103RD GENERAL ASSEMBLY State of Illinois 2023 and 2024 HB2393 Introduced , by Rep. Eva-Dina Delgado SYNOPSIS AS INTRODUCED: 30 ILCS 500/30-65 new Amends the Illinois Procurement Code. Provides that, within 45 days after the date that a written request for a change order is submitted by a contractor to a State agency or within 45 days after the date that authorization for extra work is issued by a State agency to a contractor, the State agency shall either: (i) issue the change order with an agreement on price; (ii) agree on price for the authorization for extra work; (iii) counter on price in writing; (iv) give written notice to the contractor of the reasons why the change order is unreasonable; (v) accept a partial agreement on price on some of the terms of the change order or extra work; or (vi) explain in writing that an additional 30 days are necessary to make a determination. Provides that if an additional 30 days is requested, then, after the 30 additional days have elapsed, the State agency shall either: (i) issue the change order with an agreement on price; (ii) agree on price for the authorization for extra work; (iii) counter on price in writing; (iv) give written notice to the contractor of the reasons why the change order is unreasonable; (v) accept a partial agreement on price on some of the terms of the change order or extra work; or (vi) explain in writing that an additional 15 days are necessary to make a determination. Provides that if an additional 15 days is requested, then, after every 15 additional days that elapse, as necessary, the State agency shall perform one of the specified actions. Provides that the State agency shall report quarterly on its website the total number of times the State agency requested additional time to make a determination and the total number of times the State agency requested additional time for such determination for each contract. Effective immediately. LRB103 25428 DTM 51776 b A BILL FOR 103RD GENERAL ASSEMBLY State of Illinois 2023 and 2024 HB2393 Introduced , by Rep. Eva-Dina Delgado SYNOPSIS AS INTRODUCED: 30 ILCS 500/30-65 new 30 ILCS 500/30-65 new Amends the Illinois Procurement Code. Provides that, within 45 days after the date that a written request for a change order is submitted by a contractor to a State agency or within 45 days after the date that authorization for extra work is issued by a State agency to a contractor, the State agency shall either: (i) issue the change order with an agreement on price; (ii) agree on price for the authorization for extra work; (iii) counter on price in writing; (iv) give written notice to the contractor of the reasons why the change order is unreasonable; (v) accept a partial agreement on price on some of the terms of the change order or extra work; or (vi) explain in writing that an additional 30 days are necessary to make a determination. Provides that if an additional 30 days is requested, then, after the 30 additional days have elapsed, the State agency shall either: (i) issue the change order with an agreement on price; (ii) agree on price for the authorization for extra work; (iii) counter on price in writing; (iv) give written notice to the contractor of the reasons why the change order is unreasonable; (v) accept a partial agreement on price on some of the terms of the change order or extra work; or (vi) explain in writing that an additional 15 days are necessary to make a determination. Provides that if an additional 15 days is requested, then, after every 15 additional days that elapse, as necessary, the State agency shall perform one of the specified actions. Provides that the State agency shall report quarterly on its website the total number of times the State agency requested additional time to make a determination and the total number of times the State agency requested additional time for such determination for each contract. Effective immediately. LRB103 25428 DTM 51776 b LRB103 25428 DTM 51776 b A BILL FOR 103RD GENERAL ASSEMBLY State of Illinois 2023 and 2024 HB2393 Introduced , by Rep. Eva-Dina Delgado SYNOPSIS AS INTRODUCED: 30 ILCS 500/30-65 new 30 ILCS 500/30-65 new 30 ILCS 500/30-65 new Amends the Illinois Procurement Code. Provides that, within 45 days after the date that a written request for a change order is submitted by a contractor to a State agency or within 45 days after the date that authorization for extra work is issued by a State agency to a contractor, the State agency shall either: (i) issue the change order with an agreement on price; (ii) agree on price for the authorization for extra work; (iii) counter on price in writing; (iv) give written notice to the contractor of the reasons why the change order is unreasonable; (v) accept a partial agreement on price on some of the terms of the change order or extra work; or (vi) explain in writing that an additional 30 days are necessary to make a determination. Provides that if an additional 30 days is requested, then, after the 30 additional days have elapsed, the State agency shall either: (i) issue the change order with an agreement on price; (ii) agree on price for the authorization for extra work; (iii) counter on price in writing; (iv) give written notice to the contractor of the reasons why the change order is unreasonable; (v) accept a partial agreement on price on some of the terms of the change order or extra work; or (vi) explain in writing that an additional 15 days are necessary to make a determination. Provides that if an additional 15 days is requested, then, after every 15 additional days that elapse, as necessary, the State agency shall perform one of the specified actions. Provides that the State agency shall report quarterly on its website the total number of times the State agency requested additional time to make a determination and the total number of times the State agency requested additional time for such determination for each contract. Effective immediately. LRB103 25428 DTM 51776 b LRB103 25428 DTM 51776 b LRB103 25428 DTM 51776 b A BILL FOR HB2393LRB103 25428 DTM 51776 b HB2393 LRB103 25428 DTM 51776 b HB2393 LRB103 25428 DTM 51776 b 1 AN ACT concerning finance. 2 Be it enacted by the People of the State of Illinois, 3 represented in the General Assembly: 4 Section 5. The Illinois Procurement Code is amended by 5 adding Section 30-65 as follows: 6 (30 ILCS 500/30-65 new) 7 Sec. 30-65. Request for change orders. 8 (a) Within 45 days after the date that a written request 9 for a change order is submitted by a contractor to a State 10 agency or within 45 days after the date that authorization for 11 extra work is issued by a State agency to a contractor, the 12 State agency shall: (i) issue the change order with an 13 agreement on price; (ii) agree on price for the authorization 14 for extra work; (iii) counter on price in writing; (iv) give 15 written notice to the contractor of the reasons why the change 16 order is unreasonable; (v) accept a partial agreement on price 17 on some of the terms of the change order or extra work; or (vi) 18 explain in writing that an additional 30 days are necessary to 19 make a determination. 20 (b) If an additional 30 days is requested under subsection 21 (a), then, after the 30 additional days have elapsed, the 22 State agency shall: (i) issue the change order with an 23 agreement on price; (ii) agree on price for the authorization 103RD GENERAL ASSEMBLY State of Illinois 2023 and 2024 HB2393 Introduced , by Rep. Eva-Dina Delgado SYNOPSIS AS INTRODUCED: 30 ILCS 500/30-65 new 30 ILCS 500/30-65 new 30 ILCS 500/30-65 new Amends the Illinois Procurement Code. Provides that, within 45 days after the date that a written request for a change order is submitted by a contractor to a State agency or within 45 days after the date that authorization for extra work is issued by a State agency to a contractor, the State agency shall either: (i) issue the change order with an agreement on price; (ii) agree on price for the authorization for extra work; (iii) counter on price in writing; (iv) give written notice to the contractor of the reasons why the change order is unreasonable; (v) accept a partial agreement on price on some of the terms of the change order or extra work; or (vi) explain in writing that an additional 30 days are necessary to make a determination. Provides that if an additional 30 days is requested, then, after the 30 additional days have elapsed, the State agency shall either: (i) issue the change order with an agreement on price; (ii) agree on price for the authorization for extra work; (iii) counter on price in writing; (iv) give written notice to the contractor of the reasons why the change order is unreasonable; (v) accept a partial agreement on price on some of the terms of the change order or extra work; or (vi) explain in writing that an additional 15 days are necessary to make a determination. Provides that if an additional 15 days is requested, then, after every 15 additional days that elapse, as necessary, the State agency shall perform one of the specified actions. Provides that the State agency shall report quarterly on its website the total number of times the State agency requested additional time to make a determination and the total number of times the State agency requested additional time for such determination for each contract. Effective immediately. LRB103 25428 DTM 51776 b LRB103 25428 DTM 51776 b LRB103 25428 DTM 51776 b A BILL FOR 30 ILCS 500/30-65 new LRB103 25428 DTM 51776 b HB2393 LRB103 25428 DTM 51776 b HB2393- 2 -LRB103 25428 DTM 51776 b HB2393 - 2 - LRB103 25428 DTM 51776 b HB2393 - 2 - LRB103 25428 DTM 51776 b 1 for extra work; (iii) counter on price in writing; (iv) give 2 written notice to the contractor of the reasons why the change 3 order is unreasonable; (v) accept a partial agreement on price 4 on some of the terms of the change order or extra work; or (vi) 5 explain in writing that an additional 15 days are necessary to 6 make a determination. If an additional 15 days is requested 7 under this subsection (b), then, after every 15 additional 8 days that elapse, as necessary, the State agency shall perform 9 one of the actions specified in items (i) through (vi) of this 10 subsection (b). 11 (c) The State agency shall report quarterly on its website 12 the total number of times the State agency requested 13 additional time to make a determination under this Section and 14 the total number of times the State agency requested 15 additional time for such determination for each contract. 16 Section 99. Effective date. This Act takes effect upon 17 becoming law. HB2393 - 2 - LRB103 25428 DTM 51776 b