8 | | - | AN ACT |
---|
9 | | - | |
---|
10 | | - | ____________________ |
---|
11 | | - | |
---|
12 | | - | IN THE COUNCIL OF THE DISTRICT OF COLUMBIA |
---|
13 | | - | |
---|
14 | | - | _____________________________ |
---|
15 | | - | |
---|
16 | | - | |
---|
17 | | - | To exempt, on a temporary basis, the project to build an elevated park on the piers or foundation |
---|
18 | | - | of the former 11th Street Bridge from the requirements of 21 DCMR § 2605.7(a). |
---|
19 | | - | BE IT ENACTED BY THE COUNCIL OF THE DISTRICT OF COLUMBIA, That this |
---|
20 | | - | act may be cited as the “11th Street Bridge Project DOEE Permit Temporary Act of 2023”. |
---|
21 | | - | |
---|
22 | | - | Sec. 2. The requirements of 21 DCMR § 2605.7(a) shall not apply to the project to build |
---|
23 | | - | an elevated park on the piers or foundation of the former 11th Street Bridge. |
---|
24 | | - | |
---|
25 | | - | Sec. 3. Fiscal impact statement. |
---|
26 | | - | The Council adopts the fiscal impact statement of the Budget Director as the fiscal impact |
---|
27 | | - | statement required by section 4a of the General Legislative Procedures Act of 1975, approved |
---|
28 | | - | October 16, 2006 (120 Stat. 2038; D.C. Official Code § 1-301.47a). |
---|
29 | | - | |
---|
30 | | - | Sec. 4. Effective date. |
---|
31 | | - | (a) This act shall take effect following approval by the Mayor (or in the event of veto by |
---|
32 | | - | the Mayor, action by the Council to override the veto), a 30-day period of congressional review as |
---|
33 | | - | provided in section 602(c)(1) of the District of Columbia Home Rule Act, approved December 24, |
---|
34 | | - | 1973 (87 Stat. 813; D.C. Official Code § 1-206.02(c)(1)), and publication in the District of |
---|
35 | | - | Columbia Register. |
---|
36 | | - | (b) This act shall expire after 225 days of its having taken effect. |
---|
37 | | - | |
---|
38 | | - | |
---|
39 | | - | ______________________________ |
---|
40 | | - | Chairman |
---|
41 | | - | Council of the District of Columbia |
---|
42 | | - | |
---|
43 | | - | |
---|
44 | | - | |
---|
45 | | - | |
---|
46 | | - | _________________________________ |
---|
47 | | - | Mayor |
---|
48 | | - | District of Columbia |
---|
| 8 | + | A BILL 1 |
---|
| 9 | + | 2 |
---|
| 10 | + | 25-530 3 |
---|
| 11 | + | 4 |
---|
| 12 | + | IN THE COUNCIL OF THE DISTRICT OF COLUMBIA 5 |
---|
| 13 | + | 6 |
---|
| 14 | + | ____________________ 7 |
---|
| 15 | + | 8 |
---|
| 16 | + | 9 |
---|
| 17 | + | To exempt, on a temporary basis, the project to build an elevated park on the piers or foundation 10 |
---|
| 18 | + | of the former 11th Street Bridge from the requirements of 21 DCMR § 2605.7(a). 11 |
---|
| 19 | + | BE IT ENACTED BY THE COUNCIL OF THE DISTRICT OF COLUMBIA, That this 12 |
---|
| 20 | + | act may be cited as the “11th Street Bridge Project DOEE Permit Temporary Act of 2023”. 13 |
---|
| 21 | + | Sec. 2. The requirements of 21 DCMR § 2605.7(a) shall not apply to the project to build 14 |
---|
| 22 | + | an elevated park on the piers or foundation of the former 11th Street Bridge. 15 |
---|
| 23 | + | Sec. 3. Fiscal impact statement. 16 |
---|
| 24 | + | The Council adopts the fiscal impact statement of the Budget Director as the fiscal impact 17 |
---|
| 25 | + | statement required by section 4a of the General Legislative Procedures Act of 1975, approved 18 |
---|
| 26 | + | October 16, 2006 (120 Stat. 2038; D.C. Official Code § 1-301.47a). 19 |
---|
| 27 | + | Sec. 4. Effective date. 20 |
---|
| 28 | + | (a) This act shall take effect following approval by the Mayor (or in the event of veto by 21 |
---|
| 29 | + | the Mayor, action by the Council to override the veto), a 30-day period of congressional review as 22 |
---|
| 30 | + | provided in section 602(c)(1) of the District of Columbia Home Rule Act, approved December 24, 23 |
---|
| 31 | + | 1973 (87 Stat. 813; D.C. Official Code § 1-206.02(c)(1)), and publication in the District of 24 |
---|
| 32 | + | Columbia Register. 25 |
---|
| 33 | + | (b) This act shall expire after 225 days of its having taken effect. 26 |
---|