Texas 2021 87th Regular

Texas Senate Bill SB1281 Comm Sub / Bill

Filed 05/18/2021

                    87R26508 BRG-F
 By: Hancock S.B. No. 1281
 (King of Parker)
 Substitute the following for S.B. No. 1281:  No.


 A BILL TO BE ENTITLED
 AN ACT
 relating to a reliability assessment of the ERCOT power grid and
 certificates of public convenience and necessity for certain
 transmission projects.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  Section 37.052, Utilities Code, is amended by
 adding Subsection (c) to read as follows:
 (c)  An electric utility is not required to amend the
 utility's certificate of public convenience and necessity to
 construct a transmission line that connects the utility's existing
 transmission facilities to a load-serving substation or metering
 point if:
 (1)  the transmission line does not exceed three miles
 in length;
 (2)  each landowner whose property would be directly
 affected by the transmission line, as provided by commission rules,
 provides written consent for the transmission line; and
 (3)  all rights-of-way necessary for construction of
 the transmission line have been purchased.
 SECTION 2.  Section 37.056, Utilities Code, is amended by
 adding Subsection (c-1) and amending Subsection (d) to read as
 follows:
 (c-1)  In considering the need for additional service under
 Subsection (c)(2) for a reliability transmission project that
 serves the ERCOT power region, the commission must consider the
 following:
 (1)  historical load, forecasted load growth, and
 additional load currently seeking interconnection; and
 (2)  security constrained optimal power flows for a
 reasonable range of power generation dispatch scenarios, including
 reliability limitations in serving load during high and low
 renewable generation output.
 (d)  The commission by rule shall establish criteria, in
 addition to the criteria described by Subsection (c), for granting
 a certificate for a transmission project that serves the ERCOT
 power region, that is not necessary to meet state or federal
 reliability standards, and that is not included in a plan developed
 under Section 39.904(g) [does not serve a competitive renewable
 energy zone]. The criteria must include a comparison of the
 estimated cost of the transmission project for consumers and the
 estimated congestion cost savings for consumers that may result
 from the transmission project, considering both current and future
 expected congestion levels and the transmission project's ability
 to reduce those congestion levels. The commission shall include
 with its decision on an application for a certificate to which this
 subsection applies findings on the criteria.
 SECTION 3.  Subchapter D, Chapter 39, Utilities Code, is
 amended by adding Section 39.159 to read as follows:
 Sec. 39.159.  GRID RELIABILITY ASSESSMENT. (a)  The
 independent organization certified under Section 39.151 for the
 ERCOT power region shall conduct an annual assessment of the ERCOT
 power grid to assess the grid's reliability in extreme weather
 scenarios.
 (b)  Each assessment must:
 (1)  consider the impact of different levels of thermal
 and renewable generation availability; and
 (2)  recommend transmission projects that may increase
 the grid's reliability in extreme weather scenarios.
 SECTION 4.  The changes in law made by this Act apply only to
 a proceeding affecting a certificate of public convenience and
 necessity that commences on or after the effective date of this Act.
 A proceeding affecting a certificate of public convenience and
 necessity that commenced before the effective date of this Act is
 governed by the law in effect on the date the proceeding is
 commenced, and that law is continued in effect for that purpose.
 SECTION 5.  This Act takes effect September 1, 2021.