11 CALIFORNIA LEGISLATURE 20192020 REGULAR SESSION Assembly Bill No. 2186Introduced by Assembly Member GraysonFebruary 11, 2020 An act to amend Section 9203 of the Public Contract Code, relating to public contracting. LEGISLATIVE COUNSEL'S DIGESTAB 2186, as introduced, Grayson. Public contracting: contractor retention withholding.Existing law authorizes the legislative body of a local agency, as defined, to prescribe how the local agency makes payment on a contract with the local agency for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement of any kind that will exceed a total of $5,000. Existing law limits this authority by requiring progress payments on the contract to not be made in excess of 95% of the percentage of actual work completed plus a like percentage of the value of material delivered on the ground or stored subject to, or under the control of, the local agency, and unused. Existing law also requires the local agency to not withhold less than 5% of the contract price until final completion and acceptance of the project, unless, at any time after 50% of the work has been completed, the local agency finds that satisfactory progress is being made.This bill would eliminate the above described limitations on a local agencys authority to prescribe payments on these contracts. The bill would, however, prohibit the local agency from withholding more than 5% of the contract price for contracts for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement of any kind that will exceed $5,000 in total costs.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: NO Local Program: NO Bill TextThe people of the State of California do enact as follows:SECTION 1. Section 9203 of the Public Contract Code is amended to read:9203. (a) Payment on any contract with a local agency for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement, improvement of any kind which that will exceed in cost a total of five thousand dollars ($5,000), shall be made as the legislative body prescribes upon estimates approved by the legislative body, but progress payments shall not be made in excess of 95 percent of the percentage of actual work completed plus a like percentage of the value of material delivered on the ground or stored subject to, or under the control of, the local agency, and unused. The body. However, the local agency shall not withhold not less more than 5 percent of the contract price until final completion and acceptance of the project. However, at any time after 50 percent of the work has been completed, if the legislative body finds that satisfactory progress is being made, it may make any of the remaining progress payments in full for actual work completed. price.(b) Notwithstanding the dollar limit specified in subdivision (a), a county water authority shall be subject to a twenty-five thousand dollar ($25,000) limit for purposes of subdivision (a).
22
33 CALIFORNIA LEGISLATURE 20192020 REGULAR SESSION Assembly Bill No. 2186Introduced by Assembly Member GraysonFebruary 11, 2020 An act to amend Section 9203 of the Public Contract Code, relating to public contracting. LEGISLATIVE COUNSEL'S DIGESTAB 2186, as introduced, Grayson. Public contracting: contractor retention withholding.Existing law authorizes the legislative body of a local agency, as defined, to prescribe how the local agency makes payment on a contract with the local agency for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement of any kind that will exceed a total of $5,000. Existing law limits this authority by requiring progress payments on the contract to not be made in excess of 95% of the percentage of actual work completed plus a like percentage of the value of material delivered on the ground or stored subject to, or under the control of, the local agency, and unused. Existing law also requires the local agency to not withhold less than 5% of the contract price until final completion and acceptance of the project, unless, at any time after 50% of the work has been completed, the local agency finds that satisfactory progress is being made.This bill would eliminate the above described limitations on a local agencys authority to prescribe payments on these contracts. The bill would, however, prohibit the local agency from withholding more than 5% of the contract price for contracts for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement of any kind that will exceed $5,000 in total costs.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: NO Local Program: NO
44
55
66
77
88
99 CALIFORNIA LEGISLATURE 20192020 REGULAR SESSION
1010
1111 Assembly Bill
1212
1313 No. 2186
1414
1515 Introduced by Assembly Member GraysonFebruary 11, 2020
1616
1717 Introduced by Assembly Member Grayson
1818 February 11, 2020
1919
2020 An act to amend Section 9203 of the Public Contract Code, relating to public contracting.
2121
2222 LEGISLATIVE COUNSEL'S DIGEST
2323
2424 ## LEGISLATIVE COUNSEL'S DIGEST
2525
2626 AB 2186, as introduced, Grayson. Public contracting: contractor retention withholding.
2727
2828 Existing law authorizes the legislative body of a local agency, as defined, to prescribe how the local agency makes payment on a contract with the local agency for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement of any kind that will exceed a total of $5,000. Existing law limits this authority by requiring progress payments on the contract to not be made in excess of 95% of the percentage of actual work completed plus a like percentage of the value of material delivered on the ground or stored subject to, or under the control of, the local agency, and unused. Existing law also requires the local agency to not withhold less than 5% of the contract price until final completion and acceptance of the project, unless, at any time after 50% of the work has been completed, the local agency finds that satisfactory progress is being made.This bill would eliminate the above described limitations on a local agencys authority to prescribe payments on these contracts. The bill would, however, prohibit the local agency from withholding more than 5% of the contract price for contracts for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement of any kind that will exceed $5,000 in total costs.
2929
3030 Existing law authorizes the legislative body of a local agency, as defined, to prescribe how the local agency makes payment on a contract with the local agency for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement of any kind that will exceed a total of $5,000. Existing law limits this authority by requiring progress payments on the contract to not be made in excess of 95% of the percentage of actual work completed plus a like percentage of the value of material delivered on the ground or stored subject to, or under the control of, the local agency, and unused. Existing law also requires the local agency to not withhold less than 5% of the contract price until final completion and acceptance of the project, unless, at any time after 50% of the work has been completed, the local agency finds that satisfactory progress is being made.
3131
3232 This bill would eliminate the above described limitations on a local agencys authority to prescribe payments on these contracts. The bill would, however, prohibit the local agency from withholding more than 5% of the contract price for contracts for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement of any kind that will exceed $5,000 in total costs.
3333
3434 ## Digest Key
3535
3636 ## Bill Text
3737
3838 The people of the State of California do enact as follows:SECTION 1. Section 9203 of the Public Contract Code is amended to read:9203. (a) Payment on any contract with a local agency for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement, improvement of any kind which that will exceed in cost a total of five thousand dollars ($5,000), shall be made as the legislative body prescribes upon estimates approved by the legislative body, but progress payments shall not be made in excess of 95 percent of the percentage of actual work completed plus a like percentage of the value of material delivered on the ground or stored subject to, or under the control of, the local agency, and unused. The body. However, the local agency shall not withhold not less more than 5 percent of the contract price until final completion and acceptance of the project. However, at any time after 50 percent of the work has been completed, if the legislative body finds that satisfactory progress is being made, it may make any of the remaining progress payments in full for actual work completed. price.(b) Notwithstanding the dollar limit specified in subdivision (a), a county water authority shall be subject to a twenty-five thousand dollar ($25,000) limit for purposes of subdivision (a).
3939
4040 The people of the State of California do enact as follows:
4141
4242 ## The people of the State of California do enact as follows:
4343
4444 SECTION 1. Section 9203 of the Public Contract Code is amended to read:9203. (a) Payment on any contract with a local agency for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement, improvement of any kind which that will exceed in cost a total of five thousand dollars ($5,000), shall be made as the legislative body prescribes upon estimates approved by the legislative body, but progress payments shall not be made in excess of 95 percent of the percentage of actual work completed plus a like percentage of the value of material delivered on the ground or stored subject to, or under the control of, the local agency, and unused. The body. However, the local agency shall not withhold not less more than 5 percent of the contract price until final completion and acceptance of the project. However, at any time after 50 percent of the work has been completed, if the legislative body finds that satisfactory progress is being made, it may make any of the remaining progress payments in full for actual work completed. price.(b) Notwithstanding the dollar limit specified in subdivision (a), a county water authority shall be subject to a twenty-five thousand dollar ($25,000) limit for purposes of subdivision (a).
4545
4646 SECTION 1. Section 9203 of the Public Contract Code is amended to read:
4747
4848 ### SECTION 1.
4949
5050 9203. (a) Payment on any contract with a local agency for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement, improvement of any kind which that will exceed in cost a total of five thousand dollars ($5,000), shall be made as the legislative body prescribes upon estimates approved by the legislative body, but progress payments shall not be made in excess of 95 percent of the percentage of actual work completed plus a like percentage of the value of material delivered on the ground or stored subject to, or under the control of, the local agency, and unused. The body. However, the local agency shall not withhold not less more than 5 percent of the contract price until final completion and acceptance of the project. However, at any time after 50 percent of the work has been completed, if the legislative body finds that satisfactory progress is being made, it may make any of the remaining progress payments in full for actual work completed. price.(b) Notwithstanding the dollar limit specified in subdivision (a), a county water authority shall be subject to a twenty-five thousand dollar ($25,000) limit for purposes of subdivision (a).
5151
5252 9203. (a) Payment on any contract with a local agency for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement, improvement of any kind which that will exceed in cost a total of five thousand dollars ($5,000), shall be made as the legislative body prescribes upon estimates approved by the legislative body, but progress payments shall not be made in excess of 95 percent of the percentage of actual work completed plus a like percentage of the value of material delivered on the ground or stored subject to, or under the control of, the local agency, and unused. The body. However, the local agency shall not withhold not less more than 5 percent of the contract price until final completion and acceptance of the project. However, at any time after 50 percent of the work has been completed, if the legislative body finds that satisfactory progress is being made, it may make any of the remaining progress payments in full for actual work completed. price.(b) Notwithstanding the dollar limit specified in subdivision (a), a county water authority shall be subject to a twenty-five thousand dollar ($25,000) limit for purposes of subdivision (a).
5353
5454 9203. (a) Payment on any contract with a local agency for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement, improvement of any kind which that will exceed in cost a total of five thousand dollars ($5,000), shall be made as the legislative body prescribes upon estimates approved by the legislative body, but progress payments shall not be made in excess of 95 percent of the percentage of actual work completed plus a like percentage of the value of material delivered on the ground or stored subject to, or under the control of, the local agency, and unused. The body. However, the local agency shall not withhold not less more than 5 percent of the contract price until final completion and acceptance of the project. However, at any time after 50 percent of the work has been completed, if the legislative body finds that satisfactory progress is being made, it may make any of the remaining progress payments in full for actual work completed. price.(b) Notwithstanding the dollar limit specified in subdivision (a), a county water authority shall be subject to a twenty-five thousand dollar ($25,000) limit for purposes of subdivision (a).
5555
5656
5757
5858 9203. (a) Payment on any contract with a local agency for the creation, construction, alteration, repair, or improvement of any public structure, building, road, or other improvement, improvement of any kind which that will exceed in cost a total of five thousand dollars ($5,000), shall be made as the legislative body prescribes upon estimates approved by the legislative body, but progress payments shall not be made in excess of 95 percent of the percentage of actual work completed plus a like percentage of the value of material delivered on the ground or stored subject to, or under the control of, the local agency, and unused. The body. However, the local agency shall not withhold not less more than 5 percent of the contract price until final completion and acceptance of the project. However, at any time after 50 percent of the work has been completed, if the legislative body finds that satisfactory progress is being made, it may make any of the remaining progress payments in full for actual work completed. price.
5959
6060 (b) Notwithstanding the dollar limit specified in subdivision (a), a county water authority shall be subject to a twenty-five thousand dollar ($25,000) limit for purposes of subdivision (a).