Connecticut 2021 2021 Regular Session

Connecticut Senate Bill SB00970 Comm Sub / Analysis

Filed 05/14/2021

                     
Researcher: JSB 	Page 1 	5/14/21 
 
 
 
OLR Bill Analysis 
SB 970 (File 321, as amended by Senate Amendment “A”)* 
 
AN ACT CONCERNING EXTENDING THE TIME OF EXPIRATION 
OF CERTAIN LAND USE PERMITS. 
 
SUMMARY 
This bill gives developers more time to complete certain ongoing 
projects without seeking reapproval from local land use boards, 
commissions, or agencies. It applies only to approvals and permits that 
were (1) granted on or after July 1, 2011, but before the bill’s passage, 
and (2) unexpired on March 10, 2020. 
Specifically, the bill extends the initial and extended statutory 
deadlines for completing projects that require certain subdivision, 
wetlands, or site plan approval. Generally, under the bill, these 
approvals are valid for at least 14 years and up to 19 years.   
The bill’s 14- and 19-year completion timeframes also apply to site 
plan and subdivision approvals and other permits (other than special 
permits or exceptions) granted by a zoning commission, planning 
commission, combined planning and zoning commission, zoning 
board of appeals, or inland wetlands agency exercising land use 
powers under a special act. 
The bill establishes a minimum amount of time, 19 years, a 
developer has to complete work related to a special permit or special 
exception, regardless of a locally set deadline. This 19-year minimum 
applies to approvals granted by municipalities exercising land use 
powers under the statutes or a special act.   
Executive Order (EO) 7JJ, § 3, issued on May 6, 2020, and 
subsequently extended, generally tolls the expiration dates for various 
land use approvals that were valid on March 10, 2020 (including site 
plan, wetlands, subdivision, and special permit approvals), thus 
pausing these approvals so they will not expire during the declared  2021SB-00970-R01-BA.DOCX 
 
Researcher: JSB 	Page 2 	5/14/21 
 
emergencies.   
EFFECTIVE DATE:  Upon passage 
*Senate Amendment “A” (1) extends the underlying bill’s initial and 
extended completion deadlines; (2) gives developers at least 19 years 
to finish work for which a special permit or exception was required; 
and (3) applies the amended bill’s provisions to approvals granted by a 
municipality exercising land use powers under a special act. 
SPECIAL PERMIT OR EX CEPTION PROJECT COMP LETION 
DEADLINES 
The bill establishes a minimum validity period for special permit or 
exception approvals (1) granted on or after July 1, 2011, but before the 
bill’s passage; (2) that were unexpired on March 10, 2020; and (3) that 
specified a deadline by which all work in connection with the approval 
must be completed. Under the bill, these approvals are valid for a 
minimum of 19 years after the approval is granted. Existing statutes do 
not impose any minimum validity periods for these approvals (see 
BACKGROUND) .   
The bill specifies that (1) the applicable land use board, commission, 
or agency may extend these approvals beyond 19 years and (2) this 
minimum 19-year validity period applies to special permits or 
exceptions approved by a municipality exercising land use powers 
under the statutes or a special act. 
OTHER PROJECT COMPLETION D EADLINES  
Municipalities Exercising Authority Under the Statutes 
When a planning or zoning commission, combined planning and 
zoning commission, or an inland wetlands agency operating under the 
statutes approves a project, it must set an expiration date that falls 
within the timeframes the law specifies. Consequently, a developer 
must complete the project before that date or resubmit it to the local 
commission or agency for approval. Generally, under current law, the 
maximum timeframe, including extensions if permitted, is 10 years 
from the date of approval. Under the bill, except for large residential  2021SB-00970-R01-BA.DOCX 
 
Researcher: JSB 	Page 3 	5/14/21 
 
subdivisions, the initial deadline must be at least 14 years after 
approval and the extended deadline cannot be more than 19 years after 
approval. Large residential subdivision approvals are valid for 19 
years. 
Table 1, below, shows the current and extended deadlines that 
apply to subdivision, wetlands, and site plans approvals granted by 
municipalities operating under the statutes.  
Table 1: Statutory Deadlines and Extensions Under Current Law and the Bill 
Land Use Approval 
(CGS §) 
Current Law 	Bill 
Residential site plans for projects 
with 400 or more units 
(§ 8-3(j)) 
Deadline: 10 years after approval  No change 
No extensions 
Business site plans for projects 
with at least 400,000 square feet 
(§ 8-3(j)) 
Deadline: 5-10 years after approval 
(set locally) 
No change 
Extension: up to 10 years from 
approval 
Other site plans 
(§ 8-3(i)) 
Deadline: 5 years after approval  At least 14 
years after 
approval 
Extension: up to 10 years from 
approval 
Up to 19 years 
from approval 
Subdivisions plans for 400 or 
more dwelling units 
(§ 8-26g) 
Deadline: 10 years after approval  19 years after 
approval 
No extensions 	No change 
Other subdivisions 
(§ 8-26c(a)&(b)) 
Deadline: 5 years after approval  At least 14 
years after 
approval 
Extension: up to 10 years from 
approval 
Up to 19 years 
from approval 
Wetlands permits associated 
with another approval (e.g., site 
plans and subdivisions) 
(§ 22a-42a(d)(2)) 
Deadline: 10 years after approval or 
the date the associated land use 
approval expires (whichever is 
earlier) 
At least 14 
years from 
approval  
Extension: up to 10 years from 
approval 
Up to 19 years 
from approval  2021SB-00970-R01-BA.DOCX 
 
Researcher: JSB 	Page 4 	5/14/21 
 
Other wetlands 
(§ 22a-42a(d)(2)) 
Deadline: 2-5 years after approval 
(set locally) 
At least 14 
years after 
approval 
Extension: up to 10 years from 
approval 
Up to 19 years 
from approval 
 
Municipalities Exercising Authority Under a Special Act 
The bill sets a minimum approval duration of 14 years for site plan 
and subdivision approvals and other permits (except special permits 
or exceptions, see above) granted by a zoning commission, planning 
commission, combined planning and zoning commission, zoning 
board of appeals, or inland wetlands agency exercising land use 
powers under a special act.  
The bill specifies that local boards or agencies may approve 
extensions, but caps the total duration of an approval, including 
extensions, at 19 years (except special permits or exceptions, see 
above). The 14- and 19-year timeframes are calculated based on the 
initial approval date and apply regardless of conflicting special acts or 
approval conditions. 
BACKGROUND 
Related Executive Order 
Under EO 7JJ, the expiration date of various land use approvals is 
tolled during the declared emergencies (§ 3, issued on May 6, 2020, 
and subsequently extended). The tolling provision applies only if the 
approval-holder was not in violation of the approval’s conditions on 
March 10, 2020, and does not violate them during the declared 
emergencies (a waiver of this requirement is available). 
Related Bills 
sHB 6531, as amended by House “A” (File 685), extends the initial 
and extended deadlines for completing projects approved before July 
1, 2011, that require certain subdivision, wetlands, or site plan 
approval.  
sHB 6541, favorably reported by the Planning and Development  2021SB-00970-R01-BA.DOCX 
 
Researcher: JSB 	Page 5 	5/14/21 
 
Committee, for permits issued on or after July 1, 2021, delays the 
effective date of municipal inland wetlands permits to coincide with 
the effective period of related local land use approvals (e.g., special 
permits, zoning variances, site plans, subdivision plans). 
Special Permits and Exceptions and Related Caselaw 
“Special permit” and “special exception” are synonymous. The 
designated local land use agency may grant special permits or 
exceptions pursuant to the Zoning Enabling Act (CGS § 8-2) or a 
special act, as applicable. Special permits and exceptions allow one to 
use a property in a manner explicitly permitted by the zoning 
regulations, but subject to conditions not applicable to other uses in the 
same district. The rationale for special permits and exceptions is that 
while certain land uses may be generally compatible with the uses 
permitted as of right in a particular zoning district, their nature is such 
that their precise location and mode of operation must be individually 
regulated. 
In February 2021, the Connecticut Appellate Court issued a 
decision, applicable to municipalities that exercise zoning powers 
under the statutes, holding that the law authorizes them to impose 
temporal conditions on special permits or exceptions, such as a 
condition requiring development to be completed by a specific date 
(International Investors v. Fairfield Planning & Zoning Commission, 202 
Conn. App. 582, cert. granted, 336 Conn. 928 (March 30, 2021)).   
COMMITTEE ACTION 
Planning and Development Committee 
Joint Favorable 
Yea 26 Nay 0 (03/21/2021)