Indiana 2023 Regular Session

Indiana House Bill HB1173 Latest Draft

Bill / Enrolled Version Filed 04/25/2023

                            First Regular Session of the 123rd General Assembly (2023)
PRINTING CODE. Amendments: Whenever an existing statute (or a section of the Indiana
Constitution) is being amended, the text of the existing provision will appear in this style type,
additions will appear in this style type, and deletions will appear in this style type.
  Additions: Whenever a new statutory provision is being enacted (or a new constitutional
provision adopted), the text of the new provision will appear in  this  style  type. Also, the
word NEW will appear in that style type in the introductory clause of each SECTION that adds
a new provision to the Indiana Code or the Indiana Constitution.
  Conflict reconciliation: Text in a statute in this style type or this style type reconciles conflicts
between statutes enacted by the 2022 Regular Session of the General Assembly.
HOUSE ENROLLED ACT No. 1173
AN ACT to amend the Indiana Code concerning utilities.
Be it enacted by the General Assembly of the State of Indiana:
SECTION 1. IC 22-14-8 IS ADDED TO THE INDIANA CODE AS
A NEW CHAPTER TO READ AS FOLLOWS [EFFECTIVE JULY
1, 2023]:
Chapter 8. Utility Scale Battery Energy Storage Systems
Sec. 1. For purposes of NFPA 855 and this chapter, "authority
having jurisdiction" refers to the department.
Sec. 2. As used in this chapter, "NFPA 855" refers to:
(1) the 2023 edition of NFPA 855, Standard for the
Installation of Stationary Energy Storage Systems, as adopted
by the National Fire Protection Association; or
(2) if the commission adopts a rule under IC 4-22-2 to amend:
(A) the 2023 edition; or
(B) any subsequent edition;
of NFPA 855, the version of NFPA 855 as amended by the
commission.
Sec. 3. (a) As used in this chapter, "utility scale battery energy
storage system" means an energy storage system (as defined in
NFPA 855) that is capable of storing and releasing more than one
(1) megawatt of electrical energy for a minimum of one (1) hour
using an AC inverter and DC storage.
(b) The term does not include the following:
(1) Foundations or property used to directly or indirectly
HEA 1173 — CC 1 2
connect the AC inverter or DC storage of such a system to
electrical energy production equipment or to a customer's
meter.
(2) An energy storage system that is used for the purpose of
providing electricity to meet or offset all or part of a host
operation's energy needs.
(3) A battery recycling facility.
(4) The manufacturing or storage of batteries by an
automobile manufacturer.
Sec. 4. (a) After June 30, 2023, a person may not:
(1) install a new utility scale battery energy storage system; or
(2) expand the capacity of an existing utility scale battery
energy storage system by more than ten percent (10%) of the
system's original capacity;
without applying for and obtaining the prior approval of the
department.
(b) An application for approval under subsection (a) must be in
the form and manner specified by the department and must include
the following information:
(1) The proposed location, including the county, of the utility
scale battery energy storage system.
(2) Plans and specifications for the utility scale battery energy
storage system.
(3) A description of the manner in which the utility scale
battery energy storage system will comply with the
requirements set forth in sections 6 through 8 of this chapter,
as applicable.
(4) The applicant's proposed emergency response plan for
responding to a:
(A) fire at; or
(B) discharge or threatened discharge of environmental
contaminants by;
the utility scale battery energy storage system.
(5) The applicant's plan for offering emergency response
training under section 9 of this chapter.
The operator of a utility scale battery energy storage system for
which installation is complete before July 1, 2023, shall submit to
the department before January 1, 2024, a notice providing the
information set forth in this subsection with respect to the utility
scale battery energy storage system.
(c) An application fee of two hundred fifty dollars ($250) per
application must be included with each application submitted
HEA 1173 — CC 1 3
under this section.
(d) Not later than thirty (30) days after the department receives
an application for approval under subsection (a) and the
accompanying application fee under subsection (c), the department
shall provide notice to the applicant of the department's approval
or disapproval of the application. The department shall approve an
application that complies with this chapter.
(e) The department may adopt procedures under which the
department:
(1) evaluates an application for approval under subsection (a);
and
(2) makes a determination as to whether to approve the
installation or expansion proposed by the application.
(f) The department is the sole authority with respect to the
regulation and approval of the installation or expansion of a utility
scale battery energy storage system. Subject to subsection (g), a
local unit may not:
(1) require the owner or operator of a utility scale battery
energy storage system to obtain a separate approval, permit,
or license for the installation, expansion, or operation of the
utility scale battery energy storage system;
(2) impose any fee on the owner or operator of a utility scale
battery energy storage system; or
(3) regulate the ownership or operation of a utility scale
battery energy storage system.
(g) Subsection (f) does not:
(1) affect the ability of a local unit to exercise zoning, land use,
planning, or permitting authority otherwise allowed under
law, including IC 36-7, with respect to the installation or
expansion of a utility scale battery energy storage system;
(2) exempt an applicant for the installation or expansion of a
utility scale battery energy storage system from complying
with applicable laws and ordinances concerning land use; or
(3) affect the authority of the Indiana utility regulatory
commission granted under IC 8.
Sec. 5. (a) A person may not operate a utility scale battery
energy storage system installed after June 30, 2023, unless the
person has first applied for and obtained the approval of the
department to do so.
(b) An application under this section must contain:
(1) a commissioning plan; and
(2) a commissioning test;
HEA 1173 — CC 1 4
that complies with NFPA 855.
Sec. 6. (a) A utility scale battery energy storage system
installation of which is subject to department approval under
section 4(a)(1) of this chapter must comply with NFPA 855.
(b) An installation added to an existing utility scale battery
energy storage system in an expansion for which department
approval is required under section 4(a)(2) of this chapter must
comply with NFPA 855.
Sec. 7. The total capacity of the batteries contained within a
single enclosure in:
(1) a utility scale battery energy storage system installation of
which is subject to department approval under section 4(a)(1)
of this chapter; or
(2) an installation added to an existing utility scale battery
energy storage system in an expansion for which department
approval is required under section 4(a)(2) of this chapter;
may not exceed ten (10) megawatt hours unless authorized under
rules adopted by the commission under this chapter.
Sec. 8. (a) This section applies only to a utility scale battery
energy storage system installation of which is subject to
department approval under section 4(a)(1) of this chapter.
(b) If a utility scale battery energy storage system is located less
than one-half (1/2) mile from the nearest one hundred (100) year
flood plain, as determined by the most recently issued Federal
Emergency Management Agency (FEMA) Flood Insurance Rate
Maps, all of the system's equipment must be located at least two (2)
feet above the one hundred (100) year frequency flood elevation.
Sec. 9. (a) The operator of a utility scale battery energy storage
system shall:
(1) provide a copy of the emergency response plan described
in section 4(b)(4) of this chapter, as finally adopted, to the fire
department that is responsible for providing fire protection
services in the area in which the utility scale battery energy
storage system is located; and
(2) offer on an annual basis a training session described in
subsection (b) to the members of the fire department
described in subdivision (1). For a utility scale battery energy
storage system for which installation is complete before July
1, 2023, the first training under this subdivision must be
offered before January 1, 2024.
(b) Subject to subsection (c), the training offered under
subsection (a)(2) must provide participating members of the fire
HEA 1173 — CC 1 5
department with information regarding the installation and
operation of the utility scale battery energy storage system
reasonably necessary to allow the fire department to safely and
effectively respond to a:
(1) fire at; or
(2) discharge or threatened discharge of environmental
contaminants by;
the utility scale battery energy storage system.
(c) This section does not require the operator of a utility scale
battery energy storage system to divulge a trade secret (as defined
in IC 24-2-3-2).
Sec. 10. (a) The commission may adopt rules under IC 4-22-2 to
implement this chapter and to specify standards for the installation
and operation of utility scale battery energy storage systems
consistent with:
(1) this chapter; and
(2) NFPA 855.
(b) Rules adopted by the commission under subsection (a) must
include standards for:
(1) chemical spill prevention and control; and
(2) appropriate setbacks from surface water resources;
for the installation and expansion of utility scale battery energy
storage systems, as necessary to protect soil and surface water
resources from chemicals contained in or produced by utility scale
battery energy storage systems. In establishing the standards
described in this subsection, the commission shall consult with the
department of environmental management or the department of
natural resources, as appropriate.
(c) In adopting rules under this section, the commission may
adopt emergency rules in the manner provided by IC 4-22-2-37.1.
SECTION 2. [EFFECTIVE UPON PASSAGE] (a) Not later than
November 1, 2023, the department of homeland security shall issue
to the executive director of the legislative services agency for
distribution to the members of the interim study committee on
energy, utilities, and telecommunications a report regarding the
progress of the fire prevention and building safety commission in
adopting the rules described in IC 22-14-8-10, as added by this act.
(b) This SECTION expires December 31, 2023.
SECTION 3. An emergency is declared for this act.