Texas 2023 88th Regular

Texas House Bill HB2555 Engrossed / Bill

Filed 04/28/2023

                    By: Metcalf, Raymond, et al. H.B. No. 2555


 A BILL TO BE ENTITLED
 AN ACT
 relating to transmission and distribution system resiliency
 planning by and cost recovery for electric utilities.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  The legislature finds that:
 (1)  extreme weather conditions, including high winds,
 lightning, flooding, and freezes, can cause extraordinary damage to
 electrical transmission and distribution facilities, resulting in
 power outages;
 (2)  it is in the state's interest to promote the use of
 resiliency measures to enable electrical transmission and
 distribution infrastructure to withstand extreme weather
 conditions, including hardening electrical transmission and
 distribution facilities, undergrounding certain electrical
 distribution lines, lightning mitigation measures, flood
 mitigation measures, information technology, cybersecurity
 measures, physical security measures, vegetation management, and
 wildfire mitigation and response;
 (3)  protecting electrical transmission and
 distribution infrastructure from extreme weather conditions can
 effectively reduce system restoration costs to and outage times for
 customers and improve system resiliency and overall service
 reliability for customers;
 (4)  it is in the state's interest for each electric
 utility to seek to mitigate system restoration costs to and outage
 times for customers when developing plans to enhance electrical
 transmission and distribution infrastructure storm resiliency; and
 (5)  all customers benefit from reduced system
 restoration costs.
 SECTION 2.  Subchapter D, Chapter 38, Utilities Code, is
 amended by adding Section 38.078 to read as follows:
 Sec. 38.078.  TRANSMISSION AND DISTRIBUTION SYSTEM
 RESILIENCY PLAN AND COST RECOVERY. (a)  In this section, "plan"
 means a transmission and distribution system resiliency plan
 described by Subsection (b).
 (b)  An electric utility may file, in a manner authorized by
 commission rule, a plan to enhance the resiliency of the utility's
 transmission and distribution system through at least one of the
 following methods:
 (1)  hardening electrical transmission and
 distribution facilities;
 (2)  modernizing electrical transmission and
 distribution facilities;
 (3)  undergrounding certain electrical distribution
 lines;
 (4)  lightning mitigation measures;
 (5)  flood mitigation measures;
 (6)  information technology;
 (7)  cybersecurity measures;
 (8)  physical security measures;
 (9)  vegetation management; or
 (10)  wildfire mitigation and response.
 (c)  A plan must explain the systematic approach the electric
 utility will use to carry out the plan during at least a three-year
 period.
 (d)  In determining whether to approve a plan filed under
 this section, the commission shall consider:
 (1)  the extent to which the plan is expected to enhance
 system resiliency, including whether the plan prioritizes areas of
 lower performance; and
 (2)  the estimated costs of implementing the measures
 proposed in the plan.
 (e)  The commission shall issue an order to approve, modify,
 or deny a plan filed under Subsection (b) and any associated rider
 described by Subsection (i) not later than the 180th day after the
 plan is filed with the commission. The commission may not approve a
 plan if the commission determines that approving the plan is not in
 the public interest.
 (f)  For a plan approved by the commission, with or without
 modification, an electric utility may request a good cause
 exception on implementing all or some of the measures or incurring
 all or some of the estimated costs in the plan if operational needs,
 business needs, financial conditions, or supply chain or labor
 conditions dictate the exception. The commission's denial of a
 plan is not considered to be a finding of the prudence or imprudence
 of a measure or cost in the plan for the purposes of Chapter 36 or
 this chapter.
 (g)  An electric utility for which the commission has
 approved a plan under this section may request that the commission
 review an updated plan submitted by the electric utility.  The
 updated plan must comply with any applicable commission rules and
 take effect on a date that is not earlier than the third anniversary
 of the approval date of the utility's most recently approved plan.
 The commission shall review and approve, modify, or deny the
 updated plan in the manner provided by Subsections (d), (e), and
 (f).
 (h)  An electric utility's implementation of a plan approved
 under this section may not be considered imprudent for the purposes
 of Chapter 36 or this chapter.  If the commission determines that
 the costs to implement an approved plan were prudently incurred and
 otherwise reasonable, those costs are not subject to disallowance
 for exceeding the estimates in the plan.
 (i)  Notwithstanding any other law, an electric utility may
 file with a plan an application for a rider to recover all or a
 portion of the estimated costs relating to the electric utility's
 implementation of the plan, other than transmission-related costs.
 If the commission approves the plan, the commission shall determine
 the appropriate terms of the rider in the approval order. A rider
 approved under this subsection must allow the electric utility to
 begin recovering the levelized cost of implementing the approved
 plan, other than transmission-related costs, at the time the plan
 is first implemented. The commission shall adopt a procedure for
 reconciliation of an electric utility's distribution-related
 expenses to implement an approved plan.
 (j)  As part of a review described by Subsection (g), the
 commission shall reconcile the rider authorized under Subsection
 (i) to determine the electric utility's reasonably and prudently
 incurred plan costs.
 (k)  If an electric utility that files a plan with the
 commission does not apply for a rider under Subsection (i), the
 utility may defer all or a portion of the distribution-related
 costs relating to the implementation of the plan for future
 recovery as a regulatory asset, including depreciation expense and
 carrying costs at the utility's weighted average cost of capital
 established in the commission's final order in the utility's most
 recent base rate proceeding, and use commission authorized cost
 recovery alternatives under Sections 36.209 and 36.210 or another
 general rate proceeding.
 (l)  Plan costs considered by the commission to be reasonable
 and prudent may include only incremental costs that are not already
 being recovered through the electric utility's base rates or any
 other rate rider and must be allocated to customer classes pursuant
 to the rate design most recently approved by the commission.  If a
 capital investment is recoverable as a plan cost, the electric
 utility may recover all reasonable and prudent costs associated
 with the investment, including the annual depreciation expense
 related to the investment calculated at the utility's currently
 approved depreciation rates, the after-tax return on the
 undepreciated balance of the investment calculated using the rate
 of return approved by the commission in the utility's last
 comprehensive base rate proceeding, and federal income tax and
 other taxes related to the investment.
 SECTION 3.  The Public Utility Commission of Texas shall
 adopt rules to implement Section 38.078, Utilities Code, as added
 by this Act, not later than the 180th day after the effective date
 of this Act.
 SECTION 4.  This Act takes effect immediately if it receives
 a vote of two-thirds of all the members elected to each house, as
 provided by Section 39, Article III, Texas Constitution.  If this
 Act does not receive the vote necessary for immediate effect, this
 Act takes effect September 1, 2023.