 By: Troxclair H.B. No. 5582




 A BILL TO BE ENTITLED
 AN ACT
 relating to the design-build method for certain government
 construction projects.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  Subchapter G, Chapter 2269, Government Code, is
 amended by adding Section 2269.3035 to read as follows:
 Sec. 2269.3035.  ALTERNATIVE DESIGN-BUILD METHODS FOR WATER
 AND WASTEWATER INFRASTRUCTURE. (a) A governmental entity may use
 the following methods for the construction, rehabilitation,
 alteration, or repair of water or wastewater infrastructure:
 (1)  a method in which a single fixed price for both
 design and construction is established at the time the contract
 with the design-build firm is signed by the parties, commonly known
 as "fixed price design-build"; or
 (2)  a method in which the design-build firm is
 involved early in the process of developing the design and the
 contract includes a stepped payment scheme for design and
 construction services, commonly known as "progressive
 design-build."
 (b)  The requirements of this subchapter apply to a method
 described by Subsection (a) to the extent practicable.
 SECTION 2.  Section 2269.352, Government Code, is amended to
 read as follows:
 Sec. 2269.352.  APPLICABILITY. This subchapter applies to a
 governmental entity, including [that:
 [(1)  has a population of more than 100,000 within the
 entity's geographic boundary or service area; or
 [(2)  is] a board of trustees governed by Chapter 54,
 Transportation Code.
 SECTION 3.  Section 2269.353(b), Government Code, is amended
 to read as follows:
 (b)  A contract for a project under this subchapter may cover
 only a single integrated project. A governmental entity may not
 enter into a contract for aggregated projects at multiple
 locations. For purposes of this subsection:
 (1)  if a metropolitan transit authority created under
 Chapter 451, Transportation Code, enters into a contract for a
 project involving a linear transit project with multiple stops
 along the project route for boarding passengers, created under
 Chapter 451, Transportation Code, the linear transit project is a
 single integrated project; and
 (2)  a water or wastewater infrastructure project
 [treatment plant], including a desalination plant, that includes
 treatment facilities, well fields, pump stations, water storage,
 and pipelines, is a single integrated project.
 SECTION 4.  Subchapter H, Chapter 2269, Government Code, is
 amended by adding Section 2269.3535 to read as follows:
 Sec. 2269.3535.  ALTERNATIVE DESIGN-BUILD PROCEDURES FOR
 WATER AND WASTEWATER INFRASTRUCTURE. (a) A governmental entity
 may use a design-build method described by Section 2269.3035(a) for
 the construction, rehabilitation, alteration, or repair of water or
 wastewater infrastructure.
 (b)  The requirements of this subchapter apply to a method
 described by Subsection (a) to the extent practicable.
 SECTION 5.  This Act takes effect September 1, 2025.