5 | 5 | | AN ACT concerning electric transmission lines; relating to the state |
---|
6 | 6 | | corporation commission; prohibiting the permitting of transmission |
---|
7 | 7 | | lines located within any territory designated by the United States |
---|
8 | 8 | | department of energy as a national interest electric transmission |
---|
9 | 9 | | corridor; prohibiting the exercise of eminent domain in any such |
---|
10 | 10 | | territory except under limited circumstances; amending K.S.A. 66- |
---|
11 | 11 | | 1,178 and repealing the existing section. |
---|
12 | 12 | | Be it enacted by the Legislature of the State of Kansas: |
---|
13 | 13 | | New Section 1. (a) The state corporation commission shall not |
---|
14 | 14 | | authorize any electric public utility to apply for or obtain a transmission |
---|
15 | 15 | | line siting permit pursuant to K.S.A. 66-1,177 et seq., and amendments |
---|
16 | 16 | | thereto, if the proposed electric transmission lines would be located in a |
---|
17 | 17 | | national interest electric transmission corridor. |
---|
18 | 18 | | (b) Except as provided in subsection (c), no electric public utility |
---|
19 | 19 | | shall exercise the power of eminent domain pursuant to K.S.A. 17-618, |
---|
20 | 20 | | and amendments thereto, or section 216(e) of the federal power act, for the |
---|
21 | 21 | | purpose of constructing electric transmission lines in a national interest |
---|
22 | 22 | | electric transmission corridor. |
---|
23 | 23 | | (c) This section shall not prohibit an electric public utility from |
---|
24 | 24 | | exercising the power of eminent domain for the construction of electric |
---|
25 | 25 | | transmission lines in a national interest electric transmission corridor if |
---|
26 | 26 | | such electric transmission lines were authorized pursuant to a transmission |
---|
27 | 27 | | line siting permit that was approved by the state corporation commission |
---|
28 | 28 | | prior to designation of such national interest electric transmission corridor |
---|
29 | 29 | | by the United States department of energy pursuant to section 216(a)(2) of |
---|
30 | 30 | | the federal power act. |
---|
31 | 31 | | (d) As used in the section: |
---|
32 | 32 | | (1) "Electric transmission lines" means the same as defined in K.S.A. |
---|
33 | 33 | | 66-1,177, and amendments thereto. |
---|
34 | 34 | | (2) "National interest electric transmission corridor" means any |
---|
35 | 35 | | territory designated as a national interest electric transmission corridor |
---|
36 | 36 | | pursuant to a national interest electric transmission corridor designation |
---|
37 | 37 | | report issued by the United States department of energy pursuant to section |
---|
38 | 38 | | 216(a)(2) of the federal power act. |
---|
39 | 39 | | Sec. 2. K.S.A. 66-1,178 is hereby amended to read as follows: 66- |
---|
40 | 40 | | 1 |
---|
41 | 41 | | 2 |
---|
42 | 42 | | 3 |
---|
43 | 43 | | 4 |
---|
44 | 44 | | 5 |
---|
45 | 45 | | 6 |
---|
46 | 46 | | 7 |
---|
47 | 47 | | 8 |
---|
48 | 48 | | 9 |
---|
49 | 49 | | 10 |
---|
50 | 50 | | 11 |
---|
51 | 51 | | 12 |
---|
52 | 52 | | 13 |
---|
53 | 53 | | 14 |
---|
54 | 54 | | 15 |
---|
55 | 55 | | 16 |
---|
56 | 56 | | 17 |
---|
57 | 57 | | 18 |
---|
58 | 58 | | 19 |
---|
59 | 59 | | 20 |
---|
60 | 60 | | 21 |
---|
61 | 61 | | 22 |
---|
62 | 62 | | 23 |
---|
63 | 63 | | 24 |
---|
64 | 64 | | 25 |
---|
65 | 65 | | 26 |
---|
66 | 66 | | 27 |
---|
67 | 67 | | 28 |
---|
68 | 68 | | 29 |
---|
69 | 69 | | 30 |
---|
70 | 70 | | 31 |
---|
71 | 71 | | 32 |
---|
72 | 72 | | 33 |
---|
73 | 73 | | 34 |
---|
74 | 74 | | 35 |
---|
75 | 75 | | 36 HB 2148 2 |
---|
76 | 76 | | 1,178. (a) No electric utility may begin site preparation for or construction |
---|
77 | 77 | | of an electric transmission line, or exercise the right of eminent domain to |
---|
78 | 78 | | acquire any interest in land in connection with the site preparation for a |
---|
79 | 79 | | construction of any such line without first acquiring a siting permit from |
---|
80 | 80 | | the commission. Except as provided in section 1, and amendments thereto, |
---|
81 | 81 | | whenever any electric utility desires to obtain such a permit, the utility |
---|
82 | 82 | | shall file an application with the commission setting forth therein that the |
---|
83 | 83 | | utility proposes to construct an electric transmission line and specifying: |
---|
84 | 84 | | (1) The proposed location thereof; |
---|
85 | 85 | | (2) the names and addresses of the landowners of record whose land |
---|
86 | 86 | | or interest therein is proposed to be acquired in connection with the |
---|
87 | 87 | | construction of or is located within 660 feet of the center line of the |
---|
88 | 88 | | easement where the line is proposed to be located; and |
---|
89 | 89 | | (3) such other information as may be required by the commission. |
---|
90 | 90 | | (b) Upon the filing of an application pursuant to subsection (a), the |
---|
91 | 91 | | commission shall fix a time for a public hearing on such application, |
---|
92 | 92 | | which shall be not more than 90 days after the date the application was |
---|
93 | 93 | | filed, to determine the necessity for and the reasonableness of the location |
---|
94 | 94 | | of the proposed electric transmission line. The commission shall fix the |
---|
95 | 95 | | place for hearing, which shall be in one of the counties through which the |
---|
96 | 96 | | electric transmission line is proposed to traverse. |
---|
97 | 97 | | (c) The commission may conduct an evidentiary hearing on an |
---|
98 | 98 | | application filed pursuant to this section at such time and place as the |
---|
99 | 99 | | commission deems appropriate. |
---|
100 | 100 | | (d) The commission shall issue a final order on the application within |
---|
101 | 101 | | 120 days after the date the application was filed. |
---|
102 | 102 | | Sec. 3. K.S.A. 66-1,178 is hereby repealed. |
---|
103 | 103 | | Sec. 4. This act shall take effect and be in force from and after its |
---|
104 | 104 | | publication in the statute book. |
---|
105 | 105 | | 1 |
---|
106 | 106 | | 2 |
---|
107 | 107 | | 3 |
---|
108 | 108 | | 4 |
---|
109 | 109 | | 5 |
---|
110 | 110 | | 6 |
---|
111 | 111 | | 7 |
---|
112 | 112 | | 8 |
---|
113 | 113 | | 9 |
---|
114 | 114 | | 10 |
---|
115 | 115 | | 11 |
---|
116 | 116 | | 12 |
---|
117 | 117 | | 13 |
---|
118 | 118 | | 14 |
---|
119 | 119 | | 15 |
---|
120 | 120 | | 16 |
---|
121 | 121 | | 17 |
---|
122 | 122 | | 18 |
---|
123 | 123 | | 19 |
---|
124 | 124 | | 20 |
---|
125 | 125 | | 21 |
---|
126 | 126 | | 22 |
---|
127 | 127 | | 23 |
---|
128 | 128 | | 24 |
---|
129 | 129 | | 25 |
---|
130 | 130 | | 26 |
---|
131 | 131 | | 27 |
---|
132 | 132 | | 28 |
---|
133 | 133 | | 29 |
---|