Hawaii 2024 Regular Session

Hawaii House Bill HB1422 Latest Draft

Bill / Introduced Version Filed 01/25/2023

                            HOUSE OF REPRESENTATIVES   H.B. NO.   1422     THIRTY-SECOND LEGISLATURE, 2023         STATE OF HAWAII                                A BILL FOR AN ACT     relating to capital improvement projects for the benefit of THE Forty-fifth REPRESENTATIVE DISTRICT.     BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:   

HOUSE OF REPRESENTATIVES H.B. NO. 1422
THIRTY-SECOND LEGISLATURE, 2023
STATE OF HAWAII

HOUSE OF REPRESENTATIVES

H.B. NO.

1422

THIRTY-SECOND LEGISLATURE, 2023

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

relating to capital improvement projects for the benefit of THE Forty-fifth REPRESENTATIVE DISTRICT.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 

      SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $161,550,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2023-2024 for the purpose of capital improvement projects for the forty-fifth representative district, as follows: 1.   Leihoku elementary school      Design and construction for covered walkways throughout the campus; ground and site improvements; equipment and appurtenances.       Design                         $210,000      Construction                   $490,000           Total funding                       $700,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 2.   Leihoku elementary school      Design and construction for parking lot expansion.       Design                         $150,000      Construction                   $350,000           Total funding                       $500,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 3.   Waianae elementary school      Design and construction for a covered play court; ground and site improvements; equipment and appurtenances.      Design                         $600,000      Construction                 $1,400,000           Total funding                     $2,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 4.   Waianae elementary school      Plans, design, construction, and equipment and appurtenances for parking lot expansion.      Plans                           $62,500      Design                         $250,000      Construction                   $875,000      Equipment                       $62,500           Total funding                     $1,250,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 5.   Waianae high school      Design and construction for a multipurpose sports facility.      Design                       $1,000,000      Construction                 $9,000,000           Total funding                    $10,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 6.   Waianae high school      Design and construction for a rubberized all-weather track.      Design                         $200,000      Construction                 $1,800,000           Total funding                     $2,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 7.   Waianae high school      Design and construction for a Waianae cultural center.      Design                         $300,000      Construction                 $2,700,000           Total funding                     $3,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 8.   Waianae high school      Design and construction for electrical upgrades for building A; ground and site improvements; equipment and appurtenances.       Design                         $600,000      Construction                 $1,400,000           Total funding                     $2,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 9.   Waianae high school      Equipment and appurtenances for Waianae high school sports programs.      Equipment                    $3,000,000           Total funding                     $3,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 10.  Waianae high school      Land, design, construction, and equipment and appurtenances for installation of a pool.       Land                           $500,000      Design                       $1,000,000      Construction                $18,000,000      Equipment                      $500,000           Total funding                    $20,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 11.  Waianae intermediate school      Design and construction for a covered campus playground and basketball court; ground and site improvements; equipment and appurtenances.      Design                       $1,000,000      Construction                 $2,000,000           Total funding                     $3,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 12.  Waianae intermediate school      Design, construction, and equipment and appurtenances for a sixth grade building; ground and site improvements; equipment and appurtenances.      Design                      $13,500,000      Construction                $31,050,000      Equipment                      $450,000           Total funding                    $45,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 13.  Pokai bay      Design and construction for repair of three coastline jetties.      Design                       $1,125,000      Construction                 $3,375,000           Total funding                     $4,500,000      The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources. 14.  Waianae small boat harbor      Design and construction for asphalt pavement and drainage improvements for the dirt parking area near harbor entrance.      Design                         $100,000      Construction                   $900,000           Total funding                     $1,000,000      The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources. 15.  Waianae small boat harbor      Design and construction for repair of damage to the main loading dock at the harbor.      Design                         $200,000      Construction                   $500,000           Total funding                       $700,000      The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources. 16.  Farrington highway      Design and construction for building a pedestrian walk bridge above the highway.      Design                       $4,500,000      Construction                $10,500,000           Total funding                    $15,000,000      The sum appropriated for this capital improvement project shall be expended by the department of transportation. 17.  Farrington highway      Plans, land, design, construction, and equipment and appurtenances for the extension of the fifth lane to widen the highway; creation of a parallel route for the Waianae coast; extension of Paakea road; and other traffic improvements.       Plans                        $1,500,000      Land                         $1,000,000      Design                       $1,500,000      Construction                $20,000,000      Equipment                    $1,000,000           Total funding                    $25,000,000      The sum appropriated for this capital improvement project shall be expended by the department of transportation. 18.  Kamaile Academy public charter school      Design and construction for installation of air conditioning systems in the cafeteria, library, and administrative buildings; ground and site improvements; equipment and appurtenances.      Design                         $330,000      Construction                 $1,370,000           Total funding                     $1,700,000      The sum appropriated for this capital improvement project shall be expended by the state public charter school commission. 19.  Kamaile Academy public charter school      Design and construction for installing campus playground, additional parking, irrigation system, and fencing; grade and condition the soil; ground and site improvements; equipment and appurtenances.       Design                          $80,000      Construction                 $1,120,000           Total funding                     $1,200,000      The sum appropriated for this capital improvement project shall be expended by the state public charter school commission. 20.  Kamaile Academy public charter school      Plans, design, and construction for 10-classroom building in place of four existing portables.      Plans                        $1,250,000      Design                       $4,350,000      Construction                $14,400,000           Total funding                    $20,000,000      The sum appropriated for this capital improvement project shall be expended by the state public charter school commission.      SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2026, shall lapse as of that date.      SECTION 3.  This Act shall take effect on July 1, 2023.      INTRODUCED BY:   _____________________________              

     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $161,550,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2023-2024 for the purpose of capital improvement projects for the forty-fifth representative district, as follows:

1.   Leihoku elementary school

     Design and construction for covered walkways throughout the campus; ground and site improvements; equipment and appurtenances. 

     Design                         $210,000

     Construction                   $490,000

          Total funding                       $700,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

2.   Leihoku elementary school

     Design and construction for parking lot expansion. 

     Design                         $150,000

     Construction                   $350,000

          Total funding                       $500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

3.   Waianae elementary school

     Design and construction for a covered play court; ground and site improvements; equipment and appurtenances.

     Design                         $600,000

     Construction                 $1,400,000

          Total funding                     $2,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

4.   Waianae elementary school

     Plans, design, construction, and equipment and appurtenances for parking lot expansion.

     Plans                           $62,500

     Design                         $250,000

     Construction                   $875,000

     Equipment                       $62,500

          Total funding                     $1,250,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

5.   Waianae high school

     Design and construction for a multipurpose sports facility.

     Design                       $1,000,000

     Construction                 $9,000,000

          Total funding                    $10,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

6.   Waianae high school

     Design and construction for a rubberized all-weather track.

     Design                         $200,000

     Construction                 $1,800,000

          Total funding                     $2,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

7.   Waianae high school

     Design and construction for a Waianae cultural center.

     Design                         $300,000

     Construction                 $2,700,000

          Total funding                     $3,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

8.   Waianae high school

     Design and construction for electrical upgrades for building A; ground and site improvements; equipment and appurtenances. 

     Design                         $600,000

     Construction                 $1,400,000

          Total funding                     $2,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

9.   Waianae high school

     Equipment and appurtenances for Waianae high school sports programs.

     Equipment                    $3,000,000

          Total funding                     $3,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

10.  Waianae high school

     Land, design, construction, and equipment and appurtenances for installation of a pool. 

     Land                           $500,000

     Design                       $1,000,000

     Construction                $18,000,000

     Equipment                      $500,000

          Total funding                    $20,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

11.  Waianae intermediate school

     Design and construction for a covered campus playground and basketball court; ground and site improvements; equipment and appurtenances.

     Design                       $1,000,000

     Construction                 $2,000,000

          Total funding                     $3,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

12.  Waianae intermediate school

     Design, construction, and equipment and appurtenances for a sixth grade building; ground and site improvements; equipment and appurtenances.

     Design                      $13,500,000

     Construction                $31,050,000

     Equipment                      $450,000

          Total funding                    $45,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

13.  Pokai bay

     Design and construction for repair of three coastline jetties.

     Design                       $1,125,000

     Construction                 $3,375,000

          Total funding                     $4,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources.

14.  Waianae small boat harbor

     Design and construction for asphalt pavement and drainage improvements for the dirt parking area near harbor entrance.

     Design                         $100,000

     Construction                   $900,000

          Total funding                     $1,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources.

15.  Waianae small boat harbor

     Design and construction for repair of damage to the main loading dock at the harbor.

     Design                         $200,000

     Construction                   $500,000

          Total funding                       $700,000

     The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources.

16.  Farrington highway

     Design and construction for building a pedestrian walk bridge above the highway.

     Design                       $4,500,000

     Construction                $10,500,000

          Total funding                    $15,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

17.  Farrington highway

     Plans, land, design, construction, and equipment and appurtenances for the extension of the fifth lane to widen the highway; creation of a parallel route for the Waianae coast; extension of Paakea road; and other traffic improvements. 

     Plans                        $1,500,000

     Land                         $1,000,000

     Design                       $1,500,000

     Construction                $20,000,000

     Equipment                    $1,000,000

          Total funding                    $25,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

18.  Kamaile Academy public charter school

     Design and construction for installation of air conditioning systems in the cafeteria, library, and administrative buildings; ground and site improvements; equipment and appurtenances.

     Design                         $330,000

     Construction                 $1,370,000

          Total funding                     $1,700,000

     The sum appropriated for this capital improvement project shall be expended by the state public charter school commission.

19.  Kamaile Academy public charter school

     Design and construction for installing campus playground, additional parking, irrigation system, and fencing; grade and condition the soil; ground and site improvements; equipment and appurtenances. 

     Design                          $80,000

     Construction                 $1,120,000

          Total funding                     $1,200,000

     The sum appropriated for this capital improvement project shall be expended by the state public charter school commission.

20.  Kamaile Academy public charter school

     Plans, design, and construction for 10-classroom building in place of four existing portables.

     Plans                        $1,250,000

     Design                       $4,350,000

     Construction                $14,400,000

          Total funding                    $20,000,000

     The sum appropriated for this capital improvement project shall be expended by the state public charter school commission.

     SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2026, shall lapse as of that date.

     SECTION 3.  This Act shall take effect on July 1, 2023.

 

INTRODUCED BY: _____________________________

INTRODUCED BY:

_____________________________

 

 

       Report Title: CIP; Forty-fifth Representative District; Appropriation   Description: Appropriates funds for capital improvement projects in the forty-fifth representative district.       The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent. 

 

 

Report Title:

CIP; Forty-fifth Representative District; Appropriation

 

Description:

Appropriates funds for capital improvement projects in the forty-fifth representative district.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.