11 CALIFORNIA LEGISLATURE 20192020 REGULAR SESSION Assembly Bill No. 2313Introduced by Assembly Member EggmanFebruary 14, 2020 An act to amend Section 399.14 of the Public Utilities Code, relating to energy. LEGISLATIVE COUNSEL'S DIGESTAB 2313, as introduced, Eggman. Renewable energy resources.Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations, while local publicly owned electric utilities, as defined, are under the direction of their governing boards. The existing California Renewables Portfolio Standard Program requires retail sellers of electricity and local publicly owned electric utilities to purchase specified minimum quantities of electricity products from eligible renewable energy resources, as defined. The required quantities of electricity products are based upon a percentage of the utilitys total retail sales of electricity in California. The program authorizes an electrical corporation to apply to the commission for approval to construct, own, and operate an eligible renewable energy resource, and requires the commission to approve the application if certain conditions are met.This bill would make nonsubstantive changes to this authorization for an electrical corporation to apply to the commission for approval to construct, own, and operate an eligible renewable energy resource.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: NO Local Program: NO Bill TextThe people of the State of California do enact as follows:SECTION 1. Section 399.14 of the Public Utilities Code is amended to read:399.14. (a) (1) An electrical corporation, pursuant to Chapter 5 (commencing with Section 1001), and in order to meet its unmet renewables portfolio standard procurement requirements, may apply to the commission for approval to construct, own, and operate an eligible renewable energy resource.(2) If the proposed eligible renewable energy resource complies with the requirements of subdivision (b), the commission shall approve an application filed pursuant to paragraph (1), until the commission has approved applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.(3) The commission may approve additional applications for eligible renewable energy resources once the commission has approved sufficient applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.(b) The commission shall not approve any an application by an electrical corporation pursuant to subdivision (a) unless both of the following conditions are met:(1) The eligible renewable energy resource utilizes a viable technology at a reasonable cost.(2) The eligible renewable energy resource provides comparable or superior value to ratepayers when compared to then recent contracts for generation provided by eligible renewable energy resources.(c) In approving any an application by an electrical corporation for approval to construct, own, and operate an eligible renewable energy resource, the commission shall apply traditional cost-of-service ratemaking. When applying traditional cost-of-service ratemaking, the commission, in the certificate authorizing the new construction, shall specify the maximum cost determined to be reasonable and prudent for the construction of the facility and the cost of initial operation of the facility. Upon a filing by the electrical corporation, the commission may authorize an increase in the maximum cost of construction if it determines that the cost has in fact increased, that the cost increase is determined to be reasonable and prudent, and that the present or future public convenience or necessity require construction of the project at the increased cost.
22
33 CALIFORNIA LEGISLATURE 20192020 REGULAR SESSION Assembly Bill No. 2313Introduced by Assembly Member EggmanFebruary 14, 2020 An act to amend Section 399.14 of the Public Utilities Code, relating to energy. LEGISLATIVE COUNSEL'S DIGESTAB 2313, as introduced, Eggman. Renewable energy resources.Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations, while local publicly owned electric utilities, as defined, are under the direction of their governing boards. The existing California Renewables Portfolio Standard Program requires retail sellers of electricity and local publicly owned electric utilities to purchase specified minimum quantities of electricity products from eligible renewable energy resources, as defined. The required quantities of electricity products are based upon a percentage of the utilitys total retail sales of electricity in California. The program authorizes an electrical corporation to apply to the commission for approval to construct, own, and operate an eligible renewable energy resource, and requires the commission to approve the application if certain conditions are met.This bill would make nonsubstantive changes to this authorization for an electrical corporation to apply to the commission for approval to construct, own, and operate an eligible renewable energy resource.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: NO Local Program: NO
44
55
66
77
88
99 CALIFORNIA LEGISLATURE 20192020 REGULAR SESSION
1010
1111 Assembly Bill
1212
1313 No. 2313
1414
1515 Introduced by Assembly Member EggmanFebruary 14, 2020
1616
1717 Introduced by Assembly Member Eggman
1818 February 14, 2020
1919
2020 An act to amend Section 399.14 of the Public Utilities Code, relating to energy.
2121
2222 LEGISLATIVE COUNSEL'S DIGEST
2323
2424 ## LEGISLATIVE COUNSEL'S DIGEST
2525
2626 AB 2313, as introduced, Eggman. Renewable energy resources.
2727
2828 Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations, while local publicly owned electric utilities, as defined, are under the direction of their governing boards. The existing California Renewables Portfolio Standard Program requires retail sellers of electricity and local publicly owned electric utilities to purchase specified minimum quantities of electricity products from eligible renewable energy resources, as defined. The required quantities of electricity products are based upon a percentage of the utilitys total retail sales of electricity in California. The program authorizes an electrical corporation to apply to the commission for approval to construct, own, and operate an eligible renewable energy resource, and requires the commission to approve the application if certain conditions are met.This bill would make nonsubstantive changes to this authorization for an electrical corporation to apply to the commission for approval to construct, own, and operate an eligible renewable energy resource.
2929
3030 Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations, while local publicly owned electric utilities, as defined, are under the direction of their governing boards. The existing California Renewables Portfolio Standard Program requires retail sellers of electricity and local publicly owned electric utilities to purchase specified minimum quantities of electricity products from eligible renewable energy resources, as defined. The required quantities of electricity products are based upon a percentage of the utilitys total retail sales of electricity in California. The program authorizes an electrical corporation to apply to the commission for approval to construct, own, and operate an eligible renewable energy resource, and requires the commission to approve the application if certain conditions are met.
3131
3232 This bill would make nonsubstantive changes to this authorization for an electrical corporation to apply to the commission for approval to construct, own, and operate an eligible renewable energy resource.
3333
3434 ## Digest Key
3535
3636 ## Bill Text
3737
3838 The people of the State of California do enact as follows:SECTION 1. Section 399.14 of the Public Utilities Code is amended to read:399.14. (a) (1) An electrical corporation, pursuant to Chapter 5 (commencing with Section 1001), and in order to meet its unmet renewables portfolio standard procurement requirements, may apply to the commission for approval to construct, own, and operate an eligible renewable energy resource.(2) If the proposed eligible renewable energy resource complies with the requirements of subdivision (b), the commission shall approve an application filed pursuant to paragraph (1), until the commission has approved applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.(3) The commission may approve additional applications for eligible renewable energy resources once the commission has approved sufficient applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.(b) The commission shall not approve any an application by an electrical corporation pursuant to subdivision (a) unless both of the following conditions are met:(1) The eligible renewable energy resource utilizes a viable technology at a reasonable cost.(2) The eligible renewable energy resource provides comparable or superior value to ratepayers when compared to then recent contracts for generation provided by eligible renewable energy resources.(c) In approving any an application by an electrical corporation for approval to construct, own, and operate an eligible renewable energy resource, the commission shall apply traditional cost-of-service ratemaking. When applying traditional cost-of-service ratemaking, the commission, in the certificate authorizing the new construction, shall specify the maximum cost determined to be reasonable and prudent for the construction of the facility and the cost of initial operation of the facility. Upon a filing by the electrical corporation, the commission may authorize an increase in the maximum cost of construction if it determines that the cost has in fact increased, that the cost increase is determined to be reasonable and prudent, and that the present or future public convenience or necessity require construction of the project at the increased cost.
3939
4040 The people of the State of California do enact as follows:
4141
4242 ## The people of the State of California do enact as follows:
4343
4444 SECTION 1. Section 399.14 of the Public Utilities Code is amended to read:399.14. (a) (1) An electrical corporation, pursuant to Chapter 5 (commencing with Section 1001), and in order to meet its unmet renewables portfolio standard procurement requirements, may apply to the commission for approval to construct, own, and operate an eligible renewable energy resource.(2) If the proposed eligible renewable energy resource complies with the requirements of subdivision (b), the commission shall approve an application filed pursuant to paragraph (1), until the commission has approved applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.(3) The commission may approve additional applications for eligible renewable energy resources once the commission has approved sufficient applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.(b) The commission shall not approve any an application by an electrical corporation pursuant to subdivision (a) unless both of the following conditions are met:(1) The eligible renewable energy resource utilizes a viable technology at a reasonable cost.(2) The eligible renewable energy resource provides comparable or superior value to ratepayers when compared to then recent contracts for generation provided by eligible renewable energy resources.(c) In approving any an application by an electrical corporation for approval to construct, own, and operate an eligible renewable energy resource, the commission shall apply traditional cost-of-service ratemaking. When applying traditional cost-of-service ratemaking, the commission, in the certificate authorizing the new construction, shall specify the maximum cost determined to be reasonable and prudent for the construction of the facility and the cost of initial operation of the facility. Upon a filing by the electrical corporation, the commission may authorize an increase in the maximum cost of construction if it determines that the cost has in fact increased, that the cost increase is determined to be reasonable and prudent, and that the present or future public convenience or necessity require construction of the project at the increased cost.
4545
4646 SECTION 1. Section 399.14 of the Public Utilities Code is amended to read:
4747
4848 ### SECTION 1.
4949
5050 399.14. (a) (1) An electrical corporation, pursuant to Chapter 5 (commencing with Section 1001), and in order to meet its unmet renewables portfolio standard procurement requirements, may apply to the commission for approval to construct, own, and operate an eligible renewable energy resource.(2) If the proposed eligible renewable energy resource complies with the requirements of subdivision (b), the commission shall approve an application filed pursuant to paragraph (1), until the commission has approved applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.(3) The commission may approve additional applications for eligible renewable energy resources once the commission has approved sufficient applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.(b) The commission shall not approve any an application by an electrical corporation pursuant to subdivision (a) unless both of the following conditions are met:(1) The eligible renewable energy resource utilizes a viable technology at a reasonable cost.(2) The eligible renewable energy resource provides comparable or superior value to ratepayers when compared to then recent contracts for generation provided by eligible renewable energy resources.(c) In approving any an application by an electrical corporation for approval to construct, own, and operate an eligible renewable energy resource, the commission shall apply traditional cost-of-service ratemaking. When applying traditional cost-of-service ratemaking, the commission, in the certificate authorizing the new construction, shall specify the maximum cost determined to be reasonable and prudent for the construction of the facility and the cost of initial operation of the facility. Upon a filing by the electrical corporation, the commission may authorize an increase in the maximum cost of construction if it determines that the cost has in fact increased, that the cost increase is determined to be reasonable and prudent, and that the present or future public convenience or necessity require construction of the project at the increased cost.
5151
5252 399.14. (a) (1) An electrical corporation, pursuant to Chapter 5 (commencing with Section 1001), and in order to meet its unmet renewables portfolio standard procurement requirements, may apply to the commission for approval to construct, own, and operate an eligible renewable energy resource.(2) If the proposed eligible renewable energy resource complies with the requirements of subdivision (b), the commission shall approve an application filed pursuant to paragraph (1), until the commission has approved applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.(3) The commission may approve additional applications for eligible renewable energy resources once the commission has approved sufficient applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.(b) The commission shall not approve any an application by an electrical corporation pursuant to subdivision (a) unless both of the following conditions are met:(1) The eligible renewable energy resource utilizes a viable technology at a reasonable cost.(2) The eligible renewable energy resource provides comparable or superior value to ratepayers when compared to then recent contracts for generation provided by eligible renewable energy resources.(c) In approving any an application by an electrical corporation for approval to construct, own, and operate an eligible renewable energy resource, the commission shall apply traditional cost-of-service ratemaking. When applying traditional cost-of-service ratemaking, the commission, in the certificate authorizing the new construction, shall specify the maximum cost determined to be reasonable and prudent for the construction of the facility and the cost of initial operation of the facility. Upon a filing by the electrical corporation, the commission may authorize an increase in the maximum cost of construction if it determines that the cost has in fact increased, that the cost increase is determined to be reasonable and prudent, and that the present or future public convenience or necessity require construction of the project at the increased cost.
5353
5454 399.14. (a) (1) An electrical corporation, pursuant to Chapter 5 (commencing with Section 1001), and in order to meet its unmet renewables portfolio standard procurement requirements, may apply to the commission for approval to construct, own, and operate an eligible renewable energy resource.(2) If the proposed eligible renewable energy resource complies with the requirements of subdivision (b), the commission shall approve an application filed pursuant to paragraph (1), until the commission has approved applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.(3) The commission may approve additional applications for eligible renewable energy resources once the commission has approved sufficient applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.(b) The commission shall not approve any an application by an electrical corporation pursuant to subdivision (a) unless both of the following conditions are met:(1) The eligible renewable energy resource utilizes a viable technology at a reasonable cost.(2) The eligible renewable energy resource provides comparable or superior value to ratepayers when compared to then recent contracts for generation provided by eligible renewable energy resources.(c) In approving any an application by an electrical corporation for approval to construct, own, and operate an eligible renewable energy resource, the commission shall apply traditional cost-of-service ratemaking. When applying traditional cost-of-service ratemaking, the commission, in the certificate authorizing the new construction, shall specify the maximum cost determined to be reasonable and prudent for the construction of the facility and the cost of initial operation of the facility. Upon a filing by the electrical corporation, the commission may authorize an increase in the maximum cost of construction if it determines that the cost has in fact increased, that the cost increase is determined to be reasonable and prudent, and that the present or future public convenience or necessity require construction of the project at the increased cost.
5555
5656
5757
5858 399.14. (a) (1) An electrical corporation, pursuant to Chapter 5 (commencing with Section 1001), and in order to meet its unmet renewables portfolio standard procurement requirements, may apply to the commission for approval to construct, own, and operate an eligible renewable energy resource.
5959
6060 (2) If the proposed eligible renewable energy resource complies with the requirements of subdivision (b), the commission shall approve an application filed pursuant to paragraph (1), until the commission has approved applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.
6161
6262 (3) The commission may approve additional applications for eligible renewable energy resources once the commission has approved sufficient applications for eligible renewable energy resources for the electrical corporation that, when constructed and operating, will provide 8.25 percent of the electrical corporations anticipated retail sales by December 31, 2020, and thereafter.
6363
6464 (b) The commission shall not approve any an application by an electrical corporation pursuant to subdivision (a) unless both of the following conditions are met:
6565
6666 (1) The eligible renewable energy resource utilizes a viable technology at a reasonable cost.
6767
6868 (2) The eligible renewable energy resource provides comparable or superior value to ratepayers when compared to then recent contracts for generation provided by eligible renewable energy resources.
6969
7070 (c) In approving any an application by an electrical corporation for approval to construct, own, and operate an eligible renewable energy resource, the commission shall apply traditional cost-of-service ratemaking. When applying traditional cost-of-service ratemaking, the commission, in the certificate authorizing the new construction, shall specify the maximum cost determined to be reasonable and prudent for the construction of the facility and the cost of initial operation of the facility. Upon a filing by the electrical corporation, the commission may authorize an increase in the maximum cost of construction if it determines that the cost has in fact increased, that the cost increase is determined to be reasonable and prudent, and that the present or future public convenience or necessity require construction of the project at the increased cost.