California 2023-2024 Regular Session

California Assembly Bill AB914 Compare Versions

OldNewDifferences
1-Amended IN Senate July 13, 2023 Amended IN Assembly May 01, 2023 Amended IN Assembly April 10, 2023 Amended IN Assembly March 09, 2023 CALIFORNIA LEGISLATURE 20232024 REGULAR SESSION Assembly Bill No. 914Introduced by Assembly Member Friedman(Coauthors: Assembly Members Hoover, Mathis, Muratsuchi, Wood, and Zbur)(Coauthor: Senator Stern)February 14, 2023An act to amend amend, repeal, and add Section 21100.2 of the Public Resources Code, relating to electricity. LEGISLATIVE COUNSEL'S DIGESTAB 914, as amended, Friedman. Electrical infrastructure: California Environmental Quality Act: review time period. The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA requires each state agency to establish, by resolution or order, time limits for completing the environmental review of a project where the state agency is the lead agency for the project, as specified.This bill bill, until January 1, 2031, would require a state agency, acting as the lead agency, to complete its environmental review for an electrical infrastructure project and to approve or deny the project within 2 years of the submission and acceptance of a complete application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure to the state agency. If the state agency fails to meet this time period, deadline, the bill would require the state agency to submit to the Legislature a report setting forth the reasons for why that the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: YES Local Program: NO Bill TextThe people of the State of California do enact as follows:SECTION 1. The Legislature finds and declares all of the following:(a) It is the policy of the state that Californias climate goals, greater environmental protection, and improvements in public health, particularly in communities overburdened with air pollution, can be achieved through increased use of electricity as a source of power rather than continued reliance on fossil fuels. Among other things, expanded electrification of the transportation sector and equipment and appliances within buildings, as well as the increased use of energy produced from renewable sources and stored energy, would assist in meeting the states environmental goals.(b) As codified in Section 25328 of the Public Resources Code, the state has established a goal of reaching 100 percent zero-emission vehicles for new passenger vehicle sales by 2035 and for medium- and heavy-duty vehicles by 2045. In addition, the State Energy Resources Conservation and Development Commission and the State Air Resources Board anticipate as many as 8,000,000 electric vehicles in California by 2030. To meet the states climate and air quality goals, especially in areas where there is a concentration of medium- and heavy-duty vehicles and other goods movement equipment, electrical corporations and local publicly owned electric utilities must be able to proactively plan and build electrical grid upgrades to accommodate the level of electric vehicle charging associated with these goals and projections.(c) Decarbonized energy use in buildings, mainly by converting space and water heating from natural gas to electricity, also supports the states climate, environmental, and public health policies. In addition, electrifying more building energy uses reduces the emissions of greenhouse gases and other pollutants more effectively if the electricity comes from zero-carbon sources.(d) Improvements in zero-carbon generation technologies are enabling cleaner electricity to be used on a greater scale, but delivering that energy to meet the anticipated increases in demand will require constructing and installing additional electrical system infrastructure.(e) For all of these climate, environmental, and public health reasons, there is a critical need to bring new electrical grid infrastructure online more quickly. This infrastructure includes (1) expanding utility infrastructure in existing utility rights-of-way and (2) developing new utility infrastructure within two miles of a source of increased or additional electrical demand related to electric vehicle charging facilities, building electrification projects, or vehicle fleets electrification projects, or a renewable generation source, which would provide reliable transmission or transformation infrastructure to interconnect to, or deliver power from, that source.SEC. 2. Section 21100.2 of the Public Resources Code is amended to read:21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.(2) If Meeting the deadline set forth in paragraph (1) is mandatory, and if the state agency fails to meet the time period set forth in paragraph (1), period, the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why that the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.(3)The time period set forth in paragraph (1) is mandatory, not discretionary.(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.(d) This section shall remain in effect only until January 1, 2031, and as of that date is repealed.SEC. 3. Section 21100.2 is added to the Public Resources Code, to read:21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.(c) This section shall become operative on January 1, 2031.
1+Amended IN Assembly May 01, 2023 Amended IN Assembly April 10, 2023 Amended IN Assembly March 09, 2023 CALIFORNIA LEGISLATURE 20232024 REGULAR SESSION Assembly Bill No. 914Introduced by Assembly Member Friedman(Coauthors: Assembly Members Hoover, Mathis, Muratsuchi, Wood, and Zbur)February 14, 2023An act to amend Section 21100.2 of, and to add Section 21080.59 to, of the Public Resources Code, relating to electricity. LEGISLATIVE COUNSEL'S DIGESTAB 914, as amended, Friedman. Electrical infrastructure: California Environmental Quality Act: exemptions: review time period. The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. This bill would exempt from CEQA specified projects relating to electrical substations and electrical line facilities owned by, and constructed by or under contract with, electrical corporations serving not less than 10,000 customers or local publicly owned electric utilities.By requiring a lead agency to determine the applicability of the above-described exemptions to a project, this bill would impose a state-mandated local program.CEQA requires each state agency to establish, by resolution or order, time limits for completing the environmental review of a project where the state agency is the lead agency for the project, as specified.This bill would require a state agency, acting as the lead agency, to complete its environmental review for an electrical infrastructure project and to approve or deny the project within 2 years of the submission and acceptance of an a complete application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure to the state agency. If the state agency fails to meet this time period, the bill would require the state agency to submit to the Legislature a report setting forth the reasons for why the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that no reimbursement is required by this act for a specified reason.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: YES Local Program: YESNO Bill TextThe people of the State of California do enact as follows:SECTION 1. The Legislature finds and declares all of the following:(a) It is the policy of the state that Californias climate goals, greater environmental protection, and improvements in public health, particularly in communities overburdened with air pollution, can be achieved through increased use of electricity as a source of power rather than continued reliance on fossil fuels. Among other things, expanded electrification of the transportation sector and equipment and appliances within buildings, as well as the increased use of energy produced from renewable sources and stored energy, would assist in meeting the states environmental goals.(b) As codified in Section 25328 of the Public Resources Code, the state has established a goal of reaching 100 percent zero-emission vehicles for new passenger vehicle sales by 2035 and for medium- and heavy-duty vehicles by 2045. In addition, the State Energy Resources Conservation and Development Commission and the State Air Resources Board anticipate as many as 8,000,000 electric vehicles in California by 2030. To meet the states climate and air quality goals, especially in areas where there is a concentration of medium- and heavy-duty vehicles and other goods movement equipment, electrical corporations and local publicly owned electric utilities must be able to proactively plan and build electrical grid upgrades to accommodate the level of electric vehicle charging associated with these goals and projections.(c) Decarbonized energy use in buildings, mainly by converting space and water heating from natural gas to electricity, also supports the states climate, environmental, and public health policies. In addition, electrifying more building energy uses reduces the emissions of greenhouse gases and other pollutants more effectively if the electricity comes from zero-carbon sources.(d) Improvements in zero-carbon generation technologies are enabling cleaner electricity to be used on a greater scale, but delivering that energy to meet the anticipated increases in demand will require constructing and installing additional electrical system infrastructure.(e) For all of these climate, environmental, and public health reasons, there is a critical need to bring new electrical grid infrastructure online more quickly. This infrastructure includes (1) expanding utility infrastructure in existing utility rights-of-way and (2) developing new utility infrastructure within two miles of a source of increased or additional electrical demand related to electric vehicle charging facilities, building electrification projects, or vehicle fleets electrification projects, or a renewable generation source, which would provide reliable transmission or transformation infrastructure to interconnect to, or deliver power from, that source.SEC. 2.Section 21080.59 is added to the Public Resources Code, to read:21080.59.(a)This division does not apply to either of the following:(1)The expansion or upgrade of an existing electrical substation, or the expansion, upgrade, or modification of existing electrical line facilities within an existing right-of-way, if the substation or facilities are owned by, and will be constructed by or under contract with, an electrical corporation serving not less than 10,000 customers or a local publicly owned electric utility.(2)The construction of a new electrical substation or new electrical line facilities, or the expansion, upgrade, or modification of an electrical substation or electrical line facilities, if the substation or facilities are owned by, and will be constructed by or under contract with, an electrical corporation serving not less than 10,000 customers or a local publicly owned electric utility, and if the substation or facilities will be located within two miles of either of the following:(A)The location of an actual or forecasted electrical demand increase associated with transportation electrification or building electrification.(B)A distributed energy project, energy storage project, or renewable generation source, where the electrical line facilities or substation would support the interconnection of the project or source to the electrical grid.(b)For purposes of this section, the following terms have the following meanings:(1)Electrical corporation has the same meaning as defined in Section 218 of the Public Utilities Code.(2)Local publicly owned electric utility has the same meaning as defined in Section 224.3 of the Public Utilities Code.SEC. 3.SEC. 2. Section 21100.2 of the Public Resources Code is amended to read:21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.(2) If the state agency fails to meet the time period set forth in paragraph (1), the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.(3) The time period set forth in paragraph (1) is mandatory, not directory. discretionary.(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIII B of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
22
3- Amended IN Senate July 13, 2023 Amended IN Assembly May 01, 2023 Amended IN Assembly April 10, 2023 Amended IN Assembly March 09, 2023 CALIFORNIA LEGISLATURE 20232024 REGULAR SESSION Assembly Bill No. 914Introduced by Assembly Member Friedman(Coauthors: Assembly Members Hoover, Mathis, Muratsuchi, Wood, and Zbur)(Coauthor: Senator Stern)February 14, 2023An act to amend amend, repeal, and add Section 21100.2 of the Public Resources Code, relating to electricity. LEGISLATIVE COUNSEL'S DIGESTAB 914, as amended, Friedman. Electrical infrastructure: California Environmental Quality Act: review time period. The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA requires each state agency to establish, by resolution or order, time limits for completing the environmental review of a project where the state agency is the lead agency for the project, as specified.This bill bill, until January 1, 2031, would require a state agency, acting as the lead agency, to complete its environmental review for an electrical infrastructure project and to approve or deny the project within 2 years of the submission and acceptance of a complete application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure to the state agency. If the state agency fails to meet this time period, deadline, the bill would require the state agency to submit to the Legislature a report setting forth the reasons for why that the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: YES Local Program: NO
3+ Amended IN Assembly May 01, 2023 Amended IN Assembly April 10, 2023 Amended IN Assembly March 09, 2023 CALIFORNIA LEGISLATURE 20232024 REGULAR SESSION Assembly Bill No. 914Introduced by Assembly Member Friedman(Coauthors: Assembly Members Hoover, Mathis, Muratsuchi, Wood, and Zbur)February 14, 2023An act to amend Section 21100.2 of, and to add Section 21080.59 to, of the Public Resources Code, relating to electricity. LEGISLATIVE COUNSEL'S DIGESTAB 914, as amended, Friedman. Electrical infrastructure: California Environmental Quality Act: exemptions: review time period. The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. This bill would exempt from CEQA specified projects relating to electrical substations and electrical line facilities owned by, and constructed by or under contract with, electrical corporations serving not less than 10,000 customers or local publicly owned electric utilities.By requiring a lead agency to determine the applicability of the above-described exemptions to a project, this bill would impose a state-mandated local program.CEQA requires each state agency to establish, by resolution or order, time limits for completing the environmental review of a project where the state agency is the lead agency for the project, as specified.This bill would require a state agency, acting as the lead agency, to complete its environmental review for an electrical infrastructure project and to approve or deny the project within 2 years of the submission and acceptance of an a complete application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure to the state agency. If the state agency fails to meet this time period, the bill would require the state agency to submit to the Legislature a report setting forth the reasons for why the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that no reimbursement is required by this act for a specified reason.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: YES Local Program: YESNO
44
5- Amended IN Senate July 13, 2023 Amended IN Assembly May 01, 2023 Amended IN Assembly April 10, 2023 Amended IN Assembly March 09, 2023
5+ Amended IN Assembly May 01, 2023 Amended IN Assembly April 10, 2023 Amended IN Assembly March 09, 2023
66
7-Amended IN Senate July 13, 2023
87 Amended IN Assembly May 01, 2023
98 Amended IN Assembly April 10, 2023
109 Amended IN Assembly March 09, 2023
1110
1211 CALIFORNIA LEGISLATURE 20232024 REGULAR SESSION
1312
1413 Assembly Bill
1514
1615 No. 914
1716
18-Introduced by Assembly Member Friedman(Coauthors: Assembly Members Hoover, Mathis, Muratsuchi, Wood, and Zbur)(Coauthor: Senator Stern)February 14, 2023
17+Introduced by Assembly Member Friedman(Coauthors: Assembly Members Hoover, Mathis, Muratsuchi, Wood, and Zbur)February 14, 2023
1918
20-Introduced by Assembly Member Friedman(Coauthors: Assembly Members Hoover, Mathis, Muratsuchi, Wood, and Zbur)(Coauthor: Senator Stern)
19+Introduced by Assembly Member Friedman(Coauthors: Assembly Members Hoover, Mathis, Muratsuchi, Wood, and Zbur)
2120 February 14, 2023
2221
23-An act to amend amend, repeal, and add Section 21100.2 of the Public Resources Code, relating to electricity.
22+An act to amend Section 21100.2 of, and to add Section 21080.59 to, of the Public Resources Code, relating to electricity.
2423
2524 LEGISLATIVE COUNSEL'S DIGEST
2625
2726 ## LEGISLATIVE COUNSEL'S DIGEST
2827
29-AB 914, as amended, Friedman. Electrical infrastructure: California Environmental Quality Act: review time period.
28+AB 914, as amended, Friedman. Electrical infrastructure: California Environmental Quality Act: exemptions: review time period.
3029
31-The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA requires each state agency to establish, by resolution or order, time limits for completing the environmental review of a project where the state agency is the lead agency for the project, as specified.This bill bill, until January 1, 2031, would require a state agency, acting as the lead agency, to complete its environmental review for an electrical infrastructure project and to approve or deny the project within 2 years of the submission and acceptance of a complete application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure to the state agency. If the state agency fails to meet this time period, deadline, the bill would require the state agency to submit to the Legislature a report setting forth the reasons for why that the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.
30+The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. This bill would exempt from CEQA specified projects relating to electrical substations and electrical line facilities owned by, and constructed by or under contract with, electrical corporations serving not less than 10,000 customers or local publicly owned electric utilities.By requiring a lead agency to determine the applicability of the above-described exemptions to a project, this bill would impose a state-mandated local program.CEQA requires each state agency to establish, by resolution or order, time limits for completing the environmental review of a project where the state agency is the lead agency for the project, as specified.This bill would require a state agency, acting as the lead agency, to complete its environmental review for an electrical infrastructure project and to approve or deny the project within 2 years of the submission and acceptance of an a complete application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure to the state agency. If the state agency fails to meet this time period, the bill would require the state agency to submit to the Legislature a report setting forth the reasons for why the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that no reimbursement is required by this act for a specified reason.
3231
3332 The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment.
3433
34+This bill would exempt from CEQA specified projects relating to electrical substations and electrical line facilities owned by, and constructed by or under contract with, electrical corporations serving not less than 10,000 customers or local publicly owned electric utilities.
35+
36+
37+
38+By requiring a lead agency to determine the applicability of the above-described exemptions to a project, this bill would impose a state-mandated local program.
39+
40+
41+
3542 CEQA requires each state agency to establish, by resolution or order, time limits for completing the environmental review of a project where the state agency is the lead agency for the project, as specified.
3643
37-This bill bill, until January 1, 2031, would require a state agency, acting as the lead agency, to complete its environmental review for an electrical infrastructure project and to approve or deny the project within 2 years of the submission and acceptance of a complete application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure to the state agency. If the state agency fails to meet this time period, deadline, the bill would require the state agency to submit to the Legislature a report setting forth the reasons for why that the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.
44+This bill would require a state agency, acting as the lead agency, to complete its environmental review for an electrical infrastructure project and to approve or deny the project within 2 years of the submission and acceptance of an a complete application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure to the state agency. If the state agency fails to meet this time period, the bill would require the state agency to submit to the Legislature a report setting forth the reasons for why the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.
45+
46+The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
47+
48+
49+
50+This bill would provide that no reimbursement is required by this act for a specified reason.
51+
52+
3853
3954 ## Digest Key
4055
4156 ## Bill Text
4257
43-The people of the State of California do enact as follows:SECTION 1. The Legislature finds and declares all of the following:(a) It is the policy of the state that Californias climate goals, greater environmental protection, and improvements in public health, particularly in communities overburdened with air pollution, can be achieved through increased use of electricity as a source of power rather than continued reliance on fossil fuels. Among other things, expanded electrification of the transportation sector and equipment and appliances within buildings, as well as the increased use of energy produced from renewable sources and stored energy, would assist in meeting the states environmental goals.(b) As codified in Section 25328 of the Public Resources Code, the state has established a goal of reaching 100 percent zero-emission vehicles for new passenger vehicle sales by 2035 and for medium- and heavy-duty vehicles by 2045. In addition, the State Energy Resources Conservation and Development Commission and the State Air Resources Board anticipate as many as 8,000,000 electric vehicles in California by 2030. To meet the states climate and air quality goals, especially in areas where there is a concentration of medium- and heavy-duty vehicles and other goods movement equipment, electrical corporations and local publicly owned electric utilities must be able to proactively plan and build electrical grid upgrades to accommodate the level of electric vehicle charging associated with these goals and projections.(c) Decarbonized energy use in buildings, mainly by converting space and water heating from natural gas to electricity, also supports the states climate, environmental, and public health policies. In addition, electrifying more building energy uses reduces the emissions of greenhouse gases and other pollutants more effectively if the electricity comes from zero-carbon sources.(d) Improvements in zero-carbon generation technologies are enabling cleaner electricity to be used on a greater scale, but delivering that energy to meet the anticipated increases in demand will require constructing and installing additional electrical system infrastructure.(e) For all of these climate, environmental, and public health reasons, there is a critical need to bring new electrical grid infrastructure online more quickly. This infrastructure includes (1) expanding utility infrastructure in existing utility rights-of-way and (2) developing new utility infrastructure within two miles of a source of increased or additional electrical demand related to electric vehicle charging facilities, building electrification projects, or vehicle fleets electrification projects, or a renewable generation source, which would provide reliable transmission or transformation infrastructure to interconnect to, or deliver power from, that source.SEC. 2. Section 21100.2 of the Public Resources Code is amended to read:21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.(2) If Meeting the deadline set forth in paragraph (1) is mandatory, and if the state agency fails to meet the time period set forth in paragraph (1), period, the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why that the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.(3)The time period set forth in paragraph (1) is mandatory, not discretionary.(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.(d) This section shall remain in effect only until January 1, 2031, and as of that date is repealed.SEC. 3. Section 21100.2 is added to the Public Resources Code, to read:21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.(c) This section shall become operative on January 1, 2031.
58+The people of the State of California do enact as follows:SECTION 1. The Legislature finds and declares all of the following:(a) It is the policy of the state that Californias climate goals, greater environmental protection, and improvements in public health, particularly in communities overburdened with air pollution, can be achieved through increased use of electricity as a source of power rather than continued reliance on fossil fuels. Among other things, expanded electrification of the transportation sector and equipment and appliances within buildings, as well as the increased use of energy produced from renewable sources and stored energy, would assist in meeting the states environmental goals.(b) As codified in Section 25328 of the Public Resources Code, the state has established a goal of reaching 100 percent zero-emission vehicles for new passenger vehicle sales by 2035 and for medium- and heavy-duty vehicles by 2045. In addition, the State Energy Resources Conservation and Development Commission and the State Air Resources Board anticipate as many as 8,000,000 electric vehicles in California by 2030. To meet the states climate and air quality goals, especially in areas where there is a concentration of medium- and heavy-duty vehicles and other goods movement equipment, electrical corporations and local publicly owned electric utilities must be able to proactively plan and build electrical grid upgrades to accommodate the level of electric vehicle charging associated with these goals and projections.(c) Decarbonized energy use in buildings, mainly by converting space and water heating from natural gas to electricity, also supports the states climate, environmental, and public health policies. In addition, electrifying more building energy uses reduces the emissions of greenhouse gases and other pollutants more effectively if the electricity comes from zero-carbon sources.(d) Improvements in zero-carbon generation technologies are enabling cleaner electricity to be used on a greater scale, but delivering that energy to meet the anticipated increases in demand will require constructing and installing additional electrical system infrastructure.(e) For all of these climate, environmental, and public health reasons, there is a critical need to bring new electrical grid infrastructure online more quickly. This infrastructure includes (1) expanding utility infrastructure in existing utility rights-of-way and (2) developing new utility infrastructure within two miles of a source of increased or additional electrical demand related to electric vehicle charging facilities, building electrification projects, or vehicle fleets electrification projects, or a renewable generation source, which would provide reliable transmission or transformation infrastructure to interconnect to, or deliver power from, that source.SEC. 2.Section 21080.59 is added to the Public Resources Code, to read:21080.59.(a)This division does not apply to either of the following:(1)The expansion or upgrade of an existing electrical substation, or the expansion, upgrade, or modification of existing electrical line facilities within an existing right-of-way, if the substation or facilities are owned by, and will be constructed by or under contract with, an electrical corporation serving not less than 10,000 customers or a local publicly owned electric utility.(2)The construction of a new electrical substation or new electrical line facilities, or the expansion, upgrade, or modification of an electrical substation or electrical line facilities, if the substation or facilities are owned by, and will be constructed by or under contract with, an electrical corporation serving not less than 10,000 customers or a local publicly owned electric utility, and if the substation or facilities will be located within two miles of either of the following:(A)The location of an actual or forecasted electrical demand increase associated with transportation electrification or building electrification.(B)A distributed energy project, energy storage project, or renewable generation source, where the electrical line facilities or substation would support the interconnection of the project or source to the electrical grid.(b)For purposes of this section, the following terms have the following meanings:(1)Electrical corporation has the same meaning as defined in Section 218 of the Public Utilities Code.(2)Local publicly owned electric utility has the same meaning as defined in Section 224.3 of the Public Utilities Code.SEC. 3.SEC. 2. Section 21100.2 of the Public Resources Code is amended to read:21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.(2) If the state agency fails to meet the time period set forth in paragraph (1), the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.(3) The time period set forth in paragraph (1) is mandatory, not directory. discretionary.(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.SEC. 4.No reimbursement is required by this act pursuant to Section 6 of Article XIII B of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.
4459
4560 The people of the State of California do enact as follows:
4661
4762 ## The people of the State of California do enact as follows:
4863
4964 SECTION 1. The Legislature finds and declares all of the following:(a) It is the policy of the state that Californias climate goals, greater environmental protection, and improvements in public health, particularly in communities overburdened with air pollution, can be achieved through increased use of electricity as a source of power rather than continued reliance on fossil fuels. Among other things, expanded electrification of the transportation sector and equipment and appliances within buildings, as well as the increased use of energy produced from renewable sources and stored energy, would assist in meeting the states environmental goals.(b) As codified in Section 25328 of the Public Resources Code, the state has established a goal of reaching 100 percent zero-emission vehicles for new passenger vehicle sales by 2035 and for medium- and heavy-duty vehicles by 2045. In addition, the State Energy Resources Conservation and Development Commission and the State Air Resources Board anticipate as many as 8,000,000 electric vehicles in California by 2030. To meet the states climate and air quality goals, especially in areas where there is a concentration of medium- and heavy-duty vehicles and other goods movement equipment, electrical corporations and local publicly owned electric utilities must be able to proactively plan and build electrical grid upgrades to accommodate the level of electric vehicle charging associated with these goals and projections.(c) Decarbonized energy use in buildings, mainly by converting space and water heating from natural gas to electricity, also supports the states climate, environmental, and public health policies. In addition, electrifying more building energy uses reduces the emissions of greenhouse gases and other pollutants more effectively if the electricity comes from zero-carbon sources.(d) Improvements in zero-carbon generation technologies are enabling cleaner electricity to be used on a greater scale, but delivering that energy to meet the anticipated increases in demand will require constructing and installing additional electrical system infrastructure.(e) For all of these climate, environmental, and public health reasons, there is a critical need to bring new electrical grid infrastructure online more quickly. This infrastructure includes (1) expanding utility infrastructure in existing utility rights-of-way and (2) developing new utility infrastructure within two miles of a source of increased or additional electrical demand related to electric vehicle charging facilities, building electrification projects, or vehicle fleets electrification projects, or a renewable generation source, which would provide reliable transmission or transformation infrastructure to interconnect to, or deliver power from, that source.
5065
5166 SECTION 1. The Legislature finds and declares all of the following:(a) It is the policy of the state that Californias climate goals, greater environmental protection, and improvements in public health, particularly in communities overburdened with air pollution, can be achieved through increased use of electricity as a source of power rather than continued reliance on fossil fuels. Among other things, expanded electrification of the transportation sector and equipment and appliances within buildings, as well as the increased use of energy produced from renewable sources and stored energy, would assist in meeting the states environmental goals.(b) As codified in Section 25328 of the Public Resources Code, the state has established a goal of reaching 100 percent zero-emission vehicles for new passenger vehicle sales by 2035 and for medium- and heavy-duty vehicles by 2045. In addition, the State Energy Resources Conservation and Development Commission and the State Air Resources Board anticipate as many as 8,000,000 electric vehicles in California by 2030. To meet the states climate and air quality goals, especially in areas where there is a concentration of medium- and heavy-duty vehicles and other goods movement equipment, electrical corporations and local publicly owned electric utilities must be able to proactively plan and build electrical grid upgrades to accommodate the level of electric vehicle charging associated with these goals and projections.(c) Decarbonized energy use in buildings, mainly by converting space and water heating from natural gas to electricity, also supports the states climate, environmental, and public health policies. In addition, electrifying more building energy uses reduces the emissions of greenhouse gases and other pollutants more effectively if the electricity comes from zero-carbon sources.(d) Improvements in zero-carbon generation technologies are enabling cleaner electricity to be used on a greater scale, but delivering that energy to meet the anticipated increases in demand will require constructing and installing additional electrical system infrastructure.(e) For all of these climate, environmental, and public health reasons, there is a critical need to bring new electrical grid infrastructure online more quickly. This infrastructure includes (1) expanding utility infrastructure in existing utility rights-of-way and (2) developing new utility infrastructure within two miles of a source of increased or additional electrical demand related to electric vehicle charging facilities, building electrification projects, or vehicle fleets electrification projects, or a renewable generation source, which would provide reliable transmission or transformation infrastructure to interconnect to, or deliver power from, that source.
5267
5368 SECTION 1. The Legislature finds and declares all of the following:
5469
5570 ### SECTION 1.
5671
5772 (a) It is the policy of the state that Californias climate goals, greater environmental protection, and improvements in public health, particularly in communities overburdened with air pollution, can be achieved through increased use of electricity as a source of power rather than continued reliance on fossil fuels. Among other things, expanded electrification of the transportation sector and equipment and appliances within buildings, as well as the increased use of energy produced from renewable sources and stored energy, would assist in meeting the states environmental goals.
5873
5974 (b) As codified in Section 25328 of the Public Resources Code, the state has established a goal of reaching 100 percent zero-emission vehicles for new passenger vehicle sales by 2035 and for medium- and heavy-duty vehicles by 2045. In addition, the State Energy Resources Conservation and Development Commission and the State Air Resources Board anticipate as many as 8,000,000 electric vehicles in California by 2030. To meet the states climate and air quality goals, especially in areas where there is a concentration of medium- and heavy-duty vehicles and other goods movement equipment, electrical corporations and local publicly owned electric utilities must be able to proactively plan and build electrical grid upgrades to accommodate the level of electric vehicle charging associated with these goals and projections.
6075
6176 (c) Decarbonized energy use in buildings, mainly by converting space and water heating from natural gas to electricity, also supports the states climate, environmental, and public health policies. In addition, electrifying more building energy uses reduces the emissions of greenhouse gases and other pollutants more effectively if the electricity comes from zero-carbon sources.
6277
6378 (d) Improvements in zero-carbon generation technologies are enabling cleaner electricity to be used on a greater scale, but delivering that energy to meet the anticipated increases in demand will require constructing and installing additional electrical system infrastructure.
6479
6580 (e) For all of these climate, environmental, and public health reasons, there is a critical need to bring new electrical grid infrastructure online more quickly. This infrastructure includes (1) expanding utility infrastructure in existing utility rights-of-way and (2) developing new utility infrastructure within two miles of a source of increased or additional electrical demand related to electric vehicle charging facilities, building electrification projects, or vehicle fleets electrification projects, or a renewable generation source, which would provide reliable transmission or transformation infrastructure to interconnect to, or deliver power from, that source.
6681
67-SEC. 2. Section 21100.2 of the Public Resources Code is amended to read:21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.(2) If Meeting the deadline set forth in paragraph (1) is mandatory, and if the state agency fails to meet the time period set forth in paragraph (1), period, the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why that the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.(3)The time period set forth in paragraph (1) is mandatory, not discretionary.(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.(d) This section shall remain in effect only until January 1, 2031, and as of that date is repealed.
6882
69-SEC. 2. Section 21100.2 of the Public Resources Code is amended to read:
7083
71-### SEC. 2.
7284
73-21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.(2) If Meeting the deadline set forth in paragraph (1) is mandatory, and if the state agency fails to meet the time period set forth in paragraph (1), period, the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why that the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.(3)The time period set forth in paragraph (1) is mandatory, not discretionary.(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.(d) This section shall remain in effect only until January 1, 2031, and as of that date is repealed.
7485
75-21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.(2) If Meeting the deadline set forth in paragraph (1) is mandatory, and if the state agency fails to meet the time period set forth in paragraph (1), period, the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why that the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.(3)The time period set forth in paragraph (1) is mandatory, not discretionary.(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.(d) This section shall remain in effect only until January 1, 2031, and as of that date is repealed.
86+(a)This division does not apply to either of the following:
7687
77-21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.(2) If Meeting the deadline set forth in paragraph (1) is mandatory, and if the state agency fails to meet the time period set forth in paragraph (1), period, the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why that the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.(3)The time period set forth in paragraph (1) is mandatory, not discretionary.(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.(d) This section shall remain in effect only until January 1, 2031, and as of that date is repealed.
88+
89+
90+(1)The expansion or upgrade of an existing electrical substation, or the expansion, upgrade, or modification of existing electrical line facilities within an existing right-of-way, if the substation or facilities are owned by, and will be constructed by or under contract with, an electrical corporation serving not less than 10,000 customers or a local publicly owned electric utility.
91+
92+
93+
94+(2)The construction of a new electrical substation or new electrical line facilities, or the expansion, upgrade, or modification of an electrical substation or electrical line facilities, if the substation or facilities are owned by, and will be constructed by or under contract with, an electrical corporation serving not less than 10,000 customers or a local publicly owned electric utility, and if the substation or facilities will be located within two miles of either of the following:
95+
96+
97+
98+(A)The location of an actual or forecasted electrical demand increase associated with transportation electrification or building electrification.
99+
100+
101+
102+(B)A distributed energy project, energy storage project, or renewable generation source, where the electrical line facilities or substation would support the interconnection of the project or source to the electrical grid.
103+
104+
105+
106+(b)For purposes of this section, the following terms have the following meanings:
107+
108+
109+
110+(1)Electrical corporation has the same meaning as defined in Section 218 of the Public Utilities Code.
111+
112+
113+
114+(2)Local publicly owned electric utility has the same meaning as defined in Section 224.3 of the Public Utilities Code.
115+
116+
117+
118+SEC. 3.SEC. 2. Section 21100.2 of the Public Resources Code is amended to read:21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.(2) If the state agency fails to meet the time period set forth in paragraph (1), the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.(3) The time period set forth in paragraph (1) is mandatory, not directory. discretionary.(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.
119+
120+SEC. 3.SEC. 2. Section 21100.2 of the Public Resources Code is amended to read:
121+
122+### SEC. 3.SEC. 2.
123+
124+21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.(2) If the state agency fails to meet the time period set forth in paragraph (1), the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.(3) The time period set forth in paragraph (1) is mandatory, not directory. discretionary.(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.
125+
126+21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.(2) If the state agency fails to meet the time period set forth in paragraph (1), the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.(3) The time period set forth in paragraph (1) is mandatory, not directory. discretionary.(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.
127+
128+21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.(2) If the state agency fails to meet the time period set forth in paragraph (1), the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.(3) The time period set forth in paragraph (1) is mandatory, not directory. discretionary.(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.
78129
79130
80131
81132 21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:
82133
83134 (A) One year for completing and certifying environmental impact reports.
84135
85136 (B) One hundred eighty days for completing and adopting negative declarations.
86137
87138 (2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.
88139
89140 (3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.
90141
91142 (4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.
92143
93-(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.
144+(b) (1) Notwithstanding any other provision of this division, within two years from the date on which an application for the issuance of a lease, permit, license, certificate, or other entitlement for use for electrical infrastructure is submitted to to, and accepted as complete by, a state agency that is a lead agency for the project, the state agency shall complete the review of the environmental impacts of the proposed project pursuant to this division, including the completion and certification of an environmental impact report or the completion or adoption of a negative declaration or mitigated negative declaration, and shall approve or deny the application.
94145
95-(2) If Meeting the deadline set forth in paragraph (1) is mandatory, and if the state agency fails to meet the time period set forth in paragraph (1), period, the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why that the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.
146+(2) If the state agency fails to meet the time period set forth in paragraph (1), the state agency shall, in accordance with Section 9795 of the Government Code, submit to the Legislature a report setting forth the reasons why the review could not be completed within the time period and identifying potential impacts to the electrical system that could result from the delay.
96147
97-(3)The time period set forth in paragraph (1) is mandatory, not discretionary.
148+(3) The time period set forth in paragraph (1) is mandatory, not directory. discretionary.
149+
150+(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.
98151
99152
100153
101-(c) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.
102-
103-(d) This section shall remain in effect only until January 1, 2031, and as of that date is repealed.
104-
105-SEC. 3. Section 21100.2 is added to the Public Resources Code, to read:21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.(c) This section shall become operative on January 1, 2031.
106-
107-SEC. 3. Section 21100.2 is added to the Public Resources Code, to read:
108-
109-### SEC. 3.
110-
111-21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.(c) This section shall become operative on January 1, 2031.
112-
113-21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.(c) This section shall become operative on January 1, 2031.
114-
115-21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:(A) One year for completing and certifying environmental impact reports.(B) One hundred eighty days for completing and adopting negative declarations.(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.(b) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.(c) This section shall become operative on January 1, 2031.
116-
117-
118-
119-21100.2. (a) (1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:
120-
121-(A) One year for completing and certifying environmental impact reports.
122-
123-(B) One hundred eighty days for completing and adopting negative declarations.
124-
125-(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.
126-
127-(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.
128-
129-(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents to the extension.
130-
131-(b) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.
132-
133-(c) This section shall become operative on January 1, 2031.
154+No reimbursement is required by this act pursuant to Section 6 of Article XIII B of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act, within the meaning of Section 17556 of the Government Code.