California 2019-2020 Regular Session

California Senate Bill SB1365 Compare Versions

Only one version of the bill is available at this time.
OldNewDifferences
11 CALIFORNIA LEGISLATURE 20192020 REGULAR SESSION Senate Bill No. 1365Introduced by Senator HertzbergFebruary 21, 2020 An act to amend Section 399.20 of, and to add Section 399.20.1 to, the Public Utilities Code, relating to energy. LEGISLATIVE COUNSEL'S DIGESTSB 1365, as introduced, Hertzberg. California Renewables Portfolio Standard Program: renewable feed-in tariff.Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations. The California Renewables Portfolio Standard Program requires the commission to establish a renewables portfolio standard requiring all retail sellers, defined to include electrical corporations, electric service providers, and community choice aggregators, to procure a minimum quantity of electricity products from eligible renewable energy resources, as defined, so that the total kilowatthours of those products sold to their retail end-use customers achieves 25% of retail sales by December 31, 2016, 33% by December 31, 2020, 44% by December 31, 2024, 52% by December 31, 2027, and 60% by December 31, 2030. The California Renewables Portfolio Standard program additionally requires every electrical corporation to file with the commission a standard tariff for electricity purchased from an electric generation facility, as defined, that qualifies for the tariff, is owned and operated by a retail customer of the electrical corporation, and is located within the service territory of, and developed to sell electricity to, the electrical corporation. The commission refers to this requirement as the renewable feed-in tariff. Existing law requires that the tariff provide for payment for every kilowatthour of electricity purchased from an electric generation facility for a period of 10, 15, or 20 years, as authorized by the commission, requires that the payment be the market price determined by the commission using a methodology established by the commission that considers specified matters, and requires the price to include all current and anticipated environmental compliance costs.This bill would authorize the commission, in its discretion, to instead determine payment through competitive solicitations held not less often than biannually by electrical corporations, or by any other mechanism determined by the commission.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: YES Local Program: NO Bill TextThe people of the State of California do enact as follows:SECTION 1. Section 399.20 of the Public Utilities Code is amended to read:399.20. (a) It is the policy of this state and the intent of the Legislature to encourage electrical generation from eligible renewable energy resources.(b) As used in this section, electric generation facility means an electric generation facility located within the service territory of, and developed to sell electricity to, an electrical corporation that meets all of the following criteria:(1) Has an effective capacity of not more than three megawatts, with the exception of those facilities participating in a tariff made available pursuant to paragraph (2) of subdivision (f).(2) Is interconnected and operates in parallel with the electrical transmission and distribution grid.(3) (A) Except as provided in subparagraph (B), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers.(B) For purposes of paragraph (2) of subdivision (f), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers or is interconnected to an existing transmission line.(4) Is an eligible renewable energy resource.(c) Every electrical corporation shall file with the commission a standard tariff for electricity purchased from an electric generation facility. The commission may modify or adjust the requirements of this section for any electrical corporation with less than 100,000 service connections, as individual circumstances merit.(d) (1) The tariff shall provide for payment for every kilowatthour of electricity purchased from an electric generation facility for a period of 10, 15, or 20 years, as authorized by the commission. The Except as authorized in Section 399.20.1, the payment shall be the market price determined by the commission pursuant to paragraph (2) this subdivision and shall include all current and anticipated environmental compliance costs, including, but not limited to, mitigation of emissions of greenhouse gases and air pollution offsets associated with the operation of new generating facilities in the local air pollution control or air quality management district where the electric generation facility is located.(2) The commission shall establish a methodology to determine the market price of electricity for terms corresponding to the length of contracts with an electric generation facility, in consideration of the following:(A) The long-term market price of electricity for fixed price contracts, determined pursuant to an electrical corporations general procurement activities as authorized by the commission.(B) The long-term ownership, operating, and fixed-price fuel costs associated with fixed-price electricity from new generating facilities.(C) The value of different electricity products including baseload, peaking, and as-available electricity.(3) The commission may adjust the payment rate to reflect the value of every kilowatthour of electricity generated on a time-of-delivery basis.(4) The commission shall ensure, with respect to rates and charges, that ratepayers that do not receive service pursuant to the tariff are indifferent to whether a ratepayer with an electric generation facility receives service pursuant to the tariff.(e) An electrical corporation shall provide expedited interconnection procedures to an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit, if the electrical corporation determines that the electric generation facility will not adversely affect the distribution grid. The commission shall consider and may establish a value for an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit.(f) (1) An electrical corporation shall make the tariff available to the owner or operator of an electric generation facility within the service territory of the electrical corporation, upon request, on a first-come-first-served basis, until the electrical corporation meets its proportionate share of a statewide cap of 750 megawatts cumulative rated generation capacity served under this section and Section 399.32. The proportionate share shall be calculated based on the ratio of the electrical corporations peak demand compared to the total statewide peak demand.(2) By June 1, 2013, the commission shall, in addition to the 750 megawatts identified in paragraph (1), direct the electrical corporations to collectively procure at least 250 megawatts of cumulative rated generating capacity from developers of bioenergy projects that commence operation on or after June 1, 2013. The commission shall, for each electrical corporation, allocate shares of the additional 250 megawatts based on the ratio of each electrical corporations peak demand compared to the total statewide peak demand. In implementing this paragraph, the commission shall do all of the following:(A) Allocate the 250 megawatts identified in this paragraph among the electrical corporations based on the following categories:(i) For biogas from wastewater treatment, municipal organic waste diversion, food processing, and codigestion, 110 megawatts.(ii) For dairy and other agricultural bioenergy, 90 megawatts.(iii) For bioenergy using byproducts of sustainable forest management, 50 megawatts. Allocations under this category shall be determined based on the proportion of bioenergy that sustainable forest management providers derive from sustainable forest management in fire threat treatment areas, as designated by the Department of Forestry and Fire Protection.(B) Direct the electrical corporations to develop standard contract terms and conditions that reflect the operational characteristics of the projects, and to provide a streamlined contracting process.(C) Coordinate, to the maximum extent feasible, any incentive or subsidy programs for bioenergy with the agencies listed in subparagraph (A) of paragraph (3) in order to provide maximum benefits to ratepayers and to ensure that incentives are used to reduce contract prices.(D) The commission shall encourage gas and electrical corporations to develop and offer programs and services to facilitate development of in-state biogas for a broad range of purposes.(E) Direct the electrical corporations to authorize a bioenergy electric generation facility with an effective capacity of up to five megawatts to participate in the tariff made available pursuant to this paragraph, if it meets the following conditions:(i) It delivers no more than three megawatts to the grid at any time.(ii) It complies with the electrical corporations Electric Rule 21 tariff or other distribution access tariff.(F) Payment Ensure payment is made pursuant to paragraph (1) of subdivision (d) or Section 399.20.1 and no payment is made for any electricity delivered to the grid in excess of three megawatts at any time.(3) (A) The commission, in consultation with the Energy Commission, the State Air Resources Board, the Department of Forestry and Fire Protection, the Department of Food and Agriculture, and the Department of Resources Recycling and Recovery, may review the allocations of the 250 additional megawatts identified in paragraph (2) to determine if those allocations are appropriate.(B) If the commission finds that the allocations of the 250 additional megawatts identified in paragraph (2) are not appropriate, the commission may reallocate the 250 megawatts among the categories established in subparagraph (A) of paragraph (2).(4) (A) A project identified in clause (iii) of subparagraph (A) of paragraph (2) is eligible, in regards to interconnection, for the tariff established to implement paragraph (2) or to participate in any program or auction established to implement paragraph (2), if it meets at least one of the following requirements:(i) The project is already interconnected.(ii) The project has been found to be eligible for interconnection pursuant to the fast track process under the relevant tariff.(iii) A system impact study or other interconnection study has been completed for the project under the relevant tariff, and there was no determination in the study that, with the identified interconnection upgrades, if any, a condition specified in paragraph (2), (3), or (4) of subdivision (n) would exist. Such a project is not required to have a pending, active interconnection application to be eligible.(B) For a project meeting the eligibility requirements pursuant to clause (iii) of subparagraph (A) of this paragraph, both of the following apply:(i) The project is hereby deemed to be able to interconnect within the required time limits for the purpose of determining eligibility for the tariff.(ii) The project shall submit a new application for interconnection within 30 days of execution of a standard contract pursuant to the tariff if it does not have a pending, active interconnection application or a completed interconnection. For those projects, the time to achieve commercial operation shall begin to run from the date when the new system impact study or other interconnection study is completed rather than from the date of execution of the standard contract.(5) For the purposes of this subdivision, bioenergy means biogas and biomass.(g) The electrical corporation may make the terms of the tariff available to owners and operators of an electric generation facility in the form of a standard contract subject to commission approval.(h) Every kilowatthour of electricity purchased from an electric generation facility shall count toward meeting the electrical corporations renewables portfolio standard annual procurement targets for purposes of paragraph (1) of subdivision (b) of Section 399.15.(i) The physical generating capacity of an electric generation facility shall count toward the electrical corporations resource adequacy requirement for purposes of Section 380.(j) (1) The commission shall establish performance standards for any electric generation facility that has a capacity greater than one megawatt to ensure that those facilities are constructed, operated, and maintained to generate the expected annual net production of electricity and do not impact system reliability.(2) The commission may reduce the three megawatt capacity limitation of paragraph (1) of subdivision (b) if the commission finds that a reduced capacity limitation is necessary to maintain system reliability within that electrical corporations service territory.(k) (1) Any owner or operator of an electric generation facility that received ratepayer-funded incentives in accordance with Section 379.6 of this code, or with Section 25782 of the Public Resources Code, and participated in a net metering program pursuant to Sections 2827, 2827.9, and 2827.10 of this code before January 1, 2010, shall be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section.(2) In establishing the tariffs or standard contracts pursuant to this section, the commission shall consider ratepayer-funded incentive payments previously received by the generation facility pursuant to Section 379.6 of this code or Section 25782 of the Public Resources Code. The commission shall require reimbursement of any funds received from these incentive programs to an electric generation facility, in order for that facility to be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section, unless the commission determines ratepayers have received sufficient value from the incentives provided to the facility based on how long the project has been in operation and the amount of renewable electricity previously generated by the facility.(3) A customer that receives service under a tariff or contract approved by the commission pursuant to this section is not eligible to participate in any net metering program.(l) An owner or operator of an electric generation facility electing to receive service under a tariff or contract approved by the commission shall continue to receive service under the tariff or contract until either of the following occurs:(1) The owner or operator of an electric generation facility no longer meets the eligibility requirements for receiving service pursuant to the tariff or contract.(2) The period of service established by the commission pursuant to subdivision (d) is completed.(m) Within 10 days of receipt of a request for a tariff pursuant to this section from an owner or operator of an electric generation facility, the electrical corporation that receives the request shall post a copy of the request on its internet website. The information posted on the internet website shall include the name of the city in which the facility is located, but information that is proprietary and confidential, including, but not limited to, address information beyond the name of the city in which the facility is located, shall be redacted.(n) An electrical corporation may deny a tariff request pursuant to this section if the electrical corporation makes any of the following findings:(1) The electric generation facility does not meet the requirements of this section.(2) The transmission or distribution grid that would serve as the point of interconnection is inadequate.(3) The electric generation facility does not meet all applicable state and local laws and building standards and utility interconnection requirements.(4) The aggregate of all electric generating facilities on a distribution circuit would adversely impact utility operation and load restoration efforts of the distribution system.(o) Upon receiving a notice of denial from an electrical corporation, the owner or operator of the electric generation facility denied a tariff pursuant to this section shall have the right to appeal that decision to the commission.(p) In order to ensure the safety and reliability of electric generation facilities, the owner of an electric generation facility receiving a tariff pursuant to this section shall provide an inspection and maintenance report to the electrical corporation at least once every other year. The inspection and maintenance report shall be prepared at the owners or operators expense by a California-licensed contractor who is not the owner or operator of the electric generation facility. A California-licensed electrician shall perform the inspection of the electrical portion of the generation facility.(q) The contract between the electric generation facility receiving the tariff and the electrical corporation shall contain provisions that ensure that construction of the electric generating facility complies with all applicable state and local laws and building standards, and utility interconnection requirements.(r) (1) All construction and installation of facilities of the electrical corporation, including at the point of the output meter or at the transmission or distribution grid, shall be performed only by that electrical corporation.(2) All interconnection facilities installed on the electrical corporations side of the transfer point for electricity between the electrical corporation and the electrical conductors of the electric generation facility shall be owned, operated, and maintained only by the electrical corporation. The ownership, installation, operation, reading, and testing of revenue metering equipment for electric generating facilities shall only be performed by the electrical corporation.SEC. 2. Section 399.20.1 is added to the Public Utilities Code, to read:399.20.1. At the commissions discretion, instead of using the market price determined by the commission pursuant to subdivision (d) of Section 399.20, the payment may be determined through competitive solicitations held not less often than biannually by electrical corporations, or any other mechanism determined by the commission.
22
33 CALIFORNIA LEGISLATURE 20192020 REGULAR SESSION Senate Bill No. 1365Introduced by Senator HertzbergFebruary 21, 2020 An act to amend Section 399.20 of, and to add Section 399.20.1 to, the Public Utilities Code, relating to energy. LEGISLATIVE COUNSEL'S DIGESTSB 1365, as introduced, Hertzberg. California Renewables Portfolio Standard Program: renewable feed-in tariff.Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations. The California Renewables Portfolio Standard Program requires the commission to establish a renewables portfolio standard requiring all retail sellers, defined to include electrical corporations, electric service providers, and community choice aggregators, to procure a minimum quantity of electricity products from eligible renewable energy resources, as defined, so that the total kilowatthours of those products sold to their retail end-use customers achieves 25% of retail sales by December 31, 2016, 33% by December 31, 2020, 44% by December 31, 2024, 52% by December 31, 2027, and 60% by December 31, 2030. The California Renewables Portfolio Standard program additionally requires every electrical corporation to file with the commission a standard tariff for electricity purchased from an electric generation facility, as defined, that qualifies for the tariff, is owned and operated by a retail customer of the electrical corporation, and is located within the service territory of, and developed to sell electricity to, the electrical corporation. The commission refers to this requirement as the renewable feed-in tariff. Existing law requires that the tariff provide for payment for every kilowatthour of electricity purchased from an electric generation facility for a period of 10, 15, or 20 years, as authorized by the commission, requires that the payment be the market price determined by the commission using a methodology established by the commission that considers specified matters, and requires the price to include all current and anticipated environmental compliance costs.This bill would authorize the commission, in its discretion, to instead determine payment through competitive solicitations held not less often than biannually by electrical corporations, or by any other mechanism determined by the commission.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: YES Local Program: NO
44
55
66
77
88
99 CALIFORNIA LEGISLATURE 20192020 REGULAR SESSION
1010
1111 Senate Bill
1212
1313 No. 1365
1414
1515 Introduced by Senator HertzbergFebruary 21, 2020
1616
1717 Introduced by Senator Hertzberg
1818 February 21, 2020
1919
2020 An act to amend Section 399.20 of, and to add Section 399.20.1 to, the Public Utilities Code, relating to energy.
2121
2222 LEGISLATIVE COUNSEL'S DIGEST
2323
2424 ## LEGISLATIVE COUNSEL'S DIGEST
2525
2626 SB 1365, as introduced, Hertzberg. California Renewables Portfolio Standard Program: renewable feed-in tariff.
2727
2828 Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations. The California Renewables Portfolio Standard Program requires the commission to establish a renewables portfolio standard requiring all retail sellers, defined to include electrical corporations, electric service providers, and community choice aggregators, to procure a minimum quantity of electricity products from eligible renewable energy resources, as defined, so that the total kilowatthours of those products sold to their retail end-use customers achieves 25% of retail sales by December 31, 2016, 33% by December 31, 2020, 44% by December 31, 2024, 52% by December 31, 2027, and 60% by December 31, 2030. The California Renewables Portfolio Standard program additionally requires every electrical corporation to file with the commission a standard tariff for electricity purchased from an electric generation facility, as defined, that qualifies for the tariff, is owned and operated by a retail customer of the electrical corporation, and is located within the service territory of, and developed to sell electricity to, the electrical corporation. The commission refers to this requirement as the renewable feed-in tariff. Existing law requires that the tariff provide for payment for every kilowatthour of electricity purchased from an electric generation facility for a period of 10, 15, or 20 years, as authorized by the commission, requires that the payment be the market price determined by the commission using a methodology established by the commission that considers specified matters, and requires the price to include all current and anticipated environmental compliance costs.This bill would authorize the commission, in its discretion, to instead determine payment through competitive solicitations held not less often than biannually by electrical corporations, or by any other mechanism determined by the commission.
2929
3030 Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations. The California Renewables Portfolio Standard Program requires the commission to establish a renewables portfolio standard requiring all retail sellers, defined to include electrical corporations, electric service providers, and community choice aggregators, to procure a minimum quantity of electricity products from eligible renewable energy resources, as defined, so that the total kilowatthours of those products sold to their retail end-use customers achieves 25% of retail sales by December 31, 2016, 33% by December 31, 2020, 44% by December 31, 2024, 52% by December 31, 2027, and 60% by December 31, 2030. The California Renewables Portfolio Standard program additionally requires every electrical corporation to file with the commission a standard tariff for electricity purchased from an electric generation facility, as defined, that qualifies for the tariff, is owned and operated by a retail customer of the electrical corporation, and is located within the service territory of, and developed to sell electricity to, the electrical corporation. The commission refers to this requirement as the renewable feed-in tariff. Existing law requires that the tariff provide for payment for every kilowatthour of electricity purchased from an electric generation facility for a period of 10, 15, or 20 years, as authorized by the commission, requires that the payment be the market price determined by the commission using a methodology established by the commission that considers specified matters, and requires the price to include all current and anticipated environmental compliance costs.
3131
3232 This bill would authorize the commission, in its discretion, to instead determine payment through competitive solicitations held not less often than biannually by electrical corporations, or by any other mechanism determined by the commission.
3333
3434 ## Digest Key
3535
3636 ## Bill Text
3737
3838 The people of the State of California do enact as follows:SECTION 1. Section 399.20 of the Public Utilities Code is amended to read:399.20. (a) It is the policy of this state and the intent of the Legislature to encourage electrical generation from eligible renewable energy resources.(b) As used in this section, electric generation facility means an electric generation facility located within the service territory of, and developed to sell electricity to, an electrical corporation that meets all of the following criteria:(1) Has an effective capacity of not more than three megawatts, with the exception of those facilities participating in a tariff made available pursuant to paragraph (2) of subdivision (f).(2) Is interconnected and operates in parallel with the electrical transmission and distribution grid.(3) (A) Except as provided in subparagraph (B), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers.(B) For purposes of paragraph (2) of subdivision (f), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers or is interconnected to an existing transmission line.(4) Is an eligible renewable energy resource.(c) Every electrical corporation shall file with the commission a standard tariff for electricity purchased from an electric generation facility. The commission may modify or adjust the requirements of this section for any electrical corporation with less than 100,000 service connections, as individual circumstances merit.(d) (1) The tariff shall provide for payment for every kilowatthour of electricity purchased from an electric generation facility for a period of 10, 15, or 20 years, as authorized by the commission. The Except as authorized in Section 399.20.1, the payment shall be the market price determined by the commission pursuant to paragraph (2) this subdivision and shall include all current and anticipated environmental compliance costs, including, but not limited to, mitigation of emissions of greenhouse gases and air pollution offsets associated with the operation of new generating facilities in the local air pollution control or air quality management district where the electric generation facility is located.(2) The commission shall establish a methodology to determine the market price of electricity for terms corresponding to the length of contracts with an electric generation facility, in consideration of the following:(A) The long-term market price of electricity for fixed price contracts, determined pursuant to an electrical corporations general procurement activities as authorized by the commission.(B) The long-term ownership, operating, and fixed-price fuel costs associated with fixed-price electricity from new generating facilities.(C) The value of different electricity products including baseload, peaking, and as-available electricity.(3) The commission may adjust the payment rate to reflect the value of every kilowatthour of electricity generated on a time-of-delivery basis.(4) The commission shall ensure, with respect to rates and charges, that ratepayers that do not receive service pursuant to the tariff are indifferent to whether a ratepayer with an electric generation facility receives service pursuant to the tariff.(e) An electrical corporation shall provide expedited interconnection procedures to an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit, if the electrical corporation determines that the electric generation facility will not adversely affect the distribution grid. The commission shall consider and may establish a value for an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit.(f) (1) An electrical corporation shall make the tariff available to the owner or operator of an electric generation facility within the service territory of the electrical corporation, upon request, on a first-come-first-served basis, until the electrical corporation meets its proportionate share of a statewide cap of 750 megawatts cumulative rated generation capacity served under this section and Section 399.32. The proportionate share shall be calculated based on the ratio of the electrical corporations peak demand compared to the total statewide peak demand.(2) By June 1, 2013, the commission shall, in addition to the 750 megawatts identified in paragraph (1), direct the electrical corporations to collectively procure at least 250 megawatts of cumulative rated generating capacity from developers of bioenergy projects that commence operation on or after June 1, 2013. The commission shall, for each electrical corporation, allocate shares of the additional 250 megawatts based on the ratio of each electrical corporations peak demand compared to the total statewide peak demand. In implementing this paragraph, the commission shall do all of the following:(A) Allocate the 250 megawatts identified in this paragraph among the electrical corporations based on the following categories:(i) For biogas from wastewater treatment, municipal organic waste diversion, food processing, and codigestion, 110 megawatts.(ii) For dairy and other agricultural bioenergy, 90 megawatts.(iii) For bioenergy using byproducts of sustainable forest management, 50 megawatts. Allocations under this category shall be determined based on the proportion of bioenergy that sustainable forest management providers derive from sustainable forest management in fire threat treatment areas, as designated by the Department of Forestry and Fire Protection.(B) Direct the electrical corporations to develop standard contract terms and conditions that reflect the operational characteristics of the projects, and to provide a streamlined contracting process.(C) Coordinate, to the maximum extent feasible, any incentive or subsidy programs for bioenergy with the agencies listed in subparagraph (A) of paragraph (3) in order to provide maximum benefits to ratepayers and to ensure that incentives are used to reduce contract prices.(D) The commission shall encourage gas and electrical corporations to develop and offer programs and services to facilitate development of in-state biogas for a broad range of purposes.(E) Direct the electrical corporations to authorize a bioenergy electric generation facility with an effective capacity of up to five megawatts to participate in the tariff made available pursuant to this paragraph, if it meets the following conditions:(i) It delivers no more than three megawatts to the grid at any time.(ii) It complies with the electrical corporations Electric Rule 21 tariff or other distribution access tariff.(F) Payment Ensure payment is made pursuant to paragraph (1) of subdivision (d) or Section 399.20.1 and no payment is made for any electricity delivered to the grid in excess of three megawatts at any time.(3) (A) The commission, in consultation with the Energy Commission, the State Air Resources Board, the Department of Forestry and Fire Protection, the Department of Food and Agriculture, and the Department of Resources Recycling and Recovery, may review the allocations of the 250 additional megawatts identified in paragraph (2) to determine if those allocations are appropriate.(B) If the commission finds that the allocations of the 250 additional megawatts identified in paragraph (2) are not appropriate, the commission may reallocate the 250 megawatts among the categories established in subparagraph (A) of paragraph (2).(4) (A) A project identified in clause (iii) of subparagraph (A) of paragraph (2) is eligible, in regards to interconnection, for the tariff established to implement paragraph (2) or to participate in any program or auction established to implement paragraph (2), if it meets at least one of the following requirements:(i) The project is already interconnected.(ii) The project has been found to be eligible for interconnection pursuant to the fast track process under the relevant tariff.(iii) A system impact study or other interconnection study has been completed for the project under the relevant tariff, and there was no determination in the study that, with the identified interconnection upgrades, if any, a condition specified in paragraph (2), (3), or (4) of subdivision (n) would exist. Such a project is not required to have a pending, active interconnection application to be eligible.(B) For a project meeting the eligibility requirements pursuant to clause (iii) of subparagraph (A) of this paragraph, both of the following apply:(i) The project is hereby deemed to be able to interconnect within the required time limits for the purpose of determining eligibility for the tariff.(ii) The project shall submit a new application for interconnection within 30 days of execution of a standard contract pursuant to the tariff if it does not have a pending, active interconnection application or a completed interconnection. For those projects, the time to achieve commercial operation shall begin to run from the date when the new system impact study or other interconnection study is completed rather than from the date of execution of the standard contract.(5) For the purposes of this subdivision, bioenergy means biogas and biomass.(g) The electrical corporation may make the terms of the tariff available to owners and operators of an electric generation facility in the form of a standard contract subject to commission approval.(h) Every kilowatthour of electricity purchased from an electric generation facility shall count toward meeting the electrical corporations renewables portfolio standard annual procurement targets for purposes of paragraph (1) of subdivision (b) of Section 399.15.(i) The physical generating capacity of an electric generation facility shall count toward the electrical corporations resource adequacy requirement for purposes of Section 380.(j) (1) The commission shall establish performance standards for any electric generation facility that has a capacity greater than one megawatt to ensure that those facilities are constructed, operated, and maintained to generate the expected annual net production of electricity and do not impact system reliability.(2) The commission may reduce the three megawatt capacity limitation of paragraph (1) of subdivision (b) if the commission finds that a reduced capacity limitation is necessary to maintain system reliability within that electrical corporations service territory.(k) (1) Any owner or operator of an electric generation facility that received ratepayer-funded incentives in accordance with Section 379.6 of this code, or with Section 25782 of the Public Resources Code, and participated in a net metering program pursuant to Sections 2827, 2827.9, and 2827.10 of this code before January 1, 2010, shall be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section.(2) In establishing the tariffs or standard contracts pursuant to this section, the commission shall consider ratepayer-funded incentive payments previously received by the generation facility pursuant to Section 379.6 of this code or Section 25782 of the Public Resources Code. The commission shall require reimbursement of any funds received from these incentive programs to an electric generation facility, in order for that facility to be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section, unless the commission determines ratepayers have received sufficient value from the incentives provided to the facility based on how long the project has been in operation and the amount of renewable electricity previously generated by the facility.(3) A customer that receives service under a tariff or contract approved by the commission pursuant to this section is not eligible to participate in any net metering program.(l) An owner or operator of an electric generation facility electing to receive service under a tariff or contract approved by the commission shall continue to receive service under the tariff or contract until either of the following occurs:(1) The owner or operator of an electric generation facility no longer meets the eligibility requirements for receiving service pursuant to the tariff or contract.(2) The period of service established by the commission pursuant to subdivision (d) is completed.(m) Within 10 days of receipt of a request for a tariff pursuant to this section from an owner or operator of an electric generation facility, the electrical corporation that receives the request shall post a copy of the request on its internet website. The information posted on the internet website shall include the name of the city in which the facility is located, but information that is proprietary and confidential, including, but not limited to, address information beyond the name of the city in which the facility is located, shall be redacted.(n) An electrical corporation may deny a tariff request pursuant to this section if the electrical corporation makes any of the following findings:(1) The electric generation facility does not meet the requirements of this section.(2) The transmission or distribution grid that would serve as the point of interconnection is inadequate.(3) The electric generation facility does not meet all applicable state and local laws and building standards and utility interconnection requirements.(4) The aggregate of all electric generating facilities on a distribution circuit would adversely impact utility operation and load restoration efforts of the distribution system.(o) Upon receiving a notice of denial from an electrical corporation, the owner or operator of the electric generation facility denied a tariff pursuant to this section shall have the right to appeal that decision to the commission.(p) In order to ensure the safety and reliability of electric generation facilities, the owner of an electric generation facility receiving a tariff pursuant to this section shall provide an inspection and maintenance report to the electrical corporation at least once every other year. The inspection and maintenance report shall be prepared at the owners or operators expense by a California-licensed contractor who is not the owner or operator of the electric generation facility. A California-licensed electrician shall perform the inspection of the electrical portion of the generation facility.(q) The contract between the electric generation facility receiving the tariff and the electrical corporation shall contain provisions that ensure that construction of the electric generating facility complies with all applicable state and local laws and building standards, and utility interconnection requirements.(r) (1) All construction and installation of facilities of the electrical corporation, including at the point of the output meter or at the transmission or distribution grid, shall be performed only by that electrical corporation.(2) All interconnection facilities installed on the electrical corporations side of the transfer point for electricity between the electrical corporation and the electrical conductors of the electric generation facility shall be owned, operated, and maintained only by the electrical corporation. The ownership, installation, operation, reading, and testing of revenue metering equipment for electric generating facilities shall only be performed by the electrical corporation.SEC. 2. Section 399.20.1 is added to the Public Utilities Code, to read:399.20.1. At the commissions discretion, instead of using the market price determined by the commission pursuant to subdivision (d) of Section 399.20, the payment may be determined through competitive solicitations held not less often than biannually by electrical corporations, or any other mechanism determined by the commission.
3939
4040 The people of the State of California do enact as follows:
4141
4242 ## The people of the State of California do enact as follows:
4343
4444 SECTION 1. Section 399.20 of the Public Utilities Code is amended to read:399.20. (a) It is the policy of this state and the intent of the Legislature to encourage electrical generation from eligible renewable energy resources.(b) As used in this section, electric generation facility means an electric generation facility located within the service territory of, and developed to sell electricity to, an electrical corporation that meets all of the following criteria:(1) Has an effective capacity of not more than three megawatts, with the exception of those facilities participating in a tariff made available pursuant to paragraph (2) of subdivision (f).(2) Is interconnected and operates in parallel with the electrical transmission and distribution grid.(3) (A) Except as provided in subparagraph (B), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers.(B) For purposes of paragraph (2) of subdivision (f), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers or is interconnected to an existing transmission line.(4) Is an eligible renewable energy resource.(c) Every electrical corporation shall file with the commission a standard tariff for electricity purchased from an electric generation facility. The commission may modify or adjust the requirements of this section for any electrical corporation with less than 100,000 service connections, as individual circumstances merit.(d) (1) The tariff shall provide for payment for every kilowatthour of electricity purchased from an electric generation facility for a period of 10, 15, or 20 years, as authorized by the commission. The Except as authorized in Section 399.20.1, the payment shall be the market price determined by the commission pursuant to paragraph (2) this subdivision and shall include all current and anticipated environmental compliance costs, including, but not limited to, mitigation of emissions of greenhouse gases and air pollution offsets associated with the operation of new generating facilities in the local air pollution control or air quality management district where the electric generation facility is located.(2) The commission shall establish a methodology to determine the market price of electricity for terms corresponding to the length of contracts with an electric generation facility, in consideration of the following:(A) The long-term market price of electricity for fixed price contracts, determined pursuant to an electrical corporations general procurement activities as authorized by the commission.(B) The long-term ownership, operating, and fixed-price fuel costs associated with fixed-price electricity from new generating facilities.(C) The value of different electricity products including baseload, peaking, and as-available electricity.(3) The commission may adjust the payment rate to reflect the value of every kilowatthour of electricity generated on a time-of-delivery basis.(4) The commission shall ensure, with respect to rates and charges, that ratepayers that do not receive service pursuant to the tariff are indifferent to whether a ratepayer with an electric generation facility receives service pursuant to the tariff.(e) An electrical corporation shall provide expedited interconnection procedures to an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit, if the electrical corporation determines that the electric generation facility will not adversely affect the distribution grid. The commission shall consider and may establish a value for an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit.(f) (1) An electrical corporation shall make the tariff available to the owner or operator of an electric generation facility within the service territory of the electrical corporation, upon request, on a first-come-first-served basis, until the electrical corporation meets its proportionate share of a statewide cap of 750 megawatts cumulative rated generation capacity served under this section and Section 399.32. The proportionate share shall be calculated based on the ratio of the electrical corporations peak demand compared to the total statewide peak demand.(2) By June 1, 2013, the commission shall, in addition to the 750 megawatts identified in paragraph (1), direct the electrical corporations to collectively procure at least 250 megawatts of cumulative rated generating capacity from developers of bioenergy projects that commence operation on or after June 1, 2013. The commission shall, for each electrical corporation, allocate shares of the additional 250 megawatts based on the ratio of each electrical corporations peak demand compared to the total statewide peak demand. In implementing this paragraph, the commission shall do all of the following:(A) Allocate the 250 megawatts identified in this paragraph among the electrical corporations based on the following categories:(i) For biogas from wastewater treatment, municipal organic waste diversion, food processing, and codigestion, 110 megawatts.(ii) For dairy and other agricultural bioenergy, 90 megawatts.(iii) For bioenergy using byproducts of sustainable forest management, 50 megawatts. Allocations under this category shall be determined based on the proportion of bioenergy that sustainable forest management providers derive from sustainable forest management in fire threat treatment areas, as designated by the Department of Forestry and Fire Protection.(B) Direct the electrical corporations to develop standard contract terms and conditions that reflect the operational characteristics of the projects, and to provide a streamlined contracting process.(C) Coordinate, to the maximum extent feasible, any incentive or subsidy programs for bioenergy with the agencies listed in subparagraph (A) of paragraph (3) in order to provide maximum benefits to ratepayers and to ensure that incentives are used to reduce contract prices.(D) The commission shall encourage gas and electrical corporations to develop and offer programs and services to facilitate development of in-state biogas for a broad range of purposes.(E) Direct the electrical corporations to authorize a bioenergy electric generation facility with an effective capacity of up to five megawatts to participate in the tariff made available pursuant to this paragraph, if it meets the following conditions:(i) It delivers no more than three megawatts to the grid at any time.(ii) It complies with the electrical corporations Electric Rule 21 tariff or other distribution access tariff.(F) Payment Ensure payment is made pursuant to paragraph (1) of subdivision (d) or Section 399.20.1 and no payment is made for any electricity delivered to the grid in excess of three megawatts at any time.(3) (A) The commission, in consultation with the Energy Commission, the State Air Resources Board, the Department of Forestry and Fire Protection, the Department of Food and Agriculture, and the Department of Resources Recycling and Recovery, may review the allocations of the 250 additional megawatts identified in paragraph (2) to determine if those allocations are appropriate.(B) If the commission finds that the allocations of the 250 additional megawatts identified in paragraph (2) are not appropriate, the commission may reallocate the 250 megawatts among the categories established in subparagraph (A) of paragraph (2).(4) (A) A project identified in clause (iii) of subparagraph (A) of paragraph (2) is eligible, in regards to interconnection, for the tariff established to implement paragraph (2) or to participate in any program or auction established to implement paragraph (2), if it meets at least one of the following requirements:(i) The project is already interconnected.(ii) The project has been found to be eligible for interconnection pursuant to the fast track process under the relevant tariff.(iii) A system impact study or other interconnection study has been completed for the project under the relevant tariff, and there was no determination in the study that, with the identified interconnection upgrades, if any, a condition specified in paragraph (2), (3), or (4) of subdivision (n) would exist. Such a project is not required to have a pending, active interconnection application to be eligible.(B) For a project meeting the eligibility requirements pursuant to clause (iii) of subparagraph (A) of this paragraph, both of the following apply:(i) The project is hereby deemed to be able to interconnect within the required time limits for the purpose of determining eligibility for the tariff.(ii) The project shall submit a new application for interconnection within 30 days of execution of a standard contract pursuant to the tariff if it does not have a pending, active interconnection application or a completed interconnection. For those projects, the time to achieve commercial operation shall begin to run from the date when the new system impact study or other interconnection study is completed rather than from the date of execution of the standard contract.(5) For the purposes of this subdivision, bioenergy means biogas and biomass.(g) The electrical corporation may make the terms of the tariff available to owners and operators of an electric generation facility in the form of a standard contract subject to commission approval.(h) Every kilowatthour of electricity purchased from an electric generation facility shall count toward meeting the electrical corporations renewables portfolio standard annual procurement targets for purposes of paragraph (1) of subdivision (b) of Section 399.15.(i) The physical generating capacity of an electric generation facility shall count toward the electrical corporations resource adequacy requirement for purposes of Section 380.(j) (1) The commission shall establish performance standards for any electric generation facility that has a capacity greater than one megawatt to ensure that those facilities are constructed, operated, and maintained to generate the expected annual net production of electricity and do not impact system reliability.(2) The commission may reduce the three megawatt capacity limitation of paragraph (1) of subdivision (b) if the commission finds that a reduced capacity limitation is necessary to maintain system reliability within that electrical corporations service territory.(k) (1) Any owner or operator of an electric generation facility that received ratepayer-funded incentives in accordance with Section 379.6 of this code, or with Section 25782 of the Public Resources Code, and participated in a net metering program pursuant to Sections 2827, 2827.9, and 2827.10 of this code before January 1, 2010, shall be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section.(2) In establishing the tariffs or standard contracts pursuant to this section, the commission shall consider ratepayer-funded incentive payments previously received by the generation facility pursuant to Section 379.6 of this code or Section 25782 of the Public Resources Code. The commission shall require reimbursement of any funds received from these incentive programs to an electric generation facility, in order for that facility to be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section, unless the commission determines ratepayers have received sufficient value from the incentives provided to the facility based on how long the project has been in operation and the amount of renewable electricity previously generated by the facility.(3) A customer that receives service under a tariff or contract approved by the commission pursuant to this section is not eligible to participate in any net metering program.(l) An owner or operator of an electric generation facility electing to receive service under a tariff or contract approved by the commission shall continue to receive service under the tariff or contract until either of the following occurs:(1) The owner or operator of an electric generation facility no longer meets the eligibility requirements for receiving service pursuant to the tariff or contract.(2) The period of service established by the commission pursuant to subdivision (d) is completed.(m) Within 10 days of receipt of a request for a tariff pursuant to this section from an owner or operator of an electric generation facility, the electrical corporation that receives the request shall post a copy of the request on its internet website. The information posted on the internet website shall include the name of the city in which the facility is located, but information that is proprietary and confidential, including, but not limited to, address information beyond the name of the city in which the facility is located, shall be redacted.(n) An electrical corporation may deny a tariff request pursuant to this section if the electrical corporation makes any of the following findings:(1) The electric generation facility does not meet the requirements of this section.(2) The transmission or distribution grid that would serve as the point of interconnection is inadequate.(3) The electric generation facility does not meet all applicable state and local laws and building standards and utility interconnection requirements.(4) The aggregate of all electric generating facilities on a distribution circuit would adversely impact utility operation and load restoration efforts of the distribution system.(o) Upon receiving a notice of denial from an electrical corporation, the owner or operator of the electric generation facility denied a tariff pursuant to this section shall have the right to appeal that decision to the commission.(p) In order to ensure the safety and reliability of electric generation facilities, the owner of an electric generation facility receiving a tariff pursuant to this section shall provide an inspection and maintenance report to the electrical corporation at least once every other year. The inspection and maintenance report shall be prepared at the owners or operators expense by a California-licensed contractor who is not the owner or operator of the electric generation facility. A California-licensed electrician shall perform the inspection of the electrical portion of the generation facility.(q) The contract between the electric generation facility receiving the tariff and the electrical corporation shall contain provisions that ensure that construction of the electric generating facility complies with all applicable state and local laws and building standards, and utility interconnection requirements.(r) (1) All construction and installation of facilities of the electrical corporation, including at the point of the output meter or at the transmission or distribution grid, shall be performed only by that electrical corporation.(2) All interconnection facilities installed on the electrical corporations side of the transfer point for electricity between the electrical corporation and the electrical conductors of the electric generation facility shall be owned, operated, and maintained only by the electrical corporation. The ownership, installation, operation, reading, and testing of revenue metering equipment for electric generating facilities shall only be performed by the electrical corporation.
4545
4646 SECTION 1. Section 399.20 of the Public Utilities Code is amended to read:
4747
4848 ### SECTION 1.
4949
5050 399.20. (a) It is the policy of this state and the intent of the Legislature to encourage electrical generation from eligible renewable energy resources.(b) As used in this section, electric generation facility means an electric generation facility located within the service territory of, and developed to sell electricity to, an electrical corporation that meets all of the following criteria:(1) Has an effective capacity of not more than three megawatts, with the exception of those facilities participating in a tariff made available pursuant to paragraph (2) of subdivision (f).(2) Is interconnected and operates in parallel with the electrical transmission and distribution grid.(3) (A) Except as provided in subparagraph (B), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers.(B) For purposes of paragraph (2) of subdivision (f), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers or is interconnected to an existing transmission line.(4) Is an eligible renewable energy resource.(c) Every electrical corporation shall file with the commission a standard tariff for electricity purchased from an electric generation facility. The commission may modify or adjust the requirements of this section for any electrical corporation with less than 100,000 service connections, as individual circumstances merit.(d) (1) The tariff shall provide for payment for every kilowatthour of electricity purchased from an electric generation facility for a period of 10, 15, or 20 years, as authorized by the commission. The Except as authorized in Section 399.20.1, the payment shall be the market price determined by the commission pursuant to paragraph (2) this subdivision and shall include all current and anticipated environmental compliance costs, including, but not limited to, mitigation of emissions of greenhouse gases and air pollution offsets associated with the operation of new generating facilities in the local air pollution control or air quality management district where the electric generation facility is located.(2) The commission shall establish a methodology to determine the market price of electricity for terms corresponding to the length of contracts with an electric generation facility, in consideration of the following:(A) The long-term market price of electricity for fixed price contracts, determined pursuant to an electrical corporations general procurement activities as authorized by the commission.(B) The long-term ownership, operating, and fixed-price fuel costs associated with fixed-price electricity from new generating facilities.(C) The value of different electricity products including baseload, peaking, and as-available electricity.(3) The commission may adjust the payment rate to reflect the value of every kilowatthour of electricity generated on a time-of-delivery basis.(4) The commission shall ensure, with respect to rates and charges, that ratepayers that do not receive service pursuant to the tariff are indifferent to whether a ratepayer with an electric generation facility receives service pursuant to the tariff.(e) An electrical corporation shall provide expedited interconnection procedures to an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit, if the electrical corporation determines that the electric generation facility will not adversely affect the distribution grid. The commission shall consider and may establish a value for an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit.(f) (1) An electrical corporation shall make the tariff available to the owner or operator of an electric generation facility within the service territory of the electrical corporation, upon request, on a first-come-first-served basis, until the electrical corporation meets its proportionate share of a statewide cap of 750 megawatts cumulative rated generation capacity served under this section and Section 399.32. The proportionate share shall be calculated based on the ratio of the electrical corporations peak demand compared to the total statewide peak demand.(2) By June 1, 2013, the commission shall, in addition to the 750 megawatts identified in paragraph (1), direct the electrical corporations to collectively procure at least 250 megawatts of cumulative rated generating capacity from developers of bioenergy projects that commence operation on or after June 1, 2013. The commission shall, for each electrical corporation, allocate shares of the additional 250 megawatts based on the ratio of each electrical corporations peak demand compared to the total statewide peak demand. In implementing this paragraph, the commission shall do all of the following:(A) Allocate the 250 megawatts identified in this paragraph among the electrical corporations based on the following categories:(i) For biogas from wastewater treatment, municipal organic waste diversion, food processing, and codigestion, 110 megawatts.(ii) For dairy and other agricultural bioenergy, 90 megawatts.(iii) For bioenergy using byproducts of sustainable forest management, 50 megawatts. Allocations under this category shall be determined based on the proportion of bioenergy that sustainable forest management providers derive from sustainable forest management in fire threat treatment areas, as designated by the Department of Forestry and Fire Protection.(B) Direct the electrical corporations to develop standard contract terms and conditions that reflect the operational characteristics of the projects, and to provide a streamlined contracting process.(C) Coordinate, to the maximum extent feasible, any incentive or subsidy programs for bioenergy with the agencies listed in subparagraph (A) of paragraph (3) in order to provide maximum benefits to ratepayers and to ensure that incentives are used to reduce contract prices.(D) The commission shall encourage gas and electrical corporations to develop and offer programs and services to facilitate development of in-state biogas for a broad range of purposes.(E) Direct the electrical corporations to authorize a bioenergy electric generation facility with an effective capacity of up to five megawatts to participate in the tariff made available pursuant to this paragraph, if it meets the following conditions:(i) It delivers no more than three megawatts to the grid at any time.(ii) It complies with the electrical corporations Electric Rule 21 tariff or other distribution access tariff.(F) Payment Ensure payment is made pursuant to paragraph (1) of subdivision (d) or Section 399.20.1 and no payment is made for any electricity delivered to the grid in excess of three megawatts at any time.(3) (A) The commission, in consultation with the Energy Commission, the State Air Resources Board, the Department of Forestry and Fire Protection, the Department of Food and Agriculture, and the Department of Resources Recycling and Recovery, may review the allocations of the 250 additional megawatts identified in paragraph (2) to determine if those allocations are appropriate.(B) If the commission finds that the allocations of the 250 additional megawatts identified in paragraph (2) are not appropriate, the commission may reallocate the 250 megawatts among the categories established in subparagraph (A) of paragraph (2).(4) (A) A project identified in clause (iii) of subparagraph (A) of paragraph (2) is eligible, in regards to interconnection, for the tariff established to implement paragraph (2) or to participate in any program or auction established to implement paragraph (2), if it meets at least one of the following requirements:(i) The project is already interconnected.(ii) The project has been found to be eligible for interconnection pursuant to the fast track process under the relevant tariff.(iii) A system impact study or other interconnection study has been completed for the project under the relevant tariff, and there was no determination in the study that, with the identified interconnection upgrades, if any, a condition specified in paragraph (2), (3), or (4) of subdivision (n) would exist. Such a project is not required to have a pending, active interconnection application to be eligible.(B) For a project meeting the eligibility requirements pursuant to clause (iii) of subparagraph (A) of this paragraph, both of the following apply:(i) The project is hereby deemed to be able to interconnect within the required time limits for the purpose of determining eligibility for the tariff.(ii) The project shall submit a new application for interconnection within 30 days of execution of a standard contract pursuant to the tariff if it does not have a pending, active interconnection application or a completed interconnection. For those projects, the time to achieve commercial operation shall begin to run from the date when the new system impact study or other interconnection study is completed rather than from the date of execution of the standard contract.(5) For the purposes of this subdivision, bioenergy means biogas and biomass.(g) The electrical corporation may make the terms of the tariff available to owners and operators of an electric generation facility in the form of a standard contract subject to commission approval.(h) Every kilowatthour of electricity purchased from an electric generation facility shall count toward meeting the electrical corporations renewables portfolio standard annual procurement targets for purposes of paragraph (1) of subdivision (b) of Section 399.15.(i) The physical generating capacity of an electric generation facility shall count toward the electrical corporations resource adequacy requirement for purposes of Section 380.(j) (1) The commission shall establish performance standards for any electric generation facility that has a capacity greater than one megawatt to ensure that those facilities are constructed, operated, and maintained to generate the expected annual net production of electricity and do not impact system reliability.(2) The commission may reduce the three megawatt capacity limitation of paragraph (1) of subdivision (b) if the commission finds that a reduced capacity limitation is necessary to maintain system reliability within that electrical corporations service territory.(k) (1) Any owner or operator of an electric generation facility that received ratepayer-funded incentives in accordance with Section 379.6 of this code, or with Section 25782 of the Public Resources Code, and participated in a net metering program pursuant to Sections 2827, 2827.9, and 2827.10 of this code before January 1, 2010, shall be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section.(2) In establishing the tariffs or standard contracts pursuant to this section, the commission shall consider ratepayer-funded incentive payments previously received by the generation facility pursuant to Section 379.6 of this code or Section 25782 of the Public Resources Code. The commission shall require reimbursement of any funds received from these incentive programs to an electric generation facility, in order for that facility to be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section, unless the commission determines ratepayers have received sufficient value from the incentives provided to the facility based on how long the project has been in operation and the amount of renewable electricity previously generated by the facility.(3) A customer that receives service under a tariff or contract approved by the commission pursuant to this section is not eligible to participate in any net metering program.(l) An owner or operator of an electric generation facility electing to receive service under a tariff or contract approved by the commission shall continue to receive service under the tariff or contract until either of the following occurs:(1) The owner or operator of an electric generation facility no longer meets the eligibility requirements for receiving service pursuant to the tariff or contract.(2) The period of service established by the commission pursuant to subdivision (d) is completed.(m) Within 10 days of receipt of a request for a tariff pursuant to this section from an owner or operator of an electric generation facility, the electrical corporation that receives the request shall post a copy of the request on its internet website. The information posted on the internet website shall include the name of the city in which the facility is located, but information that is proprietary and confidential, including, but not limited to, address information beyond the name of the city in which the facility is located, shall be redacted.(n) An electrical corporation may deny a tariff request pursuant to this section if the electrical corporation makes any of the following findings:(1) The electric generation facility does not meet the requirements of this section.(2) The transmission or distribution grid that would serve as the point of interconnection is inadequate.(3) The electric generation facility does not meet all applicable state and local laws and building standards and utility interconnection requirements.(4) The aggregate of all electric generating facilities on a distribution circuit would adversely impact utility operation and load restoration efforts of the distribution system.(o) Upon receiving a notice of denial from an electrical corporation, the owner or operator of the electric generation facility denied a tariff pursuant to this section shall have the right to appeal that decision to the commission.(p) In order to ensure the safety and reliability of electric generation facilities, the owner of an electric generation facility receiving a tariff pursuant to this section shall provide an inspection and maintenance report to the electrical corporation at least once every other year. The inspection and maintenance report shall be prepared at the owners or operators expense by a California-licensed contractor who is not the owner or operator of the electric generation facility. A California-licensed electrician shall perform the inspection of the electrical portion of the generation facility.(q) The contract between the electric generation facility receiving the tariff and the electrical corporation shall contain provisions that ensure that construction of the electric generating facility complies with all applicable state and local laws and building standards, and utility interconnection requirements.(r) (1) All construction and installation of facilities of the electrical corporation, including at the point of the output meter or at the transmission or distribution grid, shall be performed only by that electrical corporation.(2) All interconnection facilities installed on the electrical corporations side of the transfer point for electricity between the electrical corporation and the electrical conductors of the electric generation facility shall be owned, operated, and maintained only by the electrical corporation. The ownership, installation, operation, reading, and testing of revenue metering equipment for electric generating facilities shall only be performed by the electrical corporation.
5151
5252 399.20. (a) It is the policy of this state and the intent of the Legislature to encourage electrical generation from eligible renewable energy resources.(b) As used in this section, electric generation facility means an electric generation facility located within the service territory of, and developed to sell electricity to, an electrical corporation that meets all of the following criteria:(1) Has an effective capacity of not more than three megawatts, with the exception of those facilities participating in a tariff made available pursuant to paragraph (2) of subdivision (f).(2) Is interconnected and operates in parallel with the electrical transmission and distribution grid.(3) (A) Except as provided in subparagraph (B), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers.(B) For purposes of paragraph (2) of subdivision (f), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers or is interconnected to an existing transmission line.(4) Is an eligible renewable energy resource.(c) Every electrical corporation shall file with the commission a standard tariff for electricity purchased from an electric generation facility. The commission may modify or adjust the requirements of this section for any electrical corporation with less than 100,000 service connections, as individual circumstances merit.(d) (1) The tariff shall provide for payment for every kilowatthour of electricity purchased from an electric generation facility for a period of 10, 15, or 20 years, as authorized by the commission. The Except as authorized in Section 399.20.1, the payment shall be the market price determined by the commission pursuant to paragraph (2) this subdivision and shall include all current and anticipated environmental compliance costs, including, but not limited to, mitigation of emissions of greenhouse gases and air pollution offsets associated with the operation of new generating facilities in the local air pollution control or air quality management district where the electric generation facility is located.(2) The commission shall establish a methodology to determine the market price of electricity for terms corresponding to the length of contracts with an electric generation facility, in consideration of the following:(A) The long-term market price of electricity for fixed price contracts, determined pursuant to an electrical corporations general procurement activities as authorized by the commission.(B) The long-term ownership, operating, and fixed-price fuel costs associated with fixed-price electricity from new generating facilities.(C) The value of different electricity products including baseload, peaking, and as-available electricity.(3) The commission may adjust the payment rate to reflect the value of every kilowatthour of electricity generated on a time-of-delivery basis.(4) The commission shall ensure, with respect to rates and charges, that ratepayers that do not receive service pursuant to the tariff are indifferent to whether a ratepayer with an electric generation facility receives service pursuant to the tariff.(e) An electrical corporation shall provide expedited interconnection procedures to an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit, if the electrical corporation determines that the electric generation facility will not adversely affect the distribution grid. The commission shall consider and may establish a value for an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit.(f) (1) An electrical corporation shall make the tariff available to the owner or operator of an electric generation facility within the service territory of the electrical corporation, upon request, on a first-come-first-served basis, until the electrical corporation meets its proportionate share of a statewide cap of 750 megawatts cumulative rated generation capacity served under this section and Section 399.32. The proportionate share shall be calculated based on the ratio of the electrical corporations peak demand compared to the total statewide peak demand.(2) By June 1, 2013, the commission shall, in addition to the 750 megawatts identified in paragraph (1), direct the electrical corporations to collectively procure at least 250 megawatts of cumulative rated generating capacity from developers of bioenergy projects that commence operation on or after June 1, 2013. The commission shall, for each electrical corporation, allocate shares of the additional 250 megawatts based on the ratio of each electrical corporations peak demand compared to the total statewide peak demand. In implementing this paragraph, the commission shall do all of the following:(A) Allocate the 250 megawatts identified in this paragraph among the electrical corporations based on the following categories:(i) For biogas from wastewater treatment, municipal organic waste diversion, food processing, and codigestion, 110 megawatts.(ii) For dairy and other agricultural bioenergy, 90 megawatts.(iii) For bioenergy using byproducts of sustainable forest management, 50 megawatts. Allocations under this category shall be determined based on the proportion of bioenergy that sustainable forest management providers derive from sustainable forest management in fire threat treatment areas, as designated by the Department of Forestry and Fire Protection.(B) Direct the electrical corporations to develop standard contract terms and conditions that reflect the operational characteristics of the projects, and to provide a streamlined contracting process.(C) Coordinate, to the maximum extent feasible, any incentive or subsidy programs for bioenergy with the agencies listed in subparagraph (A) of paragraph (3) in order to provide maximum benefits to ratepayers and to ensure that incentives are used to reduce contract prices.(D) The commission shall encourage gas and electrical corporations to develop and offer programs and services to facilitate development of in-state biogas for a broad range of purposes.(E) Direct the electrical corporations to authorize a bioenergy electric generation facility with an effective capacity of up to five megawatts to participate in the tariff made available pursuant to this paragraph, if it meets the following conditions:(i) It delivers no more than three megawatts to the grid at any time.(ii) It complies with the electrical corporations Electric Rule 21 tariff or other distribution access tariff.(F) Payment Ensure payment is made pursuant to paragraph (1) of subdivision (d) or Section 399.20.1 and no payment is made for any electricity delivered to the grid in excess of three megawatts at any time.(3) (A) The commission, in consultation with the Energy Commission, the State Air Resources Board, the Department of Forestry and Fire Protection, the Department of Food and Agriculture, and the Department of Resources Recycling and Recovery, may review the allocations of the 250 additional megawatts identified in paragraph (2) to determine if those allocations are appropriate.(B) If the commission finds that the allocations of the 250 additional megawatts identified in paragraph (2) are not appropriate, the commission may reallocate the 250 megawatts among the categories established in subparagraph (A) of paragraph (2).(4) (A) A project identified in clause (iii) of subparagraph (A) of paragraph (2) is eligible, in regards to interconnection, for the tariff established to implement paragraph (2) or to participate in any program or auction established to implement paragraph (2), if it meets at least one of the following requirements:(i) The project is already interconnected.(ii) The project has been found to be eligible for interconnection pursuant to the fast track process under the relevant tariff.(iii) A system impact study or other interconnection study has been completed for the project under the relevant tariff, and there was no determination in the study that, with the identified interconnection upgrades, if any, a condition specified in paragraph (2), (3), or (4) of subdivision (n) would exist. Such a project is not required to have a pending, active interconnection application to be eligible.(B) For a project meeting the eligibility requirements pursuant to clause (iii) of subparagraph (A) of this paragraph, both of the following apply:(i) The project is hereby deemed to be able to interconnect within the required time limits for the purpose of determining eligibility for the tariff.(ii) The project shall submit a new application for interconnection within 30 days of execution of a standard contract pursuant to the tariff if it does not have a pending, active interconnection application or a completed interconnection. For those projects, the time to achieve commercial operation shall begin to run from the date when the new system impact study or other interconnection study is completed rather than from the date of execution of the standard contract.(5) For the purposes of this subdivision, bioenergy means biogas and biomass.(g) The electrical corporation may make the terms of the tariff available to owners and operators of an electric generation facility in the form of a standard contract subject to commission approval.(h) Every kilowatthour of electricity purchased from an electric generation facility shall count toward meeting the electrical corporations renewables portfolio standard annual procurement targets for purposes of paragraph (1) of subdivision (b) of Section 399.15.(i) The physical generating capacity of an electric generation facility shall count toward the electrical corporations resource adequacy requirement for purposes of Section 380.(j) (1) The commission shall establish performance standards for any electric generation facility that has a capacity greater than one megawatt to ensure that those facilities are constructed, operated, and maintained to generate the expected annual net production of electricity and do not impact system reliability.(2) The commission may reduce the three megawatt capacity limitation of paragraph (1) of subdivision (b) if the commission finds that a reduced capacity limitation is necessary to maintain system reliability within that electrical corporations service territory.(k) (1) Any owner or operator of an electric generation facility that received ratepayer-funded incentives in accordance with Section 379.6 of this code, or with Section 25782 of the Public Resources Code, and participated in a net metering program pursuant to Sections 2827, 2827.9, and 2827.10 of this code before January 1, 2010, shall be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section.(2) In establishing the tariffs or standard contracts pursuant to this section, the commission shall consider ratepayer-funded incentive payments previously received by the generation facility pursuant to Section 379.6 of this code or Section 25782 of the Public Resources Code. The commission shall require reimbursement of any funds received from these incentive programs to an electric generation facility, in order for that facility to be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section, unless the commission determines ratepayers have received sufficient value from the incentives provided to the facility based on how long the project has been in operation and the amount of renewable electricity previously generated by the facility.(3) A customer that receives service under a tariff or contract approved by the commission pursuant to this section is not eligible to participate in any net metering program.(l) An owner or operator of an electric generation facility electing to receive service under a tariff or contract approved by the commission shall continue to receive service under the tariff or contract until either of the following occurs:(1) The owner or operator of an electric generation facility no longer meets the eligibility requirements for receiving service pursuant to the tariff or contract.(2) The period of service established by the commission pursuant to subdivision (d) is completed.(m) Within 10 days of receipt of a request for a tariff pursuant to this section from an owner or operator of an electric generation facility, the electrical corporation that receives the request shall post a copy of the request on its internet website. The information posted on the internet website shall include the name of the city in which the facility is located, but information that is proprietary and confidential, including, but not limited to, address information beyond the name of the city in which the facility is located, shall be redacted.(n) An electrical corporation may deny a tariff request pursuant to this section if the electrical corporation makes any of the following findings:(1) The electric generation facility does not meet the requirements of this section.(2) The transmission or distribution grid that would serve as the point of interconnection is inadequate.(3) The electric generation facility does not meet all applicable state and local laws and building standards and utility interconnection requirements.(4) The aggregate of all electric generating facilities on a distribution circuit would adversely impact utility operation and load restoration efforts of the distribution system.(o) Upon receiving a notice of denial from an electrical corporation, the owner or operator of the electric generation facility denied a tariff pursuant to this section shall have the right to appeal that decision to the commission.(p) In order to ensure the safety and reliability of electric generation facilities, the owner of an electric generation facility receiving a tariff pursuant to this section shall provide an inspection and maintenance report to the electrical corporation at least once every other year. The inspection and maintenance report shall be prepared at the owners or operators expense by a California-licensed contractor who is not the owner or operator of the electric generation facility. A California-licensed electrician shall perform the inspection of the electrical portion of the generation facility.(q) The contract between the electric generation facility receiving the tariff and the electrical corporation shall contain provisions that ensure that construction of the electric generating facility complies with all applicable state and local laws and building standards, and utility interconnection requirements.(r) (1) All construction and installation of facilities of the electrical corporation, including at the point of the output meter or at the transmission or distribution grid, shall be performed only by that electrical corporation.(2) All interconnection facilities installed on the electrical corporations side of the transfer point for electricity between the electrical corporation and the electrical conductors of the electric generation facility shall be owned, operated, and maintained only by the electrical corporation. The ownership, installation, operation, reading, and testing of revenue metering equipment for electric generating facilities shall only be performed by the electrical corporation.
5353
5454 399.20. (a) It is the policy of this state and the intent of the Legislature to encourage electrical generation from eligible renewable energy resources.(b) As used in this section, electric generation facility means an electric generation facility located within the service territory of, and developed to sell electricity to, an electrical corporation that meets all of the following criteria:(1) Has an effective capacity of not more than three megawatts, with the exception of those facilities participating in a tariff made available pursuant to paragraph (2) of subdivision (f).(2) Is interconnected and operates in parallel with the electrical transmission and distribution grid.(3) (A) Except as provided in subparagraph (B), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers.(B) For purposes of paragraph (2) of subdivision (f), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers or is interconnected to an existing transmission line.(4) Is an eligible renewable energy resource.(c) Every electrical corporation shall file with the commission a standard tariff for electricity purchased from an electric generation facility. The commission may modify or adjust the requirements of this section for any electrical corporation with less than 100,000 service connections, as individual circumstances merit.(d) (1) The tariff shall provide for payment for every kilowatthour of electricity purchased from an electric generation facility for a period of 10, 15, or 20 years, as authorized by the commission. The Except as authorized in Section 399.20.1, the payment shall be the market price determined by the commission pursuant to paragraph (2) this subdivision and shall include all current and anticipated environmental compliance costs, including, but not limited to, mitigation of emissions of greenhouse gases and air pollution offsets associated with the operation of new generating facilities in the local air pollution control or air quality management district where the electric generation facility is located.(2) The commission shall establish a methodology to determine the market price of electricity for terms corresponding to the length of contracts with an electric generation facility, in consideration of the following:(A) The long-term market price of electricity for fixed price contracts, determined pursuant to an electrical corporations general procurement activities as authorized by the commission.(B) The long-term ownership, operating, and fixed-price fuel costs associated with fixed-price electricity from new generating facilities.(C) The value of different electricity products including baseload, peaking, and as-available electricity.(3) The commission may adjust the payment rate to reflect the value of every kilowatthour of electricity generated on a time-of-delivery basis.(4) The commission shall ensure, with respect to rates and charges, that ratepayers that do not receive service pursuant to the tariff are indifferent to whether a ratepayer with an electric generation facility receives service pursuant to the tariff.(e) An electrical corporation shall provide expedited interconnection procedures to an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit, if the electrical corporation determines that the electric generation facility will not adversely affect the distribution grid. The commission shall consider and may establish a value for an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit.(f) (1) An electrical corporation shall make the tariff available to the owner or operator of an electric generation facility within the service territory of the electrical corporation, upon request, on a first-come-first-served basis, until the electrical corporation meets its proportionate share of a statewide cap of 750 megawatts cumulative rated generation capacity served under this section and Section 399.32. The proportionate share shall be calculated based on the ratio of the electrical corporations peak demand compared to the total statewide peak demand.(2) By June 1, 2013, the commission shall, in addition to the 750 megawatts identified in paragraph (1), direct the electrical corporations to collectively procure at least 250 megawatts of cumulative rated generating capacity from developers of bioenergy projects that commence operation on or after June 1, 2013. The commission shall, for each electrical corporation, allocate shares of the additional 250 megawatts based on the ratio of each electrical corporations peak demand compared to the total statewide peak demand. In implementing this paragraph, the commission shall do all of the following:(A) Allocate the 250 megawatts identified in this paragraph among the electrical corporations based on the following categories:(i) For biogas from wastewater treatment, municipal organic waste diversion, food processing, and codigestion, 110 megawatts.(ii) For dairy and other agricultural bioenergy, 90 megawatts.(iii) For bioenergy using byproducts of sustainable forest management, 50 megawatts. Allocations under this category shall be determined based on the proportion of bioenergy that sustainable forest management providers derive from sustainable forest management in fire threat treatment areas, as designated by the Department of Forestry and Fire Protection.(B) Direct the electrical corporations to develop standard contract terms and conditions that reflect the operational characteristics of the projects, and to provide a streamlined contracting process.(C) Coordinate, to the maximum extent feasible, any incentive or subsidy programs for bioenergy with the agencies listed in subparagraph (A) of paragraph (3) in order to provide maximum benefits to ratepayers and to ensure that incentives are used to reduce contract prices.(D) The commission shall encourage gas and electrical corporations to develop and offer programs and services to facilitate development of in-state biogas for a broad range of purposes.(E) Direct the electrical corporations to authorize a bioenergy electric generation facility with an effective capacity of up to five megawatts to participate in the tariff made available pursuant to this paragraph, if it meets the following conditions:(i) It delivers no more than three megawatts to the grid at any time.(ii) It complies with the electrical corporations Electric Rule 21 tariff or other distribution access tariff.(F) Payment Ensure payment is made pursuant to paragraph (1) of subdivision (d) or Section 399.20.1 and no payment is made for any electricity delivered to the grid in excess of three megawatts at any time.(3) (A) The commission, in consultation with the Energy Commission, the State Air Resources Board, the Department of Forestry and Fire Protection, the Department of Food and Agriculture, and the Department of Resources Recycling and Recovery, may review the allocations of the 250 additional megawatts identified in paragraph (2) to determine if those allocations are appropriate.(B) If the commission finds that the allocations of the 250 additional megawatts identified in paragraph (2) are not appropriate, the commission may reallocate the 250 megawatts among the categories established in subparagraph (A) of paragraph (2).(4) (A) A project identified in clause (iii) of subparagraph (A) of paragraph (2) is eligible, in regards to interconnection, for the tariff established to implement paragraph (2) or to participate in any program or auction established to implement paragraph (2), if it meets at least one of the following requirements:(i) The project is already interconnected.(ii) The project has been found to be eligible for interconnection pursuant to the fast track process under the relevant tariff.(iii) A system impact study or other interconnection study has been completed for the project under the relevant tariff, and there was no determination in the study that, with the identified interconnection upgrades, if any, a condition specified in paragraph (2), (3), or (4) of subdivision (n) would exist. Such a project is not required to have a pending, active interconnection application to be eligible.(B) For a project meeting the eligibility requirements pursuant to clause (iii) of subparagraph (A) of this paragraph, both of the following apply:(i) The project is hereby deemed to be able to interconnect within the required time limits for the purpose of determining eligibility for the tariff.(ii) The project shall submit a new application for interconnection within 30 days of execution of a standard contract pursuant to the tariff if it does not have a pending, active interconnection application or a completed interconnection. For those projects, the time to achieve commercial operation shall begin to run from the date when the new system impact study or other interconnection study is completed rather than from the date of execution of the standard contract.(5) For the purposes of this subdivision, bioenergy means biogas and biomass.(g) The electrical corporation may make the terms of the tariff available to owners and operators of an electric generation facility in the form of a standard contract subject to commission approval.(h) Every kilowatthour of electricity purchased from an electric generation facility shall count toward meeting the electrical corporations renewables portfolio standard annual procurement targets for purposes of paragraph (1) of subdivision (b) of Section 399.15.(i) The physical generating capacity of an electric generation facility shall count toward the electrical corporations resource adequacy requirement for purposes of Section 380.(j) (1) The commission shall establish performance standards for any electric generation facility that has a capacity greater than one megawatt to ensure that those facilities are constructed, operated, and maintained to generate the expected annual net production of electricity and do not impact system reliability.(2) The commission may reduce the three megawatt capacity limitation of paragraph (1) of subdivision (b) if the commission finds that a reduced capacity limitation is necessary to maintain system reliability within that electrical corporations service territory.(k) (1) Any owner or operator of an electric generation facility that received ratepayer-funded incentives in accordance with Section 379.6 of this code, or with Section 25782 of the Public Resources Code, and participated in a net metering program pursuant to Sections 2827, 2827.9, and 2827.10 of this code before January 1, 2010, shall be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section.(2) In establishing the tariffs or standard contracts pursuant to this section, the commission shall consider ratepayer-funded incentive payments previously received by the generation facility pursuant to Section 379.6 of this code or Section 25782 of the Public Resources Code. The commission shall require reimbursement of any funds received from these incentive programs to an electric generation facility, in order for that facility to be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section, unless the commission determines ratepayers have received sufficient value from the incentives provided to the facility based on how long the project has been in operation and the amount of renewable electricity previously generated by the facility.(3) A customer that receives service under a tariff or contract approved by the commission pursuant to this section is not eligible to participate in any net metering program.(l) An owner or operator of an electric generation facility electing to receive service under a tariff or contract approved by the commission shall continue to receive service under the tariff or contract until either of the following occurs:(1) The owner or operator of an electric generation facility no longer meets the eligibility requirements for receiving service pursuant to the tariff or contract.(2) The period of service established by the commission pursuant to subdivision (d) is completed.(m) Within 10 days of receipt of a request for a tariff pursuant to this section from an owner or operator of an electric generation facility, the electrical corporation that receives the request shall post a copy of the request on its internet website. The information posted on the internet website shall include the name of the city in which the facility is located, but information that is proprietary and confidential, including, but not limited to, address information beyond the name of the city in which the facility is located, shall be redacted.(n) An electrical corporation may deny a tariff request pursuant to this section if the electrical corporation makes any of the following findings:(1) The electric generation facility does not meet the requirements of this section.(2) The transmission or distribution grid that would serve as the point of interconnection is inadequate.(3) The electric generation facility does not meet all applicable state and local laws and building standards and utility interconnection requirements.(4) The aggregate of all electric generating facilities on a distribution circuit would adversely impact utility operation and load restoration efforts of the distribution system.(o) Upon receiving a notice of denial from an electrical corporation, the owner or operator of the electric generation facility denied a tariff pursuant to this section shall have the right to appeal that decision to the commission.(p) In order to ensure the safety and reliability of electric generation facilities, the owner of an electric generation facility receiving a tariff pursuant to this section shall provide an inspection and maintenance report to the electrical corporation at least once every other year. The inspection and maintenance report shall be prepared at the owners or operators expense by a California-licensed contractor who is not the owner or operator of the electric generation facility. A California-licensed electrician shall perform the inspection of the electrical portion of the generation facility.(q) The contract between the electric generation facility receiving the tariff and the electrical corporation shall contain provisions that ensure that construction of the electric generating facility complies with all applicable state and local laws and building standards, and utility interconnection requirements.(r) (1) All construction and installation of facilities of the electrical corporation, including at the point of the output meter or at the transmission or distribution grid, shall be performed only by that electrical corporation.(2) All interconnection facilities installed on the electrical corporations side of the transfer point for electricity between the electrical corporation and the electrical conductors of the electric generation facility shall be owned, operated, and maintained only by the electrical corporation. The ownership, installation, operation, reading, and testing of revenue metering equipment for electric generating facilities shall only be performed by the electrical corporation.
5555
5656
5757
5858 399.20. (a) It is the policy of this state and the intent of the Legislature to encourage electrical generation from eligible renewable energy resources.
5959
6060 (b) As used in this section, electric generation facility means an electric generation facility located within the service territory of, and developed to sell electricity to, an electrical corporation that meets all of the following criteria:
6161
6262 (1) Has an effective capacity of not more than three megawatts, with the exception of those facilities participating in a tariff made available pursuant to paragraph (2) of subdivision (f).
6363
6464 (2) Is interconnected and operates in parallel with the electrical transmission and distribution grid.
6565
6666 (3) (A) Except as provided in subparagraph (B), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers.
6767
6868 (B) For purposes of paragraph (2) of subdivision (f), is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers or is interconnected to an existing transmission line.
6969
7070 (4) Is an eligible renewable energy resource.
7171
7272 (c) Every electrical corporation shall file with the commission a standard tariff for electricity purchased from an electric generation facility. The commission may modify or adjust the requirements of this section for any electrical corporation with less than 100,000 service connections, as individual circumstances merit.
7373
7474 (d) (1) The tariff shall provide for payment for every kilowatthour of electricity purchased from an electric generation facility for a period of 10, 15, or 20 years, as authorized by the commission. The Except as authorized in Section 399.20.1, the payment shall be the market price determined by the commission pursuant to paragraph (2) this subdivision and shall include all current and anticipated environmental compliance costs, including, but not limited to, mitigation of emissions of greenhouse gases and air pollution offsets associated with the operation of new generating facilities in the local air pollution control or air quality management district where the electric generation facility is located.
7575
7676 (2) The commission shall establish a methodology to determine the market price of electricity for terms corresponding to the length of contracts with an electric generation facility, in consideration of the following:
7777
7878 (A) The long-term market price of electricity for fixed price contracts, determined pursuant to an electrical corporations general procurement activities as authorized by the commission.
7979
8080 (B) The long-term ownership, operating, and fixed-price fuel costs associated with fixed-price electricity from new generating facilities.
8181
8282 (C) The value of different electricity products including baseload, peaking, and as-available electricity.
8383
8484 (3) The commission may adjust the payment rate to reflect the value of every kilowatthour of electricity generated on a time-of-delivery basis.
8585
8686 (4) The commission shall ensure, with respect to rates and charges, that ratepayers that do not receive service pursuant to the tariff are indifferent to whether a ratepayer with an electric generation facility receives service pursuant to the tariff.
8787
8888 (e) An electrical corporation shall provide expedited interconnection procedures to an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit, if the electrical corporation determines that the electric generation facility will not adversely affect the distribution grid. The commission shall consider and may establish a value for an electric generation facility located on a distribution circuit that generates electricity at a time and in a manner so as to offset the peak demand on the distribution circuit.
8989
9090 (f) (1) An electrical corporation shall make the tariff available to the owner or operator of an electric generation facility within the service territory of the electrical corporation, upon request, on a first-come-first-served basis, until the electrical corporation meets its proportionate share of a statewide cap of 750 megawatts cumulative rated generation capacity served under this section and Section 399.32. The proportionate share shall be calculated based on the ratio of the electrical corporations peak demand compared to the total statewide peak demand.
9191
9292 (2) By June 1, 2013, the commission shall, in addition to the 750 megawatts identified in paragraph (1), direct the electrical corporations to collectively procure at least 250 megawatts of cumulative rated generating capacity from developers of bioenergy projects that commence operation on or after June 1, 2013. The commission shall, for each electrical corporation, allocate shares of the additional 250 megawatts based on the ratio of each electrical corporations peak demand compared to the total statewide peak demand. In implementing this paragraph, the commission shall do all of the following:
9393
9494 (A) Allocate the 250 megawatts identified in this paragraph among the electrical corporations based on the following categories:
9595
9696 (i) For biogas from wastewater treatment, municipal organic waste diversion, food processing, and codigestion, 110 megawatts.
9797
9898 (ii) For dairy and other agricultural bioenergy, 90 megawatts.
9999
100100 (iii) For bioenergy using byproducts of sustainable forest management, 50 megawatts. Allocations under this category shall be determined based on the proportion of bioenergy that sustainable forest management providers derive from sustainable forest management in fire threat treatment areas, as designated by the Department of Forestry and Fire Protection.
101101
102102 (B) Direct the electrical corporations to develop standard contract terms and conditions that reflect the operational characteristics of the projects, and to provide a streamlined contracting process.
103103
104104 (C) Coordinate, to the maximum extent feasible, any incentive or subsidy programs for bioenergy with the agencies listed in subparagraph (A) of paragraph (3) in order to provide maximum benefits to ratepayers and to ensure that incentives are used to reduce contract prices.
105105
106106 (D) The commission shall encourage gas and electrical corporations to develop and offer programs and services to facilitate development of in-state biogas for a broad range of purposes.
107107
108108 (E) Direct the electrical corporations to authorize a bioenergy electric generation facility with an effective capacity of up to five megawatts to participate in the tariff made available pursuant to this paragraph, if it meets the following conditions:
109109
110110 (i) It delivers no more than three megawatts to the grid at any time.
111111
112112 (ii) It complies with the electrical corporations Electric Rule 21 tariff or other distribution access tariff.
113113
114114 (F) Payment Ensure payment is made pursuant to paragraph (1) of subdivision (d) or Section 399.20.1 and no payment is made for any electricity delivered to the grid in excess of three megawatts at any time.
115115
116116 (3) (A) The commission, in consultation with the Energy Commission, the State Air Resources Board, the Department of Forestry and Fire Protection, the Department of Food and Agriculture, and the Department of Resources Recycling and Recovery, may review the allocations of the 250 additional megawatts identified in paragraph (2) to determine if those allocations are appropriate.
117117
118118 (B) If the commission finds that the allocations of the 250 additional megawatts identified in paragraph (2) are not appropriate, the commission may reallocate the 250 megawatts among the categories established in subparagraph (A) of paragraph (2).
119119
120120 (4) (A) A project identified in clause (iii) of subparagraph (A) of paragraph (2) is eligible, in regards to interconnection, for the tariff established to implement paragraph (2) or to participate in any program or auction established to implement paragraph (2), if it meets at least one of the following requirements:
121121
122122 (i) The project is already interconnected.
123123
124124 (ii) The project has been found to be eligible for interconnection pursuant to the fast track process under the relevant tariff.
125125
126126 (iii) A system impact study or other interconnection study has been completed for the project under the relevant tariff, and there was no determination in the study that, with the identified interconnection upgrades, if any, a condition specified in paragraph (2), (3), or (4) of subdivision (n) would exist. Such a project is not required to have a pending, active interconnection application to be eligible.
127127
128128 (B) For a project meeting the eligibility requirements pursuant to clause (iii) of subparagraph (A) of this paragraph, both of the following apply:
129129
130130 (i) The project is hereby deemed to be able to interconnect within the required time limits for the purpose of determining eligibility for the tariff.
131131
132132 (ii) The project shall submit a new application for interconnection within 30 days of execution of a standard contract pursuant to the tariff if it does not have a pending, active interconnection application or a completed interconnection. For those projects, the time to achieve commercial operation shall begin to run from the date when the new system impact study or other interconnection study is completed rather than from the date of execution of the standard contract.
133133
134134 (5) For the purposes of this subdivision, bioenergy means biogas and biomass.
135135
136136 (g) The electrical corporation may make the terms of the tariff available to owners and operators of an electric generation facility in the form of a standard contract subject to commission approval.
137137
138138 (h) Every kilowatthour of electricity purchased from an electric generation facility shall count toward meeting the electrical corporations renewables portfolio standard annual procurement targets for purposes of paragraph (1) of subdivision (b) of Section 399.15.
139139
140140 (i) The physical generating capacity of an electric generation facility shall count toward the electrical corporations resource adequacy requirement for purposes of Section 380.
141141
142142 (j) (1) The commission shall establish performance standards for any electric generation facility that has a capacity greater than one megawatt to ensure that those facilities are constructed, operated, and maintained to generate the expected annual net production of electricity and do not impact system reliability.
143143
144144 (2) The commission may reduce the three megawatt capacity limitation of paragraph (1) of subdivision (b) if the commission finds that a reduced capacity limitation is necessary to maintain system reliability within that electrical corporations service territory.
145145
146146 (k) (1) Any owner or operator of an electric generation facility that received ratepayer-funded incentives in accordance with Section 379.6 of this code, or with Section 25782 of the Public Resources Code, and participated in a net metering program pursuant to Sections 2827, 2827.9, and 2827.10 of this code before January 1, 2010, shall be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section.
147147
148148 (2) In establishing the tariffs or standard contracts pursuant to this section, the commission shall consider ratepayer-funded incentive payments previously received by the generation facility pursuant to Section 379.6 of this code or Section 25782 of the Public Resources Code. The commission shall require reimbursement of any funds received from these incentive programs to an electric generation facility, in order for that facility to be eligible for a tariff or standard contract filed by an electrical corporation pursuant to this section, unless the commission determines ratepayers have received sufficient value from the incentives provided to the facility based on how long the project has been in operation and the amount of renewable electricity previously generated by the facility.
149149
150150 (3) A customer that receives service under a tariff or contract approved by the commission pursuant to this section is not eligible to participate in any net metering program.
151151
152152 (l) An owner or operator of an electric generation facility electing to receive service under a tariff or contract approved by the commission shall continue to receive service under the tariff or contract until either of the following occurs:
153153
154154 (1) The owner or operator of an electric generation facility no longer meets the eligibility requirements for receiving service pursuant to the tariff or contract.
155155
156156 (2) The period of service established by the commission pursuant to subdivision (d) is completed.
157157
158158 (m) Within 10 days of receipt of a request for a tariff pursuant to this section from an owner or operator of an electric generation facility, the electrical corporation that receives the request shall post a copy of the request on its internet website. The information posted on the internet website shall include the name of the city in which the facility is located, but information that is proprietary and confidential, including, but not limited to, address information beyond the name of the city in which the facility is located, shall be redacted.
159159
160160 (n) An electrical corporation may deny a tariff request pursuant to this section if the electrical corporation makes any of the following findings:
161161
162162 (1) The electric generation facility does not meet the requirements of this section.
163163
164164 (2) The transmission or distribution grid that would serve as the point of interconnection is inadequate.
165165
166166 (3) The electric generation facility does not meet all applicable state and local laws and building standards and utility interconnection requirements.
167167
168168 (4) The aggregate of all electric generating facilities on a distribution circuit would adversely impact utility operation and load restoration efforts of the distribution system.
169169
170170 (o) Upon receiving a notice of denial from an electrical corporation, the owner or operator of the electric generation facility denied a tariff pursuant to this section shall have the right to appeal that decision to the commission.
171171
172172 (p) In order to ensure the safety and reliability of electric generation facilities, the owner of an electric generation facility receiving a tariff pursuant to this section shall provide an inspection and maintenance report to the electrical corporation at least once every other year. The inspection and maintenance report shall be prepared at the owners or operators expense by a California-licensed contractor who is not the owner or operator of the electric generation facility. A California-licensed electrician shall perform the inspection of the electrical portion of the generation facility.
173173
174174 (q) The contract between the electric generation facility receiving the tariff and the electrical corporation shall contain provisions that ensure that construction of the electric generating facility complies with all applicable state and local laws and building standards, and utility interconnection requirements.
175175
176176 (r) (1) All construction and installation of facilities of the electrical corporation, including at the point of the output meter or at the transmission or distribution grid, shall be performed only by that electrical corporation.
177177
178178 (2) All interconnection facilities installed on the electrical corporations side of the transfer point for electricity between the electrical corporation and the electrical conductors of the electric generation facility shall be owned, operated, and maintained only by the electrical corporation. The ownership, installation, operation, reading, and testing of revenue metering equipment for electric generating facilities shall only be performed by the electrical corporation.
179179
180180 SEC. 2. Section 399.20.1 is added to the Public Utilities Code, to read:399.20.1. At the commissions discretion, instead of using the market price determined by the commission pursuant to subdivision (d) of Section 399.20, the payment may be determined through competitive solicitations held not less often than biannually by electrical corporations, or any other mechanism determined by the commission.
181181
182182 SEC. 2. Section 399.20.1 is added to the Public Utilities Code, to read:
183183
184184 ### SEC. 2.
185185
186186 399.20.1. At the commissions discretion, instead of using the market price determined by the commission pursuant to subdivision (d) of Section 399.20, the payment may be determined through competitive solicitations held not less often than biannually by electrical corporations, or any other mechanism determined by the commission.
187187
188188 399.20.1. At the commissions discretion, instead of using the market price determined by the commission pursuant to subdivision (d) of Section 399.20, the payment may be determined through competitive solicitations held not less often than biannually by electrical corporations, or any other mechanism determined by the commission.
189189
190190 399.20.1. At the commissions discretion, instead of using the market price determined by the commission pursuant to subdivision (d) of Section 399.20, the payment may be determined through competitive solicitations held not less often than biannually by electrical corporations, or any other mechanism determined by the commission.
191191
192192
193193
194194 399.20.1. At the commissions discretion, instead of using the market price determined by the commission pursuant to subdivision (d) of Section 399.20, the payment may be determined through competitive solicitations held not less often than biannually by electrical corporations, or any other mechanism determined by the commission.