Indiana 2025 Regular Session

Indiana Senate Bill SB0424 Compare Versions

OldNewDifferences
1+*ES0424.1*
2+March 13, 2025
3+ENGROSSED
4+SENATE BILL No. 424
5+_____
6+DIGEST OF SB 424 (Updated March 11, 2025 2:09 pm - DI 101)
7+Citations Affected: IC 8-1.
8+Synopsis: Small modular nuclear reactor development costs. Amends
9+as follows the Indiana Code section concerning certificates of public
10+convenience and necessity (certificates) for small modular nuclear
11+reactors: (1) Authorizes a public utility to petition the Indiana utility
12+regulatory commission (IURC) for approval to incur, before obtaining
13+a certificate, project development costs for the development of one or
14+more small modular nuclear reactors. (2) Sets forth certain factors that
15+the IURC must consider in reviewing a public utility's petition to incur
16+project development costs. (3) Requires the IURC to issue a final order
17+approving or denying the petition not later than 180 days after
18+receiving the petition and the public utility's complete case in chief,
19+subject to the IURC's right to extend the time for review if the public
20+utility does not object to the extension. (4) Provides that if a public
21+utility receives approval to incur project development costs, the public
22+utility may petition the IURC at any time before or during the
23+development and execution of a small modular nuclear reactor project
24+(Continued next page)
25+Effective: July 1, 2025.
26+Koch, Buchanan, Leising, Doriot,
27+Zay, Byrne, Schmitt, Buck, Raatz,
28+Donato, Maxwell
29+(HOUSE SPONSOR — SOLIDAY)
30+January 13, 2025, read first time and referred to Committee on Utilities.
31+January 27, 2025, amended, reported favorably — Do Pass.
32+January 30, 2025, read second time, ordered engrossed. Engrossed.
33+February 3, 2025, read third time, passed. Yeas 34, nays 14.
34+HOUSE ACTION
35+March 3, 2025, read first time and referred to Committee on Utilities, Energy and
36+Telecommunications.
37+March 13, 2025, amended, reported — Do Pass.
38+ES 424—LS 7481/DI 101 Digest Continued
39+for the approval of a rate schedule that periodically adjusts the public
40+utility's rates and charges to provide for the timely recovery of project
41+development costs. (5) Provides that after reviewing a public utility's
42+proposed rate schedule, the IURC shall approve the recovery of project
43+development costs by the public utility if the IURC finds that project
44+development costs that have been or will be incurred are: (A)
45+reasonable in amount; (B) necessary to support the construction,
46+purchase, or lease of a small modular nuclear reactor; and (C)
47+consistent with the commission's finding as to the best estimate of
48+project development costs. (6) Provides that a public utility that is
49+authorized to recover project development costs shall: (A) recover 80%
50+of the approved project development costs under the approved rate
51+schedule; and (B) defer the remaining 20% of approved project
52+development costs for recovery as part of public utility's next general
53+rate case before the IURC. (7) Provides that the recovery of a public
54+utility's project development costs through an approved periodic rate
55+adjustment mechanism must occur over a period that is equal to: (A)
56+the period over which the approved project development costs are
57+incurred; or (B) three years; whichever is less. (8) Provides that project
58+development costs that: (A) are incurred by a public utility; and (B)
59+exceed the best estimate of project development costs included in the
60+IURC's order authorizing the public utility to incur project development
61+costs; may not be included in the public utility's rates and charges
62+unless found by the IURC to be reasonable, necessary, and prudent in
63+supporting the construction, purchase, or lease of the small modular
64+nuclear reactor for which they were incurred. (9) Provides that: (A)
65+project development costs incurred for a project that is canceled or not
66+completed may be recovered by the public utility if found by the IURC
67+to be reasonable, necessary, and prudently incurred; but (B) such costs
68+shall be recovered without a return unless the IURC makes certain
69+additional findings. (10) Provides that if a public utility does not seek:
70+(A) approval of; or (B) cost recovery for; project development costs
71+under the bill's provisions, the IURC may approve the deferral and
72+amortization of project development costs in accordance with the
73+statutory procedures set forth for construction costs.
74+ES 424—LS 7481/DI 101ES 424—LS 7481/DI 101 March 13, 2025
175 First Regular Session of the 124th General Assembly (2025)
276 PRINTING CODE. Amendments: Whenever an existing statute (or a section of the Indiana
377 Constitution) is being amended, the text of the existing provision will appear in this style type,
478 additions will appear in this style type, and deletions will appear in this style type.
579 Additions: Whenever a new statutory provision is being enacted (or a new constitutional
680 provision adopted), the text of the new provision will appear in this style type. Also, the
781 word NEW will appear in that style type in the introductory clause of each SECTION that adds
882 a new provision to the Indiana Code or the Indiana Constitution.
983 Conflict reconciliation: Text in a statute in this style type or this style type reconciles conflicts
1084 between statutes enacted by the 2024 Regular Session of the General Assembly.
11-SENATE ENROLLED ACT No. 424
12-AN ACT to amend the Indiana Code concerning utilities.
85+ENGROSSED
86+SENATE BILL No. 424
87+A BILL FOR AN ACT to amend the Indiana Code concerning
88+utilities.
1389 Be it enacted by the General Assembly of the State of Indiana:
14-SECTION 1. IC 8-1-8.5-12.1, AS AMENDED BY P.L.93-2024,
15-SECTION 67, IS AMENDED TO READ AS FOLLOWS [EFFECTIVE
16-JULY 1, 2025]: Sec. 12.1. (a) As used in this section, "project
17-development costs" means costs that have been incurred, or are
18-reasonably estimated to be incurred, in the development of one (1)
19-or more small modular nuclear reactors, including:
20-(1) evaluation, design, and engineering costs;
21-(2) costs for federal approvals and licensing;
22-(3) costs for environmental analyses and permitting;
23-(4) early site permit (as defined in 10 CFR 52.1) costs;
24-(5) equipment procurement costs; and
25-(6) authorized carrying costs.
26-(a) (b) As used in this section, "small modular nuclear reactor"
27-means a nuclear reactor that:
28-(1) has a rated electric generating capacity of not more than four
29-hundred seventy (470) megawatts;
30-(2) is capable of being constructed and operated, either:
31-(A) alone; or
32-(B) in combination with one (1) or more similar reactors if
33-additional reactors are, or become, necessary;
34-at a single site; and
35-(3) is required to be licensed by the United States Nuclear
36-SEA 424 — Concur 2
37-Regulatory Commission.
38-The term includes a nuclear reactor that is described in this subsection
39-and that uses a process to produce hydrogen that can be used for energy
40-storage, as a fuel, or for other uses.
41-(b) (c) Not later than July 1, 2023, the commission, in consultation
42-with the department of environmental management, shall adopt rules
43-under IC 4-22-2 concerning the granting of certificates under this
44-chapter for the construction, purchase, or lease of small modular
45-nuclear reactors:
46-(1) in Indiana for the generation of electricity to be directly or
47-indirectly used to furnish public utility service to Indiana
48-customers; or
49-(2) at the site of a nuclear energy production or generating facility
50-that supplies electricity to Indiana retail customers on July 1,
51-2011.
52-(c) (d) Rules adopted by the commission under this section must
53-provide for the following:
54-(1) That in acting on a public utility's petition for the construction,
55-purchase, or lease of one (1) or more small modular nuclear
56-reactors, as described in subsection (b), (c), the commission shall
57-consider the following:
58-(A) Whether, and to what extent, the one (1) or more small
59-modular nuclear reactors proposed by the public utility will
60-replace a loss of generating capacity in the public utility's
61-portfolio resulting from the retirement or planned retirement
62-of one (1) or more of the public utility's existing electric
63-generating facilities that:
64-(i) are located in Indiana; and
65-(ii) use coal or natural gas as a fuel source.
66-(B) Whether one (1) or more of the small modular nuclear
67-reactors that will replace an existing facility will be located on
68-the same site as or near the existing facility and, if so, potential
69-opportunities for the public utility to:
70-(i) make use of any land and existing infrastructure or
71-facilities already owned or under the control of the public
72-utility; or
73-(ii) create new employment opportunities for workers who
74-have been, or would be, displaced as a result of the
75-retirement of the existing facility.
76-(2) That the commission may grant a certificate under this chapter
77-under circumstances and for locations other than those described
78-in subdivision (1).
79-SEA 424 — Concur 3
80-(3) That the commission may not grant a certificate under this
81-chapter unless the owner or operator of a proposed small modular
82-nuclear reactor provides evidence of a plan to apply for all
83-licenses or permits to construct or operate the proposed small
84-modular nuclear reactor as may be required by:
85-(A) the United States Nuclear Regulatory Commission;
86-(B) the department of environmental management; or
87-(C) any other relevant state or federal regulatory agency with
88-jurisdiction over the construction or operation of nuclear
89-generating facilities.
90-(4) That any:
91-(A) reports;
92-(B) notices of violations; or
93-(C) other notifications;
94-sent to or from the United States Nuclear Regulatory Commission
95-by or to the owner or operator of a proposed small nuclear reactor
96-must be submitted by the owner or operator to the commission
97-within such times as prescribed by the commission, subject to the
98-commission's duty to treat as confidential and protect from public
99-access and disclosure any information that is contained in a report
100-or notice and that is considered confidential or exempt from
101-public access and disclosure under state or federal law.
102-(5) That any person that owns or operates a small modular nuclear
103-reactor in Indiana may not store:
104-(A) spent nuclear fuel (as defined in IC 13-11-2-216); or
105-(B) high level radioactive waste (as defined in
106-IC 13-11-2-102);
107-from the small modular nuclear reactor on the site of the small
108-modular nuclear reactor without first meeting all applicable
109-requirements of the United States Nuclear Regulatory
110-Commission.
111-(d) In adopting the rules required by this section, the commission
112-may adopt rules under IC 4-22-2.
113-(e) A public utility may petition the commission for approval to
114-incur, before obtaining a certificate under this chapter, project
115-development costs for the development of one (1) or more small
116-modular nuclear reactors. The public utility must file with the
117-petition the public utility's case in chief, which must contain the
118-information and supporting documentation regarding the factors
119-the commission must consider under this subsection. In reviewing
120-a petition and the supporting case in chief under this subsection,
121-the commission shall consider the following:
122-SEA 424 — Concur 4
123-(1) Whether a project by the utility to construct, purchase, or
124-lease a small modular nuclear reactor is reasonably consistent
125-with:
126-(A) this section and rules adopted by the commission under
127-this section; and
128-(B) the purposes set forth in IC 8-1-8.8-1(b), as applicable.
129-(2) The following factors with respect to the project
130-development costs and the project for which they are to be
131-incurred:
132-(A) The amount of project development costs the public
133-utility anticipates incurring.
134-(B) The anticipated timeline for incurring the project
135-development costs.
136-(C) The anticipated date by which the public utility will
137-make a decision as to whether to seek a certificate under
138-this chapter.
139-The commission shall review a petition submitted under this
140-subsection and issue a final order approving or denying the petition
141-not later than one hundred eighty (180) days after receiving the
142-petition and complete case in chief. However, if the commission
143-makes a docket entry extending the procedural schedule and the
144-public utility does not object to the entered extension, the
145-commission may extend the one hundred eighty (180) day time
146-frame for issuing a final order under this subsection for the
147-amount of time set forth in the docket entry. In an order approving
148-a petition, the commission must make a finding as to the best
149-estimate and reasonableness of project development costs based on
150-the evidence of record.
151-(f) If a public utility has received approval from the commission
152-under subsection (e) to incur project development costs, the public
153-utility may petition the commission at any time before or during
154-the development and execution of a small modular nuclear reactor
155-project for the approval of a rate schedule that periodically adjusts
156-the public utility's rates and charges to provide for the timely
157-recovery of project development costs. A petition under this
158-subsection must describe any efforts by the public utility to pursue
159-funding opportunities from the United States Department of
160-Energy to offset the project development costs that the public
161-utility seeks to recover under the proposed rate schedule.
162-(g) If, after reviewing a public utility's proposed rate schedule
163-in a petition submitted under subsection (f), the commission
164-determines that the public utility has incurred or will incur project
165-SEA 424 — Concur 5
166-development costs that are:
167-(1) reasonable in amount;
168-(2) necessary to support the construction, purchase, or lease
169-of a small modular nuclear reactor; and
170-(3) consistent with the commission's finding as to the best
171-estimate of project development costs in the commission's
172-order of approval under subsection (e);
173-the commission shall approve the recovery of the project
174-development costs, subject to subsections (h) and (i). However, a
175-public utility may not file adjustments to a rate schedule to adjust
176-for cost recovery approved under this subsection more than one (1)
177-time every twelve (12) months.
178-(h) A public utility that recovers project development costs
179-under subsection (g) shall recover eighty percent (80%) of the
180-approved project development costs under the rate schedule
181-approved under subsection (g) and shall defer the remaining
182-twenty percent (20%) of approved project development costs,
183-including, to the extent applicable, depreciation, allowance for
184-funds used during construction, and post in service carrying costs,
185-based on the overall cost of capital most recently approved by the
186-commission, and shall recover those project development costs as
187-part of the next general rate case that the public utility files with
188-the commission.
189-(i) The recovery of a public utility's project development costs
190-through a periodic rate adjustment mechanism approved by the
191-commission under subsection (g) must occur over a period that is
192-equal to:
193-(1) the period over which the approved project development
194-costs are incurred; or
195-(2) three (3) years;
196-whichever is less.
197-(j) Project development costs that are found by the commission
198-to be reasonable, necessary, and consistent with the best estimate
199-of project development costs in the commission's order of approval
200-under subsection (e) shall be recovered by a public utility by
201-inclusion in the public utility's rates and charges. Project
202-development costs that are incurred by a public utility and that
203-exceed the best estimate of project development costs under
204-subsection (e) may not be included in the public utility's rates and
205-charges unless found by the commission to be reasonable,
206-necessary, and prudent in supporting the construction, purchase,
207-or lease of the small modular nuclear reactor for which they were
208-SEA 424 — Concur 6
209-incurred. Project development costs that are incurred by a public
210-utility for a project that is canceled or not completed may be
211-recovered by the public utility if found by the commission to be
212-reasonable, necessary, and prudently incurred, but such costs shall
213-be recovered without a return unless the commission also finds
214-that:
90+1 SECTION 1. IC 8-1-8.5-12.1, AS AMENDED BY P.L.93-2024,
91+2 SECTION 67, IS AMENDED TO READ AS FOLLOWS [EFFECTIVE
92+3 JULY 1, 2025]: Sec. 12.1. (a) As used in this section, "project
93+4 development costs" means costs that have been incurred, or are
94+5 reasonably estimated to be incurred, in the development of one (1)
95+6 or more small modular nuclear reactors, including:
96+7 (1) evaluation, design, and engineering costs;
97+8 (2) costs for federal approvals and licensing;
98+9 (3) costs for environmental analyses and permitting;
99+10 (4) early site permit (as defined in 10 CFR 52.1) costs;
100+11 (5) equipment procurement costs; and
101+12 (6) authorized carrying costs.
102+13 (a) (b) As used in this section, "small modular nuclear reactor"
103+14 means a nuclear reactor that:
104+15 (1) has a rated electric generating capacity of not more than four
105+ES 424—LS 7481/DI 101 2
106+1 hundred seventy (470) megawatts;
107+2 (2) is capable of being constructed and operated, either:
108+3 (A) alone; or
109+4 (B) in combination with one (1) or more similar reactors if
110+5 additional reactors are, or become, necessary;
111+6 at a single site; and
112+7 (3) is required to be licensed by the United States Nuclear
113+8 Regulatory Commission.
114+9 The term includes a nuclear reactor that is described in this subsection
115+10 and that uses a process to produce hydrogen that can be used for energy
116+11 storage, as a fuel, or for other uses.
117+12 (b) (c) Not later than July 1, 2023, the commission, in consultation
118+13 with the department of environmental management, shall adopt rules
119+14 under IC 4-22-2 concerning the granting of certificates under this
120+15 chapter for the construction, purchase, or lease of small modular
121+16 nuclear reactors:
122+17 (1) in Indiana for the generation of electricity to be directly or
123+18 indirectly used to furnish public utility service to Indiana
124+19 customers; or
125+20 (2) at the site of a nuclear energy production or generating facility
126+21 that supplies electricity to Indiana retail customers on July 1,
127+22 2011.
128+23 (c) (d) Rules adopted by the commission under this section must
129+24 provide for the following:
130+25 (1) That in acting on a public utility's petition for the construction,
131+26 purchase, or lease of one (1) or more small modular nuclear
132+27 reactors, as described in subsection (b), (c), the commission shall
133+28 consider the following:
134+29 (A) Whether, and to what extent, the one (1) or more small
135+30 modular nuclear reactors proposed by the public utility will
136+31 replace a loss of generating capacity in the public utility's
137+32 portfolio resulting from the retirement or planned retirement
138+33 of one (1) or more of the public utility's existing electric
139+34 generating facilities that:
140+35 (i) are located in Indiana; and
141+36 (ii) use coal or natural gas as a fuel source.
142+37 (B) Whether one (1) or more of the small modular nuclear
143+38 reactors that will replace an existing facility will be located on
144+39 the same site as or near the existing facility and, if so, potential
145+40 opportunities for the public utility to:
146+41 (i) make use of any land and existing infrastructure or
147+42 facilities already owned or under the control of the public
148+ES 424—LS 7481/DI 101 3
149+1 utility; or
150+2 (ii) create new employment opportunities for workers who
151+3 have been, or would be, displaced as a result of the
152+4 retirement of the existing facility.
153+5 (2) That the commission may grant a certificate under this chapter
154+6 under circumstances and for locations other than those described
155+7 in subdivision (1).
156+8 (3) That the commission may not grant a certificate under this
157+9 chapter unless the owner or operator of a proposed small modular
158+10 nuclear reactor provides evidence of a plan to apply for all
159+11 licenses or permits to construct or operate the proposed small
160+12 modular nuclear reactor as may be required by:
161+13 (A) the United States Nuclear Regulatory Commission;
162+14 (B) the department of environmental management; or
163+15 (C) any other relevant state or federal regulatory agency with
164+16 jurisdiction over the construction or operation of nuclear
165+17 generating facilities.
166+18 (4) That any:
167+19 (A) reports;
168+20 (B) notices of violations; or
169+21 (C) other notifications;
170+22 sent to or from the United States Nuclear Regulatory Commission
171+23 by or to the owner or operator of a proposed small nuclear reactor
172+24 must be submitted by the owner or operator to the commission
173+25 within such times as prescribed by the commission, subject to the
174+26 commission's duty to treat as confidential and protect from public
175+27 access and disclosure any information that is contained in a report
176+28 or notice and that is considered confidential or exempt from
177+29 public access and disclosure under state or federal law.
178+30 (5) That any person that owns or operates a small modular nuclear
179+31 reactor in Indiana may not store:
180+32 (A) spent nuclear fuel (as defined in IC 13-11-2-216); or
181+33 (B) high level radioactive waste (as defined in
182+34 IC 13-11-2-102);
183+35 from the small modular nuclear reactor on the site of the small
184+36 modular nuclear reactor without first meeting all applicable
185+37 requirements of the United States Nuclear Regulatory
186+38 Commission.
187+39 (d) In adopting the rules required by this section, the commission
188+40 may adopt rules under IC 4-22-2.
189+41 (e) A public utility may petition the commission for approval to
190+42 incur, before obtaining a certificate under this chapter, project
191+ES 424—LS 7481/DI 101 4
192+1 development costs for the development of one (1) or more small
193+2 modular nuclear reactors. The public utility must file with the
194+3 petition the public utility's case in chief, which must contain the
195+4 information and supporting documentation regarding the factors
196+5 the commission must consider under this subsection. In reviewing
197+6 a petition and the supporting case in chief under this subsection,
198+7 the commission shall consider the following:
199+8 (1) Whether a project by the utility to construct, purchase, or
200+9 lease a small modular nuclear reactor is reasonably consistent
201+10 with:
202+11 (A) this section and rules adopted by the commission under
203+12 this section; and
204+13 (B) the purposes set forth in IC 8-1-8.8-1(b), as applicable.
205+14 (2) The following factors with respect to the project
206+15 development costs and the project for which they are to be
207+16 incurred:
208+17 (A) The amount of project development costs the public
209+18 utility anticipates incurring.
210+19 (B) The anticipated timeline for incurring the project
211+20 development costs.
212+21 (C) The anticipated date by which the public utility will
213+22 make a decision as to whether to seek a certificate under
214+23 this chapter.
215+24 The commission shall review a petition submitted under this
216+25 subsection and issue a final order approving or denying the petition
217+26 not later than one hundred eighty (180) days after receiving the
218+27 petition and complete case in chief. However, if the commission
219+28 makes a docket entry extending the procedural schedule and the
220+29 public utility does not object to the entered extension, the
221+30 commission may extend the one hundred eighty (180) day time
222+31 frame for issuing a final order under this subsection for the
223+32 amount of time set forth in the docket entry. In an order approving
224+33 a petition, the commission must make a finding as to the best
225+34 estimate and reasonableness of project development costs based on
226+35 the evidence of record.
227+36 (f) If a public utility has received approval from the commission
228+37 under subsection (e) to incur project development costs, the public
229+38 utility may petition the commission at any time before or during
230+39 the development and execution of a small modular nuclear reactor
231+40 project for the approval of a rate schedule that periodically adjusts
232+41 the public utility's rates and charges to provide for the timely
233+42 recovery of project development costs. A petition under this
234+ES 424—LS 7481/DI 101 5
235+1 subsection must describe any efforts by the public utility to pursue
236+2 funding opportunities from the United States Department of
237+3 Energy to offset the project development costs that the public
238+4 utility seeks to recover under the proposed rate schedule.
239+5 (g) If, after reviewing a public utility's proposed rate schedule
240+6 in a petition submitted under subsection (f), the commission
241+7 determines that the public utility has incurred or will incur project
242+8 development costs that are:
243+9 (1) reasonable in amount;
244+10 (2) necessary to support the construction, purchase, or lease
245+11 of a small modular nuclear reactor; and
246+12 (3) consistent with the commission's finding as to the best
247+13 estimate of project development costs in the commission's
248+14 order of approval under subsection (e);
249+15 the commission shall approve the recovery of the project
250+16 development costs, subject to subsections (h) and (i). However, a
251+17 public utility may not file adjustments to a rate schedule to adjust
252+18 for cost recovery approved under this subsection more than one (1)
253+19 time every twelve (12) months.
254+20 (h) A public utility that recovers project development costs
255+21 under subsection (g) shall recover eighty percent (80%) of the
256+22 approved project development costs under the rate schedule
257+23 approved under subsection (g) and shall defer the remaining
258+24 twenty percent (20%) of approved project development costs,
259+25 including, to the extent applicable, depreciation, allowance for
260+26 funds used during construction, and post in service carrying costs,
261+27 based on the overall cost of capital most recently approved by the
262+28 commission, and shall recover those project development costs as
263+29 part of the next general rate case that the public utility files with
264+30 the commission.
265+31 (i) The recovery of a public utility's project development costs
266+32 through a periodic rate adjustment mechanism approved by the
267+33 commission under subsection (g) must occur over a period that is
268+34 equal to:
269+35 (1) the period over which the approved project development
270+36 costs are incurred; or
271+37 (2) three (3) years;
272+38 whichever is less.
273+39 (j) Project development costs that are found by the commission
274+40 to be reasonable, necessary, and consistent with the best estimate
275+41 of project development costs in the commission's order of approval
276+42 under subsection (e) shall be recovered by a public utility by
277+ES 424—LS 7481/DI 101 6
278+1 inclusion in the public utility's rates and charges. Project
279+2 development costs that are incurred by a public utility and that
280+3 exceed the best estimate of project development costs under
281+4 subsection (e) may not be included in the public utility's rates and
282+5 charges unless found by the commission to be reasonable,
283+6 necessary, and prudent in supporting the construction, purchase,
284+7 or lease of the small modular nuclear reactor for which they were
285+8 incurred. Project development costs that are incurred by a public
286+9 utility for a project that is canceled or not completed may be
287+10 recovered by the public utility if found by the commission to be
288+11 reasonable, necessary, and prudently incurred, but such costs shall
289+12 be recovered without a return unless the commission also finds
290+13 that:
291+14 (1) the decision to cancel or not complete the project was
292+15 prudently made for good cause;
293+16 (2) the project development costs incurred will be offset, as
294+17 applicable, by:
295+18 (A) funding opportunities from the United States
296+19 Department of Energy that are pursued in good faith by
297+20 the public utility;
298+21 (B) a recoupment of revenues received by the public utility
299+22 from one (1) or more third parties for the transfer of assets
300+23 created through the costs incurred; or
301+24 (C) a reimbursement of costs by a single customer or
302+25 prospective customer at whose request the project was
303+26 pursued; and
304+27 (3) a return on the project development costs incurred is
305+28 appropriate under the circumstances to avoid harm to the
306+29 public utility and its customers.
307+30 (k) A public utility may elect not to seek approval of, or cost
308+31 recovery for, project development costs under subsections (e)
309+32 through (i) and instead seek approval from the commission to defer
310+33 and amortize project development costs in accordance with the
311+34 procedures set forth in section 6.5 of this chapter with respect to
312+35 construction costs.
313+36 (l) The commission may adopt rules under IC 4-22-2 to
314+37 implement subsections (e) through (k).
315+38 (e) (m) This section shall not be construed to affect the authority of
316+39 the United States Nuclear Regulatory Commission.
317+ES 424—LS 7481/DI 101 7
318+COMMITTEE REPORT
319+Mr. President: The Senate Committee on Utilities, to which was
320+referred Senate Bill No. 424, has had the same under consideration and
321+begs leave to report the same back to the Senate with the
322+recommendation that said bill be AMENDED as follows:
323+Page 2, line 27, delete "(c)" and insert "(c),".
324+Page 5, line 30, delete "Actual project development costs that are".
325+Page 5, delete lines 31 through 36.
326+Page 6, line 3, delete "Reasonable and necessary project
327+development costs that are" and insert "Project development costs
328+that are found by the commission to be reasonable, necessary, and
329+consistent with the best estimate of project development costs in
330+the commission's order of approval under subsection (e) shall be
331+recovered by a public utility by inclusion in the public utility's
332+rates and charges. Project development costs that are incurred by
333+a public utility and that exceed the best estimate of project
334+development costs under subsection (e) may not be included in the
335+public utility's rates and charges unless found by the commission
336+to be reasonable, necessary, and prudent in supporting the
337+construction, purchase, or lease of the small modular nuclear
338+reactor for which they were incurred. Project development costs
339+that are incurred by a public utility for a project that is canceled
340+or not completed may be recovered by the public utility if found by
341+the commission to be reasonable, necessary, and prudently
342+incurred, but such costs shall be recovered without a return unless
343+the commission also finds that:
215344 (1) the decision to cancel or not complete the project was
216345 prudently made for good cause;
217346 (2) the project development costs incurred will be offset, as
218347 applicable, by:
219348 (A) funding opportunities from the United States
220349 Department of Energy that are pursued in good faith by
221350 the public utility;
222351 (B) a recoupment of revenues received by the public utility
223352 from one (1) or more third parties for the transfer of assets
224353 created through the costs incurred; or
225354 (C) a reimbursement of costs by a single customer or
226355 prospective customer at whose request the project was
227356 pursued; and
228357 (3) a return on the project development costs incurred is
229358 appropriate under the circumstances to avoid harm to the
230359 public utility and its customers.
360+ES 424—LS 7481/DI 101 8
231361 (k) A public utility may elect not to seek approval of, or cost
232362 recovery for, project development costs under subsections (e)
233363 through (i) and instead seek approval from the commission to defer
234364 and amortize project development costs in accordance with the
235365 procedures set forth in section 6.5 of this chapter with respect to
236-construction costs.
237-(l) The commission may adopt rules under IC 4-22-2 to
238-implement subsections (e) through (k).
239-(e) (m) This section shall not be construed to affect the authority of
240-the United States Nuclear Regulatory Commission.
241-SEA 424 — Concur President of the Senate
242-President Pro Tempore
243-Speaker of the House of Representatives
244-Governor of the State of Indiana
245-Date: Time:
246-SEA 424 — Concur
366+construction costs.".
367+Page 6, delete lines 4 through 17.
368+Page 6, line 18, delete "(k)" and insert "(l)".
369+Page 6, line 19, delete "(j)." and insert "(k).".
370+Page 6, line 20, delete "(l)" and insert "(m)".
371+Page 6, line 22, delete "(m)" and insert "(n)".
372+Page 6, line 22, delete "(k)" and insert "(l)".
373+and when so amended that said bill do pass.
374+(Reference is to SB 424 as introduced.)
375+KOCH, Chairperson
376+Committee Vote: Yeas 8, Nays 3.
377+_____
378+COMMITTEE REPORT
379+Mr. Speaker: Your Committee on Utilities, Energy and
380+Telecommunications, to which was referred Senate Bill 424, has had
381+the same under consideration and begs leave to report the same back
382+to the House with the recommendation that said bill be amended as
383+follows:
384+Page 6, delete lines 40 through 41.
385+and when so amended that said bill do pass.
386+(Reference is to SB 424 as printed January 28, 2025.)
387+SOLIDAY
388+Committee Vote: yeas 10, nays 3.
389+ES 424—LS 7481/DI 101