11 HOUSE OF REPRESENTATIVES H.B. NO. 363 THIRTY-SECOND LEGISLATURE, 2023 STATE OF HAWAII A BILL FOR AN ACT relating to capital improvement projects for the benefit of THE Thirty-first REPRESENTATIVE DISTRICT. BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
22
33 HOUSE OF REPRESENTATIVES H.B. NO. 363
44 THIRTY-SECOND LEGISLATURE, 2023
55 STATE OF HAWAII
66
77 HOUSE OF REPRESENTATIVES
88
99 H.B. NO.
1010
1111 363
1212
1313 THIRTY-SECOND LEGISLATURE, 2023
1414
1515
1616
1717 STATE OF HAWAII
1818
1919
2020
2121
2222
2323
2424
2525
2626
2727
2828
2929
3030
3131 A BILL FOR AN ACT
3232
3333
3434
3535
3636
3737 relating to capital improvement projects for the benefit of THE Thirty-first REPRESENTATIVE DISTRICT.
3838
3939
4040
4141
4242
4343 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
4444
4545
4646
4747 SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $35,982,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2023-2024 for the purpose of capital improvement projects for the thirty-first representative district, as follows: 1. Aliamanu elementary school Plans, land, design, construction, and equipment and appurtenances for the redesign and expansion of the common area, offices, and conference room and additional storage. Plans $49,000 Land $1,000 Design $600,000 Construction $10,000,000 Equipment $1,000,000 Total funding $11,650,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 2. Aliamanu middle school Plans, land, design, construction, and equipment and appurtenances for building a 21st century maker space room. Plans $30,000 Land $1,000 Design $60,000 Construction $400,000 Equipment $710,000 Total funding $1,201,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 3. Aliamanu middle school Plans, land, design, construction, and equipment and appurtenances for covering E Quad. Plans $30,000 Land $1,000 Design $60,000 Construction $4,300,000 Equipment $110,000 Total funding $4,501,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 4. Aliamanu middle school Plans, land, design, construction, and equipment and appurtenances for phone/intercom upgrades for safety and security. Plans $25,000 Land $1,000 Design $50,000 Construction $300,000 Equipment $400,000 Total funding $776,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 5. Aliamanu middle school Plans, land, design, construction, and equipment and appurtenances for resurfacing the basketball and volleyball courts. Plans $40,000 Land $1,000 Design $60,000 Construction $1,000,000 Equipment $200,000 Total funding $1,301,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 6. Makalapa elementary school Plans, land, design, construction, and equipment and appurtenances for a school-wide electrical upgrade to provide appropriate technological classroom advancements and a comfortable learning environment by employing the use of air conditioning. Plans $1,000 Land $1,000 Design $337,000 Construction $1,500,000 Equipment $1,000 Total funding $1,840,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 7. Makalapa elementary school Plans, land, design, construction, and equipment and appurtenances for installing covered walkways and awnings. Plans $1,000 Land $1,000 Design $25,000 Construction $125,000 Equipment $1,000 Total funding $153,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 8. Moanalua high school Plans, land, design, construction, and equipment and appurtenances for synthetic turf field and track improvements. Plans $1,000 Land $1,000 Design $600,000 Construction $5,100,000 Equipment $100,000 Total funding $5,802,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 9. Moanalua middle school Plans, land, design, construction, and equipment and appurtenances for the completion of the outdoor covered playcourt. Plans $1,000 Land $1,000 Design $1,000 Construction $2,000,000 Equipment $2,000,000 Total funding $4,003,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 10. Pearl Harbor elementary school Plans, land, design, construction, and equipment and appurtenances for expanding the library and computer lab. Plans $1,000 Land $1,000 Design $400,000 Construction $1,100,000 Equipment $1,000 Total funding $1,503,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 11. Radford high school Plans, land, design, construction, and equipment and appurtenances for the installation of gym fans. Plans $100,000 Land $1,000 Design $100,000 Construction $1,000,000 Equipment $800,000 Total funding $2,001,000 The sum appropriated for this capital improvement project shall be expended by the department of education. 12. Salt Lake elementary school Plans, land, design, construction, and equipment and appurtenances for the installation of synthetic turf on the school playground. Plans $50,000 Land $1,000 Design $200,000 Construction $500,000 Equipment $500,000 Total funding $1,251,000 The sum appropriated for this capital improvement project shall be expended by the department of education. SECTION 2. The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2026, shall lapse as of that date. SECTION 3. This Act shall take effect on July 1, 2023. INTRODUCED BY: _____________________________
4848
4949 SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $35,982,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2023-2024 for the purpose of capital improvement projects for the thirty-first representative district, as follows:
5050
5151 1. Aliamanu elementary school
5252
5353 Plans, land, design, construction, and equipment and appurtenances for the redesign and expansion of the common area, offices, and conference room and additional storage.
5454
5555 Plans $49,000
5656
5757 Land $1,000
5858
5959 Design $600,000
6060
6161 Construction $10,000,000
6262
6363 Equipment $1,000,000
6464
6565 Total funding $11,650,000
6666
6767 The sum appropriated for this capital improvement project shall be expended by the department of education.
6868
6969 2. Aliamanu middle school
7070
7171 Plans, land, design, construction, and equipment and appurtenances for building a 21st century maker space room.
7272
7373 Plans $30,000
7474
7575 Land $1,000
7676
7777 Design $60,000
7878
7979 Construction $400,000
8080
8181 Equipment $710,000
8282
8383 Total funding $1,201,000
8484
8585 The sum appropriated for this capital improvement project shall be expended by the department of education.
8686
8787 3. Aliamanu middle school
8888
8989 Plans, land, design, construction, and equipment and appurtenances for covering E Quad.
9090
9191 Plans $30,000
9292
9393 Land $1,000
9494
9595 Design $60,000
9696
9797 Construction $4,300,000
9898
9999 Equipment $110,000
100100
101101 Total funding $4,501,000
102102
103103 The sum appropriated for this capital improvement project shall be expended by the department of education.
104104
105105 4. Aliamanu middle school
106106
107107 Plans, land, design, construction, and equipment and appurtenances for phone/intercom upgrades for safety and security.
108108
109109 Plans $25,000
110110
111111 Land $1,000
112112
113113 Design $50,000
114114
115115 Construction $300,000
116116
117117 Equipment $400,000
118118
119119 Total funding $776,000
120120
121121 The sum appropriated for this capital improvement project shall be expended by the department of education.
122122
123123 5. Aliamanu middle school
124124
125125 Plans, land, design, construction, and equipment and appurtenances for resurfacing the basketball and volleyball courts.
126126
127127 Plans $40,000
128128
129129 Land $1,000
130130
131131 Design $60,000
132132
133133 Construction $1,000,000
134134
135135 Equipment $200,000
136136
137137 Total funding $1,301,000
138138
139139 The sum appropriated for this capital improvement project shall be expended by the department of education.
140140
141141 6. Makalapa elementary school
142142
143143 Plans, land, design, construction, and equipment and appurtenances for a school-wide electrical upgrade to provide appropriate technological classroom advancements and a comfortable learning environment by employing the use of air conditioning.
144144
145145 Plans $1,000
146146
147147 Land $1,000
148148
149149 Design $337,000
150150
151151 Construction $1,500,000
152152
153153 Equipment $1,000
154154
155155 Total funding $1,840,000
156156
157157 The sum appropriated for this capital improvement project shall be expended by the department of education.
158158
159159 7. Makalapa elementary school
160160
161161 Plans, land, design, construction, and equipment and appurtenances for installing covered walkways and awnings.
162162
163163 Plans $1,000
164164
165165 Land $1,000
166166
167167 Design $25,000
168168
169169 Construction $125,000
170170
171171 Equipment $1,000
172172
173173 Total funding $153,000
174174
175175 The sum appropriated for this capital improvement project shall be expended by the department of education.
176176
177177 8. Moanalua high school
178178
179179 Plans, land, design, construction, and equipment and appurtenances for synthetic turf field and track improvements.
180180
181181 Plans $1,000
182182
183183 Land $1,000
184184
185185 Design $600,000
186186
187187 Construction $5,100,000
188188
189189 Equipment $100,000
190190
191191 Total funding $5,802,000
192192
193193 The sum appropriated for this capital improvement project shall be expended by the department of education.
194194
195195 9. Moanalua middle school
196196
197197 Plans, land, design, construction, and equipment and appurtenances for the completion of the outdoor covered playcourt.
198198
199199 Plans $1,000
200200
201201 Land $1,000
202202
203203 Design $1,000
204204
205205 Construction $2,000,000
206206
207207 Equipment $2,000,000
208208
209209 Total funding $4,003,000
210210
211211 The sum appropriated for this capital improvement project shall be expended by the department of education.
212212
213213 10. Pearl Harbor elementary school
214214
215215 Plans, land, design, construction, and equipment and appurtenances for expanding the library and computer lab.
216216
217217 Plans $1,000
218218
219219 Land $1,000
220220
221221 Design $400,000
222222
223223 Construction $1,100,000
224224
225225 Equipment $1,000
226226
227227 Total funding $1,503,000
228228
229229 The sum appropriated for this capital improvement project shall be expended by the department of education.
230230
231231 11. Radford high school
232232
233233 Plans, land, design, construction, and equipment and appurtenances for the installation of gym fans.
234234
235235 Plans $100,000
236236
237237 Land $1,000
238238
239239 Design $100,000
240240
241241 Construction $1,000,000
242242
243243 Equipment $800,000
244244
245245 Total funding $2,001,000
246246
247247 The sum appropriated for this capital improvement project shall be expended by the department of education.
248248
249249 12. Salt Lake elementary school
250250
251251 Plans, land, design, construction, and equipment and appurtenances for the installation of synthetic turf on the school playground.
252252
253253 Plans $50,000
254254
255255 Land $1,000
256256
257257 Design $200,000
258258
259259 Construction $500,000
260260
261261 Equipment $500,000
262262
263263 Total funding $1,251,000
264264
265265 The sum appropriated for this capital improvement project shall be expended by the department of education.
266266
267267 SECTION 2. The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2026, shall lapse as of that date.
268268
269269 SECTION 3. This Act shall take effect on July 1, 2023.
270270
271271
272272
273273 INTRODUCED BY: _____________________________
274274
275275 INTRODUCED BY:
276276
277277 _____________________________
278278
279279
280280
281281
282282
283283 Report Title: CIP; Thirty-first Representative District; Appropriation Description: Appropriates funds for capital improvement projects in the thirty-first representative district. The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.
284284
285285
286286
287287
288288
289289 Report Title:
290290
291291 CIP; Thirty-first Representative District; Appropriation
292292
293293
294294
295295 Description:
296296
297297 Appropriates funds for capital improvement projects in the thirty-first representative district.
298298
299299
300300
301301
302302
303303
304304
305305 The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.