11 HOUSE OF REPRESENTATIVES H.B. NO. 2352 THIRTY-FIRST LEGISLATURE, 2022 STATE OF HAWAII A BILL FOR AN ACT relating to capital improvement projects for the benefit of THE Forty-first REPRESENTATIVE DISTRICT. BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
22
33 HOUSE OF REPRESENTATIVES H.B. NO. 2352
44 THIRTY-FIRST LEGISLATURE, 2022
55 STATE OF HAWAII
66
77 HOUSE OF REPRESENTATIVES
88
99 H.B. NO.
1010
1111 2352
1212
1313 THIRTY-FIRST LEGISLATURE, 2022
1414
1515
1616
1717 STATE OF HAWAII
1818
1919
2020
2121
2222
2323
2424
2525
2626
2727
2828
2929
3030
3131 A BILL FOR AN ACT
3232
3333
3434
3535
3636
3737 relating to capital improvement projects for the benefit of THE Forty-first REPRESENTATIVE DISTRICT.
3838
3939
4040
4141
4242
4343 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
4444
4545
4646
4747 SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $622,097,250 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2022-2023 for the purpose of capital improvement projects for the forty-first representative district, as follows: 1. Saratoga Avenue electrical and communication infrastructure improvements in Kalaeloa, Oahu Construction for Saratoga Avenue electrical and communication infrastructure improvements in Kalaeloa, Oahu. Construction $12,125,000 Total funding $12,125,000 The sum appropriated for this capital improvement project shall be expended by the department of business, economic development, and tourism. 2. Barbers point elementary school, Oahu Design and construction for air conditioning for the entire school. Design $500,000 Construction $4,500,000 Total funding $5,000,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 3. Barbers point elementary school, Oahu Design and construction for cafeteria restrooms. Design $150,000 Construction $1,350,000 Total funding $1,500,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 4. East Kapolei high school, Oahu Plans, design, construction, and equipment for a new high school; ground and site improvements; and equipment and appurtenances. Plans $1,499,000 Design $16,000,000 Construction $132,000,000 Equipment $1,000 Total funding $149,500,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 5. East Kapolei middle school, Oahu Plans, design, construction, and equipment for a new middle school; ground and site improvements; and equipment and appurtenances. Plans $1,000,000 Design $2,000,000 Construction $120,640,000 Equipment $10,000,000 Total funding $133,640,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 6. Ewa beach elementary school, Oahu Construction for asphalt paving and parking lot. Construction $3,000,000 Total funding $3,000,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 7. Ewa beach elementary school, Oahu Plans and construction for covering of play courts and night lighting. Plans $500,000 Construction $4,500,000 Total funding $5,000,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 8. Ewa beach performing arts center, Oahu Plans, land, design, construction, and equipment for phase one of a new performing arts center; ground and site improvements; and equipment and appurtenances. Plans $100,000 Land $1,000 Design $1,498,000 Construction $20,000,000 Equipment $1,000 Total funding $21,600,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 9. Ewa Beach public library, Oahu Plans and design for a new public library. Plans $50,000 Design $100,000 Total funding $150,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 10. Ilima intermediate school, Oahu Construction for concrete walkway. Construction $40,000 Total funding $40,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 11. Ilima intermediate school, Oahu Construction for renovation of cafeteria restroom. Construction $87,500 Total funding $87,500 The sum appropriated for this capital improvement project shall be expended by the department of education. 12. Ilima intermediate school, Oahu Construction for replacement of cafeteria kitchen light fixture. Construction $40,000 Total funding $40,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 13. Ilima intermediate school, Oahu Construction for replacement of drains leaking from the second floor of D building. Construction $200,000 Total funding $200,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 14. Ilima intermediate school, Oahu Construction for replacement of exterior doors of R building (computer lab). Construction $26,000 Total funding $26,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 15. Ilima intermediate school, Oahu Construction for replacement of floor tiles in front office. Construction $400,000 Total funding $400,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 16. Ilima intermediate school, Oahu Construction for replacement of front of campus fence. Construction $120,000 Total funding $120,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 17. Ilima intermediate school, Oahu Construction for replacement of walkway behind C building with concrete. Construction $50,000 Total funding $50,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 18. Ilima intermediate school, Oahu Construction for reroofing of cafeteria. Construction $468,750 Total funding $468,750 The sum appropriated for this capital improvement project shall be expended by the department of education. 19. Ilima intermediate school, Oahu Construction for small retaining wall located three feet behind D building. Construction $200,000 Total funding $200,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 20. Ilima intermediate school, Oahu Design and construction for sixth grade building. Design $10,000,000 Construction $25,000,000 Total funding $35,000,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 21. Ilima intermediate school, Oahu Plans and construction for campus-wide painting of the exterior building walls and remodeling and repainting of the interior of the cafeteria. Plans $500,000 Construction $7,500,000 Total funding $8,000,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 22. Ilima intermediate school, Oahu Plans, design, and construction for cafetorium renovations. Plans $900,000 Design $100,000 Construction $4,000,000 Total funding $5,000,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 23. Ilima intermediate school, Oahu Plans, design, and construction for replacement of the existing fence and cattle gates at the front of the school with a reinforced wall and new gates; ground and site improvements. Plans $500,000 Design $500,000 Construction $7,000,000 Total funding $8,000,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 24. Iroquois point elementary school, Oahu Plans, design, and construction for a playground cover or awning. Plans $1,000 Land $1,000 Construction $48,000 Total funding $50,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 25. James Campbell high school, Oahu Design and construction for an athletic complex, including a new stadium; a new Title IX-compliant girls' athletic locker room; restroom facilities; ground and site improvements; and equipment and appurtenances, per master plan. Design $1,500,000 Construction $28,800,000 Total funding $30,300,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 26. Kapolei high school, Oahu Design and construction for a fine arts auditorium. Design $4,000,000 Construction $36,000,000 Total funding $40,000,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 27. Kapolei high school, Oahu Design and construction for a shelter in place (administration buildings B, D, G, H). Design $200,000 Construction $1,300,000 Total funding $1,500,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 28. Kapolei high school, Oahu Design and construction for restrooms for portables. Design $100,000 Construction $750,000 Total funding $850,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 29. Kapolei high school, Oahu Plans, design, and construction for new classroom building; ground and site improvements. Plans $1,000,000 Design $2,000,000 Construction $37,000,000 Total funding $40,000,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 30. Kapolei middle school, Oahu Design and construction for a classroom building. Design $4,500,000 Construction $40,500,000 Total funding $45,000,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 31. Kapolei middle school, Oahu Design and construction for a shelter in place (library buildings A, C, E, F, G, H, I). Design $150,000 Construction $1,600,000 Total funding $1,750,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 32. Kapolei middle school, Oahu Design and construction for restrooms for portables. Design $100,000 Construction $750,000 Total funding $850,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 33. Fort Weaver road, Oahu Design and construction for Fort Weaver road, sidewalks, crosswalks, signals, and related signage. Design $1,600,000 Construction $20,000,000 Total funding $21,600,000 The sum appropriated for this capital improvement project shall be expended by the department of transportation. 34. Fort Weaver road, Oahu Plans and construction for installation of additional traffic cameras along Fort Weaver road at the intersections of Keoneula boulevard, Papipi road, and Keaunui Drive and along Kapolei parkway. Plans $50,000 Construction $500,000 Total funding $550,000 The sum appropriated for this capital improvement project shall be expended by the department of transportation. 35. Fort Weaver road, Oahu Plans, design, and construction for a pedestrian bridge overpass for Ft. Weaver road near Child and Family Service; ground and site improvements. Plans $200,000 Design $600,000 Construction $3,700,000 Total funding $4,500,000 The sum appropriated for this capital improvement project shall be expended by the department of transportation. 36. Fort Weaver road, Oahu Plans, design, and construction for widening of Fort Weaver road to add a third lane and sidewalks to Fort Weaver road in both directions from Geiger road to Keoneula boulevard; ground and site improvements. Plans $1,000 Design $1,000 Construction $33,998,000 Total funding $34,000,000 The sum appropriated for this capital improvement project shall be expended by the department of transportation. 37. Kalaeloa Enterprise street lighting project, Oahu Design and construction for the Kalaeloa Enterprise street lighting project. Design $400,000 Construction $1,600,000 Total funding $2,000,000 The sum appropriated for this capital improvement project shall be expended by the Hawaii community development authority. 38. University of Hawaii, west Oahu, Oahu Plans, design, and construction for campus improvements. Plans $1,000,000 Design $1,000,000 Construction $8,000,000 Total funding $10,000,000 The sum appropriated for this capital improvement project shall be expended by the university of Hawaii. SECTION 2. The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2024, shall lapse as of that date. SECTION 3. This Act shall take effect on July 1, 2022. INTRODUCED BY: _____________________________
4848
4949 SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $622,097,250 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2022-2023 for the purpose of capital improvement projects for the forty-first representative district, as follows:
5050
5151 1. Saratoga Avenue electrical and communication infrastructure improvements in Kalaeloa, Oahu
5252
5353 Construction for Saratoga Avenue electrical and communication infrastructure improvements in Kalaeloa, Oahu.
5454
5555 Construction $12,125,000
5656
5757 Total funding $12,125,000
5858
5959 The sum appropriated for this capital improvement project shall be expended by the department of business, economic development, and tourism.
6060
6161 2. Barbers point elementary school, Oahu
6262
6363 Design and construction for air conditioning for the entire school.
6464
6565 Design $500,000
6666
6767 Construction $4,500,000
6868
6969 Total funding $5,000,000
7070
7171 The sum appropriated for this capital improvement project shall be expended by the department of education.
7272
7373 3. Barbers point elementary school, Oahu
7474
7575 Design and construction for cafeteria restrooms.
7676
7777 Design $150,000
7878
7979 Construction $1,350,000
8080
8181 Total funding $1,500,000
8282
8383 The sum appropriated for this capital improvement project shall be expended by the department of education.
8484
8585 4. East Kapolei high school, Oahu
8686
8787 Plans, design, construction, and equipment for a new high school; ground and site improvements; and equipment and appurtenances.
8888
8989 Plans $1,499,000
9090
9191 Design $16,000,000
9292
9393 Construction $132,000,000
9494
9595 Equipment $1,000
9696
9797 Total funding $149,500,000
9898
9999 The sum appropriated for this capital improvement project shall be expended by the department of education.
100100
101101 5. East Kapolei middle school, Oahu
102102
103103 Plans, design, construction, and equipment for a new middle school; ground and site improvements; and equipment and appurtenances.
104104
105105 Plans $1,000,000
106106
107107 Design $2,000,000
108108
109109 Construction $120,640,000
110110
111111 Equipment $10,000,000
112112
113113 Total funding $133,640,000
114114
115115 The sum appropriated for this capital improvement project shall be expended by the department of education.
116116
117117 6. Ewa beach elementary school, Oahu
118118
119119 Construction for asphalt paving and parking lot.
120120
121121 Construction $3,000,000
122122
123123 Total funding $3,000,000
124124
125125 The sum appropriated for this capital improvement project shall be expended by the department of education.
126126
127127 7. Ewa beach elementary school, Oahu
128128
129129 Plans and construction for covering of play courts and night lighting.
130130
131131 Plans $500,000
132132
133133 Construction $4,500,000
134134
135135 Total funding $5,000,000
136136
137137 The sum appropriated for this capital improvement project shall be expended by the department of education.
138138
139139 8. Ewa beach performing arts center, Oahu
140140
141141 Plans, land, design, construction, and equipment for phase one of a new performing arts center; ground and site improvements; and equipment and appurtenances.
142142
143143 Plans $100,000
144144
145145 Land $1,000
146146
147147 Design $1,498,000
148148
149149 Construction $20,000,000
150150
151151 Equipment $1,000
152152
153153 Total funding $21,600,000
154154
155155 The sum appropriated for this capital improvement project shall be expended by the department of education.
156156
157157 9. Ewa Beach public library, Oahu
158158
159159 Plans and design for a new public library.
160160
161161 Plans $50,000
162162
163163 Design $100,000
164164
165165 Total funding $150,000
166166
167167 The sum appropriated for this capital improvement project shall be expended by the department of education.
168168
169169 10. Ilima intermediate school, Oahu
170170
171171 Construction for concrete walkway.
172172
173173 Construction $40,000
174174
175175 Total funding $40,000
176176
177177 The sum appropriated for this capital improvement project shall be expended by the department of education.
178178
179179 11. Ilima intermediate school, Oahu
180180
181181 Construction for renovation of cafeteria restroom.
182182
183183 Construction $87,500
184184
185185 Total funding $87,500
186186
187187 The sum appropriated for this capital improvement project shall be expended by the department of education.
188188
189189 12. Ilima intermediate school, Oahu
190190
191191 Construction for replacement of cafeteria kitchen light fixture.
192192
193193 Construction $40,000
194194
195195 Total funding $40,000
196196
197197 The sum appropriated for this capital improvement project shall be expended by the department of education.
198198
199199 13. Ilima intermediate school, Oahu
200200
201201 Construction for replacement of drains leaking from the second floor of D building.
202202
203203 Construction $200,000
204204
205205 Total funding $200,000
206206
207207 The sum appropriated for this capital improvement project shall be expended by the department of education.
208208
209209 14. Ilima intermediate school, Oahu
210210
211211 Construction for replacement of exterior doors of R building (computer lab).
212212
213213 Construction $26,000
214214
215215 Total funding $26,000
216216
217217 The sum appropriated for this capital improvement project shall be expended by the department of education.
218218
219219 15. Ilima intermediate school, Oahu
220220
221221 Construction for replacement of floor tiles in front office.
222222
223223 Construction $400,000
224224
225225 Total funding $400,000
226226
227227 The sum appropriated for this capital improvement project shall be expended by the department of education.
228228
229229 16. Ilima intermediate school, Oahu
230230
231231 Construction for replacement of front of campus fence.
232232
233233 Construction $120,000
234234
235235 Total funding $120,000
236236
237237 The sum appropriated for this capital improvement project shall be expended by the department of education.
238238
239239 17. Ilima intermediate school, Oahu
240240
241241 Construction for replacement of walkway behind C building with concrete.
242242
243243 Construction $50,000
244244
245245 Total funding $50,000
246246
247247 The sum appropriated for this capital improvement project shall be expended by the department of education.
248248
249249 18. Ilima intermediate school, Oahu
250250
251251 Construction for reroofing of cafeteria.
252252
253253 Construction $468,750
254254
255255 Total funding $468,750
256256
257257 The sum appropriated for this capital improvement project shall be expended by the department of education.
258258
259259 19. Ilima intermediate school, Oahu
260260
261261 Construction for small retaining wall located three feet behind D building.
262262
263263 Construction $200,000
264264
265265 Total funding $200,000
266266
267267 The sum appropriated for this capital improvement project shall be expended by the department of education.
268268
269269 20. Ilima intermediate school, Oahu
270270
271271 Design and construction for sixth grade building.
272272
273273 Design $10,000,000
274274
275275 Construction $25,000,000
276276
277277 Total funding $35,000,000
278278
279279 The sum appropriated for this capital improvement project shall be expended by the department of education.
280280
281281 21. Ilima intermediate school, Oahu
282282
283283 Plans and construction for campus-wide painting of the exterior building walls and remodeling and repainting of the interior of the cafeteria.
284284
285285 Plans $500,000
286286
287287 Construction $7,500,000
288288
289289 Total funding $8,000,000
290290
291291 The sum appropriated for this capital improvement project shall be expended by the department of education.
292292
293293 22. Ilima intermediate school, Oahu
294294
295295 Plans, design, and construction for cafetorium renovations.
296296
297297 Plans $900,000
298298
299299 Design $100,000
300300
301301 Construction $4,000,000
302302
303303 Total funding $5,000,000
304304
305305 The sum appropriated for this capital improvement project shall be expended by the department of education.
306306
307307 23. Ilima intermediate school, Oahu
308308
309309 Plans, design, and construction for replacement of the existing fence and cattle gates at the front of the school with a reinforced wall and new gates; ground and site improvements.
310310
311311 Plans $500,000
312312
313313 Design $500,000
314314
315315 Construction $7,000,000
316316
317317 Total funding $8,000,000
318318
319319 The sum appropriated for this capital improvement project shall be expended by the department of education.
320320
321321 24. Iroquois point elementary school, Oahu
322322
323323 Plans, design, and construction for a playground cover or awning.
324324
325325 Plans $1,000
326326
327327 Land $1,000
328328
329329 Construction $48,000
330330
331331 Total funding $50,000
332332
333333 The sum appropriated for this capital improvement project shall be expended by the department of education.
334334
335335 25. James Campbell high school, Oahu
336336
337337 Design and construction for an athletic complex, including a new stadium; a new Title IX-compliant girls' athletic locker room; restroom facilities; ground and site improvements; and equipment and appurtenances, per master plan.
338338
339339 Design $1,500,000
340340
341341 Construction $28,800,000
342342
343343 Total funding $30,300,000
344344
345345 The sum appropriated for this capital improvement project shall be expended by the department of education.
346346
347347 26. Kapolei high school, Oahu
348348
349349 Design and construction for a fine arts auditorium.
350350
351351 Design $4,000,000
352352
353353 Construction $36,000,000
354354
355355 Total funding $40,000,000
356356
357357 The sum appropriated for this capital improvement project shall be expended by the department of education.
358358
359359 27. Kapolei high school, Oahu
360360
361361 Design and construction for a shelter in place (administration buildings B, D, G, H).
362362
363363 Design $200,000
364364
365365 Construction $1,300,000
366366
367367 Total funding $1,500,000
368368
369369 The sum appropriated for this capital improvement project shall be expended by the department of education.
370370
371371 28. Kapolei high school, Oahu
372372
373373 Design and construction for restrooms for portables.
374374
375375 Design $100,000
376376
377377 Construction $750,000
378378
379379 Total funding $850,000
380380
381381 The sum appropriated for this capital improvement project shall be expended by the department of education.
382382
383383 29. Kapolei high school, Oahu
384384
385385 Plans, design, and construction for new classroom building; ground and site improvements.
386386
387387 Plans $1,000,000
388388
389389 Design $2,000,000
390390
391391 Construction $37,000,000
392392
393393 Total funding $40,000,000
394394
395395 The sum appropriated for this capital improvement project shall be expended by the department of education.
396396
397397 30. Kapolei middle school, Oahu
398398
399399 Design and construction for a classroom building.
400400
401401 Design $4,500,000
402402
403403 Construction $40,500,000
404404
405405 Total funding $45,000,000
406406
407407 The sum appropriated for this capital improvement project shall be expended by the department of education.
408408
409409 31. Kapolei middle school, Oahu
410410
411411 Design and construction for a shelter in place (library buildings A, C, E, F, G, H, I).
412412
413413 Design $150,000
414414
415415 Construction $1,600,000
416416
417417 Total funding $1,750,000
418418
419419 The sum appropriated for this capital improvement project shall be expended by the department of education.
420420
421421 32. Kapolei middle school, Oahu
422422
423423 Design and construction for restrooms for portables.
424424
425425 Design $100,000
426426
427427 Construction $750,000
428428
429429 Total funding $850,000
430430
431431 The sum appropriated for this capital improvement project shall be expended by the department of education.
432432
433433 33. Fort Weaver road, Oahu
434434
435435 Design and construction for Fort Weaver road, sidewalks, crosswalks, signals, and related signage.
436436
437437 Design $1,600,000
438438
439439 Construction $20,000,000
440440
441441 Total funding $21,600,000
442442
443443 The sum appropriated for this capital improvement project shall be expended by the department of transportation.
444444
445445 34. Fort Weaver road, Oahu
446446
447447 Plans and construction for installation of additional traffic cameras along Fort Weaver road at the intersections of Keoneula boulevard, Papipi road, and Keaunui Drive and along Kapolei parkway.
448448
449449 Plans $50,000
450450
451451 Construction $500,000
452452
453453 Total funding $550,000
454454
455455 The sum appropriated for this capital improvement project shall be expended by the department of transportation.
456456
457457 35. Fort Weaver road, Oahu
458458
459459 Plans, design, and construction for a pedestrian bridge overpass for Ft. Weaver road near Child and Family Service; ground and site improvements.
460460
461461 Plans $200,000
462462
463463 Design $600,000
464464
465465 Construction $3,700,000
466466
467467 Total funding $4,500,000
468468
469469 The sum appropriated for this capital improvement project shall be expended by the department of transportation.
470470
471471 36. Fort Weaver road, Oahu
472472
473473 Plans, design, and construction for widening of Fort Weaver road to add a third lane and sidewalks to Fort Weaver road in both directions from Geiger road to Keoneula boulevard; ground and site improvements.
474474
475475 Plans $1,000
476476
477477 Design $1,000
478478
479479 Construction $33,998,000
480480
481481 Total funding $34,000,000
482482
483483 The sum appropriated for this capital improvement project shall be expended by the department of transportation.
484484
485485 37. Kalaeloa Enterprise street lighting project, Oahu
486486
487487 Design and construction for the Kalaeloa Enterprise street lighting project.
488488
489489 Design $400,000
490490
491491 Construction $1,600,000
492492
493493 Total funding $2,000,000
494494
495495 The sum appropriated for this capital improvement project shall be expended by the Hawaii community development authority.
496496
497497 38. University of Hawaii, west Oahu, Oahu
498498
499499 Plans, design, and construction for campus improvements.
500500
501501 Plans $1,000,000
502502
503503 Design $1,000,000
504504
505505 Construction $8,000,000
506506
507507 Total funding $10,000,000
508508
509509 The sum appropriated for this capital improvement project shall be expended by the university of Hawaii.
510510
511511 SECTION 2. The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2024, shall lapse as of that date.
512512
513513 SECTION 3. This Act shall take effect on July 1, 2022.
514514
515515
516516
517517 INTRODUCED BY: _____________________________
518518
519519 INTRODUCED BY:
520520
521521 _____________________________
522522
523523
524524
525525
526526
527527 Report Title: CIP; Forty-first Representative District; Appropriation Description: Appropriates funds for capital improvement projects in the forty-first representative district. The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.
528528
529529
530530
531531
532532
533533 Report Title:
534534
535535 CIP; Forty-first Representative District; Appropriation
536536
537537
538538
539539 Description:
540540
541541 Appropriates funds for capital improvement projects in the forty-first representative district.
542542
543543
544544
545545
546546
547547
548548
549549 The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.