Connecticut 2022 2022 Regular Session

Connecticut House Bill HB05456 Introduced / Fiscal Note

Filed 04/29/2022

                    OFFICE OF FISCAL ANALYSIS 
Legislative Office Building, Room 5200 
Hartford, CT 06106  (860) 240-0200 
http://www.cga.ct.gov/ofa 
HB-5456 
AN ACT AUTHORIZING THE PURCHASE OF THE CAPITOL 
DISTRICT ENERGY CENTER COGENERATION ASSOCIATES 
ENERGY PRODUCTION PLANT. 
As Amended by House "A" (LCO 5519) 
House Calendar No.: 353  
 
Primary Analyst: CP 	4/28/22 
Contributing Analyst(s):    
 
 
 
 
OFA Fiscal Note 
 
State Impact: 
Agency Affected Fund-Effect FY 23 $ FY 24 $ 
Treasurer, Debt Serv. GF - None See Below See Below 
Department of Administrative 
Services;  Judicial Dept.;  
Legislative Mgmt. 
GF – Potential 
Savings; Potential 
Cost Avoidance 
See Below See Below 
Note: GF=General Fund  
Municipal Impact: None  
Explanation 
The bill enables the Commissioner of the Department of 
Administrative Services (DAS) to purchase the energy production plant 
in Hartford which produces and provides steam and heated and chilled 
water for the Capitol Area System, including certain state agencies. It is 
anticipated that the purchase would produce long-term savings and 
cost avoidance to the agencies impacted, according to projections by the 
DAS that reflect increasing efficiencies in the facility's operation due to 
planned investments in its infrastructure. The DAS projections 
demonstrate state agency savings of over $20 million in total over 
twenty years relative to the current contract to purchase energy from the 
facility, in addition to the avoidance of potential future costs to the 
agencies consuming energy from the facility as planned or unplanned 
maintenance and repair costs are incurred and passed on to the state.  2022HB-05456-R010685-FN.DOCX 	Page 2 of 2 
 
 
There is no anticipated, additional projected cost to the State 
Treasurer's debt service line item because General Obligation bond 
funds authorized for the program (over $15 million in total) have 
already been allocated and made available. 
Electric ratepayer impact 
The energy production plant in Hartford has been decommissioned 
as a generator of electrical energy. However, some electricity is 
consumed in operating the facility. Purchase of the facility by the state 
would result in a shift in accounting for the cost of electricity to run the 
facility. Instead of being a component of the overall cost of procuring 
energy from the third-party operator of the facility as it is done 
currently, the state agency DAS (as a potential future owner) would 
need to negotiate and pay for electricity directly via Northeast Utilities. 
Overall usage and rates are uncertain, pending improved efficiencies 
and negotiations.  
The potential estimated savings indicated above of over $20 million 
in total is through calendar year 2040. 
House "A" strikes the original bill and its associated fiscal impact, 
thus becoming the bill with the above referenced fiscal impact.  
The Out Years 
The potential estimated savings indicated above of over $20 million 
in total is through calendar year 2040. 
The preceding Fiscal Impact statement is prepared for the benefit of the members of the General Assembly, solely 
for the purposes of information, summarization and explanation and does not represent the intent of the General 
Assembly or either chamber thereof for any purpose. In general, fiscal impacts are based upon a variety of 
informational sources, including the analyst’s professional knowledge. Whenever applicable, agency data is 
consulted as part of the analysis, however final products do not necessarily reflect an assessment from any 
specific department.