                            HOUSE OF REPRESENTATIVES   H.B. NO.   509     THIRTY-FIRST LEGISLATURE, 2021         STATE OF HAWAII                                A BILL FOR AN ACT     relating to capital improvement projects for the benefit of THE Thirty-ninth REPRESENTATIVE DISTRICT.     BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:   

HOUSE OF REPRESENTATIVES H.B. NO. 509
THIRTY-FIRST LEGISLATURE, 2021
STATE OF HAWAII

HOUSE OF REPRESENTATIVES

H.B. NO.

509

THIRTY-FIRST LEGISLATURE, 2021

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

relating to capital improvement projects for the benefit of THE Thirty-ninth REPRESENTATIVE DISTRICT.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 

      SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $678,295,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2021-2022 for the purpose of capital improvement projects for the thirty-ninth representative district, as follows: 1.   Campbell high school, Oahu      Design and construction for athletic stadium and support facilities per master plan; ground and site improvements; equipment and appurtenances      Design                       $1,500,000      Construction                $28,800,000           Total funding                    $30,300,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 2.   East Kapolei elementary school      Construction for new school      Construction                $60,000,000           Total funding                    $60,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 3.   East Kapolei high school      Construction for new school      Construction               $350,000,000           Total funding                   $350,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 4.   East Kapolei middle school      Construction for new phase three school      Construction                $45,000,000           Total funding                    $45,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 5.   Honowai elementary school      Design and construction for covered walkway in multiple areas; ground and site improvements; equipment and appurtenances      Design                         $100,000      Construction                 $1,125,000           Total funding                     $1,225,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 6.   Honowai elementary school      Design and construction for electrical upgrade and air conditioning for multiple portables; ground and site improvements; equipment and appurtenances      Design                          $50,000      Construction                   $475,000           Total funding                       $525,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 7.   Ilima intermediate school, Oahu      Design and construction for 6th grade building; ground and site improvements; equipment and appurtenances.      Design                       $2,000,000      Construction                $33,000,000           Total funding                    $35,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 8.   Kaleiopuu elementary school      Design and construction for electrical upgrade - phase 2; ground and site improvements; equipment and appurtenances      Design                         $350,000      Construction                 $1,500,000           Total funding                     $1,850,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 9.   Kaleiopuu elementary school      Design and construction for new classroom building; ground and site improvements; equipment and appurtenances      Design                         $700,000      Construction                $19,000,000           Total funding                    $19,700,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 10.  Kaleiopuu elementary school      Design and construction for whole school renovation and improvements; ground and site improvements; equipment and appurtenances      Design                          $45,000      Construction                   $800,000           Total funding                       $845,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 11.  Kapolei high school, Oahu      Design and construction for new classroom building; ground and site improvements; equipment and appurtenances      Design                       $3,000,000      Construction                $37,000,000           Total funding                    $40,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 12.  Royal Kunia elementary school      Construction for new school      Construction                $70,000,000           Total funding                    $70,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 13.  Waipahu high school      Construction for new adult education portables      Construction                 $3,000,000           Total funding                     $3,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 14.  Waipahu high school      Construction for new integrated academic classroom building - phase 2      Construction                $20,000,000           Total funding                    $20,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 15.  Waipahu high school      Construction for phase 2 of campus painting      Construction                   $500,000           Total funding                       $500,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 16.  Waipahu high school      Design and construction for campus rekeying project - rekeying of all exterior locks on campus      Design                          $75,000      Construction                   $275,000           Total funding                       $350,000      The sum appropriated for this capital improvement project shall be expended by the department of education.      SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2024, shall lapse as of that date.      SECTION 3.  This Act shall take effect on July 1, 2021.      INTRODUCED BY:   _____________________________              

     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $678,295,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2021-2022 for the purpose of capital improvement projects for the thirty-ninth representative district, as follows:

1.   Campbell high school, Oahu

     Design and construction for athletic stadium and support facilities per master plan; ground and site improvements; equipment and appurtenances

     Design                       $1,500,000

     Construction                $28,800,000

          Total funding                    $30,300,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

2.   East Kapolei elementary school

     Construction for new school

     Construction                $60,000,000

          Total funding                    $60,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

3.   East Kapolei high school

     Construction for new school

     Construction               $350,000,000

          Total funding                   $350,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

4.   East Kapolei middle school

     Construction for new phase three school

     Construction                $45,000,000

          Total funding                    $45,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

5.   Honowai elementary school

     Design and construction for covered walkway in multiple areas; ground and site improvements; equipment and appurtenances

     Design                         $100,000

     Construction                 $1,125,000

          Total funding                     $1,225,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

6.   Honowai elementary school

     Design and construction for electrical upgrade and air conditioning for multiple portables; ground and site improvements; equipment and appurtenances

     Design                          $50,000

     Construction                   $475,000

          Total funding                       $525,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

7.   Ilima intermediate school, Oahu

     Design and construction for 6th grade building; ground and site improvements; equipment and appurtenances.

     Design                       $2,000,000

     Construction                $33,000,000

          Total funding                    $35,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

8.   Kaleiopuu elementary school

     Design and construction for electrical upgrade - phase 2; ground and site improvements; equipment and appurtenances

     Design                         $350,000

     Construction                 $1,500,000

          Total funding                     $1,850,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

9.   Kaleiopuu elementary school

     Design and construction for new classroom building; ground and site improvements; equipment and appurtenances

     Design                         $700,000

     Construction                $19,000,000

          Total funding                    $19,700,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

10.  Kaleiopuu elementary school

     Design and construction for whole school renovation and improvements; ground and site improvements; equipment and appurtenances

     Design                          $45,000

     Construction                   $800,000

          Total funding                       $845,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

11.  Kapolei high school, Oahu

     Design and construction for new classroom building; ground and site improvements; equipment and appurtenances

     Design                       $3,000,000

     Construction                $37,000,000

          Total funding                    $40,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

12.  Royal Kunia elementary school

     Construction for new school

     Construction                $70,000,000

          Total funding                    $70,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

13.  Waipahu high school

     Construction for new adult education portables

     Construction                 $3,000,000

          Total funding                     $3,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

14.  Waipahu high school

     Construction for new integrated academic classroom building - phase 2

     Construction                $20,000,000

          Total funding                    $20,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

15.  Waipahu high school

     Construction for phase 2 of campus painting

     Construction                   $500,000

          Total funding                       $500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

16.  Waipahu high school

     Design and construction for campus rekeying project - rekeying of all exterior locks on campus

     Design                          $75,000

     Construction                   $275,000

          Total funding                       $350,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

     SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2024, shall lapse as of that date.

     SECTION 3.  This Act shall take effect on July 1, 2021.

 

INTRODUCED BY: _____________________________

INTRODUCED BY:

_____________________________

 

 

       Report Title: CIP; Thirty-ninth Representative District; Appropriation   Description: Appropriates funds for capital improvement projects in the thirty-ninth representative district.       The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent. 

 

 

Report Title:

CIP; Thirty-ninth Representative District; Appropriation

 

Description:

Appropriates funds for capital improvement projects in the thirty-ninth representative district.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.