 By: Darby H.B. No. 3970




 A BILL TO BE ENTITLED
 AN ACT
 relating to electricity planning for large loads.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  Subchapter D, Chapter 39, Utilities Code, is
 amended by adding Section 39.169 to read as follows:
 Sec. 39.169.  LARGE LOAD INTERCONNECTION; RELIABILITY
 PROGRAM. (a) In this section, "behind-the-meter generation" means
 a new generation facility on the retail customer's side of the
 meter.
 (b)  The commission by rule shall require the independent
 organization certified under Section 39.151 for the ERCOT power
 region to develop and implement an interconnection program to
 provide an expedited interconnection process for operators of large
 loads who agree to cease consuming energy from the power grid
 through deployment of their behind-the-meter generation when
 directed to by the independent organization.  The program must be
 available only to large loads that are a facility at a single site
 with an aggregate peak power demand that exceeds a demand threshold
 established by the independent organization.  The threshold must be
 at least 75 megawatts unless the independent organization
 determines that a lower threshold will better ensure reliability in
 the ERCOT power region.
 (c)  The program must require the independent organization
 certified under Section 39.151 for the ERCOT power region and the
 relevant electric cooperative, municipally owned utility, or
 transmission and distribution utility to give priority to a large
 load in the interconnection queue participating in the program.
 (d)  The program must provide that:
 (1)  an interconnection application for a
 participating large load with behind-the-meter generation that
 agrees to offer the energy generated by the behind-the-meter
 generation to the power grid at times directed by the independent
 organization or reduce its energy consumption from the power grid
 to a minimum level established by the independent organization will
 be given priority over other interconnection applications that are
 pending before the independent organization and the relevant
 electric cooperative, municipally owned utility, or transmission
 and distribution utility, including any applications from other
 participating large loads without behind-the-meter generation;
 (2)  if applicable, the generator interconnection
 application for a participating large load's behind-the-meter
 generation will be processed in parallel with the load
 interconnection application; and
 (3)  an applicant for participation in the program may
 choose:
 (A)  if authorized by the independent
 organization and the relevant electric cooperative, municipally
 owned utility, or transmission and distribution utility, to
 contract with a vendor approved by the relevant electric
 cooperative, municipally owned utility, or transmission and
 distribution utility or by the independent organization to perform
 all studies required by the relevant electric cooperative,
 municipally owned utility, or transmission and distribution
 utility before the approval of the interconnection application;
 (B)  to procure equipment required for the
 interconnection in accordance with technical specifications
 provided by the relevant electric cooperative, municipally owned
 utility, or transmission and distribution utility; and
 (C)  to construct interconnection facilities in
 accordance with technical and other requirements of the relevant
 electric cooperative, municipally owned utility, or transmission
 and distribution utility.
 (e)  The program shall provide that studies required by an
 electric cooperative, municipally owned utility, or transmission
 and distribution utility before the approval of an interconnection
 application for a participating large load may evaluate the load as
 non-firm.
 SECTION 2.  This Act takes effect September 1, 2025.