11 HOUSE OF REPRESENTATIVES H.B. NO. 2568 THIRTY-SECOND LEGISLATURE, 2024 STATE OF HAWAII A BILL FOR AN ACT Relating to PROCUREMENT. BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
22
33 HOUSE OF REPRESENTATIVES H.B. NO. 2568
44 THIRTY-SECOND LEGISLATURE, 2024
55 STATE OF HAWAII
66
77 HOUSE OF REPRESENTATIVES
88
99 H.B. NO.
1010
1111 2568
1212
1313 THIRTY-SECOND LEGISLATURE, 2024
1414
1515
1616
1717 STATE OF HAWAII
1818
1919
2020
2121
2222
2323
2424
2525
2626
2727
2828
2929
3030
3131 A BILL FOR AN ACT
3232
3333
3434
3535
3636
3737 Relating to PROCUREMENT.
3838
3939
4040
4141
4242
4343 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
4444
4545
4646
4747 SECTION 1. The legislature finds that the process for protesting a procurement solicitation, award, or proposed award is confusing and raises questions regarding the fairness of the process. Consequently, agencies have taken inconsistent positions with respect to when a bidder is aggrieved. The purpose of this Act is to clearly define when a protest is required to be submitted. If a protest is based on the contents of the solicitation, a protest is required at least one day prior to the date set for the receipt of offers. In all other cases, a protest is due within seven calendar days after official action is taken, such as when an award is made. It is not the legislature's intent to dissuade bidders from raising objections with other bids prior to award. It is the legislature's intent to encourage the agency to engage with bidders throughout the entire procurement process. SECTION 2. Section 103D-701, Hawaii Revised Statutes, is amended to read as follows: "§103D-701 Authority to resolve protested solicitations and awards. (a) Any actual or prospective bidder, offeror, or contractor who is aggrieved in connection with the solicitation or award of a contract may protest to the chief procurement officer or a designee as specified in the solicitation. Except as provided in sections 103D-303 and 103D-304, a protest shall be submitted in writing within [five working days after the aggrieved person knows or should have known of the facts giving rise thereto; provided that a protest of an award or proposed award shall in any event be submitted in writing within five working days] seven calendar days after the posting of award of the contract under section 103D-302 or 103D-303, if no request for debriefing has been made, as applicable; provided further that no protest based upon the content of the solicitation shall be considered unless it is submitted in writing one day prior to the date set for the receipt of offers. (b) The chief procurement officer or a designee, prior to the commencement of an administrative proceeding under section 103D-709 or an action in court pursuant to section 103D-710, shall use their best efforts to resolve concerns raised by the protesting party through open and frank discussion and may settle and resolve a protest concerning the solicitation or award of a contract. This authority shall be exercised in accordance with rules adopted by the policy board. (c) The chief procurement officer or a designee shall resolve any protest as expeditiously as possible. If the protest is not resolved by mutual agreement, the chief procurement officer or a designee shall issue a written decision to uphold or deny the protest. The decision shall: (1) State the reasons for the action taken; and (2) Inform the protestor of the protestor's right to an administrative proceeding as provided in this part, if applicable. If the protest of a construction contract or airport contract that is awarded pursuant to section 103D-302 or 103D-303 is not resolved by mutual agreement, the chief procurement officer or a designee shall issue a written decision to uphold or deny the protest within seventy-five calendar days of receipt of the protest; provided that the chief procurement officer or a designee may grant an extension based on written justification of the extenuating circumstances; provided further that the extension shall not exceed forty-five calendar days. (d) A copy of the decision under subsection (c) shall be mailed or otherwise furnished immediately to the protestor and any other party intervening. (e) A decision under subsection (c) shall be final and conclusive, unless any person adversely affected by the decision commences an administrative proceeding under section 103D-709. (f) In the event of a timely protest under subsection (a), no further action shall be taken on the solicitation or the award of the contract until the chief procurement officer makes a written determination that the award of the contract without delay is necessary to protect substantial interests of the State. (g) In addition to any other relief, when a protest is sustained and the protestor should have been awarded the contract under the solicitation but is not, then the protestor shall be entitled to the actual costs reasonably incurred in connection with the solicitation, including bid or proposal preparation costs but not attorney's fees. (h) For the purposes of this section, a party is not aggrieved until official action, adverse to it, has been taken." SECTION 3. Section 103D-709, Hawaii Revised Statutes, is amended by amending subsection (d) to read as follows: "(d) Any bidder, offeror, contractor, or person that is a party to a protest of a solicitation or award of a contract under section 103D-302 or 103D-303 that is decided pursuant to section 103D-701 may initiate a proceeding under this section[; provided that;] if any of the following conditions are met: (1) For contracts with an estimated value of less than $1,000,000, the protest concerns a matter that is greater than $10,000; or (2) For contracts with an estimated value of $1,000,000 or more, the protest concerns a matter that is equal to no less than [ten] five per cent of the estimated value of the contract." SECTION 4. This Act does not affect rights and duties that matured, penalties that were incurred, and proceedings that were begun before its effective date. SECTION 5. Statutory material to be repealed is bracketed and stricken. New statutory material is underscored. SECTION 6. This Act shall take effect upon its approval. INTRODUCED BY: _____________________________
4848
4949 SECTION 1. The legislature finds that the process for protesting a procurement solicitation, award, or proposed award is confusing and raises questions regarding the fairness of the process. Consequently, agencies have taken inconsistent positions with respect to when a bidder is aggrieved.
5050
5151 The purpose of this Act is to clearly define when a protest is required to be submitted. If a protest is based on the contents of the solicitation, a protest is required at least one day prior to the date set for the receipt of offers. In all other cases, a protest is due within seven calendar days after official action is taken, such as when an award is made. It is not the legislature's intent to dissuade bidders from raising objections with other bids prior to award. It is the legislature's intent to encourage the agency to engage with bidders throughout the entire procurement process.
5252
5353 SECTION 2. Section 103D-701, Hawaii Revised Statutes, is amended to read as follows:
5454
5555 "§103D-701 Authority to resolve protested solicitations and awards. (a) Any actual or prospective bidder, offeror, or contractor who is aggrieved in connection with the solicitation or award of a contract may protest to the chief procurement officer or a designee as specified in the solicitation. Except as provided in sections 103D-303 and 103D-304, a protest shall be submitted in writing within [five working days after the aggrieved person knows or should have known of the facts giving rise thereto; provided that a protest of an award or proposed award shall in any event be submitted in writing within five working days] seven calendar days after the posting of award of the contract under section 103D-302 or 103D-303, if no request for debriefing has been made, as applicable; provided further that no protest based upon the content of the solicitation shall be considered unless it is submitted in writing one day prior to the date set for the receipt of offers.
5656
5757 (b) The chief procurement officer or a designee, prior to the commencement of an administrative proceeding under section 103D-709 or an action in court pursuant to section 103D-710, shall use their best efforts to resolve concerns raised by the protesting party through open and frank discussion and may settle and resolve a protest concerning the solicitation or award of a contract. This authority shall be exercised in accordance with rules adopted by the policy board.
5858
5959 (c) The chief procurement officer or a designee shall resolve any protest as expeditiously as possible. If the protest is not resolved by mutual agreement, the chief procurement officer or a designee shall issue a written decision to uphold or deny the protest. The decision shall:
6060
6161 (1) State the reasons for the action taken; and
6262
6363 (2) Inform the protestor of the protestor's right to an administrative proceeding as provided in this part, if applicable.
6464
6565 If the protest of a construction contract or airport contract that is awarded pursuant to section 103D-302 or 103D-303 is not resolved by mutual agreement, the chief procurement officer or a designee shall issue a written decision to uphold or deny the protest within seventy-five calendar days of receipt of the protest; provided that the chief procurement officer or a designee may grant an extension based on written justification of the extenuating circumstances; provided further that the extension shall not exceed forty-five calendar days.
6666
6767 (d) A copy of the decision under subsection (c) shall be mailed or otherwise furnished immediately to the protestor and any other party intervening.
6868
6969 (e) A decision under subsection (c) shall be final and conclusive, unless any person adversely affected by the decision commences an administrative proceeding under section 103D-709.
7070
7171 (f) In the event of a timely protest under subsection (a), no further action shall be taken on the solicitation or the award of the contract until the chief procurement officer makes a written determination that the award of the contract without delay is necessary to protect substantial interests of the State.
7272
7373 (g) In addition to any other relief, when a protest is sustained and the protestor should have been awarded the contract under the solicitation but is not, then the protestor shall be entitled to the actual costs reasonably incurred in connection with the solicitation, including bid or proposal preparation costs but not attorney's fees.
7474
7575 (h) For the purposes of this section, a party is not aggrieved until official action, adverse to it, has been taken."
7676
7777 SECTION 3. Section 103D-709, Hawaii Revised Statutes, is amended by amending subsection (d) to read as follows:
7878
7979 "(d) Any bidder, offeror, contractor, or person that is a party to a protest of a solicitation or award of a contract under section 103D-302 or 103D-303 that is decided pursuant to section 103D-701 may initiate a proceeding under this section[; provided that;] if any of the following conditions are met:
8080
8181 (1) For contracts with an estimated value of less than $1,000,000, the protest concerns a matter that is greater than $10,000; or
8282
8383 (2) For contracts with an estimated value of $1,000,000 or more, the protest concerns a matter that is equal to no less than [ten] five per cent of the estimated value of the contract."
8484
8585 SECTION 4. This Act does not affect rights and duties that matured, penalties that were incurred, and proceedings that were begun before its effective date.
8686
8787 SECTION 5. Statutory material to be repealed is bracketed and stricken. New statutory material is underscored.
8888
8989 SECTION 6. This Act shall take effect upon its approval.
9090
9191
9292
9393 INTRODUCED BY: _____________________________
9494
9595 INTRODUCED BY:
9696
9797 _____________________________
9898
9999
100100
101101
102102
103103 Report Title: Hawaii Public Procurement Code; Administrative Proceedings for Review; Protest Description: Requires a protest to be submitted within seven calendar days after the posting of award of the contract. Establishes that a party is not aggrieved until official action, adverse to that party, has been taken. Amends the minimum per cent value of a contract required for parties to a protest of an award to initiate proceedings from ten per cent to five per cent. The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.
104104
105105
106106
107107
108108
109109 Report Title:
110110
111111 Hawaii Public Procurement Code; Administrative Proceedings for Review; Protest
112112
113113
114114
115115 Description:
116116
117117 Requires a protest to be submitted within seven calendar days after the posting of award of the contract. Establishes that a party is not aggrieved until official action, adverse to that party, has been taken. Amends the minimum per cent value of a contract required for parties to a protest of an award to initiate proceedings from ten per cent to five per cent.
118118
119119
120120
121121
122122
123123
124124
125125 The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.