2 | | - | AN ACT concerning the state corporation commission; relating to electric transmission |
---|
3 | | - | line siting permits; extending the time in which the commission shall make a final |
---|
4 | | - | order on an electric transmission line siting application; amending K.S.A. 66-1,178 |
---|
5 | | - | and repealing the existing section. |
---|
| 3 | + | By Committee on Energy, Utilities and Telecommunications |
---|
| 4 | + | Requested by Lynn Retz, Executive Director of the Kansas Corporation |
---|
| 5 | + | Commission |
---|
| 6 | + | 1-21 |
---|
| 7 | + | AN ACT concerning the state corporation commission; relating to electric |
---|
| 8 | + | transmission line siting permits; extending the time in which the |
---|
| 9 | + | commission shall make a final order on an electric transmission line |
---|
| 10 | + | siting application; amending K.S.A. 66-1,178 and repealing the existing |
---|
| 11 | + | section. |
---|
7 | | - | Section 1. K.S.A. 66-1,178 is hereby amended to read as follows: |
---|
8 | | - | 66-1,178. (a) No electric utility may begin site preparation for or |
---|
9 | | - | construction of an electric transmission line, or exercise the right of |
---|
10 | | - | eminent domain to acquire any interest in land in connection with the |
---|
11 | | - | site preparation for a construction of any such line without first |
---|
12 | | - | acquiring a siting permit from the commission. Whenever any electric |
---|
13 | | - | utility desires to obtain such a permit, the utility shall file an application |
---|
14 | | - | with the commission setting forth therein that the utility proposes to |
---|
15 | | - | construct an electric transmission line and specifying: |
---|
| 13 | + | Section 1. K.S.A. 66-1,178 is hereby amended to read as follows: 66- |
---|
| 14 | + | 1,178. (a) No electric utility may begin site preparation for or construction |
---|
| 15 | + | of an electric transmission line, or exercise the right of eminent domain to |
---|
| 16 | + | acquire any interest in land in connection with the site preparation for a |
---|
| 17 | + | construction of any such line without first acquiring a siting permit from |
---|
| 18 | + | the commission. Whenever any electric utility desires to obtain such a |
---|
| 19 | + | permit, the utility shall file an application with the commission setting |
---|
| 20 | + | forth therein that the utility proposes to construct an electric transmission |
---|
| 21 | + | line and specifying: |
---|
22 | | - | (b) Upon the filing of an application pursuant to subsection (a), |
---|
23 | | - | the commission shall fix a time for a public hearing on such |
---|
24 | | - | application, which shall be not more than 90 days after the date the |
---|
25 | | - | application was filed, to determine the necessity for and the |
---|
26 | | - | reasonableness of the location of the proposed electric transmission |
---|
27 | | - | line. The commission shall fix the place for hearing, which shall be in |
---|
28 | | - | one of the counties through which the electric transmission line is |
---|
29 | | - | proposed to traverse. |
---|
| 28 | + | (b) Upon the filing of an application pursuant to subsection (a), the |
---|
| 29 | + | commission shall fix a time for a public hearing on such application, |
---|
| 30 | + | which shall be not more than 90 days after the date the application was |
---|
| 31 | + | filed, to determine the necessity for and the reasonableness of the location |
---|
| 32 | + | of the proposed electric transmission line. The commission shall fix the |
---|
| 33 | + | place for hearing, which shall be in one of the counties through which the |
---|
| 34 | + | electric transmission line is proposed to traverse. |
---|