Texas Senate Bill SB1287 Comm Sub / Bill

Filed 05/20/2023

                    By: King, et al. S.B. No. 1287
 (Slawson)


 A BILL TO BE ENTITLED
 AN ACT
 relating to the cost of interconnecting certain electric generation
 facilities with the ERCOT transmission system.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  Section 35.004, Utilities Code, is amended by
 amending Subsection (d) and adding Subsections (d-1), (d-2), and
 (d-3) to read as follows:
 (d)  The commission shall price wholesale transmission
 services within ERCOT based on the postage stamp method of pricing
 under which a transmission-owning utility's rate is based on the
 ERCOT utilities' combined annual costs of transmission, other than
 costs described by Subsections (d-2) and (d-3), divided by the
 total demand placed on the combined transmission systems of all
 such transmission-owning utilities within a power region.  An
 electric utility subject to the freeze period imposed by Section
 39.052 may treat transmission costs in excess of transmission
 revenues during the freeze period as an expense for purposes of
 determining annual costs in the annual report filed under Section
 39.257. Notwithstanding Section 36.201, the commission may approve
 wholesale rates that may be periodically adjusted to ensure timely
 recovery of transmission investment.  Notwithstanding Section
 36.054(a), if the commission determines that conditions warrant the
 action, the commission may authorize the inclusion of construction
 work in progress in the rate base for transmission investment
 required by the commission under Section 39.203(e).
 (d-1)  The commission by rule shall establish a reasonable
 allowance to be applied on a per megawatt basis for costs incurred
 to interconnect generation resources directly with the ERCOT
 transmission system at transmission voltage, including costs of
 utility interconnection facilities.  The allowance must:
 (1)  take into account:
 (A)  average historical dispatchable generation
 interconnection costs; and
 (B)  the reliability impact to the grid of the
 interconnecting resource and whether the interconnecting resource
 increases reliability or volatility in managing the grid; and
 (2)  be designed to lower costs to consumers and
 encourage owners of generation resources to locate the resources
 closer to load.
 (d-2)  Costs in excess of the allowance provided by
 Subsection (d-1) incurred to interconnect generation resources
 with the ERCOT transmission system, including costs of utility
 interconnection facilities, must be directly assigned to and
 collected from the generation resource interconnecting through the
 facilities.
 (d-3)  Not later than September 1 of every fifth year after
 2023, the commission shall review and may adjust the allowance
 provided by Subsection (d-1) to account for inflation or supply
 chain issues.
 SECTION 2.  This Act takes effect September 1, 2023.