46 | 46 | | Page 2 of 13 |
---|
47 | 47 | | F L O R I D A H O U S E O F R E P R E S E N T A T I V E S |
---|
48 | 48 | | |
---|
49 | 49 | | |
---|
50 | 50 | | |
---|
51 | 51 | | for development permits and orders, provide the informa tion to 26 |
---|
52 | 52 | | the applicant at a preapplication meeting, or post the 27 |
---|
53 | 53 | | information on the county's website. 28 |
---|
54 | 54 | | (2) Within 5 business days after receiving an application 29 |
---|
55 | 55 | | for approval of a development permit or development order, a 30 |
---|
56 | 56 | | county shall confirm receipt of the application using contact 31 |
---|
57 | 57 | | information provided by the applicant. Within 30 days after 32 |
---|
58 | 58 | | receiving an application for approval of a development permit or 33 |
---|
59 | 59 | | development order, a county must review the application for 34 |
---|
60 | 60 | | completeness and issue a written notification to the applicant 35 |
---|
61 | 61 | | letter indicating that all required information is submitted or 36 |
---|
62 | 62 | | specify specifying with particularity any areas that are 37 |
---|
63 | 63 | | deficient. If the application is deficient, the applicant has 30 38 |
---|
64 | 64 | | days to address the deficiencies by submitting the required 39 |
---|
65 | 65 | | additional information. For applications that do not require 40 |
---|
66 | 66 | | final action through a quasi -judicial hearing or a public 41 |
---|
67 | 67 | | hearing, the county must approve, approve with conditions, or 42 |
---|
68 | 68 | | deny the application for a development permit or development 43 |
---|
69 | 69 | | order within 120 days after the county has deemed the 44 |
---|
70 | 70 | | application complete ., or 180 days For applications that require 45 |
---|
71 | 71 | | final action through a quasi -judicial hearing or a public 46 |
---|
72 | 72 | | hearing, the county must approve, approve with conditions, or 47 |
---|
73 | 73 | | deny the application f or a development permit or development 48 |
---|
74 | 74 | | order within 180 days after the county has deemed the 49 |
---|
75 | 75 | | application complete . Both parties may agree in writing to a 50 |
---|
76 | 76 | | |
---|
96 | | - | makes a substantive change to the application. As used in this 59 |
---|
97 | | - | subsection, the term "substantive change" means an applicant -60 |
---|
98 | | - | initiated change of 15 percent or more in the proposed density, 61 |
---|
99 | | - | intensity, or square footage of a parcel. 62 |
---|
100 | | - | (3)(2)(a) When reviewing an application for a development 63 |
---|
101 | | - | permit or development order that is certified by a professional 64 |
---|
102 | | - | listed in s. 403.0877, a county may not reques t additional 65 |
---|
103 | | - | information from the applicant more than three times, unless the 66 |
---|
104 | | - | applicant waives the limitation in writing. 67 |
---|
105 | | - | (b) If a county makes a request for additional information 68 |
---|
106 | | - | and the applicant submits the required additional information 69 |
---|
107 | | - | within 30 days after receiving the request, the county must 70 |
---|
108 | | - | review the application for completeness and issue a letter 71 |
---|
109 | | - | indicating that all required information has been submitted or 72 |
---|
110 | | - | specify with particularity any areas that are deficient within 73 |
---|
111 | | - | 30 days after receivin g the additional information. 74 |
---|
112 | | - | (c) If a county makes a second request for additional 75 |
---|
| 96 | + | makes a substantive change, as defined in s. 163.3164, to the 59 |
---|
| 97 | + | application. 60 |
---|
| 98 | + | (3)(2)(a) When reviewing an application for a development 61 |
---|
| 99 | + | permit or development order that is certified by a professional 62 |
---|
| 100 | + | listed in s. 403.0877, a county may not request additional 63 |
---|
| 101 | + | information from the applicant more than three times, unless the 64 |
---|
| 102 | + | applicant waives the limitation in writing. 65 |
---|
| 103 | + | (b) If a county makes a request for additional information 66 |
---|
| 104 | + | and the applicant submits the required additional information 67 |
---|
| 105 | + | within 30 days after receiving the request, the county must 68 |
---|
| 106 | + | review the application for completeness and issue a letter 69 |
---|
| 107 | + | indicating that all required information has been submitted or 70 |
---|
| 108 | + | specify with particularity any areas that are deficient within 71 |
---|
| 109 | + | 30 days after receiving the additional information. 72 |
---|
| 110 | + | (c) If a county makes a second request for additional 73 |
---|
| 111 | + | information and the applicant submits the required additional 74 |
---|
| 112 | + | information within 30 days after receiving the request, the 75 |
---|
125 | | - | information and the applicant submits the required additional 76 |
---|
126 | | - | information within 30 days after receiving the request, the 77 |
---|
127 | | - | county must review the application for completen ess and issue a 78 |
---|
128 | | - | letter indicating that all required information has been 79 |
---|
129 | | - | submitted or specify with particularity any areas that are 80 |
---|
130 | | - | deficient within 10 days after receiving the additional 81 |
---|
131 | | - | information. 82 |
---|
132 | | - | (d) Before a third request for additional information , the 83 |
---|
133 | | - | applicant must be offered a meeting to attempt to resolve 84 |
---|
134 | | - | outstanding issues. If a county makes a third request for 85 |
---|
135 | | - | additional information and the applicant submits the required 86 |
---|
136 | | - | additional information within 30 days after receiving the 87 |
---|
137 | | - | request, the county must deem the application complete within 10 88 |
---|
138 | | - | days after receiving the additional information or proceed to 89 |
---|
139 | | - | process the application for approval or denial unless the 90 |
---|
140 | | - | applicant waived the county's limitation in writing as described 91 |
---|
141 | | - | in paragraph (a). 92 |
---|
142 | | - | (e) Except as provided in subsection (7) (5), if the 93 |
---|
143 | | - | applicant believes the request for additional information is not 94 |
---|
144 | | - | authorized by ordinance, rule, statute, or other legal 95 |
---|
145 | | - | authority, the county, at the applicant's request, shall proceed 96 |
---|
146 | | - | to process the application for approval or denial. 97 |
---|
147 | | - | (4) A county must issue a refund to an applicant equal to: 98 |
---|
148 | | - | (a) Ten percent of the application fee if the county fails 99 |
---|
149 | | - | to issue written notification of completeness or written 100 |
---|
| 125 | + | county must review the application for completeness and issue a 76 |
---|
| 126 | + | letter indicating that all required information has been 77 |
---|
| 127 | + | submitted or specify with particularity any areas that are 78 |
---|
| 128 | + | deficient within 10 days after receiving the additional 79 |
---|
| 129 | + | information. 80 |
---|
| 130 | + | (d) Before a third request for additional information, the 81 |
---|
| 131 | + | applicant must be offered a meeting to attempt to resolve 82 |
---|
| 132 | + | outstanding issues. If a county makes a third request for 83 |
---|
| 133 | + | additional information and the applicant submits the required 84 |
---|
| 134 | + | additional information within 30 days after receiving the 85 |
---|
| 135 | + | request, the county must deem the application complete within 10 86 |
---|
| 136 | + | days after receiving the additional information or proceed to 87 |
---|
| 137 | + | process the application for approval or denial unless the 88 |
---|
| 138 | + | applicant waived the county's limitation in writing as described 89 |
---|
| 139 | + | in paragraph (a). 90 |
---|
| 140 | + | (e) Except as provided in subsection (7) (5), if the 91 |
---|
| 141 | + | applicant believes the request for additional information is not 92 |
---|
| 142 | + | authorized by ordinance, rule, statute, or other legal 93 |
---|
| 143 | + | authority, the county, at the applicant's request, shall proceed 94 |
---|
| 144 | + | to process the application for approval or denial. 95 |
---|
| 145 | + | (4) A county must issue a refund to an applicant equal to: 96 |
---|
| 146 | + | (a) Ten percent of the applicat ion fee if the county fails 97 |
---|
| 147 | + | to issue written notification of completeness or written 98 |
---|
| 148 | + | specification of areas of deficiency within 30 days after 99 |
---|
| 149 | + | receiving the application. 100 |
---|
162 | | - | specification of areas of deficiency within 30 days after 101 |
---|
163 | | - | receiving the application. 102 |
---|
164 | | - | (b) Ten percent of the application fee if the county fails 103 |
---|
165 | | - | to issue a written notification of completeness or written 104 |
---|
166 | | - | specification of areas of deficiency within 30 days after 105 |
---|
167 | | - | receiving the additional information pursuant to paragraph 106 |
---|
168 | | - | (3)(b). 107 |
---|
169 | | - | (c) Twenty percent of the application fee if the county 108 |
---|
170 | | - | fails to issue a written notification of completeness or written 109 |
---|
171 | | - | specification of areas of deficiency within 10 days after 110 |
---|
172 | | - | receiving the additional information pursuant to paragraph 111 |
---|
173 | | - | (3)(c). 112 |
---|
174 | | - | (d) Fifty percent of the application fee if the county 113 |
---|
175 | | - | fails to approve, approves with conditions, or denies the 114 |
---|
176 | | - | application within 30 days after conclusion of the 120 -day or 115 |
---|
177 | | - | 180-day timeframe specified in subsection (2). 116 |
---|
178 | | - | (e) One hundred percent of the application fee if the 117 |
---|
179 | | - | county fails to approve, approves with conditions, or denies an 118 |
---|
180 | | - | application 31 days or more after conclusion of the 120 -day or 119 |
---|
181 | | - | 180-day timeframe specified in subsection (2). 120 |
---|
182 | | - | 121 |
---|
183 | | - | A county is not required to issue a refund if the applicant and 122 |
---|
184 | | - | the county agree to an extension of time, the delay is caused by 123 |
---|
185 | | - | the applicant, or the delay is attributable to a force majeure 124 |
---|
186 | | - | or other extraordinary circumstance. 125 |
---|
| 162 | + | (b) Ten percent of the application fee if the county fails 101 |
---|
| 163 | + | to issue a written notifi cation of completeness or written 102 |
---|
| 164 | + | specification of areas of deficiency within 30 days after 103 |
---|
| 165 | + | receiving the additional information pursuant to paragraph 104 |
---|
| 166 | + | (3)(b). 105 |
---|
| 167 | + | (c) Twenty percent of the application fee if the county 106 |
---|
| 168 | + | fails to issue a written notification of completeness or written 107 |
---|
| 169 | + | specification of areas of deficiency within 10 days after 108 |
---|
| 170 | + | receiving the additional information pursuant to paragraph 109 |
---|
| 171 | + | (3)(c). 110 |
---|
| 172 | + | (d) Fifty percent of the application fee if the county 111 |
---|
| 173 | + | fails to approve, approves with conditions, or denies the 112 |
---|
| 174 | + | application within 30 days after conclusion of the 120 -day or 113 |
---|
| 175 | + | 180-day timeframe specified in subsection (2). 114 |
---|
| 176 | + | (e) One hundred percent of the application fee if the 115 |
---|
| 177 | + | county fails to approve, approves with conditions, or denies an 116 |
---|
| 178 | + | application 31 days or more after conclusion of the 120 -day or 117 |
---|
| 179 | + | 180-day timeframe specified in subsection (2). 118 |
---|
| 180 | + | 119 |
---|
| 181 | + | A county is not required to issue a refund if the applicant and 120 |
---|
| 182 | + | the county agree to an extension of time, the delay is caused by 121 |
---|
| 183 | + | the applicant, or the delay is a ttributable to a force majeure 122 |
---|
| 184 | + | or other extraordinary circumstance. 123 |
---|
| 185 | + | (5)(3) When a county denies an application for a 124 |
---|
| 186 | + | development permit or development order, the county shall give 125 |
---|
199 | | - | (5)(3) When a county denies an application for a 126 |
---|
200 | | - | development permit or development order, the county shall give 127 |
---|
201 | | - | written notice to the applicant. The notice must include a 128 |
---|
202 | | - | citation to the applicable portions of an ordinance, rule, 129 |
---|
203 | | - | statute, or other legal authority for the denial of the permit 130 |
---|
204 | | - | or order. 131 |
---|
205 | | - | (6)(4) As used in this section, the terms "development 132 |
---|
206 | | - | permit" and "development order" have the same meaning as in s. 133 |
---|
207 | | - | 163.3164, but do not include building permits. 134 |
---|
208 | | - | (7)(5) For any development permit application filed with 135 |
---|
209 | | - | the county after July 1, 2012, a county may not require as a 136 |
---|
210 | | - | condition of processing or issuing a development permit or 137 |
---|
211 | | - | development order that an applicant obtain a permit or approval 138 |
---|
212 | | - | from any state or federal agency unless the agency has issued a 139 |
---|
213 | | - | final agency action that denies the federal or stat e permit 140 |
---|
214 | | - | before the county action on the local development permit. 141 |
---|
215 | | - | (8)(6) Issuance of a development permit or development 142 |
---|
216 | | - | order by a county does not in any way create any rights on the 143 |
---|
217 | | - | part of the applicant to obtain a permit from a state or federal 144 |
---|
218 | | - | agency and does not create any liability on the part of the 145 |
---|
219 | | - | county for issuance of the permit if the applicant fails to 146 |
---|
220 | | - | obtain requisite approvals or fulfill the obligations imposed by 147 |
---|
221 | | - | a state or federal agency or undertakes actions that result in a 148 |
---|
222 | | - | violation of state or federal law. A county shall attach such a 149 |
---|
223 | | - | disclaimer to the issuance of a development permit and shall 150 |
---|
| 199 | + | written notice to the applicant. The notice must include a 126 |
---|
| 200 | + | citation to the applicable portions of an ordinance, rule, 127 |
---|
| 201 | + | statute, or other legal authority for the denial of the permit 128 |
---|
| 202 | + | or order. 129 |
---|
| 203 | + | (6)(4) As used in this section, the terms "development 130 |
---|
| 204 | + | permit" and "development order" have the same meaning as in s. 131 |
---|
| 205 | + | 163.3164, but do not include building permits. 132 |
---|
| 206 | + | (7)(5) For any development permit application filed with 133 |
---|
| 207 | + | the county after July 1, 2012, a county may not require as a 134 |
---|
| 208 | + | condition of processing or issuing a development permit or 135 |
---|
| 209 | + | development order that an applicant obtain a perm it or approval 136 |
---|
| 210 | + | from any state or federal agency unless the agency has issued a 137 |
---|
| 211 | + | final agency action that denies the federal or state permit 138 |
---|
| 212 | + | before the county action on the local development permit. 139 |
---|
| 213 | + | (8)(6) Issuance of a development permit or development 140 |
---|
| 214 | + | order by a county does not in any way create any rights on the 141 |
---|
| 215 | + | part of the applicant to obtain a permit from a state or federal 142 |
---|
| 216 | + | agency and does not create any liability on the part of the 143 |
---|
| 217 | + | county for issuance of the permit if the applicant fails to 144 |
---|
| 218 | + | obtain requisite approvals or fulfill the obligations imposed by 145 |
---|
| 219 | + | a state or federal agency or undertakes actions that result in a 146 |
---|
| 220 | + | violation of state or federal law. A county shall attach such a 147 |
---|
| 221 | + | disclaimer to the issuance of a development permit and shall 148 |
---|
| 222 | + | include a permit condition that all other applicable state or 149 |
---|
| 223 | + | federal permits be obtained before commencement of the 150 |
---|
236 | | - | include a permit condition that all other applicable state or 151 |
---|
237 | | - | federal permits be obtained before commencement of the 152 |
---|
238 | | - | development. 153 |
---|
239 | | - | (9)(7) This section does not prohibit a county from 154 |
---|
240 | | - | providing information to an applicant regarding what other state 155 |
---|
241 | | - | or federal permits may apply. 156 |
---|
242 | | - | Section 2. Section 166.033, Florida Statutes, is amended 157 |
---|
243 | | - | to read: 158 |
---|
244 | | - | 166.033 Development permits and orders. — 159 |
---|
245 | | - | (1) A municipality must specify in writing the minimum 160 |
---|
246 | | - | information that must be submitted for an application for a 161 |
---|
247 | | - | zoning approval, rezoning approval, subdivision approval, 162 |
---|
248 | | - | certification, special exception, or variance. A municipality 163 |
---|
249 | | - | must make the minimum in formation available for inspection and 164 |
---|
250 | | - | copying at the location where the municipality receives 165 |
---|
251 | | - | applications for development permits and orders, provide the 166 |
---|
252 | | - | information to the applicant at a preapplication meeting, or 167 |
---|
253 | | - | post the information on the municipalit y's website. 168 |
---|
254 | | - | (2) Within 5 business days after receiving an application 169 |
---|
255 | | - | for approval of a development permit or development order, a 170 |
---|
256 | | - | municipality shall confirm receipt of the application using 171 |
---|
257 | | - | contact information provided by the applicant. Within 30 days 172 |
---|
258 | | - | after receiving an application for approval of a development 173 |
---|
259 | | - | permit or development order, a municipality must review the 174 |
---|
260 | | - | application for completeness and issue a written notification to 175 |
---|
| 236 | + | development. 151 |
---|
| 237 | + | (9)(7) This section does not prohibit a county from 152 |
---|
| 238 | + | providing information to an applicant regarding what other state 153 |
---|
| 239 | + | or federal permits may apply. 154 |
---|
| 240 | + | Section 2. Section 166.033, Florida Statutes, is amended 155 |
---|
| 241 | + | to read: 156 |
---|
| 242 | + | 166.033 Development permits and orders. — 157 |
---|
| 243 | + | (1) A municipality must specify in writing the minimum 158 |
---|
| 244 | + | information that must be submitted for an application for a 159 |
---|
| 245 | + | zoning approval, rezoning approval, subdivision approval, 160 |
---|
| 246 | + | certification, special exception, or variance. A municipality 161 |
---|
| 247 | + | must make the minimum information available for inspection and 162 |
---|
| 248 | + | copying at the location where the municipality receives 163 |
---|
| 249 | + | applications for development pe rmits and orders, provide the 164 |
---|
| 250 | + | information to the applicant at a preapplication meeting, or 165 |
---|
| 251 | + | post the information on the municipality's website. 166 |
---|
| 252 | + | (2) Within 5 business days after receiving an application 167 |
---|
| 253 | + | for approval of a development permit or development o rder, a 168 |
---|
| 254 | + | municipality shall confirm receipt of the application using 169 |
---|
| 255 | + | contact information provided by the applicant. Within 30 days 170 |
---|
| 256 | + | after receiving an application for approval of a development 171 |
---|
| 257 | + | permit or development order, a municipality must review the 172 |
---|
| 258 | + | application for completeness and issue a written notification to 173 |
---|
| 259 | + | the applicant letter indicating that all required information is 174 |
---|
| 260 | + | submitted or specify specifying with particularity any areas 175 |
---|
273 | | - | the applicant letter indicating that all required information is 176 |
---|
274 | | - | submitted or specify specifying with particularity any areas 177 |
---|
275 | | - | that are deficient. If the application is deficient, the 178 |
---|
276 | | - | applicant has 30 days to address the deficiencies by submitting 179 |
---|
277 | | - | the required additional information. For applications that do 180 |
---|
278 | | - | not require final action through a quasi -judicial hearing or a 181 |
---|
279 | | - | public hearing, the municipality must approve, approve with 182 |
---|
280 | | - | conditions, or deny the application for a development permit or 183 |
---|
281 | | - | development order within 120 days after the municipality has 184 |
---|
282 | | - | deemed the application co mplete., or 180 days For applications 185 |
---|
283 | | - | that require final action through a quasi -judicial hearing or a 186 |
---|
284 | | - | public hearing, the municipality must approve, approve with 187 |
---|
285 | | - | conditions, or deny the application for a development permit or 188 |
---|
286 | | - | development order within 180 days after the municipality has 189 |
---|
287 | | - | deemed the application complete . Both parties may agree in 190 |
---|
288 | | - | writing to a reasonable request for an extension of time, 191 |
---|
289 | | - | particularly in the event of a force majeure or other 192 |
---|
290 | | - | extraordinary circumstance. An approval, approval wit h 193 |
---|
291 | | - | conditions, or denial of the application for a development 194 |
---|
292 | | - | permit or development order must include written findings 195 |
---|
293 | | - | supporting the municipality's decision. The timeframes contained 196 |
---|
294 | | - | in this subsection do not apply in an area of critical state 197 |
---|
295 | | - | concern, as designated in s. 380.0552 or chapter 28 -36, Florida 198 |
---|
296 | | - | Administrative Code. The timeframes contained in this subsection 199 |
---|
297 | | - | restart if an applicant makes a substantive change to the 200 |
---|
| 273 | + | that are deficient. If the application is deficient, the 176 |
---|
| 274 | + | applicant has 30 days to address the deficiencies by submitting 177 |
---|
| 275 | + | the required additional information. For applications that do 178 |
---|
| 276 | + | not require final action through a quasi -judicial hearing or a 179 |
---|
| 277 | + | public hearing, the municipality must approve, approve with 180 |
---|
| 278 | + | conditions, or deny the application for a development permit or 181 |
---|
| 279 | + | development order within 120 days after the municipality has 182 |
---|
| 280 | + | deemed the application complete ., or 180 days For applications 183 |
---|
| 281 | + | that require final action through a quasi -judicial hearing or a 184 |
---|
| 282 | + | public hearing, the municipality must approve, approve with 185 |
---|
| 283 | + | conditions, or deny the application for a development permit or 186 |
---|
| 284 | + | development order within 180 days after the munici pality has 187 |
---|
| 285 | + | deemed the application complete . Both parties may agree in 188 |
---|
| 286 | + | writing to a reasonable request for an extension of time, 189 |
---|
| 287 | + | particularly in the event of a force majeure or other 190 |
---|
| 288 | + | extraordinary circumstance. An approval, approval with 191 |
---|
| 289 | + | conditions, or denial of the application for a development 192 |
---|
| 290 | + | permit or development order must include written findings 193 |
---|
| 291 | + | supporting the municipality's decision. The timeframes contained 194 |
---|
| 292 | + | in this subsection do not apply in an area of critical state 195 |
---|
| 293 | + | concern, as designated in s. 380 .0552 or chapter 28-36, Florida 196 |
---|
| 294 | + | Administrative Code. The timeframes contained in this subsection 197 |
---|
| 295 | + | restart if an applicant makes a substantive change, as defined 198 |
---|
| 296 | + | in s. 163.3164, to the application. 199 |
---|
| 297 | + | (3)(2)(a) When reviewing an application for a development 200 |
---|
310 | | - | application. As used in this subsection, the term "substantive 201 |
---|
311 | | - | change" means an applicant-initiated change of 15 percent or 202 |
---|
312 | | - | more in the proposed density, intensity, or square footage of a 203 |
---|
313 | | - | parcel. 204 |
---|
314 | | - | (3)(2)(a) When reviewing an application for a development 205 |
---|
315 | | - | permit or development order that is certified by a professional 206 |
---|
316 | | - | listed in s. 403.0877, a municipality may not request additional 207 |
---|
317 | | - | information from the applicant more than three times, unless the 208 |
---|
318 | | - | applicant waives the limitation in writing. 209 |
---|
319 | | - | (b) If a municipality makes a request for additional 210 |
---|
320 | | - | information and the applicant submits the r equired additional 211 |
---|
321 | | - | information within 30 days after receiving the request, the 212 |
---|
322 | | - | municipality must review the application for completeness and 213 |
---|
323 | | - | issue a letter indicating that all required information has been 214 |
---|
324 | | - | submitted or specify with particularity any areas that are 215 |
---|
325 | | - | deficient within 30 days after receiving the additional 216 |
---|
326 | | - | information. 217 |
---|
327 | | - | (c) If a municipality makes a second request for 218 |
---|
328 | | - | additional information and the applicant submits the required 219 |
---|
329 | | - | additional information within 30 days after receiving the 220 |
---|
330 | | - | request, the municipality must review the application for 221 |
---|
331 | | - | completeness and issue a letter indicating that all required 222 |
---|
332 | | - | information has been submitted or specify with particularity any 223 |
---|
333 | | - | areas that are deficient within 10 days after receiving the 224 |
---|
334 | | - | additional information. 225 |
---|
| 310 | + | permit or development order that is certified by a professional 201 |
---|
| 311 | + | listed in s. 403.0877, a municipality may not request additional 202 |
---|
| 312 | + | information from the applicant more than three times, unless the 203 |
---|
| 313 | + | applicant waives the limitation in writing. 204 |
---|
| 314 | + | (b) If a municipality makes a request for additional 205 |
---|
| 315 | + | information and the applicant submits the required additional 206 |
---|
| 316 | + | information within 30 days after receiving the request, the 207 |
---|
| 317 | + | municipality must review the application for completeness and 208 |
---|
| 318 | + | issue a letter indicating that all required information has been 209 |
---|
| 319 | + | submitted or specify with particularity any areas that are 210 |
---|
| 320 | + | deficient within 30 days after receiving the additional 211 |
---|
| 321 | + | information. 212 |
---|
| 322 | + | (c) If a municipality makes a second request for 213 |
---|
| 323 | + | additional information and the applicant submit s the required 214 |
---|
| 324 | + | additional information within 30 days after receiving the 215 |
---|
| 325 | + | request, the municipality must review the application for 216 |
---|
| 326 | + | completeness and issue a letter indicating that all required 217 |
---|
| 327 | + | information has been submitted or specify with particularity any 218 |
---|
| 328 | + | areas that are deficient within 10 days after receiving the 219 |
---|
| 329 | + | additional information. 220 |
---|
| 330 | + | (d) Before a third request for additional information, the 221 |
---|
| 331 | + | applicant must be offered a meeting to attempt to resolve 222 |
---|
| 332 | + | outstanding issues. If a municipality makes a third request for 223 |
---|
| 333 | + | additional information and the applicant submits the required 224 |
---|
| 334 | + | additional information within 30 days after receiving the 225 |
---|
347 | | - | (d) Before a third request for additional information, the 226 |
---|
348 | | - | applicant must be offered a meeting to attempt to resolve 227 |
---|
349 | | - | outstanding issues. If a municipality makes a third request for 228 |
---|
350 | | - | additional information and the applicant submits the required 229 |
---|
351 | | - | additional information within 30 days after receiving the 230 |
---|
352 | | - | request, the municipality must deem the application complete 231 |
---|
353 | | - | within 10 days after receiving the additional information or 232 |
---|
354 | | - | proceed to process the application for approval or denial unless 233 |
---|
355 | | - | the applicant waived the municipality's limitation in writing as 234 |
---|
356 | | - | described in paragraph (a). 235 |
---|
357 | | - | (e) Except as provided in subsection (7) (5), if the 236 |
---|
358 | | - | applicant believes the request for additional information is not 237 |
---|
359 | | - | authorized by ordinance, rule, statute, or other legal 238 |
---|
360 | | - | authority, the municipality, at the applicant's request, shall 239 |
---|
361 | | - | proceed to process the application for approval or denial. 240 |
---|
362 | | - | (4) A municipality must issue a refund to an applicant 241 |
---|
363 | | - | equal to: 242 |
---|
364 | | - | (a) Ten percent of the application fee if the municipality 243 |
---|
365 | | - | fails to issue written notification of completeness or written 244 |
---|
366 | | - | specification of areas of deficiency within 30 days after 245 |
---|
367 | | - | receiving the application. 246 |
---|
368 | | - | (b) Ten percent of the application fee if the municipality 247 |
---|
369 | | - | fails to issue written notification of completeness or wri tten 248 |
---|
370 | | - | specification of areas of deficiency within 30 days after 249 |
---|
371 | | - | receiving the additional information pursuant to paragraph 250 |
---|
| 347 | + | request, the municipality must deem the application complete 226 |
---|
| 348 | + | within 10 days after receiving the additional information or 227 |
---|
| 349 | + | proceed to process the application for approval or denial unless 228 |
---|
| 350 | + | the applicant waived the municipality's limitation in writing as 229 |
---|
| 351 | + | described in paragraph (a). 230 |
---|
| 352 | + | (e) Except as provided in subsection (7) (5), if the 231 |
---|
| 353 | + | applicant believes the request for additional information is not 232 |
---|
| 354 | + | authorized by ordinance, rule, statute, or other legal 233 |
---|
| 355 | + | authority, the municipality, at the applicant's request, shall 234 |
---|
| 356 | + | proceed to process the application for approval or denial. 235 |
---|
| 357 | + | (4) A municipality must issue a refund to an applicant 236 |
---|
| 358 | + | equal to: 237 |
---|
| 359 | + | (a) Ten percent of the application fee if the municipality 238 |
---|
| 360 | + | fails to issue written notification of completeness or written 239 |
---|
| 361 | + | specification of areas of deficiency within 30 days after 240 |
---|
| 362 | + | receiving the application. 241 |
---|
| 363 | + | (b) Ten percent of the application fe e if the municipality 242 |
---|
| 364 | + | fails to issue written notification of completeness or written 243 |
---|
| 365 | + | specification of areas of deficiency within 30 days after 244 |
---|
| 366 | + | receiving the additional information pursuant to paragraph 245 |
---|
| 367 | + | (3)(b). 246 |
---|
| 368 | + | (c) Twenty percent of the application fee if the 247 |
---|
| 369 | + | municipality fails to issue written notification of completeness 248 |
---|
| 370 | + | or written specification of areas of deficiency within 10 days 249 |
---|
| 371 | + | after receiving the additional information pursuant to paragraph 250 |
---|
384 | | - | (3)(b). 251 |
---|
385 | | - | (c) Twenty percent of the application fee if the 252 |
---|
386 | | - | municipality fails to issue written notification of completeness 253 |
---|
387 | | - | or written specification of areas of deficiency within 10 days 254 |
---|
388 | | - | after receiving the additional information pursuant to paragraph 255 |
---|
389 | | - | (3)(c). 256 |
---|
390 | | - | (d) Fifty percent of the application fee if the 257 |
---|
391 | | - | municipality fails to approve, approves with conditions, or 258 |
---|
392 | | - | denies the applicati on within 30 days after conclusion of the 259 |
---|
393 | | - | 120-day or 180-day timeframe specified in subsection (2). 260 |
---|
394 | | - | (e) One hundred percent of the application fee if the 261 |
---|
395 | | - | municipality fails to approve, approves with conditions, or 262 |
---|
396 | | - | denies an application 31 days or more af ter conclusion of the 263 |
---|
397 | | - | 120-day or 180-day timeframe specified in subsection (2). 264 |
---|
398 | | - | 265 |
---|
399 | | - | A municipality is not required to issue a refund if the 266 |
---|
400 | | - | applicant and the municipality agree to an extension of time, 267 |
---|
401 | | - | the delay is caused by the applicant, or the delay is 268 |
---|
402 | | - | attributable to a force majeure or other extraordinary 269 |
---|
403 | | - | circumstance. 270 |
---|
404 | | - | (5)(3) When a municipality denies an application for a 271 |
---|
405 | | - | development permit or development order, the municipality shall 272 |
---|
406 | | - | give written notice to the applicant. The notice must include a 273 |
---|
407 | | - | citation to the applicable portions of an ordinance, rule, 274 |
---|
408 | | - | statute, or other legal authority for the denial of the permit 275 |
---|
| 384 | + | (3)(c). 251 |
---|
| 385 | + | (d) Fifty percent of the application fee if the 252 |
---|
| 386 | + | municipality fails to approve, approves with conditions, or 253 |
---|
| 387 | + | denies the application within 30 days after conclusion of the 254 |
---|
| 388 | + | 120-day or 180-day timeframe specified in subsection (2). 255 |
---|
| 389 | + | (e) One hundred percent of the application fee if the 256 |
---|
| 390 | + | municipality fails t o approve, approves with conditions, or 257 |
---|
| 391 | + | denies an application 31 days or more after conclusion of the 258 |
---|
| 392 | + | 120-day or 180-day timeframe specified in subsection (2). 259 |
---|
| 393 | + | 260 |
---|
| 394 | + | A municipality is not required to issue a refund if the 261 |
---|
| 395 | + | applicant and the municipality agree t o an extension of time, 262 |
---|
| 396 | + | the delay is caused by the applicant, or the delay is 263 |
---|
| 397 | + | attributable to a force majeure or other extraordinary 264 |
---|
| 398 | + | circumstance. 265 |
---|
| 399 | + | (5)(3) When a municipality denies an application for a 266 |
---|
| 400 | + | development permit or development order, the municip ality shall 267 |
---|
| 401 | + | give written notice to the applicant. The notice must include a 268 |
---|
| 402 | + | citation to the applicable portions of an ordinance, rule, 269 |
---|
| 403 | + | statute, or other legal authority for the denial of the permit 270 |
---|
| 404 | + | or order. 271 |
---|
| 405 | + | (6)(4) As used in this section, the terms "dev elopment 272 |
---|
| 406 | + | permit" and "development order" have the same meaning as in s. 273 |
---|
| 407 | + | 163.3164, but do not include building permits. 274 |
---|
| 408 | + | (7)(5) For any development permit application filed with 275 |
---|
421 | | - | or order. 276 |
---|
422 | | - | (6)(4) As used in this section, the terms "development 277 |
---|
423 | | - | permit" and "development order" have the same meaning as in s. 278 |
---|
424 | | - | 163.3164, but do not include building permits. 279 |
---|
425 | | - | (7)(5) For any development permit application filed with 280 |
---|
426 | | - | the municipality after July 1, 2012, a municipality may not 281 |
---|
427 | | - | require as a condition of processing or issuing a development 282 |
---|
428 | | - | permit or development order that an applicant obtain a permit or 283 |
---|
429 | | - | approval from any state or federal agency unless the agency has 284 |
---|
430 | | - | issued a final agency action that denies the federal or state 285 |
---|
431 | | - | permit before the municipal action on the local development 286 |
---|
432 | | - | permit. 287 |
---|
433 | | - | (8)(6) Issuance of a development permit or development 288 |
---|
434 | | - | order by a municipalit y does not create any right on the part of 289 |
---|
435 | | - | an applicant to obtain a permit from a state or federal agency 290 |
---|
436 | | - | and does not create any liability on the part of the 291 |
---|
437 | | - | municipality for issuance of the permit if the applicant fails 292 |
---|
438 | | - | to obtain requisite approvals or f ulfill the obligations imposed 293 |
---|
439 | | - | by a state or federal agency or undertakes actions that result 294 |
---|
440 | | - | in a violation of state or federal law. A municipality shall 295 |
---|
441 | | - | attach such a disclaimer to the issuance of development permits 296 |
---|
442 | | - | and shall include a permit condition that all other applicable 297 |
---|
443 | | - | state or federal permits be obtained before commencement of the 298 |
---|
444 | | - | development. 299 |
---|
445 | | - | (9)(7) This section does not prohibit a municipality from 300 |
---|
| 421 | + | the municipality after July 1, 2012, a municipality may not 276 |
---|
| 422 | + | require as a condition of processing or issuing a development 277 |
---|
| 423 | + | permit or development order that an applicant obtain a permit or 278 |
---|
| 424 | + | approval from any state or federal agency unless the agency has 279 |
---|
| 425 | + | issued a final agency action that denies the federal or state 280 |
---|
| 426 | + | permit before the municipal action on the local development 281 |
---|
| 427 | + | permit. 282 |
---|
| 428 | + | (8)(6) Issuance of a development permit or development 283 |
---|
| 429 | + | order by a municipality does not create any right on the part of 284 |
---|
| 430 | + | an applicant to obtain a permit from a state or federal agency 285 |
---|
| 431 | + | and does not create any liability on the part of the 286 |
---|
| 432 | + | municipality for issuance of the permit if the applicant fails 287 |
---|
| 433 | + | to obtain requisite approvals or fulfill the obligations imposed 288 |
---|
| 434 | + | by a state or federal agency or undertakes actions that result 289 |
---|
| 435 | + | in a violation of state or fede ral law. A municipality shall 290 |
---|
| 436 | + | attach such a disclaimer to the issuance of development permits 291 |
---|
| 437 | + | and shall include a permit condition that all other applicable 292 |
---|
| 438 | + | state or federal permits be obtained before commencement of the 293 |
---|
| 439 | + | development. 294 |
---|
| 440 | + | (9)(7) This section does not prohibit a municipality from 295 |
---|
| 441 | + | providing information to an applicant regarding what other state 296 |
---|
| 442 | + | or federal permits may apply. 297 |
---|
| 443 | + | Section 3. Subsections (46) through (52) of section 298 |
---|
| 444 | + | 163.3164, Florida Statutes, are renumbered as subsections (47) 299 |
---|
| 445 | + | through (53), respectively, and a new subsection (46) is added 300 |
---|