                            HOUSE OF REPRESENTATIVES   H.B. NO.   1240     THIRTY-THIRD LEGISLATURE, 2025         STATE OF HAWAII                                A BILL FOR AN ACT     relating to capital improvement projects for the benefit of THE Thirteenth REPRESENTATIVE DISTRICT.     BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:   

HOUSE OF REPRESENTATIVES H.B. NO. 1240
THIRTY-THIRD LEGISLATURE, 2025
STATE OF HAWAII

HOUSE OF REPRESENTATIVES

H.B. NO.

1240

THIRTY-THIRD LEGISLATURE, 2025

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

relating to capital improvement projects for the benefit of THE Thirteenth REPRESENTATIVE DISTRICT.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 

      SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $80,500,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2025-2026 for the purpose of capital improvement projects for the thirteenth representative district, as follows: 1.   Paia elementary school      Plans, design, and construction for the expansion of Paia elementary school.      Plans                        $1,000,000      Design                       $1,000,000      Construction                $28,000,000           Total funding                    $30,000,000      The sum appropriated for this capital improvement project shall be expended by the department of education. 2.   Hana highway      Plans and construction for the repair of Hana highway.      Plans                          $200,000      Construction                 $9,800,000           Total funding                    $10,000,000      The sum appropriated for this capital improvement project shall be expended by the department of transportation. 3.   Lanai airport      Plans and construction for a taxiway at Lanai airport.      Plans                        $1,000,000      Construction                 $9,000,000           Total funding                    $10,000,000      The sum appropriated for this capital improvement project shall be expended by the department of transportation. 4.   Molokai highway      Plans, design, and construction for repairs and maintenance of sections of roadway in east Molokai that have deteriorated due to flooding, river diversions, erosion, and sea level rise.      Plans                        $1,000,000      Design                       $1,000,000      Construction                 $8,000,000           Total funding                    $10,000,000      The sum appropriated for this capital improvement project shall be expended by the department of transportation. 5.   Molokai highway      Construction for filling or removal of rumble strips from the center of the road in east Molokai.      Construction                   $500,000           Total funding                       $500,000      The sum appropriated for this capital improvement project shall be expended by the department of transportation. 6.   Paia bypass      Plans, design, and construction for Paia bypass.      Plans                        $5,000,000      Design                       $5,000,000      Construction                $10,000,000           Total funding                    $20,000,000      The sum appropriated for this capital improvement project shall be expended by the department of transportation.      SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2028, shall lapse as of that date.      SECTION 3.  This Act shall take effect on July 1, 2025.      INTRODUCED BY:   _____________________________              

     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $80,500,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2025-2026 for the purpose of capital improvement projects for the thirteenth representative district, as follows:

1.   Paia elementary school

     Plans, design, and construction for the expansion of Paia elementary school.

     Plans                        $1,000,000

     Design                       $1,000,000

     Construction                $28,000,000

          Total funding                    $30,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

2.   Hana highway

     Plans and construction for the repair of Hana highway.

     Plans                          $200,000

     Construction                 $9,800,000

          Total funding                    $10,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

3.   Lanai airport

     Plans and construction for a taxiway at Lanai airport.

     Plans                        $1,000,000

     Construction                 $9,000,000

          Total funding                    $10,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

4.   Molokai highway

     Plans, design, and construction for repairs and maintenance of sections of roadway in east Molokai that have deteriorated due to flooding, river diversions, erosion, and sea level rise.

     Plans                        $1,000,000

     Design                       $1,000,000

     Construction                 $8,000,000

          Total funding                    $10,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

5.   Molokai highway

     Construction for filling or removal of rumble strips from the center of the road in east Molokai.

     Construction                   $500,000

          Total funding                       $500,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

6.   Paia bypass

     Plans, design, and construction for Paia bypass.

     Plans                        $5,000,000

     Design                       $5,000,000

     Construction                $10,000,000

          Total funding                    $20,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

     SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2028, shall lapse as of that date.

     SECTION 3.  This Act shall take effect on July 1, 2025.

 

INTRODUCED BY: _____________________________

INTRODUCED BY:

_____________________________

 

 

       Report Title: CIP; Thirteenth Representative District; Appropriation   Description: Appropriates funds for capital improvement projects in the thirteenth representative district.       The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent. 

 

 

Report Title:

CIP; Thirteenth Representative District; Appropriation

 

Description:

Appropriates funds for capital improvement projects in the thirteenth representative district.

 

 

 