11 THE SENATE S.B. NO. 3356 THIRTY-SECOND LEGISLATURE, 2024 STATE OF HAWAII A BILL FOR AN ACT relating to capital improvement projects for the benefit of the nineteenth senatorial district. BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
22
33 THE SENATE S.B. NO. 3356
44 THIRTY-SECOND LEGISLATURE, 2024
55 STATE OF HAWAII
66
77 THE SENATE
88
99 S.B. NO.
1010
1111 3356
1212
1313 THIRTY-SECOND LEGISLATURE, 2024
1414
1515
1616
1717 STATE OF HAWAII
1818
1919
2020
2121
2222
2323
2424
2525
2626
2727
2828
2929
3030
3131 A BILL FOR AN ACT
3232
3333
3434
3535
3636
3737 relating to capital improvement projects for the benefit of the nineteenth senatorial district.
3838
3939
4040
4141
4242
4343 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
4444
4545
4646
4747 SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $275,165,589 or so much thereof as may be necessary, and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2024-2025 for the purpose of capital improvement projects for the nineteenth senatorial district, as follows: 1. Pearl City High School A. Construction of an integrated academy, multi-use facility shared between Pearl City high school and Momilani elementary school. Plans $2,500,000 Construction $40,000,000 Equipment $2,000,000 Total funding $44,500,000 B. Resurfacing of tennis courts. Design $50,000 Construction $600,000 Total funding $650,000 C. Retrofitting and renovation of A/B, C/D, and KLM elevators. Plans $50,000 Design $200,000 Construction $1,000,000 Equipment $100,000 Total funding $1,350,000 D. Stadium lighting retrofit. Design $50,000 Construction $300,000 Equipment $150,000 Total funding $500,000 2. Honowai Elementary School A. Design and construction of covered multi-purpose outdoor spaces for learning and dining. Design $125,000 Construction $5,075,000 Total funding $5,200,000 B. Oahu-Con. Total funding $403,300 3. Waipahu Elementary School A. Classroom air conditioning. Total funding $14,000 4. East Kapolei High School A. Plans for a new East Kapolei high school, ground and site improvements, equipment and appurtenances. Total funding $500,000 5. Highlands Intermediate School A. Oahu-Con. Total funding $3,283,085 6. August Ahrens Elementary School A. Design and construction for new classroom building, ground and site improvements, equipment and appurtenances. Total funding $22,540,000 B. Oahu-Con. Total funding $470,800 C. Design and construction for phase two of the whole school renovation and improvements, ground and site improvements, equipment and appurtenances. Total funding $1,089,000 7. Waipahu High School A. Construction for the integrated academy facility, renovations and relocation for the academic health center, ground and site improvements, equipment and appurtenances. Total funding $14,775,404 8. James Campbell High School A. Updates to locker rooms. Design $160,000 Construction $7,940,000 Total funding $8,100,000 9. Ewa Elementary School A. Construction of portables to absorb the overflow of Hoopili. Design $250,000 Construction $2,500,000 Total funding $2,750,000 10. Kapolei High School A. Design and construction of auditorium and performing arts building. Design $7,750,000 Construction $47,250,000 Total funding $55,000,000 B. Design and construction of an integrated academy, fourteen-classroom building. Design $10,000,000 Construction $48,000,000 Total funding $58,000,000 11. Ilima Intermediate School A. Renovation of shop classrooms. Design $450,000 Construction $2,470,000 Equipment $80,000 Total funding $3,000,000 B. Installation of a safety security fence. Design $150,000 Construction $850,000 Total funding $1,000,000 12. Holomua Elementary School A. New three-story building. Design $7,050,000 Construction $39,550,000 Equipment $400,000 Total funding $47,000,000 B. Parking lot expansion. Design $225,000 Construction $1,275,000 Total funding $1,500,000 13. Pearl City Elementary A. Replacement of campus waterlines. Plans $10,000 Design $10,000 Construction $2,500,000 Equipment $20,000 Total funding $2,540,000 14. Department of Accounting and General Services A. Connection of Waipahu district park to Waipahu town core. Planning and Design $1,000,000 Total funding $1,000,000 SECTION 2. The appropriations made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriations are made; provided that all moneys from the appropriations that are unencumbered as of June 30, 2026, shall lapse as of that date. SECTION 3. The sums appropriated for the respective capital improvement projects set forth in section 1 shall be expended for the purposes of this Act as follows: (1) The sums appropriated in items 1 through 13 shall be expended by the department of education; and (2) The sum appropriated in item 14 shall be expended by the department of accounting and general services. SECTION 4. This Act shall take effect on July 1, 2024. INTRODUCED BY: _____________________________
4848
4949 SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $275,165,589 or so much thereof as may be necessary, and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2024-2025 for the purpose of capital improvement projects for the nineteenth senatorial district, as follows:
5050
5151 1. Pearl City High School
5252
5353 A. Construction of an integrated academy, multi-use facility shared between Pearl City high school and Momilani elementary school.
5454
5555 Plans $2,500,000
5656
5757 Construction $40,000,000
5858
5959 Equipment $2,000,000
6060
6161 Total funding $44,500,000
6262
6363 B. Resurfacing of tennis courts.
6464
6565 Design $50,000
6666
6767 Construction $600,000
6868
6969 Total funding $650,000
7070
7171 C. Retrofitting and renovation of A/B, C/D, and KLM elevators.
7272
7373 Plans $50,000
7474
7575 Design $200,000
7676
7777 Construction $1,000,000
7878
7979 Equipment $100,000
8080
8181 Total funding $1,350,000
8282
8383 D. Stadium lighting retrofit.
8484
8585 Design $50,000
8686
8787 Construction $300,000
8888
8989 Equipment $150,000
9090
9191 Total funding $500,000
9292
9393 2. Honowai Elementary School
9494
9595 A. Design and construction of covered multi-purpose outdoor spaces for learning and dining.
9696
9797 Design $125,000
9898
9999 Construction $5,075,000
100100
101101 Total funding $5,200,000
102102
103103 B. Oahu-Con.
104104
105105 Total funding $403,300
106106
107107 3. Waipahu Elementary School
108108
109109 A. Classroom air conditioning.
110110
111111 Total funding $14,000
112112
113113 4. East Kapolei High School
114114
115115 A. Plans for a new East Kapolei high school, ground and site improvements, equipment and appurtenances.
116116
117117 Total funding $500,000
118118
119119 5. Highlands Intermediate School
120120
121121 A. Oahu-Con.
122122
123123 Total funding $3,283,085
124124
125125 6. August Ahrens Elementary School
126126
127127 A. Design and construction for new classroom building, ground and site improvements, equipment and appurtenances.
128128
129129 Total funding $22,540,000
130130
131131 B. Oahu-Con.
132132
133133 Total funding $470,800
134134
135135 C. Design and construction for phase two of the whole school renovation and improvements, ground and site improvements, equipment and appurtenances.
136136
137137 Total funding $1,089,000
138138
139139 7. Waipahu High School
140140
141141 A. Construction for the integrated academy facility, renovations and relocation for the academic health center, ground and site improvements, equipment and appurtenances.
142142
143143 Total funding $14,775,404
144144
145145 8. James Campbell High School
146146
147147 A. Updates to locker rooms.
148148
149149 Design $160,000
150150
151151 Construction $7,940,000
152152
153153 Total funding $8,100,000
154154
155155 9. Ewa Elementary School
156156
157157 A. Construction of portables to absorb the overflow of Hoopili.
158158
159159 Design $250,000
160160
161161 Construction $2,500,000
162162
163163 Total funding $2,750,000
164164
165165 10. Kapolei High School
166166
167167 A. Design and construction of auditorium and performing arts building.
168168
169169 Design $7,750,000
170170
171171 Construction $47,250,000
172172
173173 Total funding $55,000,000
174174
175175 B. Design and construction of an integrated academy, fourteen-classroom building.
176176
177177 Design $10,000,000
178178
179179 Construction $48,000,000
180180
181181 Total funding $58,000,000
182182
183183 11. Ilima Intermediate School
184184
185185 A. Renovation of shop classrooms.
186186
187187 Design $450,000
188188
189189 Construction $2,470,000
190190
191191 Equipment $80,000
192192
193193 Total funding $3,000,000
194194
195195 B. Installation of a safety security fence.
196196
197197 Design $150,000
198198
199199 Construction $850,000
200200
201201 Total funding $1,000,000
202202
203203 12. Holomua Elementary School
204204
205205 A. New three-story building.
206206
207207 Design $7,050,000
208208
209209 Construction $39,550,000
210210
211211 Equipment $400,000
212212
213213 Total funding $47,000,000
214214
215215 B. Parking lot expansion.
216216
217217 Design $225,000
218218
219219 Construction $1,275,000
220220
221221 Total funding $1,500,000
222222
223223 13. Pearl City Elementary
224224
225225 A. Replacement of campus waterlines.
226226
227227 Plans $10,000
228228
229229 Design $10,000
230230
231231 Construction $2,500,000
232232
233233 Equipment $20,000
234234
235235 Total funding $2,540,000
236236
237237 14. Department of Accounting and General Services
238238
239239 A. Connection of Waipahu district park to Waipahu town core.
240240
241241 Planning and Design $1,000,000
242242
243243 Total funding $1,000,000
244244
245245 SECTION 2. The appropriations made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriations are made; provided that all moneys from the appropriations that are unencumbered as of June 30, 2026, shall lapse as of that date.
246246
247247 SECTION 3. The sums appropriated for the respective capital improvement projects set forth in section 1 shall be expended for the purposes of this Act as follows:
248248
249249 (1) The sums appropriated in items 1 through 13 shall be expended by the department of education; and
250250
251251 (2) The sum appropriated in item 14 shall be expended by the department of accounting and general services.
252252
253253 SECTION 4. This Act shall take effect on July 1, 2024.
254254
255255
256256
257257 INTRODUCED BY: _____________________________
258258
259259 INTRODUCED BY:
260260
261261 _____________________________
262262
263263
264264
265265
266266
267267 Report Title: CIP; 19th Senatorial District; Appropriation Description: Appropriates funds for capital improvement projects in the 19th senatorial district. The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.
268268
269269
270270
271271
272272
273273
274274
275275 Report Title:
276276
277277 CIP; 19th Senatorial District; Appropriation
278278
279279
280280
281281 Description:
282282
283283 Appropriates funds for capital improvement projects in the 19th senatorial district.
284284
285285
286286
287287
288288
289289
290290
291291 The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.