Texas 2025 89th Regular

Texas House Bill HB3356 Comm Sub / Bill

Filed 04/29/2025

                    89R23752 SCR-D
 By: Patterson, McLaughlin, Leo Wilson, H.B. No. 3356
 et al.
 Substitute the following for H.B. No. 3356:
 By:  Geren C.S.H.B. No. 3356




 A BILL TO BE ENTITLED
 AN ACT
 relating to reliability requirements for certain electric
 generation facilities.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  Sections 39.1592(a) and (d), Utilities Code, are
 amended to read as follows:
 (a)  This section applies only to an electric generation
 facility in the ERCOT power region that is subject to [for which] a
 standard generator interconnection agreement, [is signed on or
 after January 1, 2027, that] has been in operation for at least one
 year, and [that] is not a self-generator.
 (d)  The independent organization certified under Section
 39.151 for the ERCOT power region may not impose penalties under
 Subsection (c):
 (1)  for resource unavailability due to planned
 maintenance outages or transmission outages;
 (2)  on resources that are already subject to
 performance obligations during the highest reliability risk hours
 under the day-ahead market rules or other ancillary or reliability
 services established by the commission or the independent
 organization; [or]
 (3)  on resources that demonstrate the ability to
 operate when called upon for dispatch for 24 continuous hours at or
 above the seasonal average generation capability through the
 resource's own generation capability or through a contract with an
 on-site or off-site resource, including a battery energy storage
 resource; or
 (4)  on resources with dual but separate grid
 interconnections that provide dispatchable generation to the ERCOT
 power region [during hours outside a baseline established by the
 commission that includes morning and evening ramping periods].
 SECTION 2.  (a)  The Public Utility Commission of Texas shall
 consider the use of a settlement price cap, a fixed reliability fee,
 and other methods of imposing penalties under Section
 39.1592(c)(1), Utilities Code.  The Public Utility Commission of
 Texas and the independent organization certified under Section
 39.151, Utilities Code, for the ERCOT power region shall:
 (1)  consider rebating penalties collected under
 Section 39.1592 directly to consumers or redirecting a portion of
 the collected penalties toward reliability incentives; and
 (2)  for the purposes of Subdivision (1) of this
 subsection, prioritize rebates of penalties or redirection of
 penalties in a manner the commission determines will provide the
 maximum financial benefit to consumers while still ensuring that
 the reliability needs of the ERCOT power region are met.
 (b)  Notwithstanding Section 39.1592(c), Utilities Code, the
 Public Utility Commission of Texas may allow the financial
 penalties and incentives required by that subsection to be adopted
 in a phased manner over multiple years to mitigate market
 disruptions that the commission determines would result in net
 increased costs to consumers.
 SECTION 3.  This Act takes effect September 1, 2025.