California 2025-2026 Regular Session

California Assembly Bill AB531 Compare Versions

Only one version of the bill is available at this time.
OldNewDifferences
11 CALIFORNIA LEGISLATURE 20252026 REGULAR SESSION Assembly Bill No. 531Introduced by Assembly Member Rogers(Coauthor: Assembly Member Papan)February 11, 2025 An act to amend Section 25545 of the Public Resources Code, relating to energy. LEGISLATIVE COUNSEL'S DIGESTAB 531, as introduced, Rogers. Geothermal powerplants and geothermal field development projects: certification and environmental review.Existing law establishes and vests in the State Energy Resources Conservation and Development Commission (Energy Commission) various responsibilities with respect to developing and implementing the states energy policies. Existing law authorizes persons proposing specified electrical generation, electrical transmission, hydrogen production, and energy storage projects to apply, on or before June 30, 2029, to the Energy Commission to certify sites and related facilities as environmental leadership development projects, as specified. Existing law makes a site and related facility certified by the Energy Commission subject to streamlining benefits related to CEQA with no further action by the applicant or the Governor. Under existing law, the Energy Commissions certification is in lieu of any permit, certificate, or similar document required by any governmental agency and supersedes any applicable statute, ordinance, or regulation, except as specified.This bill would expand the types of facilities eligible to be certified as environmental leadership development projects by the Energy Commission to include geothermal powerplants and geothermal field development projects, as defined.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: YES Local Program: NO Bill TextThe people of the State of California do enact as follows:SECTION 1. Section 25545 of the Public Resources Code is amended to read:25545. For purposes of this chapter, the following definitions apply:(a) California Native American tribe has the same meaning as set forth in Section 21073.(b) Facility means any of the following:(1) A solar photovoltaic or terrestrial wind electrical generating powerplant with a generating capacity of 50 megawatts or more and any facilities appurtenant thereto.(2) An energy storage system as defined in Section 2835 of the Public Utilities Code that is capable of storing 200 megawatthours or more of energy.(3) A stationary electrical generating powerplant using any source of thermal energy, with a generating capacity of 50 megawatts or more, excluding any powerplant that burns, uses, or relies on fossil or nuclear fuels.(4) A discretionary project as described in Section 21080 for which the applicant has certified that a capital investment of at least two hundred fifty million dollars ($250,000,000) will be made over a period of five years and the discretionary project is for (A) the manufacture, production, or assembly of an energy storage system or component manufacturing, wind system or component manufacturing, and solar photovoltaic energy system or component manufacturing, or (B) the manufacture, production, or assembly of specialized products, components, or systems that are integral to renewable energy or energy storage technologies.(5) An electrical transmission line carrying electricity from a facility described in paragraph (1), (2), or (3) that is located in the state to a point of junction with any interconnected electrical transmission system.(6) A hydrogen production facility and associated onsite storage and processing facilities that do not derive hydrogen from a fossil fuel feedstock and that receive funding from any of the following:(A) The Hydrogen Program established pursuant to Section 25664.1.(B) Section 91530, as added by the Safe Drinking Water, Wildfire Prevention, Drought Preparedness, and Clean Air Bond Act of 2024 (Section 2 of Chapter 83 of the Statutes of 2024 (Senate Bill No. 867)), if that act is approved by the voters at the November 5, 2024, statewide general election. 2024.(C) The Alliance for Renewable Clean Hydrogen Energy Systems (ARCHES) authorized by Article 15 (commencing with Section 12100.160) of Chapter 1.6 of Part 2 of Division 3 of Title 2 of the Government Code, as awarded by the United States Department of Energy Office of Clean Energy Demonstrations.(7) A geothermal powerplant or a geothermal field development project, as defined in Section 65928.5 of the Government Code.(c) Site means any location on which an eligible facility is constructed or is proposed to be constructed.
22
33 CALIFORNIA LEGISLATURE 20252026 REGULAR SESSION Assembly Bill No. 531Introduced by Assembly Member Rogers(Coauthor: Assembly Member Papan)February 11, 2025 An act to amend Section 25545 of the Public Resources Code, relating to energy. LEGISLATIVE COUNSEL'S DIGESTAB 531, as introduced, Rogers. Geothermal powerplants and geothermal field development projects: certification and environmental review.Existing law establishes and vests in the State Energy Resources Conservation and Development Commission (Energy Commission) various responsibilities with respect to developing and implementing the states energy policies. Existing law authorizes persons proposing specified electrical generation, electrical transmission, hydrogen production, and energy storage projects to apply, on or before June 30, 2029, to the Energy Commission to certify sites and related facilities as environmental leadership development projects, as specified. Existing law makes a site and related facility certified by the Energy Commission subject to streamlining benefits related to CEQA with no further action by the applicant or the Governor. Under existing law, the Energy Commissions certification is in lieu of any permit, certificate, or similar document required by any governmental agency and supersedes any applicable statute, ordinance, or regulation, except as specified.This bill would expand the types of facilities eligible to be certified as environmental leadership development projects by the Energy Commission to include geothermal powerplants and geothermal field development projects, as defined.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: YES Local Program: NO
44
55
66
77
88
99 CALIFORNIA LEGISLATURE 20252026 REGULAR SESSION
1010
1111 Assembly Bill
1212
1313 No. 531
1414
1515 Introduced by Assembly Member Rogers(Coauthor: Assembly Member Papan)February 11, 2025
1616
1717 Introduced by Assembly Member Rogers(Coauthor: Assembly Member Papan)
1818 February 11, 2025
1919
2020 An act to amend Section 25545 of the Public Resources Code, relating to energy.
2121
2222 LEGISLATIVE COUNSEL'S DIGEST
2323
2424 ## LEGISLATIVE COUNSEL'S DIGEST
2525
2626 AB 531, as introduced, Rogers. Geothermal powerplants and geothermal field development projects: certification and environmental review.
2727
2828 Existing law establishes and vests in the State Energy Resources Conservation and Development Commission (Energy Commission) various responsibilities with respect to developing and implementing the states energy policies. Existing law authorizes persons proposing specified electrical generation, electrical transmission, hydrogen production, and energy storage projects to apply, on or before June 30, 2029, to the Energy Commission to certify sites and related facilities as environmental leadership development projects, as specified. Existing law makes a site and related facility certified by the Energy Commission subject to streamlining benefits related to CEQA with no further action by the applicant or the Governor. Under existing law, the Energy Commissions certification is in lieu of any permit, certificate, or similar document required by any governmental agency and supersedes any applicable statute, ordinance, or regulation, except as specified.This bill would expand the types of facilities eligible to be certified as environmental leadership development projects by the Energy Commission to include geothermal powerplants and geothermal field development projects, as defined.
2929
3030 Existing law establishes and vests in the State Energy Resources Conservation and Development Commission (Energy Commission) various responsibilities with respect to developing and implementing the states energy policies. Existing law authorizes persons proposing specified electrical generation, electrical transmission, hydrogen production, and energy storage projects to apply, on or before June 30, 2029, to the Energy Commission to certify sites and related facilities as environmental leadership development projects, as specified. Existing law makes a site and related facility certified by the Energy Commission subject to streamlining benefits related to CEQA with no further action by the applicant or the Governor. Under existing law, the Energy Commissions certification is in lieu of any permit, certificate, or similar document required by any governmental agency and supersedes any applicable statute, ordinance, or regulation, except as specified.
3131
3232 This bill would expand the types of facilities eligible to be certified as environmental leadership development projects by the Energy Commission to include geothermal powerplants and geothermal field development projects, as defined.
3333
3434 ## Digest Key
3535
3636 ## Bill Text
3737
3838 The people of the State of California do enact as follows:SECTION 1. Section 25545 of the Public Resources Code is amended to read:25545. For purposes of this chapter, the following definitions apply:(a) California Native American tribe has the same meaning as set forth in Section 21073.(b) Facility means any of the following:(1) A solar photovoltaic or terrestrial wind electrical generating powerplant with a generating capacity of 50 megawatts or more and any facilities appurtenant thereto.(2) An energy storage system as defined in Section 2835 of the Public Utilities Code that is capable of storing 200 megawatthours or more of energy.(3) A stationary electrical generating powerplant using any source of thermal energy, with a generating capacity of 50 megawatts or more, excluding any powerplant that burns, uses, or relies on fossil or nuclear fuels.(4) A discretionary project as described in Section 21080 for which the applicant has certified that a capital investment of at least two hundred fifty million dollars ($250,000,000) will be made over a period of five years and the discretionary project is for (A) the manufacture, production, or assembly of an energy storage system or component manufacturing, wind system or component manufacturing, and solar photovoltaic energy system or component manufacturing, or (B) the manufacture, production, or assembly of specialized products, components, or systems that are integral to renewable energy or energy storage technologies.(5) An electrical transmission line carrying electricity from a facility described in paragraph (1), (2), or (3) that is located in the state to a point of junction with any interconnected electrical transmission system.(6) A hydrogen production facility and associated onsite storage and processing facilities that do not derive hydrogen from a fossil fuel feedstock and that receive funding from any of the following:(A) The Hydrogen Program established pursuant to Section 25664.1.(B) Section 91530, as added by the Safe Drinking Water, Wildfire Prevention, Drought Preparedness, and Clean Air Bond Act of 2024 (Section 2 of Chapter 83 of the Statutes of 2024 (Senate Bill No. 867)), if that act is approved by the voters at the November 5, 2024, statewide general election. 2024.(C) The Alliance for Renewable Clean Hydrogen Energy Systems (ARCHES) authorized by Article 15 (commencing with Section 12100.160) of Chapter 1.6 of Part 2 of Division 3 of Title 2 of the Government Code, as awarded by the United States Department of Energy Office of Clean Energy Demonstrations.(7) A geothermal powerplant or a geothermal field development project, as defined in Section 65928.5 of the Government Code.(c) Site means any location on which an eligible facility is constructed or is proposed to be constructed.
3939
4040 The people of the State of California do enact as follows:
4141
4242 ## The people of the State of California do enact as follows:
4343
4444 SECTION 1. Section 25545 of the Public Resources Code is amended to read:25545. For purposes of this chapter, the following definitions apply:(a) California Native American tribe has the same meaning as set forth in Section 21073.(b) Facility means any of the following:(1) A solar photovoltaic or terrestrial wind electrical generating powerplant with a generating capacity of 50 megawatts or more and any facilities appurtenant thereto.(2) An energy storage system as defined in Section 2835 of the Public Utilities Code that is capable of storing 200 megawatthours or more of energy.(3) A stationary electrical generating powerplant using any source of thermal energy, with a generating capacity of 50 megawatts or more, excluding any powerplant that burns, uses, or relies on fossil or nuclear fuels.(4) A discretionary project as described in Section 21080 for which the applicant has certified that a capital investment of at least two hundred fifty million dollars ($250,000,000) will be made over a period of five years and the discretionary project is for (A) the manufacture, production, or assembly of an energy storage system or component manufacturing, wind system or component manufacturing, and solar photovoltaic energy system or component manufacturing, or (B) the manufacture, production, or assembly of specialized products, components, or systems that are integral to renewable energy or energy storage technologies.(5) An electrical transmission line carrying electricity from a facility described in paragraph (1), (2), or (3) that is located in the state to a point of junction with any interconnected electrical transmission system.(6) A hydrogen production facility and associated onsite storage and processing facilities that do not derive hydrogen from a fossil fuel feedstock and that receive funding from any of the following:(A) The Hydrogen Program established pursuant to Section 25664.1.(B) Section 91530, as added by the Safe Drinking Water, Wildfire Prevention, Drought Preparedness, and Clean Air Bond Act of 2024 (Section 2 of Chapter 83 of the Statutes of 2024 (Senate Bill No. 867)), if that act is approved by the voters at the November 5, 2024, statewide general election. 2024.(C) The Alliance for Renewable Clean Hydrogen Energy Systems (ARCHES) authorized by Article 15 (commencing with Section 12100.160) of Chapter 1.6 of Part 2 of Division 3 of Title 2 of the Government Code, as awarded by the United States Department of Energy Office of Clean Energy Demonstrations.(7) A geothermal powerplant or a geothermal field development project, as defined in Section 65928.5 of the Government Code.(c) Site means any location on which an eligible facility is constructed or is proposed to be constructed.
4545
4646 SECTION 1. Section 25545 of the Public Resources Code is amended to read:
4747
4848 ### SECTION 1.
4949
5050 25545. For purposes of this chapter, the following definitions apply:(a) California Native American tribe has the same meaning as set forth in Section 21073.(b) Facility means any of the following:(1) A solar photovoltaic or terrestrial wind electrical generating powerplant with a generating capacity of 50 megawatts or more and any facilities appurtenant thereto.(2) An energy storage system as defined in Section 2835 of the Public Utilities Code that is capable of storing 200 megawatthours or more of energy.(3) A stationary electrical generating powerplant using any source of thermal energy, with a generating capacity of 50 megawatts or more, excluding any powerplant that burns, uses, or relies on fossil or nuclear fuels.(4) A discretionary project as described in Section 21080 for which the applicant has certified that a capital investment of at least two hundred fifty million dollars ($250,000,000) will be made over a period of five years and the discretionary project is for (A) the manufacture, production, or assembly of an energy storage system or component manufacturing, wind system or component manufacturing, and solar photovoltaic energy system or component manufacturing, or (B) the manufacture, production, or assembly of specialized products, components, or systems that are integral to renewable energy or energy storage technologies.(5) An electrical transmission line carrying electricity from a facility described in paragraph (1), (2), or (3) that is located in the state to a point of junction with any interconnected electrical transmission system.(6) A hydrogen production facility and associated onsite storage and processing facilities that do not derive hydrogen from a fossil fuel feedstock and that receive funding from any of the following:(A) The Hydrogen Program established pursuant to Section 25664.1.(B) Section 91530, as added by the Safe Drinking Water, Wildfire Prevention, Drought Preparedness, and Clean Air Bond Act of 2024 (Section 2 of Chapter 83 of the Statutes of 2024 (Senate Bill No. 867)), if that act is approved by the voters at the November 5, 2024, statewide general election. 2024.(C) The Alliance for Renewable Clean Hydrogen Energy Systems (ARCHES) authorized by Article 15 (commencing with Section 12100.160) of Chapter 1.6 of Part 2 of Division 3 of Title 2 of the Government Code, as awarded by the United States Department of Energy Office of Clean Energy Demonstrations.(7) A geothermal powerplant or a geothermal field development project, as defined in Section 65928.5 of the Government Code.(c) Site means any location on which an eligible facility is constructed or is proposed to be constructed.
5151
5252 25545. For purposes of this chapter, the following definitions apply:(a) California Native American tribe has the same meaning as set forth in Section 21073.(b) Facility means any of the following:(1) A solar photovoltaic or terrestrial wind electrical generating powerplant with a generating capacity of 50 megawatts or more and any facilities appurtenant thereto.(2) An energy storage system as defined in Section 2835 of the Public Utilities Code that is capable of storing 200 megawatthours or more of energy.(3) A stationary electrical generating powerplant using any source of thermal energy, with a generating capacity of 50 megawatts or more, excluding any powerplant that burns, uses, or relies on fossil or nuclear fuels.(4) A discretionary project as described in Section 21080 for which the applicant has certified that a capital investment of at least two hundred fifty million dollars ($250,000,000) will be made over a period of five years and the discretionary project is for (A) the manufacture, production, or assembly of an energy storage system or component manufacturing, wind system or component manufacturing, and solar photovoltaic energy system or component manufacturing, or (B) the manufacture, production, or assembly of specialized products, components, or systems that are integral to renewable energy or energy storage technologies.(5) An electrical transmission line carrying electricity from a facility described in paragraph (1), (2), or (3) that is located in the state to a point of junction with any interconnected electrical transmission system.(6) A hydrogen production facility and associated onsite storage and processing facilities that do not derive hydrogen from a fossil fuel feedstock and that receive funding from any of the following:(A) The Hydrogen Program established pursuant to Section 25664.1.(B) Section 91530, as added by the Safe Drinking Water, Wildfire Prevention, Drought Preparedness, and Clean Air Bond Act of 2024 (Section 2 of Chapter 83 of the Statutes of 2024 (Senate Bill No. 867)), if that act is approved by the voters at the November 5, 2024, statewide general election. 2024.(C) The Alliance for Renewable Clean Hydrogen Energy Systems (ARCHES) authorized by Article 15 (commencing with Section 12100.160) of Chapter 1.6 of Part 2 of Division 3 of Title 2 of the Government Code, as awarded by the United States Department of Energy Office of Clean Energy Demonstrations.(7) A geothermal powerplant or a geothermal field development project, as defined in Section 65928.5 of the Government Code.(c) Site means any location on which an eligible facility is constructed or is proposed to be constructed.
5353
5454 25545. For purposes of this chapter, the following definitions apply:(a) California Native American tribe has the same meaning as set forth in Section 21073.(b) Facility means any of the following:(1) A solar photovoltaic or terrestrial wind electrical generating powerplant with a generating capacity of 50 megawatts or more and any facilities appurtenant thereto.(2) An energy storage system as defined in Section 2835 of the Public Utilities Code that is capable of storing 200 megawatthours or more of energy.(3) A stationary electrical generating powerplant using any source of thermal energy, with a generating capacity of 50 megawatts or more, excluding any powerplant that burns, uses, or relies on fossil or nuclear fuels.(4) A discretionary project as described in Section 21080 for which the applicant has certified that a capital investment of at least two hundred fifty million dollars ($250,000,000) will be made over a period of five years and the discretionary project is for (A) the manufacture, production, or assembly of an energy storage system or component manufacturing, wind system or component manufacturing, and solar photovoltaic energy system or component manufacturing, or (B) the manufacture, production, or assembly of specialized products, components, or systems that are integral to renewable energy or energy storage technologies.(5) An electrical transmission line carrying electricity from a facility described in paragraph (1), (2), or (3) that is located in the state to a point of junction with any interconnected electrical transmission system.(6) A hydrogen production facility and associated onsite storage and processing facilities that do not derive hydrogen from a fossil fuel feedstock and that receive funding from any of the following:(A) The Hydrogen Program established pursuant to Section 25664.1.(B) Section 91530, as added by the Safe Drinking Water, Wildfire Prevention, Drought Preparedness, and Clean Air Bond Act of 2024 (Section 2 of Chapter 83 of the Statutes of 2024 (Senate Bill No. 867)), if that act is approved by the voters at the November 5, 2024, statewide general election. 2024.(C) The Alliance for Renewable Clean Hydrogen Energy Systems (ARCHES) authorized by Article 15 (commencing with Section 12100.160) of Chapter 1.6 of Part 2 of Division 3 of Title 2 of the Government Code, as awarded by the United States Department of Energy Office of Clean Energy Demonstrations.(7) A geothermal powerplant or a geothermal field development project, as defined in Section 65928.5 of the Government Code.(c) Site means any location on which an eligible facility is constructed or is proposed to be constructed.
5555
5656
5757
5858 25545. For purposes of this chapter, the following definitions apply:
5959
6060 (a) California Native American tribe has the same meaning as set forth in Section 21073.
6161
6262 (b) Facility means any of the following:
6363
6464 (1) A solar photovoltaic or terrestrial wind electrical generating powerplant with a generating capacity of 50 megawatts or more and any facilities appurtenant thereto.
6565
6666 (2) An energy storage system as defined in Section 2835 of the Public Utilities Code that is capable of storing 200 megawatthours or more of energy.
6767
6868 (3) A stationary electrical generating powerplant using any source of thermal energy, with a generating capacity of 50 megawatts or more, excluding any powerplant that burns, uses, or relies on fossil or nuclear fuels.
6969
7070 (4) A discretionary project as described in Section 21080 for which the applicant has certified that a capital investment of at least two hundred fifty million dollars ($250,000,000) will be made over a period of five years and the discretionary project is for (A) the manufacture, production, or assembly of an energy storage system or component manufacturing, wind system or component manufacturing, and solar photovoltaic energy system or component manufacturing, or (B) the manufacture, production, or assembly of specialized products, components, or systems that are integral to renewable energy or energy storage technologies.
7171
7272 (5) An electrical transmission line carrying electricity from a facility described in paragraph (1), (2), or (3) that is located in the state to a point of junction with any interconnected electrical transmission system.
7373
7474 (6) A hydrogen production facility and associated onsite storage and processing facilities that do not derive hydrogen from a fossil fuel feedstock and that receive funding from any of the following:
7575
7676 (A) The Hydrogen Program established pursuant to Section 25664.1.
7777
7878 (B) Section 91530, as added by the Safe Drinking Water, Wildfire Prevention, Drought Preparedness, and Clean Air Bond Act of 2024 (Section 2 of Chapter 83 of the Statutes of 2024 (Senate Bill No. 867)), if that act is approved by the voters at the November 5, 2024, statewide general election. 2024.
7979
8080 (C) The Alliance for Renewable Clean Hydrogen Energy Systems (ARCHES) authorized by Article 15 (commencing with Section 12100.160) of Chapter 1.6 of Part 2 of Division 3 of Title 2 of the Government Code, as awarded by the United States Department of Energy Office of Clean Energy Demonstrations.
8181
8282 (7) A geothermal powerplant or a geothermal field development project, as defined in Section 65928.5 of the Government Code.
8383
8484 (c) Site means any location on which an eligible facility is constructed or is proposed to be constructed.