF MAKE-READY ACTIVITIES
 DEADLINE. (a)  An electric cooperative may extend a deadline under
 Section 253.0201(b) or (c) for a cause that renders the deadline
 infeasible. A cooperative that chooses to extend a deadline shall:
 (1)  immediately and in writing notify the broadband
 provider and each person with an affected existing pole attachment
 about the delay; and
 (2)  identify the affected poles and provide a detailed
 explanation of the reason for the delay and an estimated new
 completion date to the broadband provider and each person with an
 affected existing pole attachment.
 (b)  An electric cooperative may not extend a deadline under
 this section for a period longer than is necessary to complete
 make-ready activities on affected poles.
 (c)  An electric cooperative may not extend a deadline under
 this section because of a preexisting violation on an affected pole
 caused by a person other than the broadband provider. The
 cooperative shall correct a preexisting violation as part of the
 make-ready process and before the applicable deadline at the cost
 of the responsible person.
 (d)  An electric cooperative shall resume make-ready
 activities without discrimination when the cooperative returns to
 routine operations.
 Sec. 253.0203.  DEADLINES NOT APPLICABLE TO CERTAIN
 APPLICATIONS. (a)  An electric cooperative is not required to meet
 the deadlines under this subchapter for an application to place
 pole attachments on more than 3,000 poles or more than five percent
 of the electric cooperative's poles.
 (b)  An electric cooperative may not act under Subsection (a)
 to delay an application unreasonably and shall negotiate in good
 faith with the applicant regarding the time required to fulfill the
 cooperative's duties.
 Sec. 253.0204.  CONTRACTORS FOR MAKE-READY ACTIVITIES.  (a)
 A broadband provider may hire a contractor approved by the electric
 cooperative to complete a survey under Section 253.0104 or perform
 a make-ready activity under this subchapter that is not timely
 completed by the electric cooperative or a person with an existing
 pole attachment.
 (b)  The broadband provider shall provide reasonably timely
 notice to the electric cooperative and each person with an existing
 pole attachment on an affected pole that the provider intends to
 hire a contractor as authorized by Subsection (a).
 (c)  The broadband provider shall provide reasonably timely
 notice to the electric cooperative and each person with an existing
 pole attachment on an affected pole of the contractor's completion
 of the make-ready activities.
 (d)  An electric cooperative may not act under Subsection (a)
 unreasonably to withhold approval of a contractor for purposes of
 this section.
 (e)  Not later than the 90th day after the date a broadband
 provider provides notice as provided by Subsection (c), the
 cooperative or person may inspect the make-ready work.
 (f)  Not later than the 14th day after the date that an
 electric cooperative or person completes an inspection under
 Subsection (e), the cooperative or person may notify the broadband
 provider of any damage or code violations caused by such work. The
 notice must include specific documentation.
 (g)  The electric cooperative or person that completes an
 inspection may:
 (1)  remedy any defective make-ready work at the cost
 of the broadband provider; or
 (2)  require the provider to remedy the defect not
 later than the 14th day after the provider receives the notice under
 Subsection (f).
 Sec. 253.0205.  LIST OF APPROVED CONTRACTORS. (a)  An
 electric cooperative shall maintain and make available a list of
 approved contractors for work above the communications space and
 pole replacements. An electric cooperative may require any work
 above the communications space and pole replacements to be
 performed by contractors on this list, including work performed by
 a contractor hired under Section 253.0204.
 (b)  An electric cooperative may not act unreasonably to
 withhold consent for a requested addition of a qualified contractor
 to the list described by Subsection (a).
 SUBCHAPTER D. OPTION FOR SIMPLE MAKE-READY ACTIVITIES
 Sec. 253.0301.  OPTION: SIMPLE MAKE-READY.  A broadband
 provider may choose to perform simple make-ready activities using
 one-touch make-ready procedures in place of the process outlined
 under Subchapter C.
 Sec. 253.0302.  GRANT OR DENIAL OF APPLICATION: SIMPLE
 MAKE-READY.  (a)  A broadband provider that chooses to perform
 simple make-ready activities as described by Section 253.0301 must
 indicate that choice and describe the work to be performed as part
 of the provider's initial application under Subchapter B.
 (b)  An electric cooperative shall grant or deny an
 application for simple make-ready activities under this section not
 later than:
 (1)  the 15th day after the date the cooperative
 receives a complete application; or
 (2)  the 30th day after the date the cooperative
 receives a complete large order application.
 Sec. 253.0303.  SIMPLE MAKE-READY ACTIVITIES PERFORMED BY
 CONTRACTOR.  (a)  If an application for activities under Section
 253.0302 is granted, a contractor hired by the broadband provider
 shall perform all necessary surveys.
 (b)  The broadband provider and contractor shall provide a
 reasonable opportunity for the electric cooperative and a person
 with an existing pole attachment on an affected pole to be present
 for any field inspections.
 (c)  A contractor hired by the broadband provider may perform
 all simple make-ready activities. Not later than the 15th day
 before the date the contractor begins performing simple make-ready
 activities, the contractor shall provide to the electric
 cooperative and a person with an existing pole attachment on an
 affected pole written notice that:
 (1)  identifies the contractor performing the
 activities; and
 (2)  sets out reasonable opportunities for the
 cooperative and person to be present for the activities.
 Sec. 253.0304.  INSPECTION OF WORK AND REMEDIATION OF
 DAMAGES. (a)  A broadband provider immediately shall notify the
 electric cooperative and a person with an existing pole attachment
 on an affected pole of any damage to the cooperative's or person's
 facilities reasonably likely to interrupt the entity's service.
 (b)  An electric cooperative or person that receives notice
 under Subsection (a) may:
 (1)  complete any remedial work at a reasonable cost to
 the broadband provider; or
 (2)  require the broadband provider immediately to
 remedy the damage at the provider's own expense.
 (c)  Not later than the 15th day after the date a broadband
 provider or contractor hired by the provider completes simple
 make-ready activities on a pole, the provider shall notify the
 electric cooperative and a person with an existing pole attachment
 on the pole of the completed work.
 (d)  Not later than the 90th day after the date an electric
 cooperative or person receives notice under Subsection (c), the
 cooperative or person may inspect the work. Not later than the 14th
 day after the date of the inspection, the cooperative or person may
 provide notice to the broadband provider, with specific
 documentation, of any damage or code violations caused by the work.
 (e)  An electric cooperative or person that provides notice
 under Subsection (d) may:
 (1)  remedy any defective make-ready work at the cost
 of the broadband provider; or
 (2)  require the provider to remedy the defect not
 later than the 14th day after the date the provider received the
 notice under Subsection (d).
 SUBCHAPTER E. POLES AND POLE ATTACHMENTS
 Sec. 253.0401.  DUTIES OF ELECTRIC COOPERATIVE. An electric
 cooperative shall rearrange, expand, replace, or otherwise safely
 reengineer any pole at the request of a broadband provider whose
 application for access to a pole is granted if the change is:
 (1)  consistent with the National Electrical Safety
 Code; and
 (2)  reasonably necessary to safely accommodate a pole
 attachment.
 Sec. 253.0402.  RECOVERY OF COSTS FOR REPLACING POLES. (a)
 If an electric cooperative is required under Section 253.0401 to
 replace a pole that has been in service for longer than 75 percent
 and less than 100 percent of the average service life of a pole
 owned by the cooperative, the cooperative may not require
 reimbursement of costs associated with replacing the pole from the
 broadband provider that exceed the cooperative's reasonable costs
 of advancing the retirement of the existing pole.
 (b)  The costs under Subsection (a) shall be determined by
 adding:
 (1)  the remaining undepreciated value of the existing
 pole;
 (2)  any interest expense of advancing the replacement
 of the pole relative to replacing the pole at the end of the average
 service life of a pole owned by the electric cooperative; and
 (3)  any reasonable incremental cost of increasing the
 capacity of the replacement pole relative to the installation cost
 of the average new pole installed by the electric cooperative.
 (c)  If an electric cooperative is required under Section
 253.0401 to replace a pole that has been in service for the average
 service life of a pole owned by the electric cooperative or longer,
 the cooperative may not require reimbursement of costs associated
 with replacing the pole from the broadband provider that exceed any
 reasonable incremental cost of increasing the capacity of the
 replacement pole relative to the installation cost of the average
 new pole installed by the electric cooperative.
 (d)  An electric cooperative shall determine the average
 service life of a pole as the period of time during which an
 electric cooperative's books maintained for tax and accounting
 purposes consider an average pole to have positive value, after
 depreciation.
 Sec. 253.0403.  SHARING COSTS OF MODIFICATION TO POLE. (a)
 The following entities must share proportionately in the costs of
 modifying a pole under Section 253.0401:
 (1)  the broadband provider who obtains access to a
 pole through a modification to the pole; and
 (2)  a person who directly benefits from a
 modification, including:
 (A)  the electric cooperative;
 (B)  a person with an existing attachment on the
 pole who adds to or modifies the person's attachment after
 receiving notice of the modification; and
 (C)  a party that makes an attachment to a pole
 after the completion of a modification that made the attachment
 possible.
 (b)  This section does not affect the responsibility of the
 electric cooperative under Sections 253.0401 and 253.0402.
 Sec. 253.0404.  EXTENSION ARMS AND TEMPORARY POLE
 ATTACHMENTS. (a)  A broadband provider may use extension arms and
 temporary attachments pending the completion of make-ready
 activities if use of extension arms and temporary attachments
 complies with the National Electrical Safety Code or other
 applicable safety codes.
 (b)  An electric cooperative may require a broadband
 provider to convert a temporary attachment to a permanent
 attachment not later than the 60th day after the date of the
 completion of make-ready activities and may require the provider to
 comply with the National Electrical Safety Code or other
 applicable safety codes.
 Sec. 253.0405.  POLE ATTACHMENT SPECIFICATIONS. (a)  A
 broadband provider may not be required to meet pole attachment
 specifications that exceed the specifications in the National
 Electrical Safety Code, applicable fire safety codes, and any
 building code or similar code of general applicability for the
 protection of public health, safety, or welfare a political
 subdivision adopted before the provider submitted an application to
 the cooperative.
 (b)  This section may not be construed to expand the power of
 any local government jurisdiction.
 Sec. 253.0406.  OVERLASHING. (a)  A broadband provider with
 an existing pole attachment may not be required to obtain advance
 approval from an electric cooperative to overlash or permit a third
 party to overlash the provider's existing wires.
 (b)  An electric cooperative may require a broadband
 provider to provide notice before and after overlashing. The
 cooperative may not require notice before overlashing to be
 provided before the 15th day before the date of the overlashing
 activities.
 (c)  An electric cooperative may require a broadband
 provider to modify an overlashing proposal to address specific and
 identified capacity, safety, reliability, or engineering issues.
 The cooperative may not prohibit the provider from overlashing
 because of a preexisting violation caused by another person.
 (d)  An electric cooperative may require a broadband
 provider to remedy damage or code violations caused by overlashing
 if the electric cooperative:
 (1)  inspects the overlash not later than the 90th day
 after the date the cooperative receives notice that an overlash is
 complete; and
 (2)  informs the provider of the damage or violation
 not later than the 14th day after the date of the inspection.
 Sec. 253.0407.  USE OF POLE ATTACHMENTS FOR MULTIPLE
 SERVICES. A broadband provider that attaches a pole attachment
 under this chapter may use the attachment for any service delivered
 over the provider's facilities, including cable service.
 SUBCHAPTER F. POLE ATTACHMENT CONTRACTS
 Sec. 253.0501.  POLE ATTACHMENT CONTRACTS WITH BROADBAND
 PROVIDERS. (a) A broadband provider and an electric cooperative
 shall establish the rates, terms, and conditions for pole
 attachments by a written pole attachment contract executed by both
 parties. The rates, terms, and conditions for attachments by a
 broadband provider on an electric cooperative's poles must be just,
 reasonable, and nondiscriminatory.
 (b)  In determining whether rates, terms, and conditions are
 just and reasonable, the following factors must be considered:
 (1)  the interests of and benefits to the consumers and
 potential consumers of the electric cooperative's services;
 (2)  the interests of and benefits to the subscribers
 and potential subscribers to broadband services offered through the
 pole attachments;
 (3)  the interests of and benefits to third parties
 from the availability of broadband services offered through the
 pole attachments;
 (4)  compliance with the specifications in the National
 Electrical Safety Code, applicable fire safety codes, and any
 building code or similar code of general applicability for the
 protection of public health, safety, or welfare applicable to the
 pole attachments; and
 (5)  the maintenance and reliability of both electric
 distribution and broadband services.
 (c)  A broadband provider and an electric cooperative shall
 negotiate a pole attachment contract and any amendment,
 modification, or renewal thereof in good faith.
 (d)  A request to negotiate a new pole attachment contract or
 to amend, modify, or renew a contract pertaining to pole
 attachments by a broadband provider or an electric cooperative must
 be made in writing.
 Sec. 253.0502.  CONTRACT NEGOTIATIONS AND MEDIATION. (a)
 If a broadband provider and an electric cooperative are unable to
 agree to a new pole attachment contract before the expiration date
 of an existing contract, the rates, terms, and conditions of the
 existing contract and the terms and conditions of the electric
 cooperative's application and permitting processes remain in
 force:
 (1)  during the 90-day negotiation period described by
 Subsection (b) and during the period of any agreed extension;
 (2)  during the 60-day mediation period described by
 Subsection (b) and during the period of any agreed extension; and
 (3)  pending final disposition of any litigation
 commenced under Subsection (c).
 (b)  If a broadband provider and an electric cooperative are
 unable to agree to a new pole attachment contract before the 91st
 day after the expiration date of an existing contract, and are
 unable to agree to an extension of the negotiation period for a
 certain number of days, the broadband provider and electric
 cooperative shall attempt to resolve any disagreement over the
 rates, terms, or conditions by submitting the contract negotiations
 to a mediation process. The mediation process may not extend later
 than the 60th day after the end of the initial 90-day negotiation
 period and any agreed extension of that period unless the broadband
 provider and electric cooperative agree to an extension of the
 mediation period for a certain number of days. The mediation
 process must be conducted in a county in which the electric
 cooperative has distribution poles. The broadband provider and
 electric cooperative must share equally the expenses for the
 mediator.
 (c)  If the mediation process under Subsection (b) does not
 resolve the disagreement over the rates, terms, or conditions of a
 new pole attachment agreement, or if a dispute arises under the
 terms of an existing agreement or the requirements of this chapter,
 the broadband provider or electric cooperative may file suit in a
 district court to resolve the disagreement or dispute, including to
 enforce the terms of the agreement or of this chapter.
 SECTION 3.  This Act takes effect September 1, 2021.