CHAPTER 193 Legislative Research Commission PDF Version 1 CHAPTER 193 ( HB 242 ) AN ACT relating to road projects and declaring an emergency. Be it enacted by the General Assembly of the Commonwealth of Kentucky: Section 1. Notwithstanding KRS 48.100, 48.110, 48.300, and 176.430, the projects authorized by the General Assembly in this Act constitute the official 2022-2024 Biennial Highway Construction Plan. Section 2. The General Assembly acknowledges that the project authorizations contained within this Act are based on the Transportation Cabinet's estimates. The Transportation Cabinet shall have the authority to expend funds necessary to complete the projects as authorized in this Act, amended only by variations dictated by bid or unforeseen circumstances. Section 3. The Secretary of the Transportation Cabinet shall produce a single document that shall detail the enacted fiscal biennium 2022-2024 Biennial Highway Construction Program and the 2024-2028 Highway Preconstruction Program. Section 4. This Act in conjunction with 2022 Regular Session HJR 82 shall constitute the Six-Year Road Plan. Section 5. Whereas the funding for these projects is provided by the Transportation Cabinet Budget Bill, which takes effect upon its passage and approval by the Governor or upon otherwise becoming law, an emergency is declared to exist and this Act takes effect upon its passage and approval by the Governor or upon otherwise becoming law. Section 6. The 2022-2024 biennial highway construction plan is as follows: Signed by Governor April 11, 2022. County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS CONDITION OF LOUI B NUNN CUMBERLAND PARKWAY F ROM MILEPOINT 36.159 TO MILEPOINT 43.02 LN-9008Adair PL22206 DN 182,000 NHPM RW UT CN 1,820,000 NHPM Project Cost: 0 0 2,002,000 K Y 55 NEW TURNING LANE AT BETTY'S OK COUNTRY COOKING. (18CCN)(2020CCR) KY-55Adair PL80003 DN 260,000 SPP RW 110,000 SPP UT 110,000 SPP CN 400,000 SPP Project Cost: 0 260,000 620,000 I MPROVE SAFETY AND MOBILITY ALONG KY 55 NEAR DOC'S MARKET. KY-55Adair PL80200 DN 249,600 SPP RW UT CN Project Cost: 0 0 249,600 T otal for Adair county PL Total Amounts: CN UT RW DN 260,000 431,600 110,000 110,000 2,220,000 0 260,000 2,871,600 I MPROVEMENTS TO KY 100: CURVE, BRIDGE, AND INTERSECTION IMPROVEMENTS FROM NEAR THE STONY POINT ROAD INTERSECTION TO EAST OF THE ALONZO LONG HOLLOW ROAD INTERSECTION (12CCR)(18CCN) (2020CCR) KY-100Allen PL320 DN RW 1,970,000 SPP UT 1,410,000 SPP CN Project Cost: 0 1,970,000 1,410,000 2 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-1578 IN ALLEN COUNTYK Y-1578Allen PL4309 DN RW UT CN 79,000 GR Project Cost: 0 0 79,000 I NSTALL GUARDRAIL ON KY-1533 IN ALLEN COUNTYKY-1533Allen PL4310 DN RW UT CN 43,000 GR Project Cost: 0 0 43,000 W IDENING OF KY 100 (FRANKLIN ROAD) TO 3 LANES WITH URBAN SECTION FROM OLIVER STREET TO US 31E TO INCREASE CAPACITY/SAFETY. MP 11.800-12.700 (14CCN)(18CCN) (2020CCR) KY-100Allen PL8802 DN 380,000 STP2 RW UT CN Project Cost: 0 380,000 0 I MPROVE ACCESS ROAD ON EACH END OF INDUSTRIAL ACCESS ROAD IN SCOTTSVILLE. (16CCN)(18CCN) (2020CCR) KY-3499Allen PL8901 DN RW UT CN 320,000 SPP Project Cost: 320,000 0 0 R ECONSTRUCT 1.0 MILE EAST OF BRIDGE OVER BARREN RIVER LAKE TO CORRECT VERTICAL AND HORIZONTAL DEFICIENCIES. (2020CCN) KY-98Allen PL8902 DN RW 440,000 SPP UT 330,000 SPP CN 1,460,000 SPP Project Cost: 0 770,000 1,460,000 3 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN ALLEN COUNTY ON (002C00019N) OLD BUCK C REEK RD AT BUCK CREEK CR-1239Allen PL10027 DN 44,000 BRZ RW UT CN 440,000 BRZ Project Cost: 0 44,000 440,000 B RIDGE PROJECT IN ALLEN COUNTY ON (002C00033N) PETROLEUM RD AT LITTLE TRAMMEL CREEK CR-1220Allen PL10028 DN 54,000 BRZ RW UT CN 540,000 BRZ Project Cost: 0 594,000 0 R ECONSTRUCT KY-100 FROM KY-622 IN SIMPSON COUNTY TO EST OF SULPHUR FORK CREEK IN ALLEN COUNTY (2012CCR) ky-100Allen PL80206 DN 300,000 SPP RW 2,440,000 SPP UT CN Project Cost: 0 2,740,000 0 I mprove safety on KY 101 from KY 234 to the Warren County Line.ky-101Allen PL80207 DN 810,000 STP RW UT CN Project Cost: 0 0 810,000 T otal for Allen county PL Total Amounts: CN UT RW DN 778,000 810,000 4,850,000 330,000 1,410,000 320,000 540,000 2,022,000 320,000 6,498,000 4,242,000 4 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 RECONSTRUCT KY 151 FROM US 127 AT LAWRENCEBURG TO I-64 IN F RANKLIN COUNTY. (2020CCN) KY-151A nderson PL806 DN 1,750,000 SPP RW 5,000,000 SPP UT CN Project Cost: 0 1,750,000 5,000,000 A DDRESS DEFICIENCIES ON HYATT ROAD (CR 1305) OVER EAST PRONG CROOKED CREEK. (003C00050N) CR-1305Anderson PL10017 DN 62,000 BRZ RW UT CN 620,000 BRZ Project Cost: 0 682,000 0 A DDRESS CONDITION OF MARTHA LAYNE COLLINS BLUEGRASS PARKWAY FROM MILEPOINT 44.807 TO MILEPOINT 47.2 BG-9002Anderson PL22179 DN 170,000 NHPM RW UT CN 1,700,000 NHPM Project Cost: 0 1,870,000 0 A DDRESS CONDITION OF MARTHA LAYNE COLLINS BLUEGRASS PARKWAY FROM MILEPOINT 47.2 TO MILEPOINT 51.838 BG-9002Anderson PL22180 DN 1,100,000 NHPM RW UT CN 11,000,000 NHPM Project Cost: 0 12,100,000 0 IMPROVE US-62 (VERSAILLES RD.) FROM HILLTOP DR. TO WEST END OF BRIDGE OVER KENTUCKY RIVER AT TYRONE(18CCN) (2020CCR) US-62A nderson PL80001 DN RW 3,830,000 STP2 UT CN Project Cost: 0 0 3,830,000 T otal for Anderson county PL Total Amounts: CN UT RW DN 3,082,000 8,830,000 13,320,000 0 16,402,000 8,830,000 5 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 PADUCAH-WICKLIFFE RD: IMPROVE US-60 FROM STAFFORD ROAD TO BETHEL CHURCH ROAD (INCLUDES KEVIL BYPASS)(TO BE LET WITH 1-115.10) (06CCR)(12CCR)(14CCR)(18CCR). (2020CCR) US-60Ballard PL115 DN RW UT CN 10,000,000 STP Project Cost: 0 0 10,000,000 I MPROVE US-60 FROM PROPOSED SOUTHERN BYPASS OF LA CENTER TO EAST OF DENIS JONES ROAD. (02CCR) (2020CCR) US-60Ballard PL118 DN RW 4,400,000 NH UT CN Project Cost: 0 4,400,000 0 C ONDUCT A PLANNING STUDY FOR EXTENDING US 60 FROM BARLOW, KY WEST TO I 57 NEAR FUTURE CITY, IL. US-60Ballard PL 2,000,000 SPP80250 DN RW UT CN Project Cost: 0 0 2,000,000 T otal for Ballard county PL Total Amounts: CN UT RW DN 2,000,000 4,400,000 10,000,000 0 4,400,000 12,000,000 M AJOR WIDENING FROM SANDERS STREET IN CAVE CITY TO US 68 (GLASGOW OUTER LOOP) IN GLASGOW. (14CCN) (2020CCN) KY-90Barren PL8819 DN RW 440,000 SPP UT 1,500,000 SPP CN Project Cost: 0 1,940,000 0 6 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE KY-1297 FROM CR-1366 (DONNELLY DRIVE) TO US-31E ( ROGER WELLS), AND IMPROVE CR-1366 (DONNELLY DRIVE) FROM KY-1297 TO US-68 IN GLASGOW. (14CCN) (16CCN) (2020CCR) CR-1366, KY-1297 Barren PL8821 DN RW UT CN 4,000,000 SPP Project Cost: 0 0 4,000,000 ADDRESS DEFICIENCIES OF US 31EX BRIDGE OVER WATER STREET. ( 005B00058N) US-31B arren PL10001 DN RW 100,000 BRX UT 550,000 BRX CN Project Cost: 0 650,000 0 ADDRESS CONDITION OF I-65 FROM MILEPOINT 45.935 TO MILEPOINT 4 9.65 (48.3 NON-CARDINAL) I-65B arren PL22058 DN 325,000 NHPM RW UT CN 3,250,000 NHPM Project Cost: 0 0 3,575,000 A DDRESS CONDITION OF US-68X FROM MILEPOINT 2.753 TO MILEPOINT 4.145 US-68Barren PL22300 DN 500,000 STP3 RW UT CN 4,500,000 STP3 Project Cost: 0 5,000,000 0 NEW INTERCHANGE ON THE LOUIE NUNN CUMBERLAND PARKWAY A T KY (CONTINGENT ON ECONOMIC DEVELOPMENT PROJECTS)-249 IN GLASGOW(18CCN) LN-9008B arren PL80002 DN 1,830,000 SPP RW 2,790,000 SPP UT 1,020,000 SPP CN Project Cost: 0 1,830,000 3,810,000 7 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 UPGRADE THE LOUIE B. NUNN CUMBERLAND EXPRESSWAY TO I NTERSTATE STANDARDS IN ORDER TO ESTABLISH THE I 65 SPUR ROUTE BETWEEN I 65 AND SOMERSET (2020CCN) LN-9008Barren PL 500,000 SPP80150 DN RW UT CN Project Cost: 0 500,000 0 T otal for Barren county PL Total Amounts: CN UT RW DN 500,000 2,330,000 325,000 540,000 2,790,000 2,050,000 1,020,000 4,500,000 7,250,000 0 9,920,000 11,385,000 RECONSTRUCT CURVE AT .8 MILE SOUTH OF KY-36 (08CCN)(12CCR) M ILEPOINT 7.147 TO 7.247) KY-965B ath PL8404 DN RW UT CN 1,470,000 SPP Project Cost: 0 1,470,000 0 IMPROVE SAFETY ON KY 36 FROM THE INTERSECTION WITH I-64 TO T HE INTERSECTION OF KY 965 INCLUDING THE CURVES KNOWN AS CLEAR CREEK FURNACE AND THOMAS HILL (2020CCN) MILEPOINT 13.394 TO MILEPOINT 17.104 KY-36B ath PL80101 DN RW 2,250,000 SPP UT CN Project Cost: 0 2,250,000 0 IMPROVE SAFETY AND OPERATIONAL EFFICIENCY ON KY 36 FROM N ORTH OF MARIELLA DR TO THE INTERSECTION OF OLD KY 36 (2020 CCN) KY-36B ath PL80102 DN RW 425,000 SPP UT 1,320,000 SPP CN Project Cost: 0 425,000 1,320,000 8 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 REALIGN ROADWAY ON US 60 NEAR OWINGSVILLE BEGINNING IN T HE VICINITY OF ROSE BUSH LN AND ENDING AT WELLS ROAD NEAR I 64 EXIT 123 US-60Bath PL80250 DN 1,000,000 SPP RW UT CN Project Cost: 0 1,000,000 0 T otal for Bath county PL Total Amounts: CN UT RW DN 1,000,000 2,675,000 1,320,000 1,470,000 0 5,145,000 1,320,000 ENHANCING CUMBERLAND AVENUE FROM US 25E TO 18TH STREET W ITH STREET IMPROVEMENTS FOR VEHICLE AND PEDESTRIANS, AS WELL AS STORM WATER MANAGEMENT TO IMPROVE SAFETY, CONGESTION, AND ENVIRONMENTAL IMPACT. (2020CCR) KY-74B ell PL167 DN 990,000 SPP RW UT CN Project Cost: 0 0 990,000 I NSTALL GUARDRAIL ON KY-190 IN BELL COUNTYKY-190Bell PL4314 DN RW UT CN 68,000 GR Project Cost: 68,000 0 0 I NSTALL GUARDRAIL ON KY-2394 IN BELL COUNTYKY-2394Bell PL4315 DN RW UT CN 69,000 GR Project Cost: 69,000 0 0 9 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-987 IN BELL COUNTYK Y-987Bell PL4316 DN RW UT CN 119,000 GR Project Cost: 119,000 0 0 I NSTALL GUARDRAIL ON KY-987 IN BELL COUNTYKY-987Bell PL4317 DN RW UT CN 70,000 GR Project Cost: 70,000 0 0 I NSTALL GUARDRAIL ON KY-987 IN BELL COUNTYKY-987Bell PL4318 DN RW UT CN 68,000 GR Project Cost: 68,000 0 0 I NSTALL GUARDRAIL ON KY-188 IN BELL COUNTYKY-188Bell PL4342 DN RW UT CN 23,000 GR Project Cost: 0 23,000 0 I NSTALL GUARDRAIL ON KY-1491 IN BELL COUNTYKY-1491Bell PL4349 DN RW UT CN 11,000 GR Project Cost: 0 0 11,000 10 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-188 IN BELL COUNTYK Y-188Bell PL4350 DN RW UT CN 16,000 GR Project Cost: 0 0 16,000 I NSTALL GUARDRAIL ON KY-188 IN BELL COUNTYKY-188Bell PL4351 DN RW UT CN 37,000 GR Project Cost: 0 0 37,000 I NSTALL GUARDRAIL ON KY-190 IN BELL COUNTYKY-190Bell PL4365 DN RW UT CN 47,000 GR Project Cost: 0 0 47,000 I NSTALL GUARDRAIL ON KY-987 IN BELL COUNTYKY-987Bell PL4366 DN RW UT CN 84,000 GR Project Cost: 0 0 84,000 P ROVIDE PASSING OPPORTUNITIES ON US 119 IN THE VICINITY OF MP 4.5 IN BELL COUNTY. (12CCN)(14CCR) (2020CCN) US-119Bell PL8702 DN RW 990,000 SPP UT 520,000 SPP CN Project Cost: 1,510,000 0 0 11 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN BELL COUNTY ON (007C00072N) 17TH STREET a t YELLOW CREEK CS-2222Bell PL10101 DN 40,000 BRZ RW UT CN 400,000 BRZ Project Cost: 0 40,000 400,000 C ONSTRUCT A NEW ROADWAY ON PAGE SPUR RD.(18CCN) (2020CCR) PF-9999Bell PL80050 DN RW UT CN 2,800,000 SPP Project Cost: 0 2,800,000 0 I MPROVE SAFETY ALONG E. CUMBERLAND AVE. (KY 74) BETWEEN MP 16.234 AND 16.753 FOR PEDESTRIAN TRAFFIC BY REPLACING DETERIORATED SIDEWALKS AND UPDATING RAMPS (2020CCN) KY-74Bell PL80150 DN RW UT 50,000 STP1 CN 400,000 STP1 Project Cost: 50,000 400,000 0 I MPROVE SAFETY ALONG W. CUMERLAND AVE. (KY 74) FROM MP 15.190 TO MP 16.234 FOR PEDESTRIAN TRAFFIC BY REPLACING DETERIORATED SIDEWALKS AND UPDATING RAMPS (2020CCN) KY-74Bell PL80151 DN RW UT 50,000 STP1 CN 750,000 STP1 Project Cost: 800,000 0 0 I MPROVE SAFETY ALONG N 25TH STREET (KY 2402) FOR PEDESTRIAN TRAFFIC BY REPLACING DETERIORATED SIDEWALKS AND UPDATING RAMPS FROM MP 0 TO 0.353 (2020CCN) KY-2402Bell PL80152 DN RW UT 50,000 STP1 CN 750,000 STP1 Project Cost: 800,000 0 0 12 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Fill in existing depressed median to install a two-way left turn lane f rom the intersection of KY 441 to intersection of Tim Short Automotive. US-25Bell PL80201 DN 200,000 NH RW UT CN 495,000 NH Project Cost: 200,000 495,000 0 T otal for Bell county PL Total Amounts: CN UT RW DN 200,000 40,000 990,000 990,000 670,000 1,894,000 3,718,000 595,000 3,754,000 3,758,000 1,585,000 R EDUCE CONGESTION AND IMPROVE TRAFFIC MOBILITY AT THE INTERCHANGE OF I-75 AND KY-14 IN WALTON. (2020CCR) I -75Boone PL80 DN 1,500,000 NH RW UT CN Project Cost: 0 0 1,500,000 C ONDUCT PLANNING STUDY TO EVALUATE OPTIONS FOR RECONSTRUCTING US 25 BETWEEN KY 14 (MARY GRUBBS HIGHWAY) AND KY 338 (RICHWOOD ROAD). US-25Boone PL 500,000 STPF105 DN RW UT CN Project Cost: 500,000 0 0 CONDUCT PLANNING STUDY TO EVALUATE OPTIONS FOR R ECONSTRUCTING KY 338 (RICHWOOD ROAD) FROM TRIPLE CROWN BLVD TO US 42. KY-338B oone PL 500,000 STPF113 DN RW UT CN Project Cost: 500,000 0 0 13 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE SAFETY AND REDUCE CONGESTION ALONG KY-236 ( DONALDSON ROAD) FROM KY-842 (HOUSTON ROAD) TO KY-3076 (MINEOLA PIKE). (18CCR) (2020CCR) KY-236Boone PL444 DN RW UT CN 8,500,000 STPF Project Cost: 0 8,500,000 0 IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON KY-3076 ( MINEOLA PIKE) FROM KY-1017 TO I-275. (18CCR) (2020CCR) KY-3076B oone PL445 DN RW UT CN 7,100,000 STPF Project Cost: 7,100,000 0 0 I MPROVE MOBILITY AND REDUCE CONGESTION ON US-25 FROM WINNING COLORS DRIVE TO THE NORFOLK SOUTHERN RAILROAD CROSSING SOUTH OF KY-1829 (INDUSTRIAL ROAD); EXCLUDES GRADE SEPARATION AT KY-536. (2020CCR) US-25Boone PL447 DN 3,720,000 STPF RW UT CN Project Cost: 0 3,720,000 0 D EDICATED FEDERAL-AID STP FUNDS EARMARKED FOR NKY URBANIZED AREA AND SUBJECT TO MPO CONTROL FOR FY 2022 THROUGH FY 2028. (FUNDING SUBJECT TO FISCAL CONSTRAINT PENDING MPO TIP) (2020CCR) CO-0Boone PL966.0800 DN RW UT CN 7,914,163 8,072,447 8,233,896 SNK Project Cost: 7,914,163 8,072,447 8,233,896 A DDRESS DEFICIENCIES OF BRIDGE OVER NS (CNO&TP)RR ON RICHARDSON ROAD (KY 842) 0.14 MI E OF US 25 NEAR INDEPENDENCE (008B00092N) (2020CCN) KY-842Boone PL1087 DN RW 3,000,000 BRX UT 1,000,000 BRX CN 5,200,000 BRX Project Cost: 4,000,000 5,200,000 0 14 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN BOONE COUNTY ON (008B00052N) I-275 AT O HIO RIVER I -275Boone PL10028 DN 400,000 FBP RW UT CN 4,000,000 FBP Project Cost: 400,000 4,000,000 0 A DDRESS CONDITION OF I-275 FROM MILEPOINT 1.054 (1.582 CARDINAL) TO MILEPOINT 7.25 I -275Boone PL20006 DN 1,250,000 NHPM RW UT CN 12,500,000 NHPM Project Cost: 0 0 13,750,000 A DDRESS CONDITION OF KY-18 FROM MILEPOINT 15.256 TO MILEPOINT 16.632 KY-18Boone PL20008 DN 250,000 STP5 RW UT CN 2,250,000 STP5 Project Cost: 0 2,500,000 0 A DDRESS CONDITION OF US-25 FROM MILEPOINT 10.603 TO MILEPOINT 10.922 US-25Boone PL22305 DN 94,000 STP5 RW UT CN 846,000 STP5 Project Cost: 0 940,000 0 R ECONSTRUCT GUNPOWDER RD. FROM US-42 TO KY-536. (18CCN) (2020CCR) KY-237Boone PL80000 DN RW 9,270,000 SPP UT 3,380,000 SPP CN Project Cost: 0 0 12,650,000 15 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 EXPANSION OF ROUNDABOUTS ALONG KY-237 AT CARDINAL COVE A ND GRAVES RD(18CCN) (2020CCR) KY-237Boone PL80001 DN RW 1,930,000 STPF UT 1,000,000 STPF CN Project Cost: 2,930,000 0 0 C ONVERT TURFWAY RD AND THOROUGHBRED BLVD FROM 2 WAY TO ONE WAY AND CONSTRUCT NEW I-75 ACCESS (2020CCN) KY-1017, KY-717 Boone PL80100 DN 2,500,000 STPF RW UT CN Project Cost: 0 2,500,000 0 C ONVERT KY 18 (BURLINGTON PIKE) TO A SUPER STREET (2020CCN) KY-18Boone PL80101 DN RW 3,000,000 STP UT 1,500,000 STP CN 12,840,000 STP Project Cost: 4,500,000 12,840,000 0 R econstruct KY 3060 (Frogtown Road) from US 42 to US 25.KY-3060Boone PL80102 DN RW 13,000,000 STP UT CN Project Cost: 0 13,000,000 0 R econstruct Turfway Road (KY 717) from Aero Parkway (MP 0.0) to Donaldson Road (MP 1.67). (2020CCN) KY-717Boone PL80150 DN RW 5,000,000 STPF UT 2,000,000 STPF CN 4,000,000 STPF Project Cost: 0 5,000,000 6,000,000 16 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Conduct a planning study to evaluate potential improvement options to p romote economic growth through central Boone County as well as improving safety and modernizing existing roadways Boone PL 750,000 SPP80202 DN RW UT CN Project Cost: 0 0 750,000 P LANNING STUDY TO IMPROVE EXISTING ALLIGNMENTS AND NEW CONSTRUCTION BETWEEN KY 536 (HATHAWAY ROAD) AND KY 14 (VERONA MUDLICK ROAD) Boone PL 750,000 SPP80204 DN RW UT CN Project Cost: 0 750,000 0 CONDUCT A PLANNING STUDY TO EVALUATE POTENTIAL I MPROVEMENT OPTIONS FOR SAFETY AND MOBILITY ON CHAMBERS ROAD AS WELL AS FLOOD MITIGATION ALONG EXISTING ROADWAY ky-2951B oone PL 600,000 SPP80205 DN RW UT CN Project Cost: 0 600,000 0 I mprove safety & mobility, reduce congestion and address geometric deficiencies along Camp Ernst Road (CR 1001) from KY 536 (Hathaway Rd) to Longbranch Rd (CR 1002). CR-1001Boone PL80207 DN 2,110,000 STPF RW UT CN Project Cost: 0 2,110,000 0 I mprove safety & mobility, reduce congestion and address geometric deficiencies along Camp Ernst Road (CR 1001) from Long Branch Rd. to KY 237 (Pleasant Valley Rd.) CR-1001Boone PL80208 DN 2,400,000 SPP RW UT CN Project Cost: 2,400,000 0 0 17 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Improve access to KY 237 for Litton Lane.k y-237Boone PL80209 DN 541,000 STPF RW 2,894,000 SPP UT CN Project Cost: 541,000 0 2,894,000 E xpand I-71 to 6 lanes from the interchange of I-75 to Boone-Gallatin County Line (MP 69.9 to MP 76.3) i-75Boone PL80212 DN 6,000,000 NH RW UT CN Project Cost: 0 0 6,000,000 C onduct Planning study evaluating Interstate 75 Interchange options at KY 14 to enhance mobility and stimulate economic growth while improving safety on existing roadways. i-75Boone PL 900,000 NH80213 DN RW UT CN Project Cost: 0 0 900,000 C onduct planning study evaluating potential improvement options to improve mobility and promote economic growth through central Boone County as well as improving safety and modernizing existing roadways. Boone PL 750,000 SPP80214 DN RW UT CN Project Cost: 0 750,000 0 C onduct Planning study evaluating potential improvement options to improve safety and mobility on Chambers Road as well as mitigation of severe flooding along the existing roadway ky-2951Boone PL80215 DN 600,000 STP1 RW UT CN Project Cost: 0 600,000 0 18 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 PLANNING STUDY TO EXPAND NORTHBOUND AND SOUTHBOUND R EST AREAS ON I-71/I-75 IN BOONE COUNTY i-75Boone PL 1,100,000 SPP80257 DN RW UT CN Project Cost: 0 1,100,000 0 T otal for Boone county PL Total Amounts: CN UT RW DN 1,000,000 3,200,000 1,650,000 3,341,000 9,274,000 8,750,000 7,930,000 18,000,000 12,164,000 3,500,000 5,380,000 15,014,163 41,708,447 24,733,896 30,785,163 72,182,447 52,677,896 ADDRESS SAFETY AND CONGESTION AT THE INTERSECTION OF US 2 7 AND KY 1939 IN PARIS us-27B ourbon PL916 DN 230,000 STP RW 370,000 STP UT CN Project Cost: 0 230,000 370,000 I MPROVE US 460 FROM RUSSELL CAVE RD TO I 75 (2ND PART OF 7-8705) (2020CCN)(SEE 7-8705.10) US-460Bourbon PL80104 DN RW 8,000,000 STP2 UT 7,000,000 STP2 CN 15,000,000 STP2 Project Cost: 8,000,000 7,000,000 15,000,000 I MPROVE SAFETY OF CANE RIDGE ROAD (KY 537) FROM THE INTERSECTION WITH 460 TO THE ENTRANCE PAST COLOR POINT (2020CCN) KY-537Bourbon PL80155 DN 925,000 SPP RW UT CN Project Cost: 0 925,000 0 19 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 MODERNIZE ROADWAY, IMPROVE CONGESTION, SAFETY AND P EDESTRIAN ACCESS FROM US 27 ALONG Y 1939 FOR .212 MILES INCLUDING IMPROVEMENTS TO THE INTERSECTION OF MATLACK ST AND THE BOURBON COUNTY SCHOOL BUS BARN KY-1939B ourbon PL80203 DN 200,000 STPF RW 200,000 STPF UT 400,000 STPF CN Project Cost: 0 200,000 600,000 T otal for Bourbon county PL Total Amounts: CN UT RW DN 1,355,000 8,000,000 570,000 7,000,000 400,000 15,000,000 8,000,000 8,355,000 15,970,000 I MPROVE SAFETY AND OPERATIONAL EFFICIENCY OF KY 168 (BLACKBURN AVE/WHEATLEY RD) FROM MILEPOINT 5.8 (US 60) TO MILEPOINT 7.4 (HOODS CREEK ROAD). (2020CCR) KY-168Boyd PL 520,000 STP1125 DN RW UT CN Project Cost: 0 0 520,000 I MPROVE SAFETY AND DECREASE CONGESTION ON KY 716 FROM MP 0.0 (US 60) TO MP 0.56 (KY 3293) (2020CCR) KY-716Boyd PL 150,000 STP1180 DN RW UT CN Project Cost: 0 150,000 0 F EDERAL 'STP' FUNDS DEDICATED TO HUNTINGTON-ASHLAND MPO FOR FY 2022-2028. (FUNDING SUBJECT TO FISCAL CONSTRAINT PENDING MPO TIP) (2020CCR) CO-0Boyd PL208.0600 DN RW UT CN 1,685,126 1,718,828 1,753,205 SAH Project Cost: 1,685,126 1,718,828 1,753,205 20 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-1012 IN BOYD COUNTYK Y-1012Boyd PL4306 DN RW UT CN 70,000 GR Project Cost: 70,000 0 0 I NSTALL GUARDRAIL ON KY-5 IN BOYD COUNTYKY-5Boyd PL4310 DN RW UT CN 31,000 GR Project Cost: 0 31,000 0 ADDRESS DEFICIENCIES ON PERRY GENTRY BRIDGES OVER THE BIG S ANDY RIVER. JOINT PROJECT WITH WEST VIRGINIA. (010B00046L AND 010B00046R)(SD) I -64B oyd PL10016 DN RW UT CN 1,500,000 BRO Project Cost: 1,500,000 0 0 T otal for Boyd county PL Total Amounts: CN UT RW DN 150,000 520,000 3,255,126 1,749,828 1,753,205 3,255,126 1,899,828 2,273,205 I NSTALL GUARDRAIL ON KY-37 IN BOYLE COUNTYKY-37Boyle PL4309 DN RW UT CN 15,000 GR Project Cost: 0 15,000 0 21 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 RECONSTRUCT KY 52 FROM KY 1805 (Goggin Ln) TO KY 590K Y-52Boyle PL80204 DN 250,000 STP2 RW UT CN Project Cost: 0 0 250,000 I MPROVE SAFETY BY DEMOLISHING AND REBUILDING THE BUSTER PIKE BRIDGE IN THE SAME LOCATION (BY MOA, NORFOLK-SOUTHERN WILL PROVIDE $200,000) KY-2168Boyle PL80211 DN RW UT CN 1,600,000 BRZ Project Cost: 0 0 1,600,000 IMPROVE THE SAFETY AND MOBILITY OF KY 34 FROM ALUM S PRINGS CROSSPIKE (MP 10.391) TO APPROX. 1,000 FEET WEST OF CORPORATE DRIVE (MP 10.800) KY-34B oyle PL80250 DN 150,000 SPP RW 100,000 SPP UT 800,000 SPP CN 1,000,000 SPP Project Cost: 0 250,000 1,800,000 T otal for Boyle county PL Total Amounts: CN UT RW DN 150,000 250,000 100,000 800,000 15,000 2,600,000 0 265,000 3,650,000 O PERATION OF AUGUSTA FERRY FOR FY 2022 THROUGH FY 2028. (12CCR)(14CCR) (2020CCR) KY-8Bracken PL355.2200 DN RW UT CN 282,000 282,000 282,000 SPP Project Cost: 282,000 282,000 282,000 22 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN BRACKEN COUNTY ON (012B00023N) KY-539 A T WILLOW CREEK KY-539Bracken PL10031 DN 198,000 BRX RW UT CN 1,980,000 BRX Project Cost: 0 198,000 1,980,000 T otal for Bracken county PL Total Amounts: CN UT RW DN 198,000 282,000 282,000 2,262,000 282,000 480,000 2,262,000 P anbowl Lake drainage and safety improvements along KY 15.KY-15Breathitt PL172 DN RW UT CN 4,000,000 PROT 2,500,000 SPP Project Cost: 0 6,500,000 0 I MPROVE KY-205 FROM NORTH OF KY-1812 TO SOUTH OF PEGGS FORK RD. (2020CCR) KY-205Breathitt PL375 DN RW 3,050,000 STPF UT CN Project Cost: 0 0 3,050,000 I NSTALL GUARDRAIL ON KY-28 IN BREATHITT COUNTYKY-28Breathitt PL4309 DN RW UT CN 72,000 GR Project Cost: 0 72,000 0 23 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ROCKFALL MITIGATION ON KY 15 FROM 0.593 MILE NORTH OF B EAVERLY ROAD (MP 13.750) TO KY 1098/KY 1813 (MP 14.644). (2018BOP) KY-15Breathitt PL5014 DN 600,000 PROT RW 250,000 PROT UT 50,000 PROT CN Project Cost: 0 600,000 300,000 B RIDGE PROJECT IN BREATHITT COUNTY ON (013C00008N) BIG BRANCH ROAD AT BIG BRANCH CREEK CR-1104Breathitt PL10011 DN 34,000 BRZ RW UT CN 340,000 BRZ Project Cost: 0 374,000 0 R EPLACE BRIDGE OVER PUNCHEON CREEK ON MAX ROARK RD (2020CCN) CR-1125Breathitt PL80107 DN 125,000 SPP RW 5,000 SPP UT CN Project Cost: 125,000 0 5,000 T otal for Breathitt county PL Total Amounts: CN UT RW DN 125,000 634,000 3,305,000 50,000 6,912,000 125,000 7,546,000 3,355,000 I NSTALL GUARDRAIL ON KY-259 IN BRECKINRIDGE COUNTYKY-259Breckinridge PL4315 DN RW UT CN 13,000 GR Project Cost: 0 0 13,000 24 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS SAFETY AND GEOMETRIC DEFICIENCIES ON KY 79 FROM K Y 477 TO KY 144 (12CCN)(14CCR)(18CCN)(2020 CCR) (COMBINED W/ 4-8703) KY-79Breckinridge PL8702 DN RW 1,700,000 SPP UT CN Project Cost: 0 0 1,700,000 R EPLACE LOW WATER STRUCTURE ON KY 261 AT MP 15.74. (18CCN) KY-261Breckinridge PL8902 DN 100,000 BRX RW 25,000 BRX UT 25,000 BRX CN Project Cost: 0 100,000 50,000 T otal for Breckinridge county PL Total Amounts: CN UT RW DN 100,000 1,725,000 25,000 13,000 0 100,000 1,763,000 R ECONSTRUCT KY 44 FROM KY 1319 KINGS CHURCH HIGHWAY TO SPENCER COUNTY LINE (2020CCN) KY-44Bullitt PL43 DN 1,200,000 SPP RW 1,000,000 SPP UT 850,000 SPP CN Project Cost: 1,200,000 1,000,000 850,000 S ECTION 5 FROM US 31EX TO US 31E BYPASS (2008BOPC)KY-44Bullitt PL150.5000 DN RW 1,630,000 SPP UT 580,000 SPP CN Project Cost: 0 1,630,000 580,000 25 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 MT. WASHINGTON-TAYLORSVILLE RD; RECONSTRUCT KY 44 FROM U S31E BYPASS TO KY 1319 KINGS CHURCH HIGHWAY (2020CCN) KY-44Bullitt PL347.5000 DN 1,300,000 SPP RW UT CN Project Cost: 1,300,000 0 0 N EW TURN LANES IN FRONT OF BULLITT EAST HIGH SCHOOL. (BREAKOUT FROM 347.50) (18CCN) KY-44Bullitt PL347.5100 DN RW UT CN 1,022,000 STPF Project Cost: 1,022,000 0 0 W IDEN CEDAR GROVE ROAD (KY-480) FROM CEDAR GROVE ELEMENTARY SCHOOL TO VALLEY VIEW DRIVE. (12CCR)(14CCR) (SEE 5-391.3 FOR INTERCHANGE IMPROVEMENTS) KY-480Bullitt PL391.2000 DN RW UT CN 7,900,000 STPF Project Cost: 0 0 7,900,000 I MPROVE OPERATIONAL PERFORMANCE OF THE I-65/KY-480 INTERCHANGE INCLUDING RAMP IMPROVEMENTS AND TURNING LANES. (12CCR)(14CCR)(2014BOP)(16CCR)(2020CCR) I-65, KY-480Bullitt PL391.3000 DN RW UT CN 9,490,000 NH Project Cost: 0 0 9,490,000 E XPAND TRUCK PARKING AT I-65 SB WELCOME CENTER.I -65Bullitt PL578 DN RW UT CN 1,000,000 NH Project Cost: 0 0 1,000,000 26 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-1319 IN BULLITT COUNTYK Y-1319Bullitt PL4307 DN RW UT CN 11,000 GR Project Cost: 0 0 11,000 W IDEN KY-245 FROM BERNHEIM FOREST TO THE COMMUNITY COLLEGE. (08CCN)(10CCR)(14CCR)(16CCR) (2020CCR) KY-245Bullitt PL8509 DN RW UT CN 6,140,000 STPF Project Cost: 0 0 6,140,000 S OUND BARRIERS ON EAST SIDE OF I-65 ACROSS FROM CONESTOGA INDUSTRIAL AREA. LOCALS WILL PROVIDE $100,000 FOR CONSTRUCTION (14CCN)(16CCR)(18CCN) (2020CCR) I -65Bullitt PL8856 DN RW UT CN 1,800,000 SPP Project Cost: 1,800,000 0 0 B RIDGE PROJECT IN BULLITT COUNTY ON (015B00057N) KY 1526 AT FLOYDS FORK KY-1526Bullitt PL10035 DN 235,000 FBP RW UT CN 2,350,000 FBP Project Cost: 2,585,000 0 0 B RIDGE PROJECT IN BULLITT COUNTY ON (015B00059N) KY 1116 AT CEDAR CREEK KY-1116Bullitt PL10036 DN 125,000 FBP RW UT CN 1,250,000 FBP Project Cost: 1,375,000 0 0 27 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS CONDITION OF I-065 FROM MILEPOINT 104.7 TO MILEPOINT 1 10.7 I -65B ullitt PL22066 DN 5,400,000 NHPM RW UT CN 54,000,000 NHPM Project Cost: 0 59,400,000 0 A CCESS, SAFETY AND ECONOMIC DEVELOPMENT IMPROVEMENT STUDY ALONG KY 61 IN LEBANON JUNCTION FROM LEBANON JUNCTION MIDDLE SCHOOL TO NELSON COUNTY LINE 9 (MP 0.0 TO 3.7) (2020CCN) KY-61Bullitt PL 250,000 SPP80100 DN RW UT CN Project Cost: 250,000 0 0 I MPROVE SAFETY AND REDUCE CONGESTION ON KY 1450 (BLUE LICK RD.) BETWEEN THE INTERSECTIONS WITH KY 1526 (JOHN HARPER HIGHWAY) AND CR 1512A (JEFFIE LANE) (2020CCN) KY-1450Bullitt PL80101 DN 1,045,000 SPP RW UT CN Project Cost: 1,045,000 0 0 R ECONSTRUCT KY 44 FROM BOGARD LANE TO ARMSTRONG LANE (2020CCN) KY-44Bullitt PL80103 DN 2,300,000 SPP RW UT CN Project Cost: 2,300,000 0 0 T otal for Bullitt county PL Total Amounts: CN UT RW DN 250,000 6,205,000 5,400,000 2,630,000 1,430,000 6,422,000 54,000,000 24,541,000 12,877,000 62,030,000 25,971,000 28 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 OPERATION OF REED'S FERRY AT LOGANSPORT FOR FY 2022 T HROUGH FY 2028.(12CCR) (2020CCR) KY-269Butler PL125.1500 DN RW UT CN 158,400 158,400 158,400 SPP Project Cost: 158,400 158,400 158,400 OPERATION OF THE ROCHESTER FERRY BY THE BUTLER AND OHIO C OUNTY FERRY AUTHORITY FOR FY 2020.(12CCR) (2020CCR) KY-369B utler PL8504.1000 DN RW UT CN 158,400 158,400 158,400 SPP Project Cost: 158,400 158,400 158,400 B RIDGE PROJECT IN BUTLER COUNTY ON (016B00061N) I-165 AT GREEN RIVER I -165Butler PL10037 DN 1,588,000 FBP2 RW UT CN 15,880,000 FBP2 Project Cost: 0 17,468,000 0 ADDRESS CONDITION OF I 165 FROM MILEPOINT 26.48 TO MILEPOINT 3 2.645 I-165B utler PL20009 DN 700,000 NHPM RW UT CN 7,000,000 NHPM Project Cost: 0 0 7,700,000 T otal for Butler county PL Total Amounts: CN UT RW DN 1,588,000 700,000 316,800 16,196,800 7,316,800 316,800 17,784,800 8,016,800 29 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 RELOCATE US-641 FROM SOUTH OF THE LYON/CALDWELL COUNTY L INE TO FREDONIA, 4.5 MILES. (2020CCN) US-641Caldwell PL187.6000 DN RW 3,000,000 STPF UT 1,500,000 STPF CN Project Cost: 0 3,000,000 1,500,000 I NSTALL GUARDRAIL ON KY-139 IN CALDWELL COUNTYKY-139Caldwell PL4314 DN RW UT CN 50,000 GR Project Cost: 0 0 50,000 B RIDGE PROJECT IN CALDWELL COUNTY ON (017B00024N) KY-126 AT BURNS CREEK KY-126Caldwell PL10061 DN 112,000 FBP RW UT CN 1,120,000 FBP Project Cost: 112,000 0 1,120,000 B RIDGE PROJECT IN CALDWELL COUNTY ON (017B00076N) KY-1592 AT TOWERY BRANCH KY-1592Caldwell PL10065 DN 50,000 FBP RW UT CN 500,000 FBP Project Cost: 50,000 0 500,000 T otal for Caldwell county PL Total Amounts: CN UT RW DN 162,000 3,000,000 1,500,000 1,670,000 162,000 3,000,000 3,170,000 30 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 CITY OF MURRAY BUSINESS LOOP FROM GLENDALE TO INDUSTRIAL R OAD. (SEE 1-120 FOR D, R, U FUNDING) (08CCN)(10CCR)(LET BY CITY) PF-9999C alloway PL8502 DN RW UT CN 3,000,000 SPP Project Cost: 0 0 3,000,000 I MPROVE N 16TH STREET FROM KY 1327 (5 POINTS) TO KY 121 (2020CCN) CS-1047, KY-748 Calloway PL8952 DN RW 2,210,000 SPP UT 2,170,000 SPP CN Project Cost: 0 2,210,000 2,170,000 B RIDGE PROJECT IN CALLOWAY COUNTY ON (018B00018N) KY-121 AT CLAYTON CREEK KY-121Calloway PL10099 DN 78,000 FBP2 RW UT CN 780,000 FBP2 Project Cost: 0 0 858,000 B RIDGE PROJECT IN CALLOWAY COUNTY ON (018B00023N) KY-121 AT BLOOD RIVER KY-121Calloway PL10100 DN 447,000 FBP RW UT CN 4,470,000 FBP Project Cost: 447,000 4,470,000 0 B RIDGE PROJECT IN CALLOWAY COUNTY ON (018B00045N) KY-783 AT Middle fork Clarks River KY-783Calloway PL10101 DN 226,000 FBP RW UT CN 2,260,000 FBP Project Cost: 226,000 2,260,000 0 31 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN CALLOWAY COUNTY ON (018B00066N) K Y-1346 AT BRANCH OF JONATHAN CREEK KY-1346Calloway PL10102 DN 155,000 FBP RW UT CN 1,550,000 FBP Project Cost: 155,000 1,550,000 0 ADDRESS CONDITION OF US-641X FROM MILEPOINT 0 TO MILEPOINT 2 .873 US-641C alloway PL22312 DN RW UT CN 1,700,000 STP4 Project Cost: 0 1,700,000 0 P LANNING STUDY FOR SCENIC BYWAY ALONG KENTUCKY LAKE (2020CCN) PF-9999Calloway PL 250,000 SPP80100 DN RW UT CN Project Cost: 0 250,000 0 A ddress congestion, geometric deficiencies, and access issues from KY121 to Utterback Road in Murray. cs-1047Calloway PL80200 DN 750,000 STP RW UT CN Project Cost: 0 750,000 0 T otal for Calloway county PL Total Amounts: CN UT RW DN 250,000 828,000 750,000 78,000 2,210,000 2,170,000 9,980,000 3,780,000 828,000 13,190,000 6,028,000 32 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADD LANE ON RAMP FROM EASTBOUND I-275 TO NORTHBOUND I -471. I -471Campbell PL 200,000 NH23 DN RW UT CN Project Cost: 0 0 200,000 REDUCE CONGESTION ALONG THE I-471 CORRIDOR FROM US-27 TO O HIO STATE LINE. I -471C ampbell PL 1,000,000 NH81 DN RW UT CN Project Cost: 0 0 1,000,000 E XTEND PROPOSED POND CREEK ROAD FROM US-27 TO AA HIGHWAY VIA PORTION OF KY 10/KY 1997 CORRIDOR (NEW KY-536)(04CCN)(12CCR)(14CCR) (2020CCN) PF-9999Campbell PL352 DN 1,500,000 SPP RW UT CN Project Cost: 1,500,000 0 0 R eplace 4th Street Bridge over the Licking River between Covington and Newport; Bridge Number 059B00037N KY-8Campbell PL1086 DN RW 2,690,000 BRO UT 1,270,000 BRO CN 15,000,000 BRO Project Cost: 0 3,960,000 15,000,000 I NSTALL GUARDRAIL ON KY-547 IN CAMPBELL COUNTYKY-547Campbell PL4308 DN RW UT CN 32,000 GR Project Cost: 0 32,000 0 33 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 CONSTRUCT NEW I-471 SOUTHBOUND OFF-RAMP AT KY-8 (SEE A LSO 6-183.00). (02CCN)(06CCN) (2020CCN) I -471, KY-8Campbell PL8104 DN 3,500,000 SPP RW 5,000,000 SPP UT 1,000,000 SPP CN Project Cost: 3,500,000 5,000,000 1,000,000 C ONSTRUCT A NEW CONNECTOR BETWEEN I-275 AND THE AA HIGHWAY. (02CCN) Campbell PL8105 DN RW UT CN 6,200,000 STP Project Cost: 0 0 6,200,000 T RANSPORTATION IMPROVEMENTS TO AA I 275; CONSTRUCT A NEW CONNECTOR RD FROM THE KY 9 TO THE END OF NEW CONSTRUCTION JUST SOUTH OF JOHN'S HILL RD. (2020CCN) PF-9999Campbell PL8105.0700 DN RW 1,900,000 STPF UT CN Project Cost: 0 1,900,000 0 S AFETY CABLE REPAIR AND PREVENTIVE MAINTENANCE ON TAYLOR SOUTHGATE BRIDGE OVER THE OHIO RIVER. JOINT PROJECT WITH OHIO. (019B00076N)(BSBP) US-27Campbell PL10007 DN RW UT CN 250,000 BRX Project Cost: 250,000 0 0 ADDRESS CONDITION OF I-471 FROM MILEPOINT 0 TO MILEPOINT 4.75I-471C ampbell PL20011 DN 635,000 NHPM RW UT CN 6,350,000 NHPM Project Cost: 0 0 6,985,000 34 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS PAVEMENT CONDITION OF AC PAVEMENT.K Y-9Campbell PL20013 DN 225,000 STP5 RW UT CN Project Cost: 0 0 225,000 A DD RIGHT TURN LANES FROM AA HIGHWAY ONTO KY 709, AND FROM KY 709 ONTO AA HIGHWAY KY-709Campbell PL80220 DN RW UT CN 950,000 SPP Project Cost: 0 950,000 0 T otal for Campbell county PL Total Amounts: CN UT RW DN 1,200,000 5,000,000 860,000 9,590,000 1,270,000 1,000,000 250,000 982,000 27,550,000 5,250,000 11,842,000 30,610,000 C ORRECT GEOMETRIC DEFICIENCIES AT INTERSECTION OF US-51/US-62/FRONT ST/ELM ST IN BARDWELL TO ADDRESS FLOW, SAFETY, AND ACCESS ISSUES.(12CCR)(18CCN) US-51, US-62Carlisle PL333 DN RW UT CN 340,000 SPP Project Cost: 0 340,000 0 B RIDGE PROJECT IN CARLISLE COUNTY ON (020B00002N) US-51 AT GADDIE CREEK US-51Carlisle PL10104 DN 41,000 FBP RW UT CN 410,000 FBP Project Cost: 41,000 410,000 0 35 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN CARLISLE COUNTY ON (020B00004N) US-51 AT L ITTLE MAYFIELD CREEK US-51Carlisle PL10105 DN 20,000 FBP RW UT CN 200,000 FBP Project Cost: 20,000 200,000 0 T otal for Carlisle county PL Total Amounts: CN UT RW DN 61,000 950,000 61,000 950,000 0 B RIDGE PROJECT IN CARROLL COUNTY ON (021B00043N) US-42 at KENTUCKY RIVER & CITY ST US-42Carroll PL1084 DN 2,262,000 BRX RW UT CN 10,000,000 BRX Project Cost: 0 2,262,000 10,000,000 B RIDGE PROJECT IN CARROLL COUNTY ON (021B00009N) KY-36 AT LICK CREEK KY-36Carroll PL10037 DN 259,000 BRX RW UT CN 590,000 BRX Project Cost: 0 259,000 590,000 A DDRESS CONDITION OF I-71 FROM MILEPOINT 46.1205 TO MILEPOINT 53.433 I-71Carroll PL20020 DN 1,600,000 NHPM RW UT CN 16,000,000 NHPM Project Cost: 0 0 17,600,000 36 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS PAVEMENT CONDITION ON KY-467 FROM MILEPOINT 0.00 TO MILEPOINT 4.52 KY-467Carroll PL20050 DN RW UT CN 365,000 STP4 Project Cost: 365,000 0 0 ADDRESS CONDITION OF I-71 FROM MILEPOINT 38.808 TO MILEPOINT 4 6.121 I-71C arroll PL22101 DN 1,600,000 NHPM RW UT CN Project Cost: 0 1,600,000 0 I mprove safety and mobility and address geometric deficiencies at the intersection of KY 36 & KY 1492 (Locust Road). KY-36Carroll PL80219 DN 658,000 SPP RW UT CN Project Cost: 0 658,000 0 T otal for Carroll county PL Total Amounts: CN UT RW DN 4,779,000 1,600,000 365,000 26,590,000 365,000 4,779,000 28,190,000 I NSTALL GUARDRAIL ON US-60 IN CARTER COUNTYUS-60Carter PL4307 DN RW UT CN 66,000 GR Project Cost: 66,000 0 0 37 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-1947 IN CARTER COUNTYK Y-1947Carter PL4313 DN RW UT CN 28,000 GR Project Cost: 0 28,000 0 I MPROVE SAFETY AT THE EAST CARTER HIGH SCHOOL. (06CCN) (08CCR)(12CCR) (2020CCR) KY-1Carter PL8311 DN RW UT CN 1,930,000 STP1 Project Cost: 0 0 1,930,000 R ECONSTRUCT US-60 FROM WEST OF GLENWOOD HOLLOW ROAD TO EAST OF KY-3296. THE PROJECT SHALL INCLUDE 12' LANES, WIDE PAVED SHOULDERS, UNOBSTRUCTED CLEAR ZONES, FLATTER VERTICAL GRADES, AND GENTLY HORIZONTAL CURVES. (08CCN)(12CCR)(14CCR)(18CCN) (2020CCR) US-60Carter PL8401 DN RW 2,000,000 SPP UT 2,000,000 SPP CN Project Cost: 0 4,000,000 0 B RIDGE PROJECT IN CARTER COUNTY ON (022B00012N) KY-1 AT LIT.FK.LITTLE SANDY RIVE KY-1Carter PL10077 DN 293,000 BRX RW UT CN 2,930,000 BRX Project Cost: 0 293,000 2,930,000 B RIDGE PROJECT IN CARTER COUNTY ON (022C00030N) GOLLIHUE RD AT LITTLE FORK CREEK CR-1197Carter PL10080 DN 101,000 BRZ RW UT CN 1,010,000 BRZ Project Cost: 0 1,111,000 0 38 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS CONDITION OF I-64 FROM MILEPOINT 154.26 TO MILEPOINT 1 66.217 I-64C arter PL22053 DN 908,732 NHPM RW UT CN 9,087,320 NHPM Project Cost: 0 0 9,996,052 A DDRESS CONDITION OF I-64 FROM MILEPOINT 166.217 TO 171.2I-64Carter PL22054 DN 378,708 NHPM RW UT CN 3,787,080 NHPM Project Cost: 0 0 4,165,788 IMPROVE US-60 GEOMETRY BEGINNING TERMINI AT NEW C ONSTRUCTION AT OLIVE HILL MP 12.4 EXTENDING 1.1 MILES TO I-64 EXIT 161.(18CCN) US-60C arter PL80050 DN 1,440,000 STP2 RW UT CN Project Cost: 0 1,440,000 0 G eometric improvements on KY 1025 from US 60 (MP 0.0),East of Olive Hill extending North 0.30 miles providing access to West Carter Middle and High Schools and facilities. Project will include bike/ped facilities. ky-1025Carter PL80200 DN 500,000 STP2 RW UT CN Project Cost: 0 0 500,000 I mprove safety and operational efficiency of KY 3297 near East Carter Middle School and the new sports complex. ky-3297Carter PL80201 DN 150,000 SPP RW UT CN Project Cost: 0 0 150,000 39 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Construct a two lane roadway from KY 3297 to the intersection of US 6 0 and KY 1 to mitigate congestion along Carol Malone Boulevard. (Phase III of proposed bypass project.) ky-1Carter PL80202 DN 1,000,000 STP1 RW 1,501,000 STP1 UT CN Project Cost: 0 1,000,000 1,501,000 T otal for Carter county PL Total Amounts: CN UT RW DN 2,834,000 1,937,440 2,000,000 1,501,000 2,000,000 66,000 1,038,000 17,734,400 66,000 7,872,000 21,172,840 IMPROVE SAFETY AND GEOMETRIC DEFICIENCIES ALONG US 127 AT D UNNVILLE US-127C asey PL164 DN 520,000 NH RW UT CN Project Cost: 0 520,000 0 N EW ALIGNMENT ON KY-70 FROM MP 16.8 TO 19 (12CCN)KY-70Casey PL8701 DN 780,000 SPP RW UT CN Project Cost: 0 780,000 0 R ECONSTRUCT BELL HILL FROM MP 10.4 TO MP 11.9.(12CCN) (16CCR)(18CCN) (2020CCR) KY-70Casey PL8703 DN RW 3,420,000 SPP UT CN Project Cost: 0 0 3,420,000 40 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 RECONSTRUCT BRUSH CREEK HILL FROM MP 1.8 TO MP 2.8.(12CCN) ( 16CCR)(18CCN) (2020CCR) KY-49Casey PL8704 DN RW 1,350,000 SPP UT CN Project Cost: 0 0 1,350,000 REALIGN KY 501 TO INTERSECT KY 70 EAST OF EXISTING LOCATION A ND CORRECT VERTICAL ALIGNMENT OF KY 70 NEAR EXISTING INTERSECTION.(12CCN) (2020CCN) KY-501C asey PL8705 DN RW 1,050,000 SPP UT CN 1,000,000 SPP Project Cost: 0 1,050,000 1,000,000 B RIDGE PROJECT IN CASEY COUNTY ON (023C00094N) BASTIN CREEK RD AT CRANE CREEK CR-1037Casey PL10050 DN 33,000 BRZ RW UT CN 330,000 BRZ Project Cost: 0 33,000 330,000 A DD LANES (TWO PLUS ONE) TO US 127 FROM LIBERTY TO THE LINCOLN CO LINE (2020CCN) US-127Casey PL80150 DN 2,880,000 NH RW UT CN Project Cost: 0 0 2,880,000 T otal for Casey county PL Total Amounts: CN UT RW DN 1,333,000 2,880,000 1,050,000 4,770,000 1,330,000 0 2,383,000 8,980,000 41 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 WIDEN KY 911 TO A 3 LANE FROM THE DEPARTMENT OF DEFENSE R AILROAD TO KY 115.(SECTION 2)(D,R,U UNDER 2-180)(2018BOP) KY-911Christian PL180.2000 DN RW UT CN 6,400,000 STPF Project Cost: 0 0 6,400,000 R ECONSTRUCT KY 1007 FROM US 68 TO SANDERSON ROAD IN HOPKINSVILLE. (SEE NORTHERN EXTENSION UNDER 2-227.10) (2020CCR) KY-1007Christian PL227 DN 400,000 STP1 RW UT CN Project Cost: 400,000 0 0 CONSTRUCT NEW CONNECTOR FROM US 41 NEAR THE INDUSTRIAL P ARK TO KY 115 SOUTH OF PEMBROKE. (16CCR)(18CCN) (2020CCR) PF-9999C hristian PL381 DN RW 1,000,000 STP2 UT 950,000 STP2 CN Project Cost: 0 1,000,000 950,000 R ECONSTRUCT THE BREATHITT PARKWAY INTERCHANGE AT KY 1682 NORTH OF HOPKINSVILLE USING DESIGN BUILD. (BREATHITT PARKWAY/FUTURE INTERSTATE SPUR PROJECT)(16CCR)(18CCN) (2020CCR) EB-9004Christian PL898 DN 250,000 NH RW 1,000,000 NH UT 1,200,000 NH CN Project Cost: 250,000 0 2,200,000 A DDRESS CONGESTION AND MOBILITY OF US 68 FROM KY 91 TO KY 1007 IN HOPKINSVILLE. (18CCN) (2020CCR) US-68Christian PL899 DN RW UT CN 5,850,000 NH Project Cost: 0 0 5,850,000 42 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE AND WIDEN KY 115 FROM ANDERSON ROAD (MP 6.87) TO J UST SOUTH OF PEMBROKE (MP 9.625)(16CCN)(18CCN) KY-115Christian PL8953 DN RW 2,750,000 STP2 UT CN Project Cost: 0 0 2,750,000 I MPROVE AND WIDEN KY 115 FROM I-24 (MP 2.901) TO ANDERSON ROAD (MP 687). (16CCN) KY-115Christian PL8954 DN 1,360,000 SPP RW UT CN Project Cost: 0 1,360,000 0 B RIDGE PROJECT IN CHRISTIAN COUNTY ON (024B00112N) WALNUT STREET AT CSX RAILROAD US-41Christian PL10075 DN 307,000 BRO RW UT CN 3,070,000 BRO Project Cost: 0 0 3,377,000 A DDRESS CONDITION OF EDWARD T. BREATHITT PENNYRILE PARKWAY FROM MILEPOIINT 0 TO MILEPOINT 4.719 EB-9004Christian PL20005 DN 350,000 NHPM RW UT CN 3,500,000 NHPM Project Cost: 0 3,850,000 0 A DDRESS CONDITION OF EDWARD T BREATHITT PENNYRILE PARKWAY FROM MILEPOINT 4.719 TO MILEPOINT 6.77 EB-9004Christian PL20008 DN 180,000 NHPM RW UT CN 1,800,000 NHPM Project Cost: 0 1,980,000 0 43 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS PAVEMENT CONDITION OF PCC PAVEMENT ON I-24 C ARDINAL DIRECTION(S) FROM MILEPOINT 69.83 TO 76.142 I-24Christian PL20010 DN 325,000 NHPM RW UT CN 3,250,000 NHPM Project Cost: 325,000 3,250,000 0 ADDRESS CONDITION OF I-24 FROM MILEPOINT 85.563 TO MILEPOINT 9 2 I-24C hristian PL20013 DN 1,850,000 NHPM RW UT CN 18,500,000 NHPM Project Cost: 20,350,000 0 0 ADDRESS CONDITION OF I-24 FROM MILEPOINT 91.978 TO MILEPOINT 9 3.373 I-24C hristian PL22016 DN 150,000 NHPM RW UT CN 1,500,000 NHPM Project Cost: 0 0 1,650,000 A DDRESS CONDITION OF EDWARD T. BREATHITT PENNYRILE PARKWAY FROM MILEPOINT 6.77 TO MILEPOINT 12.053 EB-9004Christian PL22191 DN 425,000 NHPM RW UT CN 4,250,000 NHPM Project Cost: 0 0 4,675,000 U S 41A NEW TURNING LANE NORTHBOUND AT EXISTING MEDIAN CROSSOVER NEAR MILEPOST 11.4. CITY TO CONSTRUCT AND BE REIMBURSED. (18CCN) (2020CCR) US-41Christian PL80001 DN 30,000 SPP RW UT CN 110,000 SPP Project Cost: 0 30,000 110,000 44 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS SAFETY ISSUES BY INSTALLING INTERCHANGE LIGHTING ( 2020CCN) I -24Christian PL80103 DN RW UT CN 700,000 SPP Project Cost: 700,000 0 0 I MPROVE SAFETY AND MOBILITY BY WIDENING AND CORRECTING GEOMETRIC DEFICIENCIES ON KY 107 FROM MILEPOINT 15.0 TO MILEPOINT 15.6 KY-107Christian PL80250 DN 700,000 SPP RW 800,000 SPP UT 600,000 SPP CN 1,200,000 SPP Project Cost: 0 2,100,000 1,200,000 T otal for Christian county PL Total Amounts: CN UT RW DN 2,825,000 2,620,000 882,000 1,800,000 3,750,000 600,000 2,150,000 19,200,000 8,550,000 22,380,000 22,025,000 13,570,000 29,162,000 E XTEND THE WINCHESTER EAST BYPASS (KY 1958) FROM IRVINE ROAD (KY 89) TO KY 627 SOUTH OF WINCHESTER. (08CCN)(10CCR) (18CCN) KY-1958Clark PL8401 DN RW UT CN 5,000,000 NH Project Cost: 0 0 5,000,000 E XTEND FULTON ROAD. (BY COUNTY)(10CCN)(18CCN) (2020CCR)PF-9999Clark PL8639 DN RW UT CN 1,780,000 SPP Project Cost: 0 1,780,000 0 45 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN CLARK COUNTY ON (025B00092N) KY-3369 AT L OG LICK CREEK KY-3369Clark PL10040 DN 43,000 BRX RW UT CN 430,000 BRX Project Cost: 0 43,000 430,000 ADDRESS CONDITION OF I 64 FROM MILEPOINT 89.48 TO MILEPOINT 9 4.851 I-64C lark PL20004 DN 600,000 NHPM RW UT CN 6,000,000 NHPM Project Cost: 6,600,000 0 0 ADDRESS CONDITION OF I 64 FROM MILEPOINT 94.851 TO MILEPOINT 9 8.096 I-64C lark PL20005 DN 400,000 NHPM RW UT CN 4,000,000 NHPM Project Cost: 0 0 4,400,000 ADDRESS CONDITION OF I 64 FROM MILEPOINT 98.096 TO MILEPOINT 1 01.7 I-64C lark PL22040 DN 273,904 NHPM RW UT CN 2,739,040 NHPM Project Cost: 0 0 3,012,944 A DD A LEFT TURN LANE BY THE ENTRANCE OF 1520 BOONESBORO RD. (2020CCN) KY-627Clark PL80100 DN RW 20,000 SPP UT 70,000 SPP CN 100,000 SPP Project Cost: 90,000 100,000 0 46 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 MODERNIZE AND IMPROVE CAPACITY ON US 60 FROM KY 859 ( HALEY RD) TO KY 1958 (BYPASS RD) IN CLARK COUNTY. (2020CCN) US-60Clark PL80151 DN 3,786,000 SPP RW UT CN Project Cost: 0 0 3,786,000 T otal for Clark county PL Total Amounts: CN UT RW DN 600,000 43,000 4,459,904 20,000 70,000 6,000,000 1,880,000 12,169,040 6,690,000 1,923,000 16,628,944 I NSTALL GUARDRAIL ON KY-11 IN CLAY COUNTYKY-11Clay PL4352 DN RW UT CN 126,000 GR Project Cost: 0 0 126,000 I NSTALL GUARDRAIL ON KY-11 IN CLAY COUNTYKY-11Clay PL4367 DN RW UT CN 92,000 GR Project Cost: 0 0 92,000 I NSTALL GUARDRAIL ON KY-11 IN CLAY COUNTYKY-11Clay PL4368 DN RW UT CN 51,000 GR Project Cost: 0 0 51,000 47 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE US 421 FROM GOOSE CREEK BRIDGE (MP 15.4) TO CHOP B OTTOM RD (MP 14.3) INCLUDING RECONSTRUCTION OF HIGHWAY/RAIL GRADE CROSSING ON KY-1999 AT THE INTERSECTION WITH US-421 AND KY-80 US-421Clay PL8003.1000 DN RW UT CN 10,000,000 NH Project Cost: 0 10,000,000 0 I MPROVE SAFETY AND SIGHT DISTANCE ALONG KY 638 (MP 6.7 TO MP 7.1) AND ITS INTERSECTION WITH KY 3476. (14CCN)(18CCN) (2020CCR) KY-638Clay PL8861 DN RW UT CN 2,000,000 SPP Project Cost: 2,000,000 0 0 IMPROVE GEOMETRICS ALONG URBAN CREEK ROAD (CR 1286) AND, I NCLUDING INTERSECTIONS AT HAL ROGERS PARKWAY AND KY 687. (14CCN)(18CCN) (2020CCR) CR-1286C lay PL8864 DN RW UT 445,000 SPP CN 6,600,000 SPP Project Cost: 445,000 6,600,000 0 A DDRESS CONDITION OF HAL ROGERS DANIEL BOONE PARKWAY FROM MILEPOINT 14.345 TO MILEPOINT 15.606 HR-9006Clay PL20001 DN 60,000 NHPM RW UT CN 600,000 NHPM Project Cost: 0 0 660,000 A DDRESS CONDITION OF HAL ROGERS DANIEL BOONE PARKWAY FROM MILEPOINT 22.88 TO MILEPOINT 23.305 HR-9006Clay PL22199 DN 30,000 NHPM RW UT CN 300,000 NHPM Project Cost: 0 0 330,000 48 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS CONDITION OF HAL ROGERS DANIEL BOONE PARKWAY F ROM MILEPOINT 27.068 TO MILEPOINT 27.785 HR-9006Clay PL22200 DN 40,000 NHPM RW UT CN 400,000 NHPM Project Cost: 0 0 440,000 CONSTRUCT NEW CONNECTOR ROAD BETWEEN US 421 AT MP 17.51 TO RAILROAD AVE. AT MP 0.1. THIS WILL REQUIRE APPROXIMATELY 300' OF NEW ROADWAY ALONG THE CONNECTOR, A 450' 3-LANE BRIDGE, NEW RIGHT TURN LANE ON US 421 AND NEW TRAFFIC SIGNALS AT PROPOSED INTERSECTION. THIS IS CONTINGENT ON US-421C lay PL80251 DN 354,000 SPP RW 354,000 SPP UT 354,000 SPP CN 3,540,000 SPP Project Cost: 0 708,000 3,894,000 CONSTRUCT NEW PEDESTRIAN BRIDGE IN CITY OF MANCHESTER TO C ONNECT TO BRIDGE STREET Clay P L80252 DN RW UT CN 750,000 SPP Project Cost: 0 750,000 0 IMPROVE GEOMETRIC ALIGNMENT FROM KY 3472 AT MP 1.7 C ONTINUING PAST THE BERT. T. COMBS PARK TO THE INTERSECTION OF BEECH CREEK ROAD AND WHITE OAK ROAD. (APPROXIMATELY 1.5 MILES OF ROADWAY TO IMPROVE) KY-3472C lay PL80253 DN 1,300,000 SPP RW 2,000,000 SPP UT CN Project Cost: 0 1,300,000 2,000,000 I MPROVE GEOMETRIC ALIGNMENT FROM THE INTERSECTION OF BEECH CREEK ROAD AND WHITE OAK ROAD TO KY-11 AT MP 14.24. (APPROXIMATELY 4.0 MILES OF ROAD WAY TO IMPROVE) CR-1004Clay PL80254 DN 1,600,000 SPP RW 2,000,000 SPP UT CN Project Cost: 0 1,600,000 2,000,000 T otal for Clay county PL Total Amounts: CN UT RW DN 3,254,000 130,000 354,000 4,000,000 445,000 354,000 2,000,000 17,350,000 5,109,000 2,445,000 20,958,000 9,593,000 49 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-553 IN CLINTON COUNTYK Y-553Clinton PL4309 DN RW UT CN 15,000 GR Project Cost: 15,000 0 0 R ELOCATE US-127 FROM NORTH OF THE KY-3063 AND OLD US-127 INTERSECTION, AND EXTENDING NORTHERLY TO EAST OF KY-1730 AND MANTOWN INTERSECTION. (SEE 8-108 & 8-115 FOR PE&ENV) (12CCR)(14CCR) (2020CCR) US-127Clinton PL8601.2600 DN RW UT CN 27,200,000 NH Project Cost: 27,200,000 0 0 RELOCATION OF US-127 FROM EAST OF THE AARON RIDGE RD AND O LD US-127 INTERSECTION, EXTENDING NORTHERLY TO NORTH OF THE KY-3063 AND OLD US-127 INTERSECTION. (SEE 8-108 AND 8-115 FOR PE&ENV)(12CCR) (2020CCR) US-127C linton PL8601.3000 DN RW 2,370,000 NH UT 730,000 NH CN Project Cost: 3,100,000 0 0 B RIDGE PROJECT IN CLINTON COUNTY ON (027B00026N) KY-1576 AT SPRING CREEK KY-1576Clinton PL10051 DN 162,000 BRX RW UT CN 1,620,000 BRX Project Cost: 0 162,000 1,620,000 T otal for Clinton county PL Total Amounts: CN UT RW DN 162,000 2,370,000 730,000 27,215,000 1,620,000 30,315,000 162,000 1,620,000 50 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 OPERATION OF CAVE-IN-ROCK FERRY AT OHIO RIVER FOR FY 2022 T HROUGH FY 2028 USING AUDITED COSTS AS THE BASIS.(12CCR) (2020CCR) KY-91Crittenden PL326.1700 DN RW UT CN 831,000 831,000 831,000 SPP Project Cost: 831,000 831,000 831,000 BRIDGE PROJECT IN CRITTENDEN COUNTY ON (028B00010N) KY-120 A T SLOUGH OF TRADEWATER RIV KY-120C rittenden PL10108 DN 100,000 BRX RW UT CN 1,000,000 BRX Project Cost: 0 1,100,000 0 BRIDGE PROJECT IN CRITTENDEN COUNTY ON (028B00024N) KY-135 A T HURRICANE CREEK KY-135C rittenden PL10109 DN 108,000 FBP RW UT CN 1,080,000 FBP Project Cost: 108,000 1,080,000 0 BRIDGE PROJECT IN CRITTENDEN COUNTY ON (028B00030N) KY-506 A T PINEY CREEK KY-506C rittenden PL10110 DN 68,000 FBP RW UT CN 680,000 FBP Project Cost: 748,000 0 0 BRIDGE PROJECT IN CRITTENDEN COUNTY ON (028B00051N) KY-387 A T CROOKED CREEK KY-387C rittenden PL10112 DN 246,000 FBP RW UT CN 2,460,000 FBP Project Cost: 246,000 2,460,000 0 51 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADD A LEFT TURN LANE ON GUM ST. BY THE ENTRANCE OF THE M IDDLE SCHOOL AND HIGH SCHOOL (2020CCN) US-60Crittenden PL80101 DN RW UT CN 500,000 SPP Project Cost: 500,000 0 0 A DDRESS DEFICIENCIES ON THE COTTON PATCH RD BRIDGE (2020CCN) CR-1085Crittenden PL80102 DN RW UT CN 850,000 SPP Project Cost: 850,000 0 0 R econstruct and elevate a 0.12 mile section of KY 295 above the floodplain from M.P. 1.038 to M.P. 1.605 just south of Dycusburg ky-295Crittenden PL80201 DN 150,000 SPP RW 100,000 SPP UT 75,000 SPP CN Project Cost: 150,000 100,000 75,000 T otal for Crittenden county PL Total Amounts: CN UT RW DN 572,000 100,000 100,000 75,000 2,861,000 5,371,000 831,000 3,433,000 5,571,000 906,000 BRIDGE PROJECT IN CUMBERLAND COUNTY ON (029B00019N) KY-90 A T ALLEN CREEK KY-90C umberland PL10052 DN 197,000 FBP RW UT CN 1,970,000 FBP Project Cost: 197,000 1,970,000 0 52 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN CUMBERLAND COUNTY ON (029B00020N) KY-90 A T DUTCH CREEK KY-90C umberland PL10053 DN 263,000 FBP RW UT CN 2,630,000 FBP Project Cost: 263,000 2,630,000 0 T otal for Cumberland county PL Total Amounts: CN UT RW DN 460,000 4,600,000 460,000 4,600,000 0 R ECONSTRUCT INTERSECTION AT FAIRVIEW DRIVE (KY 3143) AND KY 298. (12CCR) (16CCR)(18CCN) (2020CCR) KY-298Daviess PL229 DN RW 1,200,000 STP1 UT 1,300,000 STP1 CN Project Cost: 0 1,200,000 1,300,000 I NSTALL GUARDRAIL ON KY-144 IN DAVIESS COUNTYKY-144Daviess PL4317 DN RW UT CN 43,000 GR Project Cost: 43,000 0 0 I MPROVE KY-54 FROM WEST OF THE US-60 BYPASS TO BOLD FORBES WAY. DESIGN AND RIGHT OF WAY UNDER PARENT 2-8300.00. (2018BOP) KY-54Daviess PL8300.1000 DN RW UT 7,170,000 STP1 CN 5,000,000 STP1 Project Cost: 7,170,000 0 5,000,000 53 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE KY-54 FROM BOLD FORBES WAY TO KY 1456 ( THRUSTON-DERMONT RD). DESIGN UNDER PARENT 2-8300.00. (2018BOP) ky-54Daviess PL8300.2000 DN RW 3,000,000 SPP UT 4,600,000 SPP CN Project Cost: 0 3,000,000 4,600,000 I MPROVE KY-54 FROM BOLD FORBES WAY TO COUNTRYSIDE DRIVE; DESIGN UNDER PARENT 2-8300.00. (2018BOP) KY-54Daviess PL8300.3000 DN RW 3,000,000 SPP UT 4,400,000 SPP CN Project Cost: 0 3,000,000 4,400,000 I MPROVE KY-54 FROM COUNTRYSIDE DRIVE TO JACK HINTON RD. DESIGN UNDER PARENT 2-8300.00. (2018BOP) KY-54Daviess PL8300.4000 DN RW 5,000,000 SPP UT 6,400,000 SPP CN Project Cost: 0 5,000,000 6,400,000 A DDRESS SUBSTANDARD ROADWAY GEOMETRICS AND SAFETY CONCERNS ON KY 1456 FROM KY 54 TO HAYDEN ROAD. MP 2.778 TO 4.714 (SEE 2-8709.00)(14CCN)(16CCR) ky-1456Daviess PL8801 DN 400,000 STP RW 2,500,000 STP UT CN Project Cost: 0 400,000 2,500,000 G RAVES LANE BRIDGE REPLACEMENT-0.2 MI E JCT KY 405 (MM 1.005-1.009) OVER ALLGOOD DITCH. (14CCN) 030C00016N CR-1053Daviess PL8813 DN RW UT CN 500,000 BRZ Project Cost: 500,000 0 0 54 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE KY-3143 FROM KY-3335 TO KY 54. (14CCN) (2020CCR)K Y-3143Daviess PL8854 DN RW 4,500,000 STP UT CN Project Cost: 0 0 4,500,000 ADDRESS DEFICIENCIES OF LYDANNE BRIDGE S BRIDGE OVER FLAT L ICK CREEK. (030C00069N) CR-1257D aviess PL10004 DN 100,000 BRZ RW 5,000 BRZ UT CN 36,500 BRZ Project Cost: 100,000 5,000 36,500 A DDRESS DEFICIENCIES WITH GLOVER CARY BRIDGE OVER OHIO RIVER. JOINT PROJECT WITH INDIANA. (030B00118N)(BSBP) KY-2262Daviess PL10020 DN 200,000 BRO RW UT CN 4,250,000 BRO Project Cost: 4,450,000 0 0 ADDRESS DEFICIENCIES WITH NATCHER BRIDGE OVER OHIO RIVER. J OINT PROJECT WITH INDIANA. (030B00164N)(BSBP) US-231D aviess PL10021 DN RW UT CN 7,500,000 BRO Project Cost: 7,500,000 0 0 B RIDGE PROJECT IN DAVIESS COUNTY ON (030B00049N) US-431 AT PANTHER CREEK US-431Daviess PL10079 DN 436,000 FBP RW UT CN 4,360,000 FBP Project Cost: 436,000 0 4,360,000 55 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN DAVIESS COUNTY ON (030B00096N) US-60 AT K ATIE MEADOW SLOUGH US-60Daviess PL10081 DN 264,000 FBP RW UT CN 2,640,000 FBP Project Cost: 264,000 2,640,000 0 A DDRESS CONDITION OF US-431 FROM MILEPOINT 10.719 TO MILEPOINT 11.216 US-431Daviess PL22325 DN 550,000 STP3 RW UT CN 4,950,000 STP3 Project Cost: 0 0 5,500,000 A DDRESS SAFETY, CONGESTION, AND MOBILITY ISSUES ON KY 144 FROM MP 2.5 TO MP 3.75 INCLUDING 12 FOOT DRIVING LANES AND TURNING LANES WHERE NEEDED. (2020CCN) KY-144Daviess PL80150 DN 600,000 SPP RW UT CN Project Cost: 0 600,000 0 T otal for Daviess county PL Total Amounts: CN UT RW DN 1,000,000 1,000,000 550,000 12,205,000 7,000,000 7,170,000 16,700,000 12,293,000 2,640,000 14,346,500 20,463,000 15,845,000 38,596,500 RECONSTRUCT KY-70/KY-259 FROM 0.36 MILE NORTH GREEN RIVER B RIDGE AT BROWNSVILLE TO 0.42 MILE NORTH OF THE KY-70/KY-259 INTERSECTION.(06CCR)(2004BOPC)(12CCR)(14CCR) (18CCN) (2020CCR) KY-259, K Y-70 Edmonson PL7030.1000 DN RW 2,170,000 STP2 UT 1,930,000 STP2 CN 6,930,000 STP1 Project Cost: 2,170,000 1,930,000 6,930,000 56 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN EDMONSON COUNTY ON (031B00008N) KY-70 A T BEAR CREEK KY-70Edmonson PL10039 DN 159,000 FBP RW UT CN 1,590,000 FBP Project Cost: 1,749,000 0 0 B RIDGE PROJECT IN EDMONSON COUNTY ON (031B00019N) KY-187 AT WHETSTONE CREEK KY-187Edmonson PL10040 DN 33,000 FBP2 RW UT CN 330,000 FBP2 Project Cost: 0 0 363,000 ADDRESS CONDITION OF I 65 FROM MILEPOINT 4.618 TO MILEPOINT 4 5.935 I-65E dmonson PL20012 DN 264,138 NHPM RW UT CN 2,641,380 NHPM Project Cost: 0 0 2,905,518 I MPROVE SAFETY AND MOBILITY ON KY 259 FROM NORTH OF KYROCK ROAD TO THE GRAYSON COUNTY LINE. (2020CCN) KY-259Edmonson PL80107 DN RW 320,000 SPP UT 310,000 SPP CN 2,050,000 SPP Project Cost: 0 630,000 2,050,000 T otal for Edmonson county PL Total Amounts: CN UT RW DN 159,000 297,138 2,170,000 320,000 2,240,000 1,590,000 11,951,380 3,919,000 2,560,000 12,248,518 57 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE KY-32 FROM WEST OF STEGALL COLD SPRING ROAD TO K Y-7 NEAR NEWFOUNDLAND. (PRIORITY SECTION I)(06CCR) (08CCR) (10CCR)(12CCR)(14CCR)(16CCR)(18CCR) (2020CCR) KY-32E lliott PL192.0100 DN RW UT 5,000,000 STP2 CN 5,000,000 STP2 Project Cost: 5,000,000 0 5,000,000 3 -LANE CURB AND GUTTER IN THE VICINITY OF ELLIOT COUNTY SCHOOLS IN SANDY HOOK. (2020CCR) KY-7Elliott PL228.3000 DN RW UT CN 3,120,000 SPP Project Cost: 0 0 3,120,000 R econstruct KY 7 from Sandy Hook to the Morgan County Line.KY-7Elliott PL228.4000 DN 2,500,000 STP2 RW UT CN Project Cost: 0 0 2,500,000 K Y-32 FROM 9.2 MILE MARKER TO 10.2 MILE MARKER WIDENING. (14CCN)(16CCR)(18CCN)(2020CCR) KY-32Elliott PL8802 DN RW 1,050,000 STP2 UT 1,000,000 STP2 CN Project Cost: 0 1,050,000 1,000,000 T otal for Elliott county PL Total Amounts: CN UT RW DN 2,500,000 1,050,000 5,000,000 1,000,000 8,120,000 5,000,000 1,050,000 11,620,000 58 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE LEVEL OF SERVICE, SAFETY, AND CONNECTIVITY ON K Y-82 FROM KY-89 IN ESTILL CO. TO NEW CONSTRUCTION LOCATED NORTH OF HUDSON MILL ROAD IN ESTILL COUNTY. KY-82Estill PL205 DN 2,500,000 STP2 RW UT CN Project Cost: 0 2,500,000 0 I MPROVE SAFETY ON KY-2459 (CARHARTT AVE.) FROM KY-89 TO THE RAILROAD BRIDGE. (2020CCR) KY-2459Estill PL206 DN 520,000 STP2 RW UT CN Project Cost: 0 520,000 0 B RIDGE PROJECT IN ESTILL COUNTY ON (033B00017N) KY-52 AT DROWNING CREEK KY-52Estill PL10050 DN 402,000 FBP RW UT CN 4,020,000 FBP Project Cost: 402,000 4,020,000 0 T otal for Estill county PL Total Amounts: CN UT RW DN 402,000 3,020,000 4,020,000 402,000 7,040,000 0 I MPROVE NEW CIRCLE ROAD FROM LEESTOWN ROAD TO NEAR GEORGETOWN ROAD, INCLUDING CONSTRUCTION OF SOUND WALLS. (12CCR)(14CCR)(18CCR)(2020CCR) KY-4Fayette PL113.0200 DN RW 2,750,000 NH UT 8,000,000 NH CN 5,000,000 NH Project Cost: 2,750,000 8,000,000 5,000,000 59 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Lexington-Georgetown; Reconstruct/Widen US 25 from Kearney Road t o Ironworks Road. (Section 2) US-25Fayette PL122.3000 DN RW 2,200,000 SPP UT 9,640,000 SPP CN Project Cost: 0 2,200,000 9,640,000 V ARIOUS 'SLX' CONTINUING PROGRAM PROJECTS (RIDESHARE/MOBILITY, AIR QUALITY PLANNING, TRAFFIC SIGNAL) FOR FY 2020. (LOCAL MATCH) (ALL WORK BY LFUCG) (FUNDING SUBJECT TO FISCAL CONSTRAINT PENDING MPO TIP). (2020CCR) CO-0Fayette PL227.0900 DN RW UT CN 756,000 756,000 756,000 SLX Project Cost: 756,000 756,000 756,000 DEDICATED FEDERAL-AID STP FUNDS EARMARKED FOR LEXINGTON U RBANIZED AREA AND SUBJECT TO MPO CONTROL FOR FY 2022 THROUGH FY 2028. (FUNDING SUBJECT TO FISCAL CONTRAINT PENDING MPO TIP) (2020CCR) CO-0F ayette PL227.1400 DN RW UT CN 6,516,387 6,661,834 6,810,191 SLX Project Cost: 6,516,387 6,661,834 6,810,191 I MPROVE NEWTOWN PIKE FROM KY-4 TO I-75. (16CCR)(18CCR) (2020CCR) KY-922Fayette PL252 DN RW UT CN 3,500,000 3,500,000 STPF Project Cost: 0 3,500,000 3,500,000 P LANNING STUDY TO EVALUATE POTENTIAL DETOUR ROUTES FOR THE CLAYS FERRY BRIDGE. I -75Fayette PL 200,000 SPP264 DN RW UT CN Project Cost: 0 0 200,000 60 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 CONSTRUCT CITATION BOULEVARD FROM RUSSELL CAVE ROAD TO N EWTOWN PIKE. CO-0F ayette PL265 DN RW UT CN 3,500,000 STPF Project Cost: 0 0 3,500,000 O PERATION OF VALLEY VIEW FERRY AT KY RIVER FOR FY 2022 THROUGH FY 2028. (12CCR)(18CCR) (2020CCR) KY-169, PF-9999 Fayette PL357.1700 DN RW UT CN 332,900 332,900 332,900 SPP Project Cost: 332,900 332,900 332,900 R EPLACE RJ CORMAN RAILROAD BRIDGE OVERPASS (MP 8.378), IMPROVE DRAINAGE AND TYPICAL SECTION ON US 27 (NORTH BROADWAY)(12CCR)(14CCR)(16CCR)(18CCN) (2020CCR) US-27Fayette PL412 DN RW 3,100,000 NH UT CN Project Cost: 0 0 3,100,000 R EDUCE CONGESTION ON KY-4 (NEW CIRCLE RD) FROM TRADE CENTER DR TO WOODHILL DR. KY-4Fayette PL438 DN 2,000,000 NH RW UT CN Project Cost: 0 2,000,000 0 P LANNING STUDY TO EVALUATE THE POTENTIAL FOR DEDICATED AUTOMATED OR CONNECTED VEHICLE (C/AV) LANES ON I-64 BETWEEN LEXINGTON AND LOUISVILLE. I -64Fayette PL 750,000 NH577 DN RW UT CN Project Cost: 0 0 750,000 61 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 EXTEND CITATION BLVD. (16CCN)F ayette PL8901 DN 900,000 NH RW 2,440,000 NH UT CN Project Cost: 900,000 0 2,440,000 I MPROVE LIBERTY ROAD FROM GRAFTONS MILL LANE TO NEW CIRCLE ROAD AND IMPROVE INTERSECTION WITH NEW CIRCLE ROAD. (16CCN)(18CCR) (2020CCR) KY-1927Fayette PL8902 DN RW 2,520,000 STPF UT CN Project Cost: 0 0 2,520,000 R EDUCE CONGESTION ON I-64/I-75 FROM NORTHERN SPLIT TO NEWTOWN PIKE (MP 115.200 – 117.665). SECTION 1 I -75Fayette PL8909.1000 DN RW UT 25,000 NH CN Project Cost: 0 0 25,000 REDUCE CONGESTION ON I-64/I-75 FROM NEWTOWN PIKE TO PARIS P IKE (MP 112.900 – 115.200). SECTION 2 I -75F ayette PL8909.2000 DN RW UT 110,000 NH CN 5,000,000 5,000,000 NH Project Cost: 0 5,110,000 5,000,000 R EDUCE CONGESTION ON I-64/I-75 FROM PARIS PIKE TO THE SOUTHERN SPLIT (MP 111.000 – 112.900). SECTION 3 I -75Fayette PL8909.3000 DN RW UT 800,000 NH CN 5,000,000 5,000,000 NH Project Cost: 800,000 5,000,000 5,000,000 62 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN FAYETTE COUNTY ON (034B00150R) I-75 AT D AVID FK-ELKHORN CREEK I -75Fayette PL10045 DN 163,000 FBP2 RW UT CN 1,630,000 FBP2 Project Cost: 0 1,793,000 0 A DDRESS CONDITION OF I-64 FROM MILEPOINT 82.2 TO MILEPOINT 89.480 I-64Fayette PL20011 DN 870,000 NHPM RW UT CN 8,700,000 NHPM Project Cost: 9,570,000 0 0 ADDRESS CONDITION OF I-75 FROM MILEPOINT 97.85 TO MILEPOINT 1 05.36 I-75F ayette PL22116 DN 850,000 NHPM RW UT CN 8,500,000 NHPM Project Cost: 0 0 9,350,000 ADDRESS CONDITION OF I-75 FROM MILEPOINT 105.36 TO MILEPOINT 1 07.453 I-75F ayette PL22117 DN 250,000 NHPM RW UT CN 2,500,000 NHPM Project Cost: 0 0 2,750,000 C ONSTRUCT A RIGHT TURN LANE HEADED WESTBOUND ON VIRGINIA AVE FROM US 27 AND CONSTRUCT A BUS TURNOUT SOUTH OF VIRGINIA AVE (2020CCN) US-27Fayette PL80112 DN RW UT CN 163,000 SPP Project Cost: 163,000 0 0 63 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS CONGESTION AND IMPROVE SAFETY ON US 60 FROM M ILEPOINT 12.41 TO MILEPOINT 16.37 BY WIDENING AND MODERNIZING US 60 FROM THE END OF THE FOUR-LANE SECTION NEAR POLO CLUB BLVD TO KY 859 (HALEY RD). (2020CCN) US-60Fayette PL80150 DN RW 1,400,000 STPF UT 1,410,000 STPF CN Project Cost: 0 1,400,000 1,410,000 A CCESS MANAGEMENT IMPROVEMENT ON US 27 (NICHOLASVILLE RD) AT KY 4 (NEW CIRCLE) INTERCHANGE. US-27Fayette PL80205 DN 1,000,000 STPF RW UT CN Project Cost: 0 1,000,000 0 P rovide a safe and efficient connection with access to I-64 from US 60 near the Hamburg area. Fayette PL 310,000 SPP80207 DN RW UT CN Project Cost: 310,000 0 0 T otal for Fayette county PL Total Amounts: CN UT RW DN 310,000 950,000 1,770,000 3,163,000 1,100,000 2,750,000 3,600,000 8,060,000 800,000 8,110,000 11,075,000 16,468,287 22,880,734 40,899,091 22,098,287 37,753,734 62,084,091 I NSTALL GUARDRAIL ON KY-111 IN FLEMING COUNTYKY-111Fleming PL4305 DN RW UT CN 64,000 GR Project Cost: 64,000 0 0 64 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 RESTORATION OF GRANGE CITY COVERED BRIDGE LOCATED ON K Y-111 BETWEEN FLEMINGSBURG AND GRANGE CITY. (14CCN) (2020CCN) PF-9999Fleming PL8804 DN RW UT CN 650,000 BRZ Project Cost: 650,000 0 0 S AFETY IMPROVEMENTS AND PAVEMENT REHAB EAST OF FLEMINGSBURG BYPASS TO KY 156. (2020CCN) KY-32Fleming PL8903 DN RW 1,440,000 SPP UT 2,400,000 SPP CN Project Cost: 0 1,440,000 2,400,000 W IDEN KY 801 FROM NEAR MMRC REGIONAL PARK TO KY 158 IN FLEMING CO. (16CCN)(18CCN) (2020CCR) KY-801Fleming PL8915 DN RW 2,320,000 STP2 UT 1,130,000 STP2 CN Project Cost: 0 2,320,000 1,130,000 I MPROVE SAFETY AND SIGHT DISTANCE ON KY-32 BEGINNING AT 0.4 MILES WEST OF FLEMING/ROWAN CO LINE AND ENDING 0.3 MILES EAST OF THE LINE.(18CCN) (2020CCR) KY-32Fleming PL80051 DN RW 1,400,000 SPP UT 990,000 SPP CN Project Cost: 0 0 2,390,000 R ECONSTRUCT KY 57 TO PROVIDE BETTER HORIZONTAL AND VERTICAL ALIGNMENT, WIDER SHOULDERS, AND EXTEND CLEAR ZONES (2020CCN) KY-57Fleming PL80103 DN 2,500,000 SPP RW UT CN Project Cost: 0 2,500,000 0 65 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 RECONSTRUCT KY 801 TO IMPROVE ALIGNMENT AND WIDEN IT TO A 2 LANE HIGHWAY WITH PASSING LANES (2020CCN) KY-801Fl eming PL80104 DN 2,500,000 SPP RW UT CN Project Cost: 0 2,500,000 0 T otal for Fleming county PL Total Amounts: CN UT RW DN 5,000,000 3,760,000 1,400,000 4,520,000 714,000 714,000 8,760,000 5,920,000 P RELIMINARY ENGINEERING AND ENVIRONMENTAL - MOUNTAIN PARKWAY EXTENSION: SALYERSVILLE TO PRESTONBURG; US-460 TO KY 404. (14CCN) KY-114Floyd PL1.0200 DN 10,000,000 NH RW UT CN Project Cost: 0 10,000,000 0 M OUNTAIN PARKWAY CORRIDOR: EXTEND THE FOUR LANE MOUNTAIN PARKWAY FROM THE MAGOFFIN/FLOYD COUNTY LINE TO THE HEAD OF LEFT FORK OF ABBOTT CREEK. KY-114Floyd PL1.2000 DN 3,750,000 NH RW UT CN Project Cost: 0 3,750,000 0 M OUNTAIN PARKWAY CORRIDOR: EXTEND THE FOUR LANE MOUNTAIN PARKWAY FROM THE HEAD OF LEFT FORK OF ABBOTT CREEK TO NEELEY BRANCH ROAD. (SEE 12-1.01 FOR PE & ENV) (14CCR)(16CCR) KY-114Floyd PL1.3000 DN 4,270,000 NH RW UT CN Project Cost: 0 4,270,000 0 66 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 MOUNTAIN PARKWAY CORRIDOR: EXTEND THE FOUR LANE M OUNTAIN PARKWAY FROM NEELEY BRANCH ROAD TO COUNTY ROAD 1386 AT PRESTONSBURG ELEMENTARY SCHOOL. (SEE 12-1.01 FOR PE & ENV)(14CCR)(16CCR) KY-114Floyd PL1.4000 DN 2,080,000 NH RW UT CN Project Cost: 0 0 2,080,000 M OUNTAIN PARKWAY CORRIDOR: EXTEND THE FOUR LANE MOUNTAIN PARKWAY FROM SALYERSVILLE TO PRESTONSBBURG. (FEDERAL GRANT FUNDING) CO-0Floyd PL1.6000 DN RW UT CN 25,000,000 IF Project Cost: 0 0 25,000,000 B RIDGE PROJECT IN FLOYD COUNTY ON (036B00040N) KY-2557 at Levisa Fork KY-2557Floyd PL1119 DN 140,000 BRX RW UT CN 1,400,000 BRX Project Cost: 0 1,540,000 0 I NSTALL GUARDRAIL ON KY-1929 IN FLOYD COUNTYKY-1929Floyd PL4336 DN RW UT CN 18,000 GR Project Cost: 0 18,000 0 I NSTALL GUARDRAIL ON KY-777 IN FLOYD COUNTYKY-777Floyd PL4337 DN RW UT CN 49,000 GR Project Cost: 0 49,000 0 67 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-194 IN FLOYD COUNTYK Y-194Floyd PL4354 DN RW UT CN 16,000 GR Project Cost: 0 16,000 0 I NSTALL GUARDRAIL ON KY-404 IN FLOYD COUNTYKY-404Floyd PL4355 DN RW UT CN 115,000 GR Project Cost: 0 115,000 0 I NSTALL GUARDRAIL ON KY-404 IN FLOYD COUNTYKY-404Floyd PL4356 DN RW UT CN 55,000 GR Project Cost: 0 55,000 0 I NSTALL GUARDRAIL ON KY-1100 IN FLOYD COUNTYKY-1100Floyd PL4371 DN RW UT CN 14,000 GR Project Cost: 0 0 14,000 I NSTALL GUARDRAIL ON KY-1427 IN FLOYD COUNTYKY-1427Floyd PL4372 DN RW UT CN 85,000 GR Project Cost: 0 0 85,000 68 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-1427 IN FLOYD COUNTYK Y-1427Floyd PL4373 DN RW UT CN 90,000 GR Project Cost: 0 0 90,000 I NSTALL GUARDRAIL ON KY-850 IN FLOYD COUNTYKY-850Floyd PL4374 DN RW UT CN 20,000 GR Project Cost: 0 0 20,000 I NSTALL GUARDRAIL ON KY-1086 IN FLOYD COUNTYKY-1086Floyd PL4385 DN RW UT CN 86,000 GR Project Cost: 0 0 86,000 I NSTALL GUARDRAIL ON KY-1750 IN FLOYD COUNTYKY-1750Floyd PL4386 DN RW UT CN 54,000 GR Project Cost: 0 0 54,000 I NSTALL GUARDRAIL ON KY-3385 IN FLOYD COUNTYKY-3385Floyd PL4387 DN RW UT CN 64,000 GR Project Cost: 0 0 64,000 69 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-404 IN FLOYD COUNTYK Y-404Floyd PL4388 DN RW UT CN 99,000 GR Project Cost: 0 0 99,000 I NSTALL GUARDRAIL ON KY-680 IN FLOYD COUNTYKY-680Floyd PL4389 DN RW UT CN 84,000 GR Project Cost: 0 0 84,000 I NSTALL GUARDRAIL ON KY-1498 IN FLOYD COUNTYKY-1498Floyd PL4472 DN RW UT CN 12,000 GR Project Cost: 12,000 0 0 B RIDGE PROJECT IN FLOYD COUNTY ON (036B00135N) KY-3 AT CSX RR & Levisa Fork KY-3Floyd PL10096 DN 615,000 FBP2 RW UT CN 6,150,000 FBP2 Project Cost: 0 6,765,000 0 B RIDGE PROJECT IN FLOYD COUNTY ON (036C00074N) Martha's Vineyard AT Bull Creek CR-1655Floyd PL10098 DN 38,000 BRZ RW UT CN 380,000 BRZ Project Cost: 0 38,000 380,000 70 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 CONSTRUCT NEW INTERSECTION ON US-23 AT THE ENTRANCE TO B ETSY LANE HIGH SCHOOL(18CCN) US-23Floyd PL80000 DN RW 400,000 NH UT 350,000 NH CN 1,650,000 NH Project Cost: 2,400,000 0 0 T otal for Floyd county PL Total Amounts: CN UT RW DN 18,813,000 2,080,000 400,000 350,000 1,662,000 7,803,000 25,976,000 2,412,000 26,616,000 28,056,000 I MPROVE SAFETY, TRUCK MOBILITY, AND REDUCE CONGESTION ALONG I-64 FROM DIRECTLY EAST OF US-127 TO US-60 SOUTH OF FRANKFORT. I -64Franklin PL551 DN 1,500,000 NH RW 750,000 NH UT 300,000 NH CN Project Cost: 1,500,000 1,050,000 0 C ONSTRUCT NEW PEDESTRIAN BRIDGE AT LOCATION OF OLD BROADWAY BRIDGE IN FRANKFORT. KY-3506Franklin PL805 DN RW UT CN 3,500,000 STPF Project Cost: 0 0 3,500,000 W IDEN I-64 TO 6 LANES FROM KY-395 TO KY-151.I -64Franklin PL2035.4000 DN 1,000,000 NH RW 250,000 NH UT 250,000 NH CN Project Cost: 1,000,000 0 500,000 71 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN FRANKLIN COUNTY ON (037B00038N) KY 1665 A T S BENSON CREEK KY-1665Franklin PL10041 DN 125,000 FBP2 RW UT CN 1,250,000 FBP2 Project Cost: 0 1,375,000 0 B RIDGE PROJECT IN FRANKLIN COUNTY ON (037B00052L) I-64 WB AT KENTUCKY RIVER I -64Franklin PL10042 DN 700,000 FBP2 RW UT CN 7,000,000 FBP2 Project Cost: 0 0 7,700,000 BRIDGE PROJECT IN FRANKLIN COUNTY ON (037B00052R) I-64 EB AT K ENTUCKY RIVER I -64F ranklin PL10043 DN 700,000 FBP2 RW UT CN 7,000,000 FBP2 Project Cost: 0 0 7,700,000 B RIDGE PROJECT IN FRANKLIN COUNTY ON (037B00074N) KY 676 (E-W CONN) AT KENTUCKY RIVER & KY 1263 KY-676Franklin PL10045 DN 4,435,000 FBP2 RW UT CN Project Cost: 0 0 4,435,000 B RIDGE PROJECT IN FRANKLIN COUNTY ON (037B00080N) KY 12 AT FLAT CREEK KY-12Franklin PL10046 DN 318,000 BRX RW UT CN 3,180,000 BRX Project Cost: 0 3,498,000 0 72 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADD A TURN LANE AT THE INTERSECTION OF KY 676 AND US 60 ( 2020CCN) US-60Franklin PL80105 DN 160,000 SPP RW 150,000 SPP UT 100,000 SPP CN 1,600,000 SPP Project Cost: 160,000 250,000 1,600,000 I mprove safety and reduce congestion on US 127 in Frankfort from I-64 to US 60 us-127Franklin PL 470,000 NH80201 DN RW UT CN Project Cost: 0 0 470,000 P rovide a new roadway from the I-64 WB off-ramp at US 127 to the East-West Connector (KY 676) to reduce congestion, improve safety and enhance mobility. Franklin PL 200,000 STP80212 DN 1,380,000 STP RW 1,110,000 STP UT 710,000 STP CN Project Cost: 0 1,580,000 1,820,000 T otal for Franklin county PL Total Amounts: CN UT RW DN 200,000 470,000 2,660,000 1,823,000 5,835,000 900,000 1,360,000 400,000 960,000 4,430,000 19,100,000 2,660,000 7,753,000 27,725,000 IMPROVE THE PURCHASE PARKWAY AT THE KENTUCKY/TENNESSEE L INE TO SOUTHWEST OF THE US-51 INTERCHANGE.(I-69 CORRIDOR IMPROVEMENT) JC-9003F ulton PL25 DN RW 2,500,000 NH UT 1,000,000 NH CN 10,000,000 NH Project Cost: 0 3,500,000 10,000,000 73 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE THE PURCHASE PARKWAY FROM SOUTHWEST OF THE U S-51 INTERCHANGE TO CARDINAL ROAD NEAR MAYFIELD INCLUDING THE KY-339 INTERCHANGE IN WINGO, KY. (I-69 CORRIDOR IMPROVEMENT) JC-9003Fulton PL26 DN RW UT CN 20,000,000 NH Project Cost: 0 20,000,000 0 OPERATION OF HICKMAN FERRY AT MISSISSIPPI RIVER FOR FY 2022 T HROUGH FY 2028. (12CCR) (2020CCR) KY-1354F ulton PL320.1700 DN RW UT CN 144,000 144,000 144,000 SPP Project Cost: 144,000 144,000 144,000 S AFETY IMPROVEMENT AT INTERSECTION OF KY-1099 AND KY-125. (14CCN)(18CCN) KY-1099Fulton PL8853 DN RW 500,000 STP2 UT 750,000 STP2 CN 1,700,000 STP2 Project Cost: 500,000 750,000 1,700,000 B RIDGE PROJECT IN FULTON COUNTY ON (038B00022N) KY-166 AT BAYOU DE CHIEN KY-166Fulton PL10115 DN 81,000 FBP RW UT CN 810,000 FBP Project Cost: 81,000 810,000 0 B RIDGE PROJECT IN FULTON COUNTY ON (038B00023N) KY-166 AT MUD CREEK KY-166Fulton PL10116 DN 82,000 FBP RW UT CN 820,000 FBP Project Cost: 82,000 820,000 0 74 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS CONDITION OF JULIAN M CARROLL PURCHASE PARKWAY F ROM MILEPOINT 0 TO MILEPOINT 1.78 JC-9003F ulton PL20002 DN 180,000 NHPM RW UT CN 1,800,000 NHPM Project Cost: 0 0 1,980,000 T otal for Fulton county PL Total Amounts: CN UT RW DN 163,000 180,000 500,000 2,500,000 1,750,000 144,000 21,774,000 13,644,000 807,000 26,024,000 13,824,000 ADDRESS CONDITION OF I-71 FROM MILEPOINT 53.433 TO MILEPOINT 5 6.673 I-71G allatin PL20021 DN 950,000 NHPM RW UT CN 9,500,000 NHPM Project Cost: 0 10,450,000 0 T otal for Gallatin county PL Total Amounts: CN UT RW DN 950,000 9,500,000 0 10,450,000 0 C ONSTRUCT WEST LANCASTER BYPASS. (2020CCN)US-27Garrard PL196.2000 DN 1,500,000 NH RW 4,750,000 NH UT CN Project Cost: 1,500,000 0 4,750,000 75 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE US-27 FROM WEST LANCASTER BYPASS TO KY-34. ( 2006BOPC) (16CCN)(18CCR) (2020CCR) US-27Garrard PL196.3000 DN 2,000,000 NH RW UT CN Project Cost: 0 0 2,000,000 C ONDUCT A PLANNING STUDY ON KY 52 FROM LANCASTER TO DANVILLE TO ASSIST WITH ROAD RECONSTRUCTION KY-52Garrard PL 750,000 SPP80212 DN RW UT CN Project Cost: 0 750,000 0 T otal for Garrard county PL Total Amounts: CN UT RW DN 750,000 1,500,000 2,000,000 4,750,000 1,500,000 750,000 6,750,000 A DDRESS DEFICIENCIES OF BRIDGE ON NORTH END OF DELANEY ROAD 0.1 MILE NORTH OF THE JUNCTION WITH US 25. 041C00016N (12CCN) (2020CCR) CR-1142Grant PL8716 DN RW UT CN 3,500,000 BRZ Project Cost: 0 0 3,500,000 A DDRESS DEFICIENCIES OF KY-22 BRIDGE OVER CLARKS CRK+BATON ROUGE R. (041B00011N) KY-22Grant PL10001 DN 50,000 BRX RW UT CN Project Cost: 0 0 50,000 76 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN GRANT COUNTY ON (041B00017N) KY-491 AT B ULLOCK CREEK KY-491Grant PL10038 DN 92,000 BRX RW UT CN 920,000 BRX Project Cost: 0 92,000 920,000 ADDRESS CONDITION OF I-75 FROM MILEPOINT 145.5 TO MILEPOINT 1 52.112 I-75G rant PL20024 DN 1,100,000 NHPM RW UT CN 11,000,000 NHPM Project Cost: 0 12,100,000 0 ADDRESS CONDITION OF I 75 FROM MILEPOINT 164.4 TO MILEPOINT 1 66.263 I-75G rant PL20028 DN 225,000 NHPM RW UT CN 2,250,000 NHPM Project Cost: 0 0 2,475,000 U pdating US-25 from KY 1994 to KY 491 north junction.US-25Grant PL80216 DN 4,606,000 SPP RW UT CN Project Cost: 0 4,606,000 0 T otal for Grant county PL Total Amounts: CN UT RW DN 5,798,000 275,000 11,000,000 6,670,000 0 16,798,000 6,945,000 77 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS DEFICIENCIES OF MARTIN ROAD BRIDGE OVER B RANCH-OBION CREEK. (042C00250N) CR-1214Graves PL10002 DN 25,000 BRZ RW UT CN 50,000 BRZ Project Cost: 75,000 0 0 B RIDGE PROJECT IN GRAVES COUNTY ON (042B00090N) US-45 AT JACKSON CREEK US-45Graves PL10128 DN 29,000 FBP2 RW UT CN 290,000 FBP2 Project Cost: 0 0 319,000 W IDEN KY 303 FROM MP 16.034 (EAST FARTHING ST) TO MP 16.807 (CHARLES DR) (2020CCN) KY-303Graves PL80103 DN RW 850,000 SPP UT 3,500,000 SPP CN Project Cost: 0 850,000 3,500,000 W IDEN KY 131 FROM MP 0 (KY 58) TO MP 4.555 (KY 483) (2020CCN)KY-131Graves PL80104 DN 1,500,000 SPP RW UT CN Project Cost: 0 1,500,000 0 U pgrade/Widen KY 121 bypass in Mayfield to four lanes.ky-121Graves PL80202 DN 500,000 SPP RW 250,000 SPP UT 500,000 SPP CN Project Cost: 500,000 250,000 500,000 T otal for Graves county PL Total Amounts: CN UT RW DN 525,000 1,500,000 29,000 1,100,000 4,000,000 50,000 290,000 575,000 2,600,000 4,319,000 78 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON US-62 IN GRAYSON COUNTYU S-62Grayson PL4308 DN RW UT CN 18,000 GR Project Cost: 18,000 0 0 I MPROVE US 62 FROM JUST EAST OF BEEHIVE CURVE TO KY224. CONSTRUCTION SEGMENT 2. US-62Grayson PL8502.2000 DN RW UT CN 5,250,000 SPP Project Cost: 0 0 5,250,000 E XTEND THE WILLIAM THOMASON BYWAY (KY 3155) FROM THE SOUTHERN INTERSECTION AT KY 259 WESTERLY TO KY 54. (16CCN)(18CCN)(2020CCR) PF-9999Grayson PL8954 DN RW UT CN 10,500,000 STP Project Cost: 0 10,500,000 0 B RIDGE PROJECT IN GRAYSON COUNTY ON (043B00001N) KY-259 AT ROUGH RIVER KY-259Grayson PL10047 DN 410,000 FBP2 RW UT CN 4,100,000 FBP2 Project Cost: 0 0 4,510,000 B RIDGE PROJECT IN GRAYSON COUNTY ON (043B00053N) KY-79 AT ROUGH RIVER LAKE KY-79Grayson PL10048 DN 80,000 FBP RW UT CN 800,000 FBP Project Cost: 0 880,000 0 79 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS PAVEMENT CONDITION OF WENDELL H. FORD WESTERN K Y PARKWAY CARDINAL DIRECTION(S) FROM MILEPOINT 111.25 TO MILEPOINT 114.80. (COMBINED W/4-20002) WK-9001Grayson PL20001 DN 100,000 NHPM RW UT CN 1,000,000 NHPM Project Cost: 1,100,000 0 0 A DDRESS CONDITION OF WENDELL H. FORD WESTERN KENTUCKY PARKWAY FROM MILEPOINT 111.25 (112.400 NON-CARDINAL) TO MILEPOINT 114.80. WK-9001Grayson PL20002 DN 670,000 NHPM RW UT CN 6,700,000 NHPM Project Cost: 7,370,000 0 0 A DDRESS CONDITION OF WENDELL H. FORD WESTERN KENTUCKY PARKWAY FROM MILEPOINT 114.8 TO MILEPOINT 116.949 WK-9001Grayson PL20003 DN 150,000 NHPM RW UT CN 1,500,000 NHPM Project Cost: 0 1,650,000 0 A DDRESS CONNECTIVITY, MOBILITY, AND SAFETY CONCERNS ON THE WEST SIDE OF LEITCHFIELD FROM KY 54 TO THE NORTHERN INTERSECTION OF KY 259 AND KY 3155 (2020CCN) PF-9999Grayson PL80100 DN 2,000,000 SPP RW UT CN Project Cost: 0 2,000,000 0 ADDRESS SAFETY, GOMETRIC DEFICIENCIES, AND MAINTENANCE I SSUES ALONG KY 259 FROM BEAR CREEK ROAD (MP 9.217) TO THE NORTHERN INTERSECTION OF BLOOMINGTON ROAD (MP 11.761) SOUTH OF LEITCHFIELD (2020CCN) KY-259G rayson PL80101 DN 1,560,000 SPP RW 1,730,000 SPP UT CN Project Cost: 0 1,560,000 1,730,000 80 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS SAFETY AND TURN MOVEMENTS ALONG WALLACE A VENUE (CS 1136) IN LEITCHFIELD FROM THE INTERSECTION WITH EAST CARROLL GIBSON BLVD TO THE WILLIAM THOMASON BYWAY (2020CCN) CS-1136Grayson PL80150 DN 500,000 SPP RW 650,000 SPP UT CN Project Cost: 0 500,000 650,000 T otal for Grayson county PL Total Amounts: CN UT RW DN 770,000 4,290,000 410,000 2,380,000 7,718,000 12,800,000 9,350,000 8,488,000 17,090,000 12,140,000 A DDRESS SAFETY, GEOMETRIC DEFICIENCIES AND MAINTENANCE ISSUES ALONG US 68 FROM THE METCALFE COUNTY LINE (MP 0.000) TO 1600 FEET WEST OF SOUTH THURLOW ROAD (MP 9.682) (2020CCN) US-68Green PL397.1100 DN 250,000 STP2 RW UT CN Project Cost: 0 250,000 0 A DDRESS SAFETY, GEOMETRIC DEFICIENCIES AND MAINTENANCE ISSUES ALONG US 68 FROM 1600 FEET WEST OF SOUTH THURLOW RD (MP 9.682) EXTENDING TO THE RUSSELL CREEK BRIDGE (MP 10.775) (3-203.00 STUDY RECOMMENDATION #11)(DESIGN UNDER 4-397)(2016BOP)(18CCN) (2020CCR) US-68Green PL397.1200 DN RW UT CN 4,100,000 STPF Project Cost: 4,100,000 0 0 CONSTRUCT NEW CONNECTOR ON THE EAST SIDE OF GREENSBURG B EGINNING NEAR THE US-61 AND US-68 INTERSECTION SOUTH OF TOWN AND EXTENDING TO KY 3535 ON THE NORTH SIDE OF GREENSBURG. (2020CCR) PF-9999G reen PL398 DN 1,040,000 STP RW UT CN Project Cost: 0 1,040,000 0 81 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Horizontal and vertical alignment spot improvement on US 68 in M etcalfe and Green Counties, north of Edmonton, between the intersections of US 68/745 and US 68/KY 729. (2020BOP) US-68Green PL8706.2000 DN RW 600,000 STPF UT 500,000 STPF CN 7,725,000 STPF Project Cost: 600,000 500,000 7,725,000 I MPROVE SAFETY AND MOBILITY ON KY-61 FROM PITMAN CREEK BRIDGE TO JUST NORTH OF KY323. (12CCN)(14CCR)(16CCR) (2020CCR) KY-61Green PL8712 DN RW 1,250,000 STPF UT 2,000,000 STPF CN 8,500,000 STPF Project Cost: 0 3,250,000 8,500,000 S POT IMPROVEMENTS & IMPROVE EXISTING ALIGNMENT ON KY 88 FROM 0.20 MILES WEST OF AKIN NARROWS OF PITMAN RD (MP 8.996) TO KY 61 (MP 11.232). (14CCN)(16CCR)(18CCN) (2020CCR) KY-88Green PL8853 DN 1,000,000 SPP RW 4,200,000 SPP UT CN Project Cost: 0 1,000,000 4,200,000 B RIDGE PROJECT IN GREEN COUNTY ON (044B00029N) KY-487 AT SOUTH FK RUSSELL CREEK KY-487Green PL10143 DN 37,000 FBP2 RW UT CN 370,000 FBP2 Project Cost: 0 0 407,000 I MPROVE SAFETY AND PASSING OPPORTUNITIES ALONG US 68 FROM KY 61 IN GREEN COUNTY TO KY 323 IN TAYLOR COUNTY. (2020CCN) US-68Green PL80102 DN RW 60,000 SPP UT 520,000 SPP CN 10,800,000 SPP Project Cost: 0 580,000 10,800,000 82 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS SAFETY BY IMPROVING EXISTING ALIGNMENT IN SPOTS A ND ADD PASSING LANES ALONG KY 210 FROM CAMPBELLSVILLE TO HODGENVILLE. MILEPOINTS 0-14.148 AND 6.994-16.613 AND 0-0.750 IN TAYLOR, LARUE, AND GREEN. (2020CCN) KY-210Green PL80154 DN RW 500,000 STPF UT CN Project Cost: 0 0 500,000 I MPROVE SAFETY AT THE INTERSECTION OF US-61 AND US-68 SOUTH OF GREENSBURG US-61Green PL80260 DN RW UT CN 250,000 SPP Project Cost: 0 250,000 0 T otal for Green county PL Total Amounts: CN UT RW DN 2,290,000 37,000 600,000 1,310,000 4,700,000 3,020,000 4,100,000 250,000 27,395,000 4,700,000 6,870,000 32,132,000 R ECONSTRUCT KY-2 FROM MP 13.2 TO US-23 (MP 17.2)(08CCN) (14CCR)(16CCR)(18CCN) KY-2Greenup PL132 DN RW 5,780,000 STPF UT CN Project Cost: 0 0 5,780,000 I NSTALL GUARDRAIL ON KY-827 IN GREENUP COUNTYKY-827Greenup PL4314 DN RW UT CN 19,000 GR Project Cost: 0 19,000 0 83 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-7 IN GREENUP COUNTYK Y-7Greenup PL4316 DN RW UT CN 53,000 GR Project Cost: 0 0 53,000 I NSTALL GUARDRAIL ON KY-7 IN GREENUP COUNTYKY-7Greenup PL4317 DN RW UT CN 32,000 GR Project Cost: 0 0 32,000 B RIDGE PROJECT IN GREENUP COUNTY ON (045B00064N) KY-8S AT OHIO RVR-CSX RR-CO.RD. KY-8Greenup PL10087 DN 330,000 FBP RW UT CN Project Cost: 0 0 330,000 T otal for Greenup county PL Total Amounts: CN UT RW DN 330,000 5,780,000 19,000 85,000 0 19,000 6,195,000 I MPROVE THE WESTBOUND LANES OF US-60 FROM KY-1957 TO 0.2 MILE WEST OF KY-6106 (12CCR)(14CCR)(18CCR)(2020CCR) US-60Hancock PL226 DN RW UT CN 7,880,000 STP2 Project Cost: 0 7,880,000 0 84 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-261 IN HANCOCK COUNTYK Y-261Hancock PL4305 DN RW UT CN 24,000 GR Project Cost: 0 24,000 0 I NSTALL GUARDRAIL ON KY-69 IN HANCOCK COUNTYKY-69Hancock PL4309 DN RW UT CN 33,000 GR Project Cost: 33,000 0 0 I NSTALL GUARDRAIL ON KY-69 IN HANCOCK COUNTYKY-69Hancock PL4318 DN RW UT CN 17,000 GR Project Cost: 17,000 0 0 T otal for Hancock county PL Total Amounts: CN UT RW DN 50,000 7,904,000 50,000 7,904,000 0 K Y 251 IMPROVEMENTS FROM KY 3005 TO KY 434.KY-251Hardin PL153.0100 DN RW UT CN 4,000,000 SPP Project Cost: 0 4,000,000 0 85 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS CONGESTION, SAFETY, AND MOBILITY ALONG US 31W F ROM VETERANS WAY IN ELIZABETHTOWN TO THE NORTH WILSON ROAD OVERPASS IN RADCLIFF. (2018BOP) US-31H ardin PL154.3000 DN 1,750,000 SPP RW UT CN Project Cost: 1,750,000 0 0 R econstruction of KY 1136 from KY 1868 to US 31W in Hardin County.KY-1136Hardin PL171 DN 1,250,000 STP2 RW 2,100,000 STP2 UT 2,080,000 STP2 CN 4,000,000 STP2 Project Cost: 1,250,000 4,180,000 4,000,000 EXTEND RING ROAD FROM THE WESTERN KENTUCKY PARKWAY TO I -65. (REQUIRES RELOCATION OF I-65 SOUTHBOUND COMMERCIAL VEHICLE MONITORING STATION, PROJECT 4-286.10) (12CCR)(14CCR) (2020CCN) PF-9999H ardin PL198 DN RW 4,000,000 STP2 UT 2,000,000 STP2 CN Project Cost: 0 0 6,000,000 I -65 SOUTHBOUND PORT OF ENTRY FOR A COMMERCIAL VEHICLE MONITORING STATION. I -65Hardin PL286.1000 DN 1,000,000 NH RW 100,000 NH UT CN Project Cost: 0 1,000,000 100,000 I NSTALL GUARDRAIL ON KY-210 IN HARDIN COUNTYKY-210Hardin PL4311 DN RW UT CN 18,000 GR Project Cost: 0 18,000 0 86 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE SAFETY, GEOMETRICS, DRAINAGE AND MAINTENANCE I SSUES ALONG KY-1357 (ST. JOHNS RD) FROM US-31W BYPASS TO KY-3005 (RING ROAD). (14CCN) KY-1357Hardin PL8801 DN RW UT CN 4,000,000 STP1 Project Cost: 0 0 4,000,000 B RIDGE PROJECT IN HARDIN COUNTY ON (047B00022N) US-62 AT SLOUGH OFF ROLLING FORK US-62Hardin PL10052 DN 402,000 BRX RW UT CN 4,020,000 BRX Project Cost: 0 4,422,000 0 BRIDGE PROJECT IN HARDIN COUNTY ON (047B00133L) INTERSTATE 6 5 NC AT ROLLING FORK RIVER I -65H ardin PL10055 DN RW UT CN 750,000 FBP Project Cost: 0 0 750,000 B RIDGE PROJECT IN HARDIN COUNTY ON (047B00133R) I-65 AT ROLLING FORK RIVER I -65Hardin PL10056 DN RW UT CN 750,000 FBP Project Cost: 0 0 750,000 A DDRESS CONDITION OF US-31W FROM MILEPOINT 27.745 TO MILEPOINT 30.263 US-31Hardin PL20013 DN 100,000 NHPM RW UT CN 1,000,000 NHPM Project Cost: 0 1,100,000 0 87 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Address safety, mobility, and access management, along with p otentially reconfiguring the interchange to I 65. US-62Hardin PL80200 DN 2,000,000 SPP RW UT CN Project Cost: 0 0 2,000,000 E XTEND RING ROAD FROM US 31W TO KY 61 (LINCOLN PARKWAY)KY-3005Hardin PL80250 DN 1,000,000 STPF RW UT CN Project Cost: 0 1,000,000 0 T otal for Hardin county PL Total Amounts: CN UT RW DN 3,000,000 2,502,000 2,000,000 2,100,000 4,100,000 2,080,000 2,000,000 9,038,000 9,500,000 3,000,000 15,720,000 17,600,000 IMPROVE MOBILITY ON US 421 FROM MILEPOINT 1.5 TO THE VIRGINIA S TATE LINE. (2020CCR) US-421H arlan PL269.1100 DN RW UT CN 7,000,000 NH Project Cost: 0 0 7,000,000 A DDRESS DEFICIENCIES OF BRIDGE ON US 119 OVER KY 160/MAIN ST IN HARLAN COUNTY, KY. 048B00126N (2020CCR) US-119Harlan PL1101 DN 800,000 BRO RW 200,000 BRO UT 100,000 BRO CN 6,000,000 BRO Project Cost: 800,000 300,000 6,000,000 88 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-3449 IN HARLAN COUNTYK Y-3449Harlan PL4323 DN RW UT CN 318,000 GR Project Cost: 318,000 0 0 I NSTALL GUARDRAIL ON KY-1601 IN HARLAN COUNTYKY-1601Harlan PL4331 DN RW UT CN 19,000 GR Project Cost: 0 19,000 0 I NSTALL GUARDRAIL ON KY-1601 IN HARLAN COUNTYKY-1601Harlan PL4332 DN RW UT CN 69,000 GR Project Cost: 0 69,000 0 I NSTALL GUARDRAIL ON KY-522 IN HARLAN COUNTYKY-522Harlan PL4343 DN RW UT CN 634,000 GR Project Cost: 0 634,000 0 I NSTALL GUARDRAIL ON KY-522 IN HARLAN COUNTYKY-522Harlan PL4344 DN RW UT CN 634,000 GR Project Cost: 0 634,000 0 89 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-2007 IN HARLAN COUNTYK Y-2007Harlan PL4353 DN RW UT CN 239,000 GR Project Cost: 0 0 239,000 I NSTALL GUARDRAIL ON KY-840 IN HARLAN COUNTYKY-840Harlan PL4354 DN RW UT CN 37,000 GR Project Cost: 0 0 37,000 B RIDGE PROJECT IN HARLAN COUNTY ON (048B00179N) KY-2007 at WALLINS CREEK KY-2007Harlan PL10015 DN 25,000 BRX RW UT CN 250,000 BRX Project Cost: 0 25,000 250,000 B RIDGE PROJECT IN HARLAN COUNTY ON (048C00067N) KENTUCKY AV at MARTINS FK CUMBERLAND RV CS-1041Harlan PL10018 DN 136,000 BRZ RW UT CN Project Cost: 0 136,000 0 B RIDGE PROJECT IN HARLAN COUNTY ON (048B00053N) KY-840 AT WATTS CREEK KY-840Harlan PL10099 DN 59,000 FBP2 RW UT CN 590,000 FBP2 Project Cost: 0 649,000 0 90 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN HARLAN COUNTY ON (048B00075N) KY-2007 A T CUMBERLAND RIVER KY-2007Harlan PL10190 DN 321,000 FBP RW UT CN 3,210,000 FBP Project Cost: 3,531,000 0 0 B RIDGE PROJECT IN HARLAN COUNTY ON (048B00091N) KY-1254 AT POOR FK CUMBERLAND RVR KY-1254Harlan PL10191 DN 351,000 FBP RW UT CN 3,510,000 FBP Project Cost: 3,861,000 0 0 B RIDGE PROJECT IN HARLAN COUNTY ON (048B00095N) KY-72 AT CLOVER FK CUMBERLAND RVR KY-72Harlan PL10192 DN 594,000 FBP2 RW UT CN 5,940,000 FBP2 Project Cost: 6,534,000 0 0 B RIDGE PROJECT IN HARLAN COUNTY ON (048B00107N) US-119 AT POOR FK CUMBERLAND RVR US-119Harlan PL10194 DN RW UT CN 5,000,000 FBP Project Cost: 0 0 5,000,000 B RIDGE PROJECT IN HARLAN COUNTY ON (048B00117N) US-119 AT POOR FK CUMBERLAND RVR US-119Harlan PL10195 DN RW UT CN 4,000,000 FBP Project Cost: 0 0 4,000,000 91 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN HARLAN COUNTY ON (048B00138N) KY-72 AT P OOR FK CUMBERLAND RVR KY-72Harlan PL10196 DN 258,000 FBP2 RW UT CN 2,580,000 FBP2 Project Cost: 2,838,000 0 0 C ONSTRUCT A LEFT AND RIGHT TURN LANE ON KY 221 AT THE ENTRANCE OF GREEN HILLS ELEMENTARY SCHOOL (MILEPOINT 8.6 TO MILEPOINT 8.8) KY-221Harlan PL80255 DN RW UT CN 150,000 SPP Project Cost: 0 0 150,000 C ONSTRUCT A RIGHT TURNING LANE AT INTERSECTION OF KY 522 AND US 199W TO IMPROVE SAFETY AND ACCESS TO ROSS POINT SCHOOL KY-522Harlan PL80256 DN RW UT CN 22,000 SPP Project Cost: 0 22,000 0 I MPROVE SAFETY ALONG KY 38 BY REMOVING TRESS ALONG MILEPOINT 8.6 TO MILEPOINT 9.6 KY-38Harlan PL80258 DN RW 100,000 SPP UT CN 1,200,000 SPP Project Cost: 0 1,300,000 0 S POT IMPROVEMENTS TO IMPROVE GEOMETRICS AT PARTICULAR LOCATIONS OF US 421 CROSSING OVER PINE MOUNTAIN BETWEEN US 119 AND KY 221 IN HARLAN COUNTY TO ADDRESS SAFETY CONCERNS. MILEPOINT 17.2 TO MILEPOINT 23.0 US-421Harlan PL80259 DN 750,000 STP RW UT CN Project Cost: 0 750,000 0 T otal for Harlan county PL Total Amounts: CN UT RW DN 2,324,000 970,000 300,000 100,000 15,558,000 3,168,000 22,676,000 17,882,000 4,538,000 22,676,000 92 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN HARRISON COUNTY ON (049C00035N) OLD LAIR R D at S FK LICKING RIVER CR-1124H arrison PL1093 DN 280,000 BRZ RW UT CN 2,800,000 BRZ Project Cost: 0 3,080,000 0 I NSTALL GUARDRAIL ON KY-32 IN HARRISON COUNTYKY-32Harrison PL4307 DN RW UT CN 43,000 GR Project Cost: 0 43,000 0 I NSTALL GUARDRAIL ON US-27 IN HARRISON COUNTYUS-27Harrison PL4309 DN RW UT CN 11,000 GR Project Cost: 0 11,000 0 I NSTALL GUARDRAIL ON US-27 IN HARRISON COUNTYUS-27Harrison PL4310 DN RW UT CN 11,000 GR Project Cost: 0 11,000 0 I NSTALL GUARDRAIL ON US-27 IN HARRISON COUNTYUS-27Harrison PL4311 DN RW UT CN 11,000 GR Project Cost: 0 11,000 0 93 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON US-27 IN HARRISON COUNTYU S-27Harrison PL4312 DN RW UT CN 11,000 GR Project Cost: 0 11,000 0 R ECONSTRUCT US 27 FROM MP 11.9 TO MP 12.4. (12CCN)(14CCR) (18CCN) US-27Harrison PL8708 DN RW 480,000 SPP UT CN Project Cost: 0 0 480,000 C ONSTRUCT A CONNECTOR ROAD BETWEEN OLD LAIR ROAD AND KY 982 (NEW LAIR ROAD) NEAR THE HARRISON COUNTY HIGH SCHOOL. PF-9999Harrison PL80251 DN 1,250,000 SPP RW UT CN Project Cost: 0 1,250,000 0 C ONSTRUCT A ROUNDABOUT AT THE INTERSECTION OF WEBSTER AVENUE (CS-1071) AND EDUCATION DRIVE. CS-1071Harrison PL80252 DN 125,000 SPP RW UT CN Project Cost: 0 125,000 0 T otal for Harrison county PL Total Amounts: CN UT RW DN 1,655,000 480,000 2,887,000 0 4,542,000 480,000 94 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE MOBILITY, CONNECTIVITY AND SAFETY BY ADDRESSING C OMMERCIAL AND INDUSTRIAL TRAFFIC MOVEMENT FROM US-31W SOUTH OF KY-218 TO I-65. (16CCR)(18CCR) KY-335Hart PL441 DN RW UT CN 6,240,000 STP2 Project Cost: 0 6,240,000 0 I NSTALL GUARDRAIL ON KY-1140 IN HART COUNTYKY-1140Hart PL4312 DN RW UT CN 43,000 GR Project Cost: 0 0 43,000 T otal for Hart county PL Total Amounts: CN UT RW DN 6,240,000 43,000 0 6,240,000 43,000 I mprove the intersection of Watson Lane (CS-1372) and US 41.CS-1372Henderson PL383.1000 DN RW UT CN 2,840,000 STP1 Project Cost: 0 0 2,840,000 A ddress safety and congestion along Watson Lane (CR-1372).CS-1372Henderson PL383.2000 DN RW UT CN 2,000,000 STP1 Project Cost: 0 2,000,000 0 95 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 FEDERAL 'STP' FUNDS DEDICATED TO HENDERSON FOR FY 2 022-2028. (FUNDING SUBJECT TO FISCAL CONSTRAINT PENDING MPO TIP). (2020CCR) CO-0Henderson PL700.1500 DN RW UT CN 851,078 868,100 885,462 SHN Project Cost: 851,078 868,100 885,462 W ORK WITH INDOT TO DEVELOP A BI-STATE PACKAGE FOR THE DELIVERY OF THE PORTION OF THE PROJECT FROM US 60 NORTH TO I-69 IN EVANSVILLE. (COSTS SHARED BY KY AND IN)(KY FEDERAL GRANT FUNDING) PF-9999Henderson PL1088.5000 DN 5,000,000 NH RW UT CN Project Cost: 0 0 5,000,000 B RIDGE PROJECT IN HENDERSON COUNTY ON ( 051B00002R/051B00007L) US-41 AT OHIO RIVER US-41Henderson PL2091.1000 DN RW UT CN 2,000,000 BRX Project Cost: 0 0 2,000,000 I NSTALL GUARDRAIL ON KY-2183 IN HENDERSON COUNTYKY-2183Henderson PL4306 DN RW UT CN 63,000 GR Project Cost: 0 63,000 0 BRIDGE PROJECT IN HENDERSON COUNTY ON (051B00119N) KY-145 A T BEAVER DAM CREEK KY-145H enderson PL10091 DN 39,000 FBP2 RW UT CN 390,000 FBP2 Project Cost: 0 0 429,000 96 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN HENDERSON COUNTY ON (051B00128N) KY-812 A T NORTH FORK CANOE CREEK KY-812H enderson PL10092 DN 143,000 FBP2 RW UT CN 1,430,000 FBP2 Project Cost: 0 1,573,000 0 ADDRESS CONDITION OF I 69 FROM MILEPOINT 142.33 TO MILEPOINT 1 48.090 I-69H enderson PL20023 DN 980,000 NHPM RW UT CN 9,800,000 NHPM Project Cost: 10,780,000 0 0 E XTEND I-69 TO KY 351 AND AUDUBON PARKWAY INTERCHANGE UPGRADE AT HEBBARDSVILLE. (2020CCN) CO-0Henderson PL 250,000 SPP80104 DN RW UT CN Project Cost: 250,000 0 0 T otal for Henderson county PL Total Amounts: CN UT RW DN 250,000 980,000 143,000 5,039,000 10,651,078 4,361,100 6,115,462 11,881,078 4,504,100 11,154,462 B RIDGE PROJECT IN HENRY COUNTY ON (052B00062N) KY 1861 AT JACKSON CREEK KY-1861Henry PL10049 DN 36,000 FBP2 RW UT CN 360,000 FBP2 Project Cost: 0 0 396,000 97 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS CONDITION OF I-71 FROM MILEPOINT 29.112 TO MILEPOINT 3 8.086 I-71H enry PL22099 DN 700,000 NHPM RW UT CN 7,000,000 NHPM Project Cost: 0 0 7,700,000 B ridge repairs on five (5) KY 146 bridges between KY 153 (MP 2.169) and US 421 (MP 9.80) at New Castle, Kentucky.”(Bridge Numbers: 052B00068N; 052B00030N; 052B00074N; 052B00065N; 052B00027N) KY-146Henry PL80260 DN RW UT CN 2,000,000 FBP Project Cost: 0 0 2,000,000 T otal for Henry county PL Total Amounts: CN UT RW DN 736,000 9,360,000 0 0 10,096,000 B RIDGE PROJECT IN HICKMAN COUNTY ON (053B00002N) US-51 AT BRUSH CREEK US-51Hickman PL10144 DN 45,000 FBP2 RW UT CN 450,000 FBP2 Project Cost: 0 0 495,000 B RIDGE PROJECT IN HICKMAN COUNTY ON (053B00029N) US-51 AT CANE CREEK US-51Hickman PL10146 DN 43,000 FBP2 RW UT CN 430,000 FBP2 Project Cost: 0 0 473,000 98 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN HICKMAN COUNTY ON (053B00102N) KY-1283 A T JACKSON PURCHASE PARKWAY KY-1283Hickman PL10151 DN 471,000 FBP RW UT CN 4,710,000 FBP Project Cost: 471,000 0 4,710,000 C orrect geometric deficiencies and improve safety, access, and regional connectivity from Clayton Street to KY-703 in Clinton. us-51Hickman PL80203 DN 1,000,000 STP RW 1,500,000 STP UT CN Project Cost: 1,000,000 0 1,500,000 T otal for Hickman county PL Total Amounts: CN UT RW DN 1,471,000 88,000 1,500,000 5,590,000 1,471,000 0 7,178,000 I MPROVE KY-281 FROM ISLAND PARK DRIVE TO 0.25 MI NORTH OF CARRIAGE LANE (KY-2281). KY-281Hopkins PL384 DN 750,000 STP2 RW UT CN Project Cost: 0 750,000 0 E xtend Midtown Blvd from CSX Railroad to Whittington Drive, 500’ south of Commerce Drive. PF-9999Hopkins PL804.3000 DN 700,000 SPP RW 500,000 SPP UT 1,200,000 SPP CN Project Cost: 700,000 500,000 1,200,000 99 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Reconstruct Whittington Drive beginning 500’ south of Commerce Drive a nd ending at the intersection of Whittington Drive and Island Ford Road (KY 281), including the reconstruction of the KY 281 intersection. CS-1287Hopkins PL804.4000 DN RW 2,000,000 SPP UT 1,500,000 SPP CN Project Cost: 0 2,000,000 1,500,000 I NSTALL GUARDRAIL ON KY-85 IN HOPKINS COUNTY (2020CCR)KY-85Hopkins PL4311 DN RW UT CN 64,000 GR Project Cost: 64,000 0 0 I NSTALL GUARDRAIL ON US-0041 IN HOPKINS COUNTY (2020CCR)US-41Hopkins PL4316 DN RW UT CN 64,000 GR Project Cost: 64,000 0 0 I MPROVE NORTH MAIN STREET FROM HOSPITAL DRIVE TO KY-281. (06CCN)(12CCR)(18CCR) US-41Hopkins PL8305 DN RW 2,000,000 STP1 UT 1,280,000 STP1 CN 4,000,000 SPP Project Cost: 3,280,000 0 4,000,000 B RIDGE PROJECT IN HOPKINS COUNTY ON (054B00009N) KY-138 at POND RIVER KY-138Hopkins PL10024 DN 730,000 FBP RW UT CN 7,300,000 FBP Project Cost: 730,000 0 7,300,000 100 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN HOPKINS COUNTY ON (054B00089N) KY-70 AT R ICHLAND CREEK KY-70Hopkins PL10099 DN 239,000 FBP RW UT CN 2,390,000 FBP Project Cost: 239,000 0 2,390,000 B RIDGE PROJECT IN HOPKINS COUNTY ON (054B00118N) KY-1033 AT BR OF OTTER CREEK KY-1033Hopkins PL10100 DN 39,000 FBP RW UT CN 390,000 FBP Project Cost: 39,000 390,000 0 B RIDGE PROJECT IN HOPKINS COUNTY ON (054B00119N) KY-1033 AT OTTER CREEK KY-1033Hopkins PL10101 DN 150,000 FBP RW UT CN 1,500,000 FBP Project Cost: 150,000 0 1,500,000 B RIDGE PROJECT IN HOPKINS COUNTY ON (054B00126N) KY-502 AT CLEAR CREEK OVERFLOW KY-502Hopkins PL10104 DN 144,000 BRX RW UT CN 1,440,000 BRX Project Cost: 0 144,000 1,440,000 B RIDGE PROJECT IN HOPKINS COUNTY ON (054B00127N) KY-502 AT CLEAR CREEK OVERFLOW KY-502Hopkins PL10105 DN 142,000 BRX RW UT CN 1,420,000 BRX Project Cost: 0 142,000 1,420,000 101 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN HOPKINS COUNTY ON (054B00128N) KY-502 AT C LEAR CREEK OVERFLOW KY-502Hopkins PL10106 DN 144,000 BRX RW UT CN 1,440,000 BRX Project Cost: 0 144,000 1,440,000 B RIDGE PROJECT IN HOPKINS COUNTY ON (054B00204N) KY-2280 AT ROSE CREEK KY-2280Hopkins PL10108 DN 155,000 FBP2 RW UT CN 1,550,000 FBP2 Project Cost: 0 1,705,000 0 A DDRESS CONDITION OF I-69 FROM MILEPOINT 113.81 (114.240 CARDINAL) TO MILEPOINT 118.15 I-69Hopkins PL20029 DN 950,000 NHPM RW UT CN 9,500,000 NHPM Project Cost: 0 0 10,450,000 ADDRESS CONDITION OF I-69 FROM MILEPOINT 95.604 TO MILEPOINT 1 05.046 I-69H opkins PL20034 DN 1,720,000 NHPM RW UT CN 17,200,000 NHPM Project Cost: 18,920,000 0 0 A DDRESS CONDITION OF I-69 FROM MILEPOINT 105.046 TO MILEPOINT 107.08 I-69Hopkins PL22086 DN 150,000 NHPM RW UT CN 1,500,000 NHPM Project Cost: 0 0 1,650,000 102 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 CONSTRUCT A 3 LANE CURB, GUTTER AND SIDEWALK ROADWAY F ROM THE END OF MIDTOWN BLVD. TO THE INTERSECTION OF COMMERCE DR. AND WHITTINGTON DR. (2020CCN) PF-9999Hopkins PL80102 DN 400,000 SPP RW UT CN Project Cost: 0 400,000 0 I MPROVE US 41A BEGINNING AT INDUSTRIAL DR AT HOPKINS CO ENDING AT PROVIDENCE CO-0, US-41Hopkins PL80105 DN 2,600,000 SPP RW UT CN Project Cost: 0 2,600,000 0 T otal for Hopkins county PL Total Amounts: CN UT RW DN 3,578,000 4,335,000 1,100,000 2,000,000 2,500,000 1,280,000 2,700,000 17,328,000 1,940,000 30,490,000 24,186,000 8,775,000 34,290,000 I NSTALL GUARDRAIL ON US-421 IN JACKSON COUNTYUS-421Jackson PL4324 DN RW UT CN 31,000 GR Project Cost: 31,000 0 0 R EPLACE BRIDGE (063C00044N) ON MT ZION CHURCH ROAD (CR 1414). (16CCN) (2020CCR) CR-1340, CR-1414 Jackson PL8953 DN RW 100,000 BRZ UT 100,000 BRZ CN 1,300,000 BRZ Project Cost: 200,000 1,300,000 0 103 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN JACKSON COUNTY ON (055B00001N) US-421 A T INDIAN CREEK US-421Jackson PL10198 DN 46,000 FBP2 RW UT CN 460,000 FBP2 Project Cost: 0 0 506,000 A DDRESS SUBSTARNDARD HORIZONTAL AND VERTICAL ALIGNMENT OF US 421 IN THE CLOVER BOTTOM AREA NEAR THE STONE QUARRY. (2020CCN) US-421Jackson PL80104 DN RW 495,000 SPP UT 417,000 SPP CN 3,032,000 SPP Project Cost: 912,000 3,032,000 0 A DDRESS SAFETY ISSUES WITH VERTICAL AND HORIZONTAL ALIGNMENT ON US 421 FROM MP 11.6 EAST OF PILGRIMS REST RD TO MP 12.6 (2020CCN) US-421Jackson PL80105 DN 1,000,000 SPP RW 1,000,000 SPP UT CN Project Cost: 0 1,000,000 1,000,000 A DDRESS SAFETY AND HORIZONTAL ALIGNMENT OF THE CURVE ON US 421 WITH ITS INTERSECTION AT KY 3443 (2020CCN) US-421Jackson PL80106 DN RW 64,000 SPP UT 547,000 SPP CN Project Cost: 64,000 547,000 0 A ddress congestion, capacity, connectivity, and safety issues on KY 290 from McKee to Ky 30. KY-290Jackson PL 748,800 SPP80202 DN RW UT CN Project Cost: 748,800 0 0 104 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 MOVE KY 578 OVER 10FT FOR IMPROVED SIGHT DISTANCE AND C REATE A BETTER APPROACH FOR MOORE CREEK GREEN HILL ROAD KY-578Jackson PL80261 DN RW 40,000 SPP UT 30,000 SPP CN 793,370 SPP Project Cost: 0 70,000 793,370 T otal for Jackson county PL Total Amounts: CN UT RW DN 748,800 1,000,000 46,000 659,000 40,000 1,000,000 517,000 577,000 31,000 4,332,000 1,253,370 1,955,800 5,949,000 2,299,370 ADDITION OF NB AND SB AUXILIARY LANES ON I-71 NEAR K ENNEDY, INCLUDING OPERATIONAL IMPROVEMENTS TO THE ZORN INTERCHANGE. (2004BOPC) I -71J efferson PL48.1000 DN RW 150,000 NH UT CN Project Cost: 0 0 150,000 BRIDGE PROJECT IN JEFFERSON COUNTY ON (056B00279N) I-64 S HERMAN MINTON BRIDGE OVER OHIO RIVER. (JOINT PROJECT WITH INDIANA) I -64J efferson PL64 DN 1,600,000 1,600,000 BRO RW UT CN 16,000,000 16,000,000 BRO Project Cost: 0 17,600,000 17,600,000 MAJOR REVISION OF THE INTERSECTION LOCATED AT THE OUTER L OOP, FEGENBUSH LANE, AND BEULAH CHURCH ROAD. TURN LANE TO BE COMPLETED BY TRANSPORTATION CABINET PER AGREEMENT. (04CCN)(08CCR)(10CCR)(12CCR) (2020CCN) CR-1005, K Y-1065, KY-864 Jefferson PL122 DN RW UT CN 6,222,400 STPF Project Cost: 6,222,400 0 0 105 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 CLEAN AND PAINT ALL STEEL BRIDGES AND STEEL BEARINGS ON T HE GENE SNYDER FREEWAY(10CCR)(SD) PF-9999Jefferson PL136 DN RW UT CN 6,000,000 BRO Project Cost: 6,000,000 0 0 T RAFFIC CALMING MEASURES FOR SHELBY PARK AND SMOKETOWN NEIGHBORHOODS IN LOUISVILLE. (2020CCR) CO-0Jefferson PL193 DN RW UT CN 3,000,000 SPP Project Cost: 3,000,000 0 0 W IDEN GREENWOOD ROAD FROM GREENBELT HWY TO DIXIE HWY (US-31W) (3-LANE IMPROVEMENT) FROM MP 0.54 TO MP 3.148. (98CCR)(R-04DEOB)(04CCR)(BOP2006P)(10CCR)(12CCR) (2020CCR) KY-1931Jefferson PL323.0100 DN RW UT CN 4,000,000 STPF Project Cost: 0 0 4,000,000 E XTENSION OF OLD HENRY ROAD EAST TO ASH AVENUE (KY362). (12CCR)(18CCN) (2020CCR) CO-0, KY-146, PF-9999 Jefferson PL367.2000 DN RW UT CN 6,700,000 STPF Project Cost: 0 0 6,700,000 R ECONSTRUCT KY-22 AT SPRINGCREST DRIVE. (06CCN) (2004BOPC)(14CCR) (EMERGENCY CULVERT REPLACEMENT AWARDED UNDER 5-371.12) (2020CCR) KY-22Jefferson PL371.1000 DN RW UT CN 2,020,000 STPF Project Cost: 2,020,000 0 0 106 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Study traffic patterns in the vicinity of the new VA Medical Center at t he I-264/US-42 interchange in Louisville. CO-0Jefferson PL 250,000 SPP379 DN RW UT CN Project Cost: 0 250,000 0 R ECONSTRUCT/WIDEN I-264 (WATTERSON EXPRESSWAY) FROM WESTPORT ROAD (KY-1447) TO I-71, INCLUDING THE US-42 INTERCHANGE AS A SPUI.(PROJECT INCLUDES 5-594) I -264Jefferson PL804 DN RW UT CN 10,000,000 NH Project Cost: 0 0 10,000,000 SAFETY PROJECT FOR RECONSTRUCTION OF TAYLORSVILLE ROAD A ND SOUTH POPE LICK ROAD INTERSECTION AND BRIDGE OVER POPE LICK CREEK. (2016BOP) (2020CCR) KY-155J efferson PL808 DN RW UT CN 6,450,000 BRX Project Cost: 0 6,450,000 0 DEDICATED FEDERAL AID STP FUNDS EARMARKED FOR LOUISVILLE U RBANIZED AREA AND SUBJECT TO MPO CONTROL FOR FY 2022-2028. (FUNDING SUBJECT TO FISCAL CONSTRAINT PENDING MPO TIP). (2020CCR) CO-0J efferson PL965.1900 DN RW UT CN 24,784,266 25,279,952 25,785,551 SLO Project Cost: 24,784,266 25,279,952 25,785,551 ADDRESS DEFICIENCIES OF BRIDGE ON E KENTUCKY ST (CS 1017G) OVER SOUTH FORK BEARGRASS CREEK 0.01 MILE E OF SCHILLER AVE (CS 1138G) 056C00083N (2020CCR) CS-1017J efferson PL1070 DN RW UT CN 3,600,000 BRX Project Cost: 3,600,000 0 0 107 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN JEFFERSON COUNTY ON (056C00130N) RIVER R D AT GOOSE CREEK CR-1001Jefferson PL1079 DN 380,000 BRZ RW UT CN Project Cost: 0 380,000 0 W IDEN BUECHEL BANK ROAD TO 3 LANES FROM GE APPLIANCE PARK TO BUECHEL BY-PASS (00CCN) (FUNDING MOVED FROM 5-8105 IN 2010 ENACTED HIGHWAY PLAN FOR R, U, AND C PHASES.)(12CCR) CR-1007Jefferson PL8001 DN RW UT 800,000 SPP CN Project Cost: 800,000 0 0 R ECONSTRUCT BILLTOWN ROAD FROM NORTH OF COLONNADES PLACE TO SOUTH OF EASUM ROAD. (04CCN)(06CCN)(08CCR) (10CCR)(12CCR) (2020CCR) KY-1819Jefferson PL8203 DN RW UT CN 3,280,000 SPP Project Cost: 0 3,280,000 0 THREE LANE WIDENING ALONG KY-1931 FROM THE DOSS HIGH S CHOOL ENTRANCE TO PALATKA ROAD, INCLUDING INTERSECTION IMPROVEMENTS WITH PALATKA ROAD AND TURN LANES. (14CCN) (2020CCR) KY-1931J efferson PL8810 DN RW 2,770,000 STPF UT 4,330,000 STPF CN Project Cost: 0 2,770,000 4,330,000 W IDEN TAYLORSVILLE ROAD TO 3 LANES FROM I-265 TO KY-148. (18CCN) KY-155Jefferson PL8908 DN 580,000 STPF RW 2,500,000 STPF UT 500,000 STPF CN Project Cost: 580,000 0 3,000,000 108 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 WIDEN US 60 INCLUDING REALLIGNMENT OF GILLILAND ROAD AND E ASTWOOD CUTOFF (MP 14.7) TO ROCKCREST WAY (MP 15.1). LOCALS WILL DO DESIGN FOR $330,000. (16CCN)(18CCR)(2020CCR) US-60Jefferson PL8952 DN 200,000 NH RW 975,000 NH UT 605,000 NH CN 1,050,000 NH Project Cost: 1,780,000 1,050,000 0 C ONSTRUCT A 2+1 ROAD ON KY 55/155 (TAYLORSVILLE ROAD) IN SPENCER COUNTY AND KY 155 (TAYLORSVILLE LAKE ROAD) IN JEFFERSON COUNTY BY ADDING A CONTINUOUS THIRD LANE THAT SERVES AS AN ALTERNATING PASSING LANE.(16CCN)(18CCN) (2020CCR) KY-155, KY-55 Jefferson PL8954 DN 470,000 STPF RW 40,000 STPF UT 820,000 STPF CN 5,000,000 STPF Project Cost: 470,000 860,000 5,000,000 B RIDGE PROJECT IN JEFFERSON COUNTY ON (056C00091N) CLARK STATION RD AT S LONG RUN CR-1004Jefferson PL10007 DN 95,000 BRZ RW UT CN 950,000 BRZ Project Cost: 0 1,045,000 0 A DDRESS DEFICIENCIES OF OLD WESTPORT RD BRIDGE OVER GOOSE CREEK. (056C00113N) (2020CCR) CS-1079Jefferson PL10008 DN RW UT CN 750,000 BRX Project Cost: 750,000 0 0 B RIDGE PROJECT IN JEFFERSON COUNTY ON (056B00142N) I-64 AT KY 3077 (RIVER RD). (BRIDGE PAINTING OF I-64 RIVERSIDE EXPRESSWAY BRIDGES) I -64Jefferson PL10016 DN RW UT CN 8,500,000 FBP Project Cost: 0 0 8,500,000 109 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS DEFICIENCIES OF SCENIC LOOP BRIDGE OVER MID FK B EARGRASS CREEK. (056C00027N) (2020CCR) CS-1003Jefferson PL10019 DN 60,000 BRX RW UT CN 913,000 BRX Project Cost: 973,000 0 0 A DDRESS DEFICIENCIES OF OLD CLARK STATION BRIDGE OVER BRUSH RUN. (056C00167N) (2020CCR) CS-1004Jefferson PL10022 DN RW UT CN 357,000 BRZ Project Cost: 357,000 0 0 B RIDGE PROJECT IN JEFFERSON COUNTY ON (056B00039L) I-64 WB AT TUCKER STATION RD I -64Jefferson PL10057 DN 634,000 BRO RW UT CN 6,340,000 BRO Project Cost: 0 0 6,974,000 B RIDGE PROJECT IN JEFFERSON COUNTY ON (056B00052L) I-64 WB AT MID FK BEARGRASS CREEK I -64Jefferson PL10058 DN 148,000 FBP RW UT CN 1,480,000 FBP Project Cost: 1,628,000 0 0 B RIDGE PROJECT IN JEFFERSON COUNTY ON (056B00052R) I-64 EB AT MID FK BEARGRASS CREEK I -64Jefferson PL10059 DN 146,000 FBP RW UT CN 1,460,000 FBP Project Cost: 1,606,000 0 0 110 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN JEFFERSON COUNTY ON (056B00087R) I-265 NB A T KY 22 (BROWNSBORO RD) KY-265J efferson PL10063 DN 452,000 FBP2 RW UT CN 4,520,000 FBP2 Project Cost: 4,972,000 0 0 B RIDGE PROJECT IN JEFFERSON COUNTY ON (056B00179N) I-65 AT HILL, CSX RR & BURNETT (POTENTIAL CMGC DELIVERY PROJECT) I -65Jefferson PL10064 DN 2,288,000 BRO RW UT CN 22,880,000 BRO Project Cost: 0 25,168,000 0 BRIDGE PROJECT IN JEFFERSON COUNTY ON (056B00183N) I-65 AT E KENTUCKY & S BROOK ST (POTENTIAL CMGC DELIVERY PROJECT) I -65J efferson PL10066 DN 2,877,000 BRO RW UT CN 28,770,000 BRO Project Cost: 0 31,647,000 0 B RIDGE PROJECT IN JEFFERSON COUNTY ON (056B00205N) I-65 AT NS RAILROAD (POTENTIAL CMGC DELIVERY PROJECT) I -65Jefferson PL10070 DN 1,204,000 FBP2 RW UT CN 12,040,000 FBP2 Project Cost: 0 13,244,000 0 B RIDGE PROJECT IN JEFFERSON COUNTY ON (056B00214L) I-65 SB AT OHIO RIVER I -65Jefferson PL10074 DN 120,000 BRO RW UT CN 1,200,000 BRO Project Cost: 0 1,320,000 0 111 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN JEFFERSON COUNTY ON (056B00250N) I-264 AT P &L RAILWAY I -264J efferson PL10075 DN 2,789,000 FBP2 RW UT CN 27,890,000 FBP2 Project Cost: 30,679,000 0 0 A DDRESS CONDITION OF I 64 FROM MILEPOINT 6.581 TO 11.574I-64Jefferson PL20009 DN 500,000 NHPM RW UT CN 5,000,000 NHPM Project Cost: 0 0 5,500,000 ADDRESS CONDITION OF I 71 FROM MILEPOINT 3.706 TO MILEPOINT 8 .34 I-71J efferson PL20014 DN 800,000 NHPM RW UT CN 8,000,000 NHPM Project Cost: 0 8,800,000 0 ADDRESS CONDITION OF I 264 FROM MILEPOINT 20.7 TO MILEPOINT 2 2.927 I-264J efferson PL20017 DN 155,890 NHPM RW UT CN 1,558,900 NHPM Project Cost: 0 1,714,790 0 ADDRESS CONDITION OF I 265 FROM MILEPOINT 15.66 TO MILEPOINT 1 8.8 I-265J efferson PL20019 DN 376,800 NHPM RW UT CN 3,768,000 NHPM Project Cost: 0 4,144,800 0 112 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS PAVEMENT CONDITION OF I 265 BOTH DIRECTIONS FROM M ILEPOINT 23.364 TO MILEPOINT 26.6 I-265J efferson PL20021 DN 350,000 NHPM RW UT CN 3,500,000 NHPM Project Cost: 3,850,000 0 0 ADDRESS CONDITION OF I 64 FROM MILEPOINT 4.935 TO MILEPOINT 6 .612 I-64J efferson PL22017 DN 180,000 NHPM RW UT CN 1,800,000 NHPM Project Cost: 0 0 1,980,000 ADDRESS CONDITION OF I 64 FROM MILEPOINT 8.213 TO MILEPOINT 8 .491 I-64J efferson PL22019 DN 200,000 NHPM RW UT CN 2,000,000 NHPM Project Cost: 0 0 2,200,000 ADDRESS CONDITION OF I 64 FROM MILEPOINT 19.146 TO MILEPOINT 2 3.204 I-64J efferson PL22025 DN 500,000 NHPM RW UT CN 5,000,000 NHPM Project Cost: 0 0 5,500,000 ADDRESS CONDITION OF I 64 FROM MILEPOINT 23.204 TO MILEPOINT 2 3.974 I-64J efferson PL22026 DN 110,000 NHPM RW UT CN 1,100,000 NHPM Project Cost: 0 0 1,210,000 113 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS CONDITION OF I 65 FROM MILEPOINT 123.18 TO MILEPOINT 1 27.57 I-65J efferson PL22069 DN 1,053,600 NHPM RW UT CN 10,536,000 NHPM Project Cost: 0 0 11,589,600 E ASTWOOD FISHERSVILLE CONNECTOR TO I-64 (18CCN) (2020CCR)KY-1531Jefferson PL 750,000 SPP80000 DN RW UT CN Project Cost: 750,000 0 0 W IDEN US-60 TO 6 LANES FROM OLD SHELBYVILLE RD. TO NORTH ENGLISH STATION RD.(18CCN) (2020CCR) US-60Jefferson PL80001 DN 620,000 NH RW UT CN Project Cost: 0 0 620,000 E XTEND PLANTSIDE DRIVE FROM REHL ROAD TO TAYLORSVILLE ROAD. (18CCN)(2020CCR) PF-9999Jefferson PL80003 DN 1,000,000 STPF RW 200,000 STPF UT 800,000 STPF CN 5,000,000 STPF Project Cost: 1,000,000 1,000,000 5,000,000 R ECONSTRUCT EAST MARKET (US 31E) FROM FIRST ST TO JOHNSON ST TO IMPROVE PEDESTRIAN SAFETY AND ENHANCE ECONOMIC DEVELOPMENT. (2020CCR) US-31Jefferson PL80053 DN RW UT CN 2,500,000 SPP Project Cost: 0 0 2,500,000 114 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 REPAIR AND REHABILITATE THE BRIDGE AND DRAINAGE S TRUCTURES ACROSS TYLER PARK (2020CCN) KY-1703Jefferson PL80109 DN RW UT CN 2,516,950 SPP Project Cost: 2,516,950 0 0 C ONSTRUCT A SIDEWALK ALONG MT HOLLY RD FROM CHARLENE DR TO FOX AVE FOR CORAL RIDGE ELEMENTARY (2020CCN) KY-2055Jefferson PL80110 DN 150,000 SPP RW 30,000 SPP UT CN Project Cost: 0 150,000 30,000 RECONSTRUCT THE INTERSECTION OF BARDSTOWN ROAD (US 31E) A ND BAXTER AVENUE (KY 1703) FOR PEDESTRIAN SAFETY US-31J efferson PL80151 DN RW UT CN 150,000 SPP Project Cost: 150,000 0 0 R educe congestion, improve safety, and enhance mobility on KY 2050 (Herr Lane) from Prince Valiant Drive/Westmar Terrace to Bedford Lane. ky-2050Jefferson PL80200 DN 350,000 SPP RW UT CN Project Cost: 0 0 350,000 I mprove safety and reduce congestion on KY 1065 (Outer Loop) from I-65 to KY 2052 (Shepherdsville Road). Project will evaluate the addition of one travel lane in each direction and consider accommodations for bicyclists and pedestrians ky-1065Jefferson PL80203 DN 2,180,000 STPF RW UT CN Project Cost: 0 2,180,000 0 115 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Improve safety and reduce congestion on KY 1931 (Manslick Road) f rom KY 1931 (St. Andrews Church Road) to I-264 (Henry Watterson Expressway). Project will evaluate 3-lane widening and consider accommodations for bicyclists and pedestrians. KY-1931Jefferson PL80204 DN 1,557,500 STPF RW UT CN Project Cost: 0 0 1,557,500 I mprove safety, reduce congestion, and improve multi-modal transportation options along KY 61 from Commerce Crossings Dr (BMP 1.395) to Briden Avenue (EMP 8.400) including the I-264 (Watterson Expressway) and I-265 (Gene Snyder Freeway) interchanges. KY-61Jefferson PL 400,000 STPF80205 DN RW UT CN Project Cost: 0 0 400,000 R econstruction of Broadway to improve safety for vehicles and pedestrians. (MATCHING FUNDS FOR FEDERAL GRANT PROGRAM) -1021, US-150, US-31 Jefferson PL80214 DN 500,000 SPP RW UT CN Project Cost: 0 500,000 0 DESIGN AND CONSTRUCTION OF A REALIGNED OLD BARDSTOWN R OAD TO ALIGN WITH THE ENTRANCE TO WALGREENS AT HILLOCK. (MILEPOINT 0.0 TO MILEPOINT 0.01) WITH A MEMORANDUM OF AGREEMENT WITH THE LOUISVILLE METRO GOVERNMENT. CR-1006J efferson PL80250 DN 70,000 SPP RW UT 40,000 SPP CN 400,000 SPP Project Cost: 0 110,000 400,000 I MPROVE ALIGNMENT OF THE I 65 SOUTHBOUND RAMP TO BROOK/JEFFERSON THROUGH THE ADDITION OF LANES AND IMPROVED GEOMETRY. I-65Jefferson PL80251 DN 500,000 NH RW UT CN Project Cost: 0 500,000 0 116 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 RECONSTRUCT 9TH STREET TO IMPROVE SAFETY AND C ONNECTIVITY TO THE NEW BEECHER TERRACE AND RUSSELL NEIGHBORHOOD. MILEPOINT 0.0 TO MILEPOINT 0.748 (STATE FUNDS FOR FEDERAL GRANT MATCH). CS-1046J efferson PL80252 DN RW UT CN 500,000 SPP Project Cost: 0 0 500,000 R educe congestion, improve safety and enhance mobility along the US 31E (Bardstown Road) corridor from the Bullitt/Jefferson County line to KY 1065 (Beulah Church/Seatonville Road). (MP 0.0 – MP 5.6) us-31Jefferson PL 450,000 SPP80261 DN RW UT CN Project Cost: 0 450,000 0 T otal for Jefferson county PL Total Amounts: CN UT RW DN 750,000 700,000 400,000 6,195,000 13,296,690 7,305,100 975,000 3,010,000 2,680,000 1,405,000 1,660,000 4,830,000 89,163,616 131,226,852 116,161,551 98,488,616 149,893,542 131,376,651 EAST NICHOLASVILLE BYPASS SECTION IA: IMPROVE C ONNECTIVITY AND MOBILITY EAST AROUND NICHOLASVILLE FROM SOUTH OF KY-39 TO NORTH OF KY-169. (2020CCR) PF-9999J essamine PL87.2000 DN RW UT CN 19,610,000 SPP Project Cost: 0 19,610,000 0 MINOR WIDENING OF ASHGROVE ROAD (KY 1980) FROM US 27 TO Y OUNG DRIVE TO ACCOMODATE PROPOSED SCHOOL SITE TRAFFIC (2020CCR) KY-1980J essamine PL103 DN RW UT CN 1,000,000 SPP Project Cost: 1,000,000 0 0 117 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE ROADWAY GEOMETRICS, TYPICAL SECTION, AND R OADWAY HAZARDS ON KY 1980 (BRANNON RD) FROM US 68 (HARRODSBURG RD) TO US 27 (NICHOLASVILLE RD)(12CCR) (18CCN) KY-1980Jessamine PL414 DN RW UT 5,000,000 STPF CN Project Cost: 0 0 5,000,000 B RIDGE PROJECT IN JESSAMINE COUNTY ON (057R00605N) DRAKE LANE AT NS (CNO&TP) SYSTEM CR-1238Jessamine PL1144 DN 210,000 BRZ RW UT CN 2,100,000 BRZ Project Cost: 0 210,000 2,100,000 I NSTALL GUARDRAIL ON KY-1268 IN JESSAMINE COUNTYKY-1268Jessamine PL4308 DN RW UT CN 18,000 GR Project Cost: 18,000 0 0 A DDRESS DEFICIENCIES OF RAILROAD BRIDGE ON KY 169 (NORTH 3RD STREET) BETWEEN MEADOWLARK LANE & ILHARDT AVENUE. (057R00603N)(14CCN)(16CCR)(SD) KY-169Jessamine PL8851 DN RW UT CN 1,000,000 BRX Project Cost: 0 1,000,000 0 I MPROVE KY-169 FROM NORTH OF CLEAR CREEK RD IN JESSAMINE COUNTY TO NORTH OF KY-1967 IN WOODFORD COUNTY. (2020CCN) KY-169Jessamine PL80108 DN 910,000 SPP RW 2,020,000 SPP UT CN Project Cost: 0 910,000 2,020,000 118 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 SAFETY IMPROVEMENTS: FEASIBILITY STUDY TO IMPROVE THE S AFETY AND DRIVER EXPECTION ON US 68IN MERCER AND JESSAMINE COUNTIES NEAR THE KY RIVER. (MP 14.45 IN MERCER COUNTY TO MP 1.38 IN JESSAMINE COUNTY ) US-68Jessamine PL 250,000 NH80251 DN RW UT CN Project Cost: 0 250,000 0 T otal for Jessamine county PL Total Amounts: CN UT RW DN 250,000 1,120,000 2,020,000 5,000,000 1,018,000 20,610,000 2,100,000 1,018,000 21,980,000 9,120,000 I MPROVE ROADWAY GEOMETRICS AND CAPACITY FROM GARBAGE HOLLOW TO EAST OF MILL STREET. (2020CCR) KY-40Johnson PL149 DN 1,000,000 SPP RW UT CN Project Cost: 0 0 1,000,000 A DDRESS GEOMETRIC AND SAFETY ISSUES AND FUTURE CONGESTION MITIGATION ON KY 40 FROM 0.10 MILE WEST OF TEAYS BR. ROAD TO 0.10 MILE EAST OF TEAYS BR. ROAD.(12CCR) (2020CCN) KY-40Johnson PL194 DN RW 500,000 SPP UT 500,000 SPP CN Project Cost: 0 1,000,000 0 I NSTALL GUARDRAIL ON KY-172 IN JOHNSON COUNTYKY-172Johnson PL4307 DN RW UT CN 106,000 GR Project Cost: 106,000 0 0 119 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-1750 IN JOHNSON COUNTYK Y-1750Johnson PL4308 DN RW UT CN 106,000 GR Project Cost: 106,000 0 0 I NSTALL GUARDRAIL ON KY-1750 IN JOHNSON COUNTYKY-1750Johnson PL4309 DN RW UT CN 106,000 GR Project Cost: 106,000 0 0 I NSTALL GUARDRAIL ON KY-172 IN JOHNSON COUNTYKY-172Johnson PL4316 DN RW UT CN 106,000 GR Project Cost: 106,000 0 0 I NSTALL GUARDRAIL ON KY-825 IN JOHNSON COUNTYKY-825Johnson PL4317 DN RW UT CN 53,000 GR Project Cost: 53,000 0 0 I NSTALL GUARDRAIL ON KY-825 IN JOHNSON COUNTYKY-825Johnson PL4321 DN RW UT CN 25,000 GR Project Cost: 25,000 0 0 120 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-825 IN JOHNSON COUNTYK Y-825Johnson PL4322 DN RW UT CN 69,000 GR Project Cost: 69,000 0 0 I NSTALL GUARDRAIL ON KY-172 IN JOHNSON COUNTYKY-172Johnson PL4338 DN RW UT CN 106,000 GR Project Cost: 0 106,000 0 I NSTALL GUARDRAIL ON KY-2039 IN JOHNSON COUNTYKY-2039Johnson PL4339 DN RW UT CN 106,000 GR Project Cost: 0 106,000 0 I NSTALL GUARDRAIL ON KY-3224 IN JOHNSON COUNTYKY-3224Johnson PL4340 DN RW UT CN 71,000 GR Project Cost: 0 71,000 0 I NSTALL GUARDRAIL ON KY-3224 IN JOHNSON COUNTYKY-3224Johnson PL4341 DN RW UT CN 71,000 GR Project Cost: 0 71,000 0 121 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-1107 IN JOHNSON COUNTYK Y-1107Johnson PL4401 DN RW UT CN 74,000 GR Project Cost: 74,000 0 0 I MPROVE ROADWAY GEOMETRICS AND CAPACITY ON KY 40 FROM KY 321 TO GARBAGE HOLLOW (2020CCN) KY-40Johnson PL80100 DN 811,000 SPP RW UT CN Project Cost: 0 811,000 0 I MPROVE US 460 FROM THE INTERSECTION WITH KY 114 TO THE INTERCHANGE WITH US 23 (2020CCR) US-460Johnson PL80101 1,000,000 SPP DN 7,950,000 SPP RW 7,212,000 SPP UT CN Project Cost: 1,000,000 7,950,000 7,212,000 A DDRESS CONGESTION AND SAFETY ISSUES ON KY 321 FROM THE 6TH STREET TO THE JUNCTION OF KY 321 AND KY 40 (2020CCN) (SAME AS 12-8102 IN 2020 HIGHWAY PLAN) KY-321Johnson PL 324,000 SPP80116 DN RW UT CN Project Cost: 0 0 324,000 CONSTRUCT ACCESS ROAD TO PROPOSED JOHNSON COUNTY HIGH S CHOOL AND MIDDLE SCHOOL CAMPUS. TO INTERSECT WITH KY 40 AT MILEPOINT 8.85 Johnson P L80250 DN 1,500,000 SPP RW UT CN Project Cost: 0 1,500,000 0 122 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Total for Johnson county P L Total Amounts: CN UT RW DN 1,000,000 324,000 10,261,000 1,000,000 500,000 7,212,000 500,000 645,000 354,000 1,645,000 11,615,000 8,536,000 INITIATE PRELIMINARY ENGINEERING, ENVIRONMENTAL STUDIES AND OT HER PRECONSTRUCTION ACTIVITIES TO UPGRADE THE EXISTING I-71/75 BRENT SPENCE BRIDGE CORRIDOR AT THE OHIO RIVER BETWEEN COVINGTON, KY AND CINCINNATI, OHIO. (02KYD) I -75K enton PL17 DN 5,000,000 20,000,000 20,000,000 NH RW 5,000,000 15,000,000 25,000,000 NH UT 5,000,000 NH CN Project Cost: 10,000,000 35,000,000 50,000,000 CONSTRUCT A COMPANION BRIDGE TO THE EXISTING I-71/75 BRENT S PENCE BRIDGE OVER THE OHIO RIVER BETWEEN COVINGTON, KY AND CINCINNATI, OH. (FEDERAL GRANT FUNDING) CO-0K enton PL17.3000 DN RW UT CN 180,000,000 180,000,000 IF Project Cost: 0 180,000,000 180,000,000 CONSTRUCT A COMPANION BRIDGE TO THE EXISTING I-71/75 BRENT S PENCE BRIDGE OVER THE OHIO RIVER BETWEEN COVINGTON, KY AND CINCINNATI, OH. (DEDICATED STATE GENERAL FUNDS) CO-0K enton PL17.3100 DN RW UT CN 250,000,000 IF Project Cost: 0 250,000,000 0 CONSTRUCT A COMPANION BRIDGE TO THE EXISTING I-71/75 BRENT S PENCE BRIDGE OVER THE OHIO RIVER BETWEEN COVINGTON, KY AND CINCINNATI, OH. (GARVEE BONDS) CO-0K enton PL17.3200 DN RW UT CN 150,000,000 IF Project Cost: 0 0 150,000,000 123 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE SAFETY AND REDUCE CONGESTION ON KY-536 FROM KY 1 303 TO WILLIAMSWOOD ROAD/CALVARY DRIVE (PRIORITY SECTION 2). DESIGN PHASE UNDER PARENT NO. 6-162.01. (2012BOP)(18CCN) (2020CCR) KY-536Kenton PL162.3000 DN RW UT CN 6,300,000 5,000,000 STPF Project Cost: 0 6,300,000 5,000,000 I MPROVE SAFETY AND REDUCE CONGESTION ON KY-536 FROM WILLIAMSWOOD ROAD/CALVARY DRIVE TO KY-17 (PRIORITY SECTION 3). DESIGN PHASE UNDER PARENT NO. 6-162.01. (2012BOP)(18CCR) (2020CCR) KY-536Kenton PL162.4000 DN RW 5,000,000 STPF UT CN Project Cost: 0 0 5,000,000 I MPROVE SAFETY AND REDUCE CONGESTION ON KY-17 AT THE I-275 INTERCHANGE. (18CCR) (2020CCR) KY-17Kenton PL449 DN RW 1,500,000 STPF UT 2,000,000 STPF CN Project Cost: 0 1,500,000 2,000,000 I MPROVE SAFETY AND REDUCE CONGESTION ALONG KY-1303 (TURKEYFOOT RD) FROM DUDLEY RD TO US-25 (DIXIE HWY). (18CCR) (2020CCR) KY-1303Kenton PL450 DN 3,500,000 STPF RW UT CN Project Cost: 0 3,500,000 0 F ederal grant applications associated with Brent Spence Bridge mitigation. I -75Kenton PL1069 DN RW UT CN 10,000,000 IF Project Cost: 0 10,000,000 0 124 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 WEST 15TH STREET; ADDRESS DEFICIENCIES OF BRIDGE AND A PPROACHES OVER CSX RR IN COVINGTON (Funds to be provided by the City as per Memorandum of Agreement). (059C00029N) (12CCR)(SD) CS-2097Kenton PL1070 DN RW UT CN 2,250,000 SPP Project Cost: 0 2,250,000 0 I NSTALL GUARDRAIL ON KY-3716 IN KENTON COUNTYKY-3716Kenton PL4313 DN RW UT CN 11,000 GR Project Cost: 0 0 11,000 E XTEND HOUSTON ROAD TO CINEMA PROPERTY. (16CCN)(18CCN) (2020CCR) CS-3000Kenton PL8916 DN RW 530,000 SPP UT 520,000 SPP CN 3,790,000 SPP Project Cost: 1,050,000 3,790,000 0 I MPROVE EXISTING ALIGNMENT WITH BUTTERMILK PIKE, ORPHANAGE ROAD, AND US 25. FT. MITCHELL WILL PAY $50,000 TOWARD DESIGN. (16CCN)(18CCN) (2020CCR) US-25Kenton PL8951 DN 570,000 STPF RW UT CN Project Cost: 0 570,000 0 JOINT REPLACEMENT AND PREVENTIVE MAINTENANCE ON CLAY W ADE BAILEY BRIDGE OVER THE OHIO RIVER. JOINT PROJECT WITH OHIO. (059B00049N) US-25K enton PL10006 DN RW UT CN 1,000,000 BRX Project Cost: 1,000,000 0 0 125 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN KENTON COUNTY ON (059B00040N) I-75 NC AT 3 RD-4TH-5TH STS COVINGTO I -75Kenton PL10043 DN 1,900,000 FBP2 RW UT CN Project Cost: 0 0 1,900,000 B RIDGE PROJECT IN KENTON COUNTY ON (059C00048N) ERNEST BRIDGE DR AT CSX RAILROAD CR-1021Kenton PL10046 DN 121,000 FBP RW UT CN 1,210,000 FBP Project Cost: 0 1,331,000 0 A DDRESS CONDITION OF I-75 FROM MILEPOINT 166.263 TO MILEPOINT 169.439 I-75Kenton PL20031 DN 1,100,000 NHPM RW UT CN 11,000,000 NHPM Project Cost: 0 12,100,000 0 R ECONSTRUCT KY 236 (STEVENSON ROAD) FROM ALICE STREET TO JACQUELINE DRIVE.(18CCN) (2020CCR) Kenton Co. government will allocate $250,000 to sanitary sewer and waterline relocation. The City of Erlanger up to $350,000. The City of Erlanger is es eligible to apply to SD1 for up to 50% of the total cost of storm water KY-236Kenton PL80002 DN RW 1,660,000 NH UT 1,630,000 NH CN 6,450,000 NH Project Cost: 1,660,000 1,630,000 6,450,000 R ESURFACE AND REPAIR MEDIAN ON KY 17 FROM PIONEER PARK TO KYLES LANE (2020CCN) KY-17Kenton PL80104 DN 50,000 SPP RW UT CN 2,010,000 SPP Project Cost: 50,000 2,010,000 0 126 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 WIDEN KENTON LANDS ROAD FROM US 25 TO RIGGS ROAD ( 2020CCN) KY-2373Kenton PL80105 DN 3,000,000 SPP RW UT CN Project Cost: 0 3,000,000 0 R econstruct KY 536 to a 4-lane urban section from KY 17 to the Campbell County line. KY-536Kenton PL80203 DN 3,000,000 NH RW UT CN Project Cost: 0 3,000,000 0 P rovide connectivity, improve mobility, and reduce congestion along KY 536 from KY 17 to KY 16; include multi-modes. KY-536Kenton PL80217 DN 1,996,800 SPP RW UT CN Project Cost: 0 0 1,996,800 R EHABILITATE/RECONSTRUCT US 25 FROM BUTTERMILK PIKE (KY371) TO I-75 (MP 8.58 TO MP 9.86) US-25Kenton PL80254 DN 211,200 SPP RW UT CN 5,000,000 SPP Project Cost: 0 211,200 5,000,000 C ONSTRUCT PAVEMENT, SLOPE STABILITY, DRAINAGE, AND SIGHT DISTANCE IMPROVEMENTS ALONG THE ROUTE BETWEEN HOLLYHOCK ROAD AND DECOURSEY PIKE (KY 177). KENTON COUNTY FISCAL COURT WILL SERVE AS PROJECT MANAGER Kenton PL80255 DN RW UT CN 600,000 SPP Project Cost: 0 600,000 0 127 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 CONSTRUCT PAVEMENT, SLOPE STABILITY, DRAINAGE AND SIGHT D ISTANCE IMPROVEMENTS ALONG THE ROUTE BETWEEN HANDS PIKE AND HIGHRIDGE DRIVE. (MP 0.0 TO MP 1.320) KY-3716Kenton PL80256 DN RW UT CN 500,000 SPP Project Cost: 0 500,000 0 T otal for Kenton county PL Total Amounts: CN UT RW DN 5,050,000 31,502,200 23,896,800 7,190,000 16,500,000 30,000,000 520,000 1,630,000 7,000,000 1,000,000 467,660,000 346,461,000 13,760,000 517,292,200 407,357,800 E liminate rockfall hazards from kY 2029 to Rock Fork Road.KY-80Knott PL158 DN 541,000 PROT RW 221,000 PROT UT 649,000 PROT CN Project Cost: 0 541,000 870,000 I NSTALL GUARDRAIL ON KY-1231 IN KNOTT COUNTYKY-1231Knott PL4310 DN RW UT CN 53,000 GR Project Cost: 53,000 0 0 I NSTALL GUARDRAIL ON KY-1088 IN KNOTT COUNTYKY-1088Knott PL4323 DN RW UT CN 73,000 GR Project Cost: 73,000 0 0 128 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-1088 IN KNOTT COUNTYK Y-1088Knott PL4324 DN RW UT CN 55,000 GR Project Cost: 55,000 0 0 I NSTALL GUARDRAIL ON KY-1231 IN KNOTT COUNTYKY-1231Knott PL4325 DN RW UT CN 63,000 GR Project Cost: 63,000 0 0 I NSTALL GUARDRAIL ON KY-1088 IN KNOTT COUNTYKY-1088Knott PL4342 DN RW UT CN 50,000 GR Project Cost: 0 50,000 0 I NSTALL GUARDRAIL ON KY-160 IN KNOTT COUNTYKY-160Knott PL4357 DN RW UT CN 5,000 GR Project Cost: 0 0 5,000 I NSTALL GUARDRAIL ON KY-1088 IN KNOTT COUNTYKY-1088Knott PL4375 DN RW UT CN 63,000 GR Project Cost: 0 0 63,000 129 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-3391 IN KNOTT COUNTYK Y-3391Knott PL4376 DN RW UT CN 82,000 GR Project Cost: 0 0 82,000 I NSTALL GUARDRAIL ON KY-550 IN KNOTT COUNTYKY-550Knott PL4377 DN RW UT CN 32,000 GR Project Cost: 0 0 32,000 I NSTALL GUARDRAIL ON KY-582 IN KNOTT COUNTYKY-582Knott PL4378 DN RW UT CN 82,000 GR Project Cost: 0 0 82,000 NEW CONSTRUCTION OF ONE MILE STRETCH OF KY-1231 BEGINNING A T BRIDGE AFTER LEAVING KY-550. (04CCN)(06CCR)(08CCR) (10CCR)(12CCR) (2020CCN) KY-1231K nott PL8200 DN RW UT CN 4,920,000 SPP Project Cost: 0 0 4,920,000 B RIDGE PROJECT IN KNOTT COUNTY ON (060B00026N) KY-550 AT OGDEN CREEK KY-550Knott PL10105 DN 16,000 FBP2 RW UT CN 160,000 FBP2 Project Cost: 0 176,000 0 130 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN KNOTT COUNTY ON (060B00059N) KY-1102 AT M ontgomery Creek KY-1102Knott PL10107 DN 48,000 FBP2 RW UT CN 480,000 FBP2 Project Cost: 0 528,000 0 B RIDGE PROJECT IN KNOTT COUNTY ON (060C00060N) FROGTOWN RD AT R FRK TROUBLESOME CRK CS-1018Knott PL10109 DN 16,000 BRZ RW UT CN 160,000 BRZ Project Cost: 0 16,000 160,000 B RIDGE PROJECT IN KNOTT COUNTY ON (060C00088N) Fieldwood Dr AT R Frk Troublesome Crk CS-1016Knott PL10110 DN 22,000 BRZ RW UT CN 220,000 BRZ Project Cost: 0 22,000 220,000 T otal for Knott county PL Total Amounts: CN UT RW DN 643,000 221,000 649,000 244,000 690,000 5,564,000 244,000 1,333,000 6,434,000 I NSTALL GUARDRAIL ON KY-229 IN KNOX COUNTYKY-229Knox PL4309 DN RW UT CN 58,000 GR Project Cost: 58,000 0 0 131 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-3441 IN KNOX COUNTYK Y-3441Knox PL4310 DN RW UT CN 55,000 GR Project Cost: 55,000 0 0 I NSTALL GUARDRAIL ON KY-11 IN KNOX COUNTYKY-11Knox PL4333 DN RW UT CN 39,000 GR Project Cost: 0 39,000 0 I NSTALL GUARDRAIL ON KY-2418 IN KNOX COUNTYKY-2418Knox PL4345 DN RW UT CN 22,000 GR Project Cost: 0 0 22,000 I NSTALL GUARDRAIL ON KY-11 IN KNOX COUNTYKY-11Knox PL4355 DN RW UT CN 17,000 GR Project Cost: 0 0 17,000 I NSTALL GUARDRAIL ON KY-11 IN KNOX COUNTYKY-11Knox PL4356 DN RW UT CN 33,000 GR Project Cost: 0 0 33,000 132 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-3438 IN KNOX COUNTYK Y-3438Knox PL4357 DN RW UT CN 13,000 GR Project Cost: 0 0 13,000 RAISE KY-459 ABOVE FLOOD PLAIN FROM MP 3 TO MP 5, INCLUDING R AISING THE BULL RUN CREEK BRIDGE (INCLUDES 11-8712).(12CCN) KY-459K nox PL8713 DN RW UT CN 5,000,000 PROT Project Cost: 0 5,000,000 0 I MPROVE SAFETY OF INTERSECTION AT US 25E AND KY 3439 AND PROVIDE SIDEWALKS TO AN AREA FREQUENTED BY PEDESTRIANS (MP 0.0 - MP 0.9) KY-3439Knox PL8857 DN 300,000 SPP RW 1,300,000 SPP UT 1,000,000 SPP CN 2,000,000 SPP Project Cost: 0 2,600,000 2,000,000 B RIDGE PROJECT IN KNOX COUNTY ON (061B00035N) KY-225 AT BRUSH CREEK KY-225Knox PL10200 DN 36,000 FBP2 RW UT CN 360,000 FBP2 Project Cost: 0 396,000 0 B RIDGE PROJECT IN KNOX COUNTY ON (061B00073N) KY-6 AT BR OF INDIAN CREEK KY-6Knox PL10203 DN 49,000 FBP2 RW UT CN 490,000 FBP2 Project Cost: 0 539,000 0 133 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 CONDUCT A TRAFFIC SAFETY STUDY ON US 25E AT HEIDRICK, KY IN K NOX COUNTY.(18CCN) (2020CCR) US-25K nox PL 50,000 SPP80009 DN RW UT CN Project Cost: 0 50,000 0 C ONSTRUCT VARIOUS TURN LANES ON THE CUMBERLAND GAP PARKWAY AS NEEDED (2020CCN) US-25Knox PL80111 DN RW UT CN 48,000 SPP Project Cost: 48,000 0 0 I MPROVE SAFETY, ADDRESS GEOMETRIC DEFICIENCIES AND PROVIDE FLOOD MITIGATION ON KY 1487 (MANCHESTER STREET) FROM JUDGE STREET TO US 25E (2020CCN) KY-1487Knox PL80155 DN RW 850,000 SPP UT 1,150,000 SPP CN 5,500,000 SPP Project Cost: 2,000,000 0 5,500,000 IMPROVE SAFETY AND ADDRESS GEOMETRIC DEFICIENCIES ALONG N KY 830 FROM US 25E TO KY 1629 INCLUDING WIDENING AND NEW TURNING LANES (2020CCN) KY-830K nox PL80156 DN 300,000 SPP RW 350,000 SPP UT 1,250,000 SPP CN 2,000,000 SPP Project Cost: 300,000 1,600,000 2,000,000 I mprove safety and access along KY 11 by raising roadway above Flood X elevation. KY-11Knox PL80203 DN 403,200 STP2 RW 57,000 STP2 UT 249,600 STP2 CN Project Cost: 0 403,200 306,600 134 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Install guardrail for safety along KY 225K Y-225Knox PL80204 DN RW UT CN 71,800 SPP Project Cost: 71,800 0 0 PROVIDE LEFT AND RIGHT TURN AT NEWLY CONSTRUCTED W INNER'S WAY AND OPPORTUNITY DRIVE. RECONSTRUCTION OF WINNER'S WAY AND OPPORTUNITY DRIVE TO IMPROVE ACCESS TO KY 3041 (MILEPOINT 2.1 TO MILEPOINT 2.5) KY-3041K nox PL80263 DN 550,000 SPP RW 1,000,000 SPP UT CN 2,675,000 SPP Project Cost: 0 4,225,000 0 T otal for Knox county PL Total Amounts: CN UT RW DN 50,000 300,000 1,338,200 850,000 2,650,000 57,000 1,150,000 2,250,000 249,600 232,800 8,564,000 9,585,000 2,532,800 14,852,200 9,891,600 I NSTALL GUARDRAIL ON US-31 IN LARUE COUNTYUS-31Larue PL4314 DN RW UT CN 10,000 GR Project Cost: 0 0 10,000 A DDRESS SAFETY AND GEOMETRIC DEFICIENCIES ALONG KY 84 FROM KY 357 TO KY 61 (LINCOLN PARKWAY) NEAR HODGINSVILLE (2020CCR) KY-84Larue PL8909 DN 100,000 SPP RW 100,000 SPP UT 300,000 SPP CN 1,800,000 SPP Project Cost: 0 200,000 2,100,000 135 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN LARUE COUNTY ON (062B00034R) KY-210 AT N ORTH FORK NOLIN RIVER KY-210Larue PL10058 DN 121,000 FBP RW UT CN 1,210,000 FBP Project Cost: 1,331,000 0 0 T otal for Larue county PL Total Amounts: CN UT RW DN 121,000 100,000 100,000 300,000 1,210,000 1,810,000 1,331,000 200,000 2,110,000 TENN. STATE LINE-LEXINGTON; PRIORITY SECTION OF WIDENING I-75 F ROM MP 20.2 IN WHITLEY COUNTY TO MP 28.85, US-25E NORTH OF CORBIN. (C-COST=$110,000,000)(18CCR) (2020CCR) I -75L aurel PL14.8000 DN 2,500,000 NH RW 500,000 NH UT 500,000 NH CN 15,000,000 NH Project Cost: 2,500,000 1,000,000 15,000,000 R EDUCE CONGESTION ON US-25 FROM KY-1006 TO KY-2069; IMPROVE CONNECTIVITY FROM US-25 NEAR KY-2069 TO KY-229; IMPROVE KY-229 FROM THE NEW CONNECTOR NORTH TO KY-192; AND IMPROVE ACCESS TO THE SCHOOL FROM KY-192 BYPASS. (06CCR)(10CCR)(12CCR)(14CCR) (2020CCR) US-25Laurel PL147 DN RW UT CN 6,000,000 11,000,000 STP1 Project Cost: 0 6,000,000 11,000,000 I mprove Rudy Bear Road and KY 3007 from KY 80 South to KY 3432 West of I-75. CO-0Laurel PL169 DN 300,000 SPP RW 800,000 SPP UT 150,000 SPP CN Project Cost: 0 300,000 950,000 136 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 EXPAND TRUCK PARKING AT I-75 NB TRUCK REST HAVEN.I -75Laurel PL179 DN RW UT CN 1,000,000 NH Project Cost: 0 0 1,000,000 E XPAND TRUCK PARKING AT I-75 SB TRUCK REST HAVEN.I -75Laurel PL180 DN RW UT CN 1,000,000 NH Project Cost: 0 0 1,000,000 IMPROVE SAFETY, IMPROVE ACCESS MANAGEMENT, AND REDUCE C ONGESTION ON US-25E FROM THE KNOX/LAUREL COUNTY LINE TO KY-770 (12CCR)(16CCR) (2020CCR) US-25L aurel PL185 DN RW UT CN 8,000,000 NH Project Cost: 0 0 8,000,000 IMPROVE SAFETY, ACCESS MANAGEMENT, AND FREIGHT MOBILITY; A ND REDUCE CONGESTION ON KY-192 NEAR KY-1006 TO US-25 IN LONDON. (12CCR)(LET W/11-8514.10) KY-192L aurel PL187 DN RW UT CN 9,000,000 NH Project Cost: 0 0 9,000,000 R EDUCE CONGESTION ON THE HAL ROGERS PARKWAY FROM RELOCATED KY-30 TO KY-192. HR-9006Laurel PL365 DN RW 2,000,000 NH UT 1,000,000 NH CN Project Cost: 0 2,000,000 1,000,000 137 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-472 IN LAUREL COUNTYK Y-472Laurel PL4319 DN RW UT CN 86,000 GR Project Cost: 86,000 0 0 I NSTALL GUARDRAIL ON KY-192 IN LAUREL COUNTYKY-192Laurel PL4325 DN RW UT CN 18,000 GR Project Cost: 18,000 0 0 I NSTALL GUARDRAIL ON KY-472 IN LAUREL COUNTYKY-472Laurel PL4326 DN RW UT CN 27,000 GR Project Cost: 27,000 0 0 I NSTALL GUARDRAIL ON KY-312 IN LAUREL COUNTYKY-312Laurel PL4334 DN RW UT CN 20,000 GR Project Cost: 0 20,000 0 I NSTALL GUARDRAIL ON KY-3007 IN LAUREL COUNTYKY-3007Laurel PL4418 DN RW UT CN 49,000 GR Project Cost: 49,000 0 0 138 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 REPLACE BRIDGE LOCATED ON LILY ROAD (CR 1221) (MP 1.045) ( AREA ADJACENT TO FARISTON INDUSTRIAL PARK WITH NEW ROADWAY ALIGNMENT). (14CCN)(18CCN) CR-1221Laurel PL8811 DN RW UT CN 1,520,000 STP1 Project Cost: 1,520,000 0 0 I MPROVE THE HAL ROGERS PARKWAY TO INTERSTATE STANDARDS FROM 4.0 MI EAST OF KY 192 TO LAUREL/CLAY CO. LINE. (I-75 TO HAZARD) (16CCN)(18CCR) HR-9006Laurel PL8909 DN 1,040,000 NH RW UT CN Project Cost: 0 1,040,000 0 A DDRESS DEFICIENCIES OF KY-1223 BRIDGE OVER HORSE CREEK. (063B00007N) KY-1223Laurel PL10024 DN 60,000 FBP2 RW UT CN 510,000 FBP2 Project Cost: 570,000 0 0 ADDRESS CONDITION OF I-75 FROM MILEPOINT 27.943 TO MILEPOINT 2 8.9 I-75L aurel PL22109 DN 90,000 NHPM RW UT CN 900,000 NHPM Project Cost: 0 990,000 0 A DDRESS ACCESS AND SAFETY ISSUES AT THE INTERSECTION OF KY 80 AND PAYNE TRAIL AND BUSH ELEMENTARY SCHOOL BY CONSTRUCTING A CONNECTOR ROAD FROM HAL ROGERS PARKWAY (HR 9006) TO KY 6264 (PAYNE TRAIL). (2020CCN) hr-9006Laurel PL80154 DN 100,000 SPP RW 710,000 SPP UT 28,000 SPP CN Project Cost: 0 100,000 738,000 139 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Improve safety and alleviate congestion along US 25 and KY 1006 by a dding extended turning lanes. US-25Laurel PL80200 DN 300,000 SPP RW 500,000 SPP UT 600,000 SPP CN Project Cost: 0 300,000 1,100,000 C onstruct 3 new left turn lanes between milepoints 7.615 and 7.994.US-25Laurel PL80205 DN RW UT CN 325,000 STP1 Project Cost: 0 325,000 0 T otal for Laurel county PL Total Amounts: CN UT RW DN 2,560,000 1,830,000 2,500,000 2,010,000 500,000 1,778,000 2,210,000 7,245,000 45,000,000 4,770,000 12,075,000 48,788,000 I NSTALL GUARDRAIL ON KY-201 IN LAWRENCE COUNTYKY-201Lawrence PL4379 DN RW UT CN 74,000 GR Project Cost: 0 0 74,000 R eplace the Georges Creek Bridge. (12CCN) (2020CCN)KY-581Lawrence PL8701 DN RW UT CN 1,950,000 BRX Project Cost: 0 1,950,000 0 140 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN LAWRENCE COUNTY ON (064B00038N) KY-644 a t Levisa Fork KY-644Lawrence PL10016 DN 190,000 BRX RW UT CN 1,900,000 BRX Project Cost: 0 2,090,000 0 B RIDGE PROJECT IN LAWRENCE COUNTY ON (064B00061N) KY-1496 AT E Frk Little Sandy River KY-1496Lawrence PL10114 DN 56,000 FBP RW UT CN 560,000 FBP Project Cost: 56,000 560,000 0 B RIDGE PROJECT IN LAWRENCE COUNTY ON (064B00069N) KY-2037 AT Griffith Creek KY-2037Lawrence PL10115 DN 83,000 FBP RW UT CN 830,000 FBP Project Cost: 83,000 830,000 0 R EPAVE KY 32 FROM MP 21.0 TO 23.0 (2020CCN)KY-32Lawrence PL80104 DN RW UT CN 300,000 STP4 Project Cost: 0 300,000 0 R EPAVE ROUTE 3 SOUTH FROM MP 12.58 TO MP 0 AND PLACE GUARD RAILS ON FALLS HILL (2020CCN) KY-3Lawrence PL80105 DN RW UT CN 1,700,000 SPP Project Cost: 0 0 1,700,000 141 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 REPLACE BRIDGE ON KY 581 0.5 MILES FROM THE INTERSECTION OF U S 23 (2020CCN) KY-581L awrence PL80110 DN 500,000 SPP RW 50,000 SPP UT CN Project Cost: 0 500,000 50,000 T otal for Lawrence county PL Total Amounts: CN UT RW DN 139,000 690,000 50,000 5,540,000 1,774,000 139,000 6,230,000 1,824,000 R eplace or Repair multiple culverts along KY 52 in Lee County.KY-52Lee PL175 DN 250,000 PROT RW 300,000 PROT UT 300,000 PROT CN Project Cost: 0 250,000 600,000 A DDRESS DEFICIENCIES OF GOOSE CREEK RD BRIDGE OVER CSX RAILROAD. (065R00604N) CR-1124Lee PL10013 DN 90,000 BRZ RW UT CN 1,300,000 BRZ Project Cost: 1,390,000 0 0 EXTEND TWO WAY LEFT TURNING LANE FROM .047 MILES NORTH OF LEE COUNTY SENIOR CITIZENS CENTER TO .103 MILES SOUTH OF GRAND AVE (2020CCN) KY-11L ee PL80102 DN 100,000 SPP RW 25,000 SPP UT 100,000 SPP CN 500,000 SPP Project Cost: 0 100,000 625,000 142 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADD TURN LANE AT THE INTERSECTION OF KY 11 AND KY 498K Y-11Lee PL80103 DN 100,000 SPP RW 25,000 SPP UT 50,000 SPP CN 250,000 SPP Project Cost: 0 100,000 325,000 R ECONSTRUCT ALONG KY 399 BETWEEN MP 5.75 AND 6.2 (2020CCN) KY-399Lee PL80104 DN 500,000 SPP RW 200,000 SPP UT 100,000 SPP CN Project Cost: 0 500,000 300,000 T otal for Lee county PL Total Amounts: CN UT RW DN 90,000 950,000 550,000 550,000 1,300,000 750,000 1,390,000 950,000 1,850,000 ADDRESS DEFICIENCIES OF BRIDGE OVER MUNCY CREEK ON US 421 0 .5 MILE SOUTH OF TAYLOR MORGAN ROAD (CR 1090). (066B00006N) US-421L eslie PL1095 DN RW UT CN 730,000 BRZ Project Cost: 730,000 0 0 I NSTALL GUARDRAIL ON US-421 IN LESLIE COUNTYUS-421Leslie PL4320 DN RW UT CN 36,000 GR Project Cost: 36,000 0 0 143 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 CONSTRUCT A NEW APPROACH FROM KY-1482 ONTO THE HAL R OGERS PARKWAY AT MP 39. (08CCN)(10CCR)(2011BOPP)(18CCN) (2020CCR) KY-1482Leslie PL8516 DN 260,000 SPP RW 1,020,000 SPP UT CN Project Cost: 260,000 0 1,020,000 U PGRADE ROUTE FROM SOMERSET TO HAZARD TO INTERSTATE STANDARDS: 4 LANE FROM CLAY/LESLIE LINE TO HYDEN SPUR, MP 35.929 TO MP 44.188 (SEGMENT 9). (16CCN)(18CCN) HR-9006Leslie PL8912 DN 1,000,000 NH RW UT CN Project Cost: 0 0 1,000,000 C ONSTRUCT RIGHT TURN LANE ON US 421 AT INTERSECTION WITH KY 80. (16CCN)(18CCN) US-421Leslie PL8951 DN 520,000 SPP RW 120,000 SPP UT 280,000 SPP CN Project Cost: 0 520,000 400,000 B RIDGE PROJECT IN LESLIE COUNTY ON (066B00055N) KY-2057 AT CUTSHIN CREEK KY-2057Leslie PL10214 DN 103,000 BRX RW UT CN 1,030,000 BRX Project Cost: 0 103,000 1,030,000 B RIDGE PROJECT IN LESLIE COUNTY ON (066C00090N) _CR-1210 AT _MIDDLE FORK CR-1210Leslie PL10216 DN 21,000 BRZ RW UT CN 210,000 BRZ Project Cost: 0 231,000 0 144 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL NEW GUARDRAIL ON KY 2009 FROM MP 13.418 TO MP 1 4.767.(18CCN) KY-2009Leslie PL80003 DN RW UT CN 500,000 SPP Project Cost: 0 500,000 0 I NSTALL NEW GUARDRAIL ON KY 1482 FROM MP 0 TO MP 1.9. (18CCN) KY-1482Leslie PL80004 DN RW UT CN 110,000 SPP Project Cost: 0 0 110,000 I NSTALL NEW GUARDRAIL ON KY 257 FROM MP 5.723 TO MP 5.853. (18CCN) KY-257Leslie PL80005 DN RW UT CN 30,000 SPP Project Cost: 0 0 30,000 I NSTALL NEW GUARDRAIL ON KY 1807 FROM MP 0.914 TO MP 1.256. (18CCN) KY-1807Leslie PL80006 DN RW UT CN 50,000 SPP Project Cost: 0 0 50,000 CONSTRUCT A SECONDARY RUNAWAY TRUCK RAMP ON KY 118 ( HYDEN SPUR) JUST BEFORE THE INTERSECTION WITH KY 80/US 421 TO INCLUDE A NEW BOX CULVERT OR BRIDGE AT THE INTERSECTION(18CCN) (2020CCR) KY-118L eslie PL80007 DN 550,000 SPP RW UT CN Project Cost: 0 550,000 0 145 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 GUARD RAIL INSTALLATION ON BULL SKIN RD MP 1.582 TO MP 2 ( 2020CCN) KY-1482Leslie PL80108 DN RW UT CN 50,000 GR Project Cost: 50,000 0 0 G UARD RAIL INSTALLATION ON WOOTEN RD FROM MP 0.089 TO MP 3.567 AS NEEDED (2020CCN) KY-1807Leslie PL80109 DN RW UT CN 150,000 GR Project Cost: 150,000 0 0 T otal for Leslie county PL Total Amounts: CN UT RW DN 260,000 1,194,000 1,000,000 1,140,000 280,000 966,000 710,000 1,220,000 1,226,000 1,904,000 3,640,000 I MPROVE US-119 FROM NORTH OF KY-15 TO BRASS DRIVE (SOUTH).(16CCN)(18CCR) (2020CCR) US-119Letcher PL199.1000 DN RW 1,300,000 SPP UT 1,750,000 SPP CN Project Cost: 3,050,000 0 0 I MPROVE US-119 FROM KY-2034/COUGAR DRIVE TO BRASS DRIVE (MP 16.731 TO 17.740). THROUGH MAYKING (MP 19.925 TO 20.6) AND AUXILIARY LANE (MP 22.0 TO 22.75) (16CCN)(SEE 12-199.10 FOR D, R, U) (18CCR) US-119Letcher PL199.1500 DN RW UT CN 6,000,000 NH Project Cost: 0 0 6,000,000 146 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS DEFICIENCIES OF BRIDGE ON HAMPTON BRANCH (CR 1 226) (MP 0.01) OVER COWAN CREEK. 067C00021N CR-1226Letcher PL1125 DN RW UT CN 434,000 BRZ Project Cost: 434,000 0 0 I NSTALL GUARDRAIL ON KY-463 IN LETCHER COUNTYKY-463Letcher PL4311 DN RW UT CN 72,000 GR Project Cost: 72,000 0 0 I NSTALL GUARDRAIL ON KY-588 IN LETCHER COUNTYKY-588Letcher PL4318 DN RW UT CN 102,000 GR Project Cost: 102,000 0 0 I NSTALL GUARDRAIL ON KY-317 IN LETCHER COUNTYKY-317Letcher PL4326 DN RW UT CN 58,000 GR Project Cost: 58,000 0 0 I NSTALL GUARDRAIL ON KY-931 IN LETCHER COUNTYKY-931Letcher PL4327 DN RW UT CN 75,000 GR Project Cost: 75,000 0 0 147 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-588 IN LETCHER COUNTYK Y-588Letcher PL4344 DN RW UT CN 92,000 GR Project Cost: 0 92,000 0 I NSTALL GUARDRAIL ON KY-7 IN LETCHER COUNTYKY-7Letcher PL4345 DN RW UT CN 44,000 GR Project Cost: 0 44,000 0 I NSTALL GUARDRAIL ON KY-931 IN LETCHER COUNTYKY-931Letcher PL4346 DN RW UT CN 13,000 GR Project Cost: 0 13,000 0 I NSTALL GUARDRAIL ON KY-1103 IN LETCHER COUNTYKY-1103Letcher PL4358 DN RW UT CN 102,000 GR Project Cost: 0 0 102,000 I NSTALL GUARDRAIL ON KY-1103 IN LETCHER COUNTYKY-1103Letcher PL4359 DN RW UT CN 102,000 GR Project Cost: 0 0 102,000 148 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-7 IN LETCHER COUNTYK Y-7Letcher PL4360 DN RW UT CN 152,000 GR Project Cost: 0 0 152,000 I NSTALL GUARDRAIL ON KY-931 IN LETCHER COUNTYKY-931Letcher PL4361 DN RW UT CN 55,000 GR Project Cost: 0 0 55,000 I NSTALL GUARDRAIL ON KY-931 IN LETCHER COUNTYKY-931Letcher PL4362 DN RW UT CN 11,000 GR Project Cost: 0 0 11,000 I NSTALL GUARDRAIL ON KY-588 IN LETCHER COUNTYKY-588Letcher PL4380 DN RW UT CN 86,000 GR Project Cost: 0 0 86,000 B RIDGE PROJECT IN LETCHER COUNTY ON (067B00038N) KY-7 at CSX RR & N Frk KY River KY-7Letcher PL10017 DN 570,000 BRX RW UT CN 5,700,000 BRX Project Cost: 0 6,270,000 0 149 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN LETCHER COUNTY ON (067B00023N) KY-805 AT P otter Fork KY-805Letcher PL10117 DN 29,000 FBP2 RW UT CN 290,000 FBP2 Project Cost: 0 319,000 0 B RIDGE PROJECT IN LETCHER COUNTY ON (067B00113N) KY-1862 AT NORTH FORK KY RIVER KY-1862Letcher PL10123 DN 75,000 FBP2 RW UT CN 750,000 FBP2 Project Cost: 0 825,000 0 B RIDGE PROJECT IN LETCHER COUNTY ON (067B00118N) KY-1862 AT PINE CREEK KY-1862Letcher PL10124 DN 19,000 FBP2 RW UT CN 190,000 FBP2 Project Cost: 0 0 209,000 R ECONSTRUCT THE BRIDGE OVER COLLIER'S CREEK BRIDGE TO CORRECT A DIP (2020CCN) KY-3404, PF-9999 Letcher PL80113 DN 100,000 BRZ RW 50,000 BRZ UT 50,000 BRZ CN 175,000 BRZ Project Cost: 100,000 100,000 175,000 I NSTALL A LEFT TURN AT INTERSECTION OF KY 15 AND KY 3401 (2020CCN) KY-3401Letcher PL80114 DN 185,000 SPP RW 30,000 SPP UT 20,000 SPP CN Project Cost: 0 185,000 50,000 150 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Spot improvements along KY 113 from KY 2545 to Landfill Rd where t he Letcher County Transfer Station is located. KY-113Letcher PL80200 DN 30,000 STP2 RW 25,000 STP2 UT 130,000 STP2 CN Project Cost: 0 30,000 155,000 T otal for Letcher county PL Total Amounts: CN UT RW DN 100,000 889,000 19,000 1,300,000 50,000 55,000 1,750,000 50,000 150,000 741,000 6,889,000 6,873,000 3,891,000 7,878,000 7,097,000 N EW ROUTE FROM VANCEBURG TO KY-59 FROM POLLITT LANE IN VANCEBURG (ALT. 5B1-2 PER PLANNING STUDY). (2020CCR) KY-59Lewis PL231 DN 3,000,000 STP2 RW 2,500,000 STP2 UT CN Project Cost: 0 3,000,000 2,500,000 R ECONSTRUCT KY-8 FROM KY-8C IN GARRISON TO SCAFFOLD LICK ROAD.(16CCN)(18CCN) KY-8Lewis PL8806.1000 DN 500,000 SPP RW UT CN Project Cost: 0 0 500,000 R ECONSTRUCT KY-57 FROM KY-9 TO FLEMING/LEWIS COUNTY LINE (14CCN) (16CCR) (18CCN) (2020CCR) KY-57Lewis PL8807 DN 1,000,000 NH RW UT CN Project Cost: 0 1,000,000 0 151 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Total for Lewis county P L Total Amounts: CN UT RW DN 4,000,000 500,000 2,500,000 0 4,000,000 3,000,000 U S-27 CORRIDOR FROM SOMERSET TO LEXINGTON. IMPROVE SAFETY AND REDUCE CONGESTION ON US-27 FROM KY-1247 TO EDUCATION WAY. US-27Lincoln PL167 DN RW 3,800,000 4,000,000 NH UT CN Project Cost: 0 3,800,000 4,000,000 I MPROVE US-27 FROM KY-590 TO BELL STREET IN STANFORD. (INCLUDES NEW GOSHEN CUT-OFF ROAD)(2005HPP-KY115)(18CCR) US-27Lincoln PL196 DN RW UT CN 6,500,000 NH Project Cost: 6,500,000 0 0 I NSTALL GUARDRAIL ON KY-1194 IN LINCOLN COUNTY (2020CCR)KY-1194Lincoln PL4317 DN RW UT CN 11,000 GR Project Cost: 11,000 0 0 I NSTALL GUARDRAIL ON KY-1194 IN LINCOLN COUNTY (2020CCR)KY-1194Lincoln PL4319 DN RW UT CN 24,000 GR Project Cost: 24,000 0 0 152 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-39 IN LINCOLN COUNTY (2020CCR)K Y-39Lincoln PL4320 DN RW UT CN 28,000 GR Project Cost: 28,000 0 0 B RIDGE PROJECT IN LINCOLN COUNTY ON (069B00023N) KY-78 AT HANGING FORK KY-78Lincoln PL10054 DN 167,000 FBP RW UT CN 1,670,000 FBP Project Cost: 167,000 1,670,000 0 N EW TURNING LANE AT ARCADIA VIEW DRIVE(18CCN) (2020CCR)US-127Lincoln PL80000 DN RW 60,000 SPP UT 60,000 SPP CN 840,000 SPP Project Cost: 120,000 840,000 0 U S 150 NEW TURNING LANE NEAR HUBBLE ROAD AND CRAWFORD LANE(18CCN) (2020CCR) US-150Lincoln PL80001 DN 100,000 SPP RW UT 50,000 SPP CN 350,000 SPP Project Cost: 150,000 350,000 0 R econstruct US 27 From Bell Street (End of 8-196.00) in Stanford to Lincoln-Garrard County Line. (18CCN) (2020CCR) US-27Lincoln PL80009 DN 2,100,000 NH RW 7,500,000 NH UT CN Project Cost: 2,100,000 0 7,500,000 153 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARD RAIL ON GOSHEN RD AT DIX RIVER BRIDGE ( 2020CCN) CR-1043Lincoln PL80110 DN RW UT CN 25,000 GR Project Cost: 25,000 0 0 I NSTALL TURN LANE AT DOLLAR GENERAL STORE ON US 150 (2020CCN) US-150Lincoln PL80111 DN 100,000 NH RW UT CN 900,000 NH Project Cost: 1,000,000 0 0 C ontinue ongoing improvements to US 27 Corridor from Somerset to Lexington. Improve Level of Service and safety on US 27 from KY 328 to KY 501 in Lincoln County. us-27Lincoln PL80201 DN 2,455,800 NH RW UT CN Project Cost: 0 2,455,800 0 C ONDUCT A PLANNING STUDY TO ASSES HOW TO FURTHER MITIGATE ROCKSLIDE DAMAGE ON KY 300 KY-300Lincoln PL 1,000,000 SPP80202 DN RW UT CN Project Cost: 0 1,000,000 0 CONDUCT A PLANNING STUDY FOR NEW ROADWAY FROM THE END OF KY 1194 TO US 27 KY-1194L incoln PL 500,000 SPP80203 DN RW UT CN Project Cost: 0 500,000 0 T otal for Lincoln county PL Total Amounts: CN UT RW DN 1,500,000 2,467,000 2,455,800 60,000 3,800,000 11,500,000 110,000 7,488,000 2,860,000 10,125,000 10,615,800 11,500,000 154 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS CONDITION OF I-24 FROM MILEPOINT 29.543 TO MILEPOINT 3 3.664 I-24L ivingston PL20007 DN 1,075,000 NHPM RW UT CN 10,750,000 NHPM Project Cost: 0 0 11,825,000 T otal for Livingston county PL Total Amounts: CN UT RW DN 1,075,000 10,750,000 0 0 11,825,000 I MPROVE SAFETY BY IMPROVING SIGHT LINES CROSSING RAILROAD BETWEEN STOCKYARDS AND INDUSTRIAL PARK. (16CCN)(18CCN) (2020CCR) KY-2349Logan PL8908 DN 170,000 SPP RW 120,000 SPP UT 170,000 SPP CN 1,000,000 SPP Project Cost: 170,000 290,000 1,000,000 R EPLACE BRIDGE ON US 79 TO WIDEN FOR FREIGHT MOVEMENT AND IMPROVE SAFETY. BRIDGE ID (071B00025N)(BRIDGE OVER WHIPPOORWILL CREEK) AT MP 4.65 (2020CCR)(BUILD - $2.344M) (LOGAN COUNTY MATCH - $300,000) US-79Logan PL10010 DN RW UT CN 2,930,000 NH Project Cost: 2,930,000 0 0 W IDEN US-79 TO 4 LANES FROM TODD COUNTY LINE TO INTERSECTION WITH RUSSELLVILLE BYPASS.(18CCN) (2020CCR) US-79Logan PL80050 DN RW 6,740,000 NH UT CN Project Cost: 0 0 6,740,000 155 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Replace and widen bridges on US-79 at MP 2.921 in Logan County, a nd MP 7.613 in Todd County. (Includes item No. 3-80102) (2020CCN) (BUILD) (To be let with 3-10010 & 3-80001.20) US-79Logan PL80100 DN RW UT CN 4,750,000 SPP Project Cost: 0 0 4,750,000 R EPLACE AND WIDEN TO 4 LANES BRIDGE ON US-79 AT MP 5.950 (BRIDGE OVER DRY FORK) (2020CCN) US-79Logan PL80101 DN RW 150,000 SPP UT 250,000 SPP CN 1,800,000 SPP Project Cost: 0 400,000 1,800,000 I NTERSECTION IMPROVEMENTS AT US-68X AND KY-103.US-68Logan PL80216 DN 20,000 SPP RW 25,000 SPP UT 50,000 SPP CN 150,000 SPP Project Cost: 0 245,000 0 T otal for Logan county PL Total Amounts: CN UT RW DN 170,000 20,000 295,000 6,740,000 470,000 2,930,000 150,000 7,550,000 3,100,000 935,000 14,290,000 A DD RESTROOM FACILITY TO I-24 EASTBOUND & WESTBOUND WEIGH STATIONS IN LYON COUNTY (DESIGN FUNDS AUTHORIZED UNDER ITEM NO. 99-44.00) I -24Lyon PL7 DN RW UT CN 1,900,000 NH Project Cost: 0 0 1,900,000 156 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 RELOCATE US-641 FROM US-62 NEAR EDDYVILLE TO SOUTH OF T HE LYON/CALDWELL COUNTY LINE (2020CCR) Lyon PL187.5000 DN 1,500,000 STPF RW UT CN Project Cost: 1,500,000 0 0 B RIDGE PROJECT IN LYON COUNTY ON (072B00027N) KY-1943 AT CRAB CREEK KY-1943Lyon PL10154 DN 143,000 FBP RW UT CN 1,430,000 FBP Project Cost: 1,573,000 0 0 ADDRESS PAVEMENT CONDITION OF I-24 BOTH DIRECTION(S) FROM M ILEPOINT 33.988 TO MILEPOINT 45.133 (2020CCR) I-24L yon PL20008 DN 900,000 NHPM RW UT CN 9,000,000 NHPM Project Cost: 0 0 9,900,000 ADDRESS CONDITION OF I-69 FROM MILEPOINT 67.53 TO MILEPOINT 6 8.116 I-69L yon PL22075 DN 20,000 NHPM RW UT CN 200,000 NHPM Project Cost: 0 0 220,000 T otal for Lyon county PL Total Amounts: CN UT RW DN 1,643,000 920,000 1,430,000 11,100,000 3,073,000 0 12,020,000 157 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE KY-52 FROM WALLACE MILL ROAD TO INTERSTATE 75 AT T HE DUNCANNON ROAD INTERCHANGE. (02CCR)(12CCN)(14CCR) (DESIGN/BUILD)(16CCR)(18CCR) (2020CCR) KY-52Madison PL235 DN RW UT CN 5,000,000 STP2 Project Cost: 0 0 5,000,000 P RIORITY SECTION II & III: WIDEN US-25 FROM US-421 TO PUMPKIN RUN.(SEE 7-251.10 FOR SEC III UTIL & CONST) (2006BOPC)(08CCR) (10CCR)(12CCR)(14CCR) US-25Madison PL251.4000 DN RW UT CN 4,200,000 4,200,000 NH Project Cost: 0 4,200,000 4,200,000 P ROPOSED ROADWAY IMPROVEMENTS FROM DUNCANNON RD TO THE MADISON CO AIRPORT TO INCLUDE CALEAST RD (KY 2881 MP.783-MP 2.780), JOHN BALLARD RD (KY 2877 MP0-MP.806 & CR 1236 MP0-MP.429) FROM MENELAUS TO AIRPORT RD, & A NEW BRIDGE OVER SILVER CR.(14CCN)(16CCR) (2020CCR) CR-1236, KY-2877, KY-2881 Madison PL8853 DN RW 2,440,000 STP UT 820,000 STP CN Project Cost: 0 2,440,000 820,000 ADDRESS CONDITION OF I-75 FROM MILEPOINT 73.408 TO MILEPOINT 8 3.400 I-75M adison PL20017 DN 1,380,000 NHPM RW UT CN 13,800,000 NHPM Project Cost: 0 15,180,000 0 A DD A LEFT TURN LANE ON US 421 INTO THE KINGSTON ELEMENTARY SCHOOL (2020CCN) US-421Madison PL80101 DN RW UT CN 240,000 SPP Project Cost: 240,000 0 0 158 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 REHABILITATE THE BRIDGE OVER THE RAILROAD ON US 25 NEAR T HE GOLDENLEAF DEVELOPMENT AREA (2020CCN) US-25Madison PL80109 DN 350,000 SPP RW UT CN Project Cost: 0 350,000 0 E XTEND BOGGS LN TO CONNECT TO PAVILION WAY (2020CCN)CR-1200, CS-1526 Madison PL80110 DN 270,000 SPP RW UT CN Project Cost: 0 0 270,000 W IDEN KY 374 (SPEEDWELL RD) FROM KY 25 TO US 421 (2020CCN)KY-374Madison PL80111 DN 4,000,000 SPP RW UT CN Project Cost: 0 4,000,000 0 N ew road that extends from Menelaus Road (KY 1983) at existing MP 2.851 to Mayde Road in Berea. Madison PL80201 DN 450,000 SPP RW 750,000 SPP UT 750,000 SPP CN Project Cost: 0 450,000 1,500,000 S mall urban area study to evaluate potential improvements and land access opportunities on Goggins Lane, Tates Creek, Crutcher Pike, and Barnes Mill Road, with improvements on Barnes Mill Road including the length from Crutcher Pike to the interstate. ky-876Madison PL80210 DN 150,000 SPP RW UT CN Project Cost: 0 150,000 0 T otal for Madison county PL Total Amounts: CN UT RW DN 6,330,000 270,000 2,440,000 750,000 1,570,000 240,000 18,000,000 9,200,000 240,000 26,770,000 11,790,000 159 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 MOUNTAIN PARKWAY CORRIDOR: EXTEND THE FOUR LANE M OUNTAIN PARKWAY FROM US 460 TO THE MAGOFFIN/FLOYD COUNTY LINE. KY-114Magoffin PL169 DN 5,300,000 NH RW UT CN Project Cost: 0 5,300,000 0 I NSTALL GUARDRAIL ON KY-40 IN MAGOFFIN COUNTYKY-40Magoffin PL4307 DN RW UT CN 63,000 GR Project Cost: 63,000 0 0 I NSTALL GUARDRAIL ON KY-867 IN MAGOFFIN COUNTYKY-867Magoffin PL4310 DN RW UT CN 60,000 GR Project Cost: 0 0 60,000 IMPROVE US-460 IN MAGOFFIN COUNTY AT IVY POINT HILL WEST OF S ALYERSVILLE. (16CCN) (2020CCR) US-460M agoffin PL8901 DN RW UT CN 4,280,000 STPF Project Cost: 0 0 4,280,000 T otal for Magoffin county PL Total Amounts: CN UT RW DN 5,300,000 63,000 4,340,000 63,000 5,300,000 4,340,000 160 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS SAFETY AND GEOMETRIC DEFICIENCIES ALONG KY 49 F ROM RIVERSIDE BRIDGE TO NARROWS RD, APPROXIMATELY 1.3 MILES SOURTH OF KY 337 (12CCN)(2020CCN) MP 6.692 TO 10.5 KY-49Marion PL8715 DN 2,200,000 SPP RW UT CN Project Cost: 2,200,000 0 0 S POT IMPROVEMENTS ON KY-49 (MP 20.900 TO MP 21.830) AS PER THE KY-49 PLANNING STUDY. (14CCN)(18CCN) (2020CCR) KY-49Marion PL8802 DN RW UT CN 3,640,000 STP2 Project Cost: 0 3,640,000 0 REDUCE CONGESTION AT MAJOR INTERSECTION IN FRONT OF NEW S CHOOL MP 12.2 TO 12.8 (2020CCN) KY-2154, U S-68 Marion PL80152 DN RW 1,200,000 STPF UT 1,800,000 STPF CN 3,000,000 STPF Project Cost: 0 1,200,000 4,800,000 E xtend KY2154 Bypass from KY208 to KY49.KY-2154Marion PL80153 DN 1,000,000 STP2 RW 5,500,000 STP2 UT 2,320,000 STP2 CN Project Cost: 1,000,000 5,500,000 2,320,000 IMPROVE THE INTERSECTION OF KY 49 AT KY 52 IN LORETTO AT MP 2 7.374 KY-49M arion PL80251 DN 150,000 SPP RW 50,000 SPP UT 300,000 SPP CN Project Cost: 0 0 500,000 161 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 REPLACE LOW WATER STRUCTURE ON SILOAM ROAD (CR 1119) O VER NORTH ROLLING FORK NEAR KY 337 INTERSECTION MP 0.089 TO MP 0.122 CR-1119Marion PL80252 DN 200,000 FBP RW 25,000 FBP UT 150,000 FBP CN 1,000,000 FBP Project Cost: 0 375,000 1,000,000 I MPROVE CONNECTIVITY AND CONGESTION BETWEEN US 68 AND KY 55 ON THE EAST SIDE OF LEBANON (APPROXIMATELY 2 MILES) PF-9999Marion PL80259 DN 998,400 SPP RW UT CN Project Cost: 0 998,400 0 T otal for Marion county PL Total Amounts: CN UT RW DN 3,200,000 1,198,400 150,000 6,725,000 50,000 150,000 4,420,000 3,640,000 4,000,000 3,200,000 11,713,400 8,620,000 I MPROVE ACCESS AND REDUCE CONGESTION ON US-62 FROM KY-95 TO THE EXISTING FOUR-LANE HIGHWAY AT LONE VALLEY RD NEAR I-24 INTERCHANGE AND FUTURE I-69 CONNECTION. (2020CCR) US-62Marshall PL398 DN RW 250,000 STP1 UT 500,000 STP1 CN Project Cost: 0 750,000 0 B RIDGE PROJECT IN MARSHALL COUNTY ON (079B00017N) KY-408 AT OVERFLOW STRUCTURE KY-408Marshall PL10018 DN 140,000 BRX RW UT CN 1,400,000 BRX Project Cost: 0 1,540,000 0 162 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 REPLACE BRIDGE ON EGNERS FERRY RD (KY-408) LOCATED 1.1 MI E AST OF US-641 AT MP 8.94. 079B00018N KY-408Marshall PL10167 DN RW 5,000 FBP UT 5,000 FBP CN 1,600,000 FBP Project Cost: 10,000 1,600,000 0 R EPLACE BRIDGE ON EGNERS FERRY RD (KY-408) LOCATED 1.5 MI EAST OF US-641 AT MP 9.79. 079B00020N KY-408Marshall PL10168 DN RW 5,000 BRZ UT 5,000 BRZ CN 4,000,000 BRZ Project Cost: 10,000 4,000,000 0 B RIDGE PROJECT IN MARSHALL COUNTY ON (079B00018N) KY-408 AT TRIB. OF CLARKS RIVER KY-408Marshall PL10172 DN 112,000 FBP RW UT CN 1,120,000 FBP Project Cost: 112,000 1,120,000 0 B RIDGE PROJECT IN MARSHALL COUNTY ON (079B00019N) KY-408 AT CLARKS RIVER KY-408Marshall PL10173 DN 230,000 FBP RW UT CN 2,300,000 FBP Project Cost: 230,000 2,300,000 0 B RIDGE PROJECT IN MARSHALL COUNTY ON (079B00020N) KY-408 AT CLARKS RIVER KY-408Marshall PL10174 DN 575,000 FBP RW UT CN 5,750,000 FBP Project Cost: 575,000 5,750,000 0 163 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN MARSHALL COUNTY ON (079B00037N) KY-402 A T MARTIN CREEK KY-402Marshall PL10175 DN 101,000 FBP RW UT CN 1,010,000 FBP Project Cost: 101,000 0 1,010,000 B RIDGE PROJECT IN MARSHALL COUNTY ON (079B00040N) KY-402 AT EAST FORK CLARKS RIVER KY-402Marshall PL10176 DN 903,000 FBP RW UT CN 9,030,000 FBP Project Cost: 903,000 0 9,030,000 B RIDGE PROJECT IN MARSHALL COUNTY ON (079B00118L) I 24 NON CARDINAL AT TENNESSEE RIVER I -24Marshall PL10178 DN RW UT CN 15,000,000 BRO Project Cost: 0 0 15,000,000 B RIDGE PROJECT IN MARSHALL COUNTY ON (079B00118R) I-24 AT TENNESSEE RIVER I -24Marshall PL10179 DN RW UT CN 15,000,000 BRO Project Cost: 0 0 15,000,000 B RIDGE PROJECT IN MARSHALL COUNTY ON (079B00138N) KY-2603 AT SOLDIER CREEK KY-2603Marshall PL10180 DN 158,000 FBP RW UT CN 1,580,000 FBP Project Cost: 158,000 1,580,000 0 T otal for Marshall county PL Total Amounts: CN UT RW DN 2,079,000 140,000 10,000 250,000 10,000 500,000 17,750,000 40,040,000 2,099,000 18,640,000 40,040,000 164 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INEZ TO WARFIELD (SECTION 2-1): FROM LITTLE BLACKLOG TO B OOTH FORK. [STA. 190+00 TO STA. 298+00 (ENGLISH)] (2002BOP) (12CCR)(AR/W)(16CCR) KY-40Martin PL154.1100 DN RW UT 2,000,000 SPP CN Project Cost: 0 0 2,000,000 I MPROVE ALIGNMENT AND GEOMETRICS OF THE CURVE LOCATED JUST BEFORE THE JUNCTION OF KY-2031 AND KY-40 TO .1 MILES BEFORE GORDON HOLLOW ROAD, AND IMPROVE THE CULVERT/SAFETY DESIGN TO INCREASE MOTORIST AND PEDESTRIAN SAFETY. (12CCR) (2020CCR) KY-40Martin PL192 DN RW 309,400 SPP UT CN Project Cost: 0 309,400 0 S ETSER BRANCH ROAD BRIDGE AND APPROACHES OVER MIDDLE FORK OF ROCKCASTLE CREEK (C43) (OFF NHS) (FD04) (2000BOP): (080C00043N) CR-1215Martin PL4093 DN RW UT CN 480,000 BRX Project Cost: 0 480,000 0 I NSTALL GUARDRAIL ON KY-1224 IN MARTIN COUNTYKY-1224Martin PL4312 DN RW UT CN 28,000 GR Project Cost: 28,000 0 0 I NSTALL GUARDRAIL ON KY-3 IN MARTIN COUNTYKY-3Martin PL4313 DN RW UT CN 50,000 GR Project Cost: 50,000 0 0 165 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-2032 IN MARTIN COUNTYK Y-2032Martin PL4328 DN RW UT CN 74,000 GR Project Cost: 74,000 0 0 I NSTALL GUARDRAIL ON KY-292 IN MARTIN COUNTYKY-292Martin PL4329 DN RW UT CN 64,000 GR Project Cost: 64,000 0 0 I NSTALL GUARDRAIL ON KY-292 IN MARTIN COUNTYKY-292Martin PL4330 DN RW UT CN 24,000 GR Project Cost: 24,000 0 0 I NSTALL GUARDRAIL ON KY-292 IN MARTIN COUNTYKY-292Martin PL4331 DN RW UT CN 21,000 GR Project Cost: 21,000 0 0 I NSTALL GUARDRAIL ON KY-292 IN MARTIN COUNTYKY-292Martin PL4332 DN RW UT CN 210,000 GR Project Cost: 210,000 0 0 166 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-3 IN MARTIN COUNTYK Y-3Martin PL4333 DN RW UT CN 38,000 GR Project Cost: 0 38,000 0 I NSTALL GUARDRAIL ON KY-3 IN MARTIN COUNTYKY-3Martin PL4335 DN RW UT CN 83,000 GR Project Cost: 0 83,000 0 I NSTALL GUARDRAIL ON KY-292 IN MARTIN COUNTYKY-292Martin PL4347 DN RW UT CN 37,000 GR Project Cost: 0 37,000 0 I NSTALL GUARDRAIL ON KY-292 IN MARTIN COUNTYKY-292Martin PL4348 DN RW UT CN 20,000 GR Project Cost: 0 20,000 0 I NSTALL GUARDRAIL ON KY-292 IN MARTIN COUNTYKY-292Martin PL4349 DN RW UT CN 7,000 GR Project Cost: 0 7,000 0 167 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-292 IN MARTIN COUNTYK Y-292Martin PL4381 DN RW UT CN 47,000 GR Project Cost: 0 0 47,000 I NSTALL GUARDRAIL ON KY-908 IN MARTIN COUNTYKY-908Martin PL4480 DN RW UT CN 89,000 GR Project Cost: 89,000 0 0 B RIDGE PROJECT IN MARTIN COUNTY ON (080B00014N) KY-292 AT LONG BRANCH KY-292Martin PL10129 DN 34,000 BRX RW UT CN 340,000 BRX Project Cost: 0 34,000 340,000 B RIDGE PROJECT IN MARTIN COUNTY ON (080C00057N) Johnson Bottom AT Rockcastle Creek CR-1317Martin PL10130 DN 98,000 FBP2 RW UT CN 980,000 FBP2 Project Cost: 0 0 1,078,000 T otal for Martin county PL Total Amounts: CN UT RW DN 34,000 98,000 309,400 2,000,000 560,000 665,000 1,367,000 560,000 1,008,400 3,465,000 168 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 NEW FULLY CONTROLLED ACCESS ROUTE FROM US 68 NEAR W ASHINGTON EAST TO KY 11 INCLUDING A NEW I-CHNG AT KY 11. (PRIORITY SECTION)(2004BOPC)(06CCR)(18CCN) Mason PL147.2000 DN 2,000,000 SPP RW UT CN Project Cost: 0 2,000,000 0 N EW FULLY CONTROLLED ACCESS ROUTE FROM KY 11 NORTHEAST TO KY 9 (AA HWY) INCLUDING NEW I-CHNG AT KY 9. (2004BOPC)(06CCR)(18CCN) PF-9999Mason PL147.6000 DN 2,000,000 SPP RW UT CN Project Cost: 0 0 2,000,000 I NSTALL GUARDRAIL ON US-62 IN MASON COUNTYUS-62Mason PL4308 DN RW UT CN 96,000 GR Project Cost: 96,000 0 0 I NSTALL GUARDRAIL ON US-62 IN MASON COUNTYUS-62Mason PL4309 DN RW UT CN 106,000 GR Project Cost: 106,000 0 0 I NSTALL GUARDRAIL ON KY-1448 IN MASON COUNTYKY-1448Mason PL4318 DN RW UT CN 90,000 GR Project Cost: 0 0 90,000 169 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN MASON COUNTY ON (081C00009N) KENNEDY C REEK RD AT KENNEDY CREEK CR-1019Mason PL8911 DN 52,000 BRZ RW UT CN 520,000 BRZ Project Cost: 0 572,000 0 A DDRESS CABLES AND OTHER DEFICIENCIES ON WILLIAM HARSHA BRIDGE OVER THE OHIO RIVER. (JOINT PROJECT WITH OHIO 18%) (081B00069N)(BSBP)(SD) US-68Mason PL 10013.1000 DN R W UT CN 8,000,000 BRO Project Cost: 0 8,000,000 0 B RIDGE PROJECT IN MASON COUNTY ON (081B00041N) US-62X AT OHIO RIVER-MYVLLE- CSX R CS-1179Mason PL10091 DN 2,126,000 BRZ RW UT CN Project Cost: 0 2,126,000 0 I MPROVE SAFETY AND OPERATIONAL EFFICIENCY OF THE INTERSECTION OF KY 9 (AA) AND US 62 LOCATED IN MAYSVILLE. (2020CCN) KY-9Mason PL80107 DN RW 1,150,000 SPP UT 560,000 SPP CN Project Cost: 1,150,000 560,000 0 T otal for Mason county PL Total Amounts: CN UT RW DN 4,178,000 2,000,000 1,150,000 560,000 202,000 8,520,000 90,000 1,352,000 13,258,000 2,090,000 170 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Improve KY 1286 from US 45(MP 3.623) to US 62(MP 5.000)(Priority S ection 1). KY-1286McCracken PL153.1000 DN RW UT CN 6,500,000 STP1 Project Cost: 0 0 6,500,000 E xtend KY 1286 from KY 998 (MP 6.916) to US 60. (Priority Section 2)KY-1286McCracken PL153.2000 DN 250,000 STP1 RW 3,500,000 STP1 UT 250,000 STP1 CN Project Cost: 0 3,750,000 250,000 I mprove KY 1286 from US 62(MP 5.000) to Perkins Creek Bridge (MP 5.896, B00167N). (Priority Section 3) KY-1286McCracken PL153.3000 DN 150,000 STP1 RW 1,500,000 STP1 UT 500,000 STP1 CN Project Cost: 150,000 2,000,000 0 I mprove KY 1286 from Perkins Creek Bridge (MP 5.896, B00167N) to KY 998 (MP 6.916). (Priority Section 4) KY-1286McCracken PL153.4000 DN 150,000 STP1 RW 2,500,000 STP1 UT 750,000 STP1 CN Project Cost: 150,000 2,500,000 750,000 RELOCATION AND MINOR WIDENING OF US-60 FROM CLARKS RIVER TO US-62 JCT.(10CCR)(14CCR)(LET W/ 1-1115.20)(16CCR) US-60M cCracken PL1115.1000 DN 250,000 NH RW UT CN Project Cost: 0 0 250,000 171 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 NEW ACCESS ROAD FROM KY-305 NEAR KY-998, EXTENDING WEST TO THE OHIO RIVER MEGAPARK. (2-LANE INITIAL, 4-LANE ULTIMATE) (12CCN)(14CCR)(18CCN) McCracken PL8702 DN 680,000 SPP RW 2,000,000 SPP UT 500,000 SPP CN 6,500,000 SPP Project Cost: 680,000 2,500,000 6,500,000 C ONSTRUCT ULTIMATE ACCESS ROAD FROM KY-305 TO THE OHIO RIVER MEGAPARK. KY-305McCracken PL8702.1000 DN 1,040,000 SPP RW UT CN Project Cost: 0 0 1,040,000 B RIDGE PROJECT IN MCCRACKEN COUNTY ON (073B00030N) KY-3520 AT P&L RAILWAY KY-3520McCracken PL10162 DN 228,000 FBP RW UT CN 2,280,000 FBP Project Cost: 2,508,000 0 0 BRIDGE PROJECT IN MCCRACKEN COUNTY ON (073B00100N) I-24 AT O HIO RIVER I -24M cCracken PL10166 DN 1,500,000 FBP2 RW UT CN 15,000,000 FBP2 Project Cost: 0 1,500,000 15,000,000 T otal for McCracken county PL Total Amounts: CN UT RW DN 1,208,000 1,750,000 1,290,000 9,500,000 1,000,000 1,000,000 2,280,000 28,000,000 3,488,000 12,250,000 30,290,000 172 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN MCCREARY COUNTY ON (074C00008N) ROCK C REEK ROAD AR ROCK CREEK CR-1236McCreary PL1065 DN 70,000 BRZ RW UT CN 700,000 BRZ Project Cost: 0 770,000 0 BRIDGE PROJECT IN MCCREARY COUNTY ON (074C00020N) JELLICO C REEK RD AT JELLICO CREEK CR-1190M cCreary PL10062 DN 102,000 BRZ RW UT CN 1,020,000 BRZ Project Cost: 0 1,122,000 0 P RELIMINARY ENGINEERING AND ENVIRONMENTAL CORRIDOR STUDY FOR IMPROVING SAFETY AND MAKING KY-92 A SCENIC ROUTE FROM MONTICELLO TO STEARNS (FLEXIBLE SOLUTIONS) (18CCN) (2020CCR) KY-92McCreary PL 1,500,000 SPP80004 DN RW UT CN Project Cost: 1,500,000 0 0 I MPROVE SAFETY BY CONSTRUCTING TURN LANES INTO COMMUNITY PARK AND WHITLEY CITY ELEMENTARY (2020CCN) US-27McCreary PL80101 DN RW 752,000 SPP UT 1,053,000 SPP CN Project Cost: 0 752,000 1,053,000 PROVIDE CONNECTIVITY, IMPROVE MOBILITY AND RESPONSE FROM U S 27 TO MCCREARY COUNTY HIGH SCHOOL (2020CCN) US-27M cCreary PL80102 DN 700,000 SPP RW 116,000 SPP UT CN Project Cost: 700,000 0 116,000 173 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE MOBILITY AND SAFETY RR CROSSING ELIMINATION BY C ONSTRUCTING BRIDGE BETWEEN SOUTHERN HIGHWAY AND MURRAY WILSON RD (2020CCN) CR-1199McCreary PL80103 DN 550,000 SPP RW 696,000 SPP UT CN Project Cost: 550,000 696,000 0 T otal for McCreary county PL Total Amounts: CN UT RW DN 1,500,000 1,250,000 172,000 1,448,000 116,000 1,053,000 1,720,000 2,750,000 3,340,000 1,169,000 I NSTALL GUARDRAIL ON US-431 IN MCLEAN COUNTYUS-431McLean PL4304 DN RW UT CN 19,000 GR Project Cost: 19,000 0 0 I NSTALL GUARDRAIL ON US-431 IN MCLEAN COUNTYUS-431McLean PL4312 DN RW UT CN 41,000 GR Project Cost: 0 0 41,000 I NSTALL GUARDRAIL ON US-431 IN MCLEAN COUNTYUS-431McLean PL4313 DN RW UT CN 13,000 GR Project Cost: 0 0 13,000 174 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 SPOT IMPROVEMENTS AT THE INTERSECTION OF US-431 AND K Y-250. (08CCN)(12CCR)(18CCN) (2020CCR) US-431McLean PL8400 DN RW 500,000 SPP UT 190,000 SPP CN Project Cost: 500,000 0 190,000 C ORRECT LINE OF SIGHT WITH INTERSECTION OF KY 56 & KY 1233. (14CCN)(18CCN) (2020CCR) KY-56McLean PL8852 DN RW 70,000 SPP UT 70,000 SPP CN Project Cost: 140,000 0 0 B RIDGE PROJECT IN MCLEAN COUNTY ON (075B00010N) KY-136 AT BUCK CREEK KY-136McLean PL10109 DN 366,000 FBP RW UT CN 3,660,000 FBP Project Cost: 366,000 0 3,660,000 B RIDGE PROJECT IN MCCLEAN COUNTY ON (075B00025N) KY-81 AT SLOUGH KY-81McLean PL10110 DN 40,000 FBP2 RW UT CN 400,000 FBP2 Project Cost: 0 0 440,000 B RIDGE PROJECT IN MCLEAN COUNTY ON (075B00034N) KY-136 AT LONG FALLS CREEK KY-136McLean PL10114 DN 86,000 FBP2 RW UT CN 860,000 FBP2 Project Cost: 0 0 946,000 175 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN MCCLEAN COUNTY ON (075B00039N) KY-140 A T STROUD CREEK KY-140McLean PL10115 DN 117,000 BRX RW UT CN 1,170,000 BRX Project Cost: 0 117,000 1,170,000 B RIDGE PROJECT IN MCCLEAN COUNTY ON (075B00053N) KY-1412 AT OVRFLO TRIB-GREEN RIVER KY-1412McLean PL10118 DN 169,000 FBP RW UT CN 1,690,000 FBP Project Cost: 1,859,000 0 0 T otal for McLean county PL Total Amounts: CN UT RW DN 535,000 117,000 126,000 570,000 70,000 190,000 1,709,000 6,144,000 2,884,000 117,000 6,460,000 R ECONSTRUCT KY 79 FROM KY 144 TO KY 1051. (12CCN)(14CCR) (18CCN) (2020CCR) KY-79Meade PL8705 DN 250,000 SPP RW 1,250,000 SPP UT CN Project Cost: 0 250,000 1,250,000 T otal for Meade county PL Total Amounts: CN UT RW DN 250,000 1,250,000 0 250,000 1,250,000 176 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE SAFETY, CORRECT GEOMETRICS, AND ENHANCE R EGIONAL CONNECTIVITY ON US 460 FROM THE INTERSECTION OF KY 1240 TO 0.7 MILES EAST OF THE MORGAN COUNTY LINE US-460Menifee PL80200 DN 1,500,000 NH RW UT CN Project Cost: 1,500,000 0 0 I mprove safety, correct geometrics, and enhance regional connectivity on US 460 from the intersection of KY 713 to Rothwell (MP 4.8). US-460Menifee PL80201 DN 1,000,000 NH RW UT CN Project Cost: 0 1,000,000 0 T otal for Menifee county PL Total Amounts: CN UT RW DN 1,500,000 1,000,000 1,500,000 1,000,000 0 I MPROVE SYSTEM MOBILITY ALONG MOBERLY ROAD FROM KY 390 TO KY 1989 IN NORTHWEST HARRODSBURG. (12CCR) (2020CCN) CS-1237Mercer PL417 DN RW 250,000 SPP UT 240,000 SPP CN 1,790,000 SPP Project Cost: 490,000 1,790,000 0 T otal for Mercer county PL Total Amounts: CN UT RW DN 250,000 240,000 1,790,000 490,000 1,790,000 0 177 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-70 IN METCALFE COUNTYK Y-70Metcalfe PL4308 DN RW UT CN 52,000 GR Project Cost: 0 52,000 0 H orizontal and vertical alignment spot improvement on US 68 in Metcalfe County, north of Edmonton, at the KY 70 intersection. (2020BOP) US-68Metcalfe PL8706.1000 DN RW 175,000 STPF UT 400,000 STPF CN Project Cost: 175,000 400,000 0 I MPROVE HIGHWAY SAFETY AND SYSTEMS MOBILITY IN THE KY 163 CORRIDOR BETWEEN KY 90 (MP 2.907) AND THE PROPOSED WEST EDMONTON BYPASS (MP 9.777). (16CCN)(18CCN) KY-163Metcalfe PL8955 DN 2,930,000 STP2 RW UT CN Project Cost: 0 2,930,000 0 B RIDGE PROJECT IN METCALFE COUNTY ON (085C00005N) MOSBY RIDGE RD at E FORK LITTLE BARREN RVR CR-1108Metcalfe PL10006 DN 123,000 BRZ RW UT CN 1,230,000 BRZ Project Cost: 0 123,000 1,230,000 T otal for Metcalfe county PL Total Amounts: CN UT RW DN 3,053,000 175,000 400,000 52,000 1,230,000 175,000 3,505,000 1,230,000 178 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 OPERATION OF TURKEY NECK BEND FERRY FOR FY 2022-2028. ( 12CCR) (2020CCR) KY-214Monroe PL128.1100 DN RW UT CN 865,000 865,000 865,000 SPP Project Cost: 865,000 865,000 865,000 RECONSTRUCT INTERSECTION OF KY 63 AND POPLAR LOG CHURCH R OAD (2020CCN) KY-63M onroe PL8954 DN RW 440,000 STP2 UT 510,000 STP2 CN 960,000 STP2 Project Cost: 950,000 0 960,000 R EPLACE BRIDGE ON KY-100 BETWEEN MP 14.7 AND 14.9. (18CCN)KY-100Monroe PL80003 DN RW 180,000 BRX UT 570,000 BRX CN Project Cost: 0 750,000 0 T urkey Neck Bend Bridge FeasibilityKY-214Monroe PL 300,000 SPP80200 DN RW UT CN Project Cost: 0 300,000 0 I mprove safety and mobility and address deficiencies with Town Creek bridge on KY-100 from KY-163 to KY-3144 in Tompkinsville. Includes Bridge ID 086B00005 ky-100Monroe PL80208 DN 930,000 BRO RW 2,600,000 BRO UT CN Project Cost: 0 930,000 2,600,000 T otal for Monroe county PL Total Amounts: CN UT RW DN 300,000 930,000 440,000 180,000 2,600,000 510,000 570,000 865,000 865,000 1,825,000 1,815,000 2,845,000 4,425,000 179 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 WIDEN KY-1991 FROM MAYSVILLE ROAD TO MIDLAND TRAIL I NDUSTRIAL PARK, MONTGOMERY COUNTY. (SEE 7-8501.00 FOR "SPB" FUNDS) (2005HPP-KY129) KY-1991Montgomery PL240 DN RW 1,000,000 STP1 UT 1,820,000 STP1 CN Project Cost: 2,820,000 0 0 U PGRADE HINKSTON PIKE IN MT. STERLING FROM NEW MIDLAND TRAIL TO THE NEW INDUSTRIAL PARK ENTRANCE (INCLUDES EXTENSION OF INDUSTRIAL ACCESS ROAD TO HINKSTON PIKE). (12CCR)(18CCN) KY-1991Montgomery PL411 DN RW 400,000 SPP UT 715,000 SPP CN Project Cost: 400,000 715,000 0 W IDEN EXISTING PAVEMENT & IMPROVE VERTICAL & HORIZONTAL CURVES FROM EXISTING MT STERLING BYPASS (KY 686) TO 500' W OF BENTBROOK SUBDIVISION. ADD FULL WIDTH SHOULDERS & A CENTER TURNING LANE IN CONGESTION AREAS FROM MP 2.2 TO 4.311.(14CCN)(16CCR)(18CCN) (2020CCR) US-60Montgomery PL8810 DN RW 4,600,000 STPF UT CN Project Cost: 0 0 4,600,000 T otal for Montgomery county PL Total Amounts: CN UT RW DN 1,400,000 4,600,000 1,820,000 715,000 3,220,000 715,000 4,600,000 P ROVIDE ACCESS ROAD TO TRAINING FACILITY IN WEST LIBERTY. (2020CCR) PR-1045Morgan PL157 DN RW UT CN 1,500,000 STP2 Project Cost: 1,500,000 0 0 180 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 WEST LIBERTY BYPASS - CONSTRUCT NEW ROUTE FROM US 460 @ K Y 2498 TO US 460 @ KY 172. (00CCN) PF-9999M organ PL8004 DN 1,600,000 SPP RW UT CN Project Cost: 0 0 1,600,000 I MPROVE KY-2498 FROM US-460 TO THE ARH HOSPITAL. (14CCN) (16CCN) KY-2498Morgan PL8804 DN RW 1,045,000 SPP UT 560,000 SPP CN Project Cost: 0 1,045,000 560,000 ADDRESS DEFICIENCIES OF BRIDGE ON KY 191 OVER CANEY CREEK . 5 MILES WEST OF KY 1162. (16CCN)(SD) KY-191M organ PL8902 DN RW 70,000 BRZ UT 140,000 BRZ CN 1,000,000 BRZ Project Cost: 1,210,000 0 0 B RIDGE PROJECT IN MORGAN COUNTY ON (088B00039N) KY-1950 AT BLACKWATER CREEK KY-1950Morgan PL10055 DN 151,000 FBP2 RW UT CN 1,510,000 FBP2 Project Cost: 0 1,661,000 0 I mprove safety and substandard geometrics on US 460 from the Menifee County Line to approximately milepoint 0.8. US-460Morgan PL80202 DN 500,000 NH RW UT CN Project Cost: 500,000 0 0 T otal for Morgan county PL Total Amounts: CN UT RW DN 500,000 151,000 1,600,000 70,000 1,045,000 140,000 560,000 2,500,000 1,510,000 3,210,000 2,706,000 2,160,000 181 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-171 IN MUHLENBERG COUNTYK Y-171Muhlenberg PL4307 DN RW UT CN 27,000 GR Project Cost: 0 27,000 0 I NSTALL GUARDRAIL ON US-62 IN MUHLENBERG COUNTYUS-62Muhlenberg PL4308 DN RW UT CN 35,000 GR Project Cost: 0 35,000 0 S TRAIGHTEN DEAN ROAD INTERSECTION OF 189 BYPASS TO KY 181 NORTH NEAR THE INTERSECTION WITH THE WKY PARKWAY, WENDELL FORD NATIONAL GUARD CENTER, AND JOB CORP. (14CCN)(18CCN) (2020CCR) KY-2533Muhlenberg PL8803 DN RW 1,500,000 SPP UT 1,000,000 SPP CN Project Cost: 0 1,500,000 1,000,000 A DDRESS CONDITION OF WENDELL H. FORD WESTERN KY PARKWAY FROM MILEPOINT 43.424 TO MILEPOINT 45.95 WK-9001Muhlenberg PL20036 DN 220,000 NHPM RW UT CN 2,200,000 NHPM Project Cost: 0 2,420,000 0 A DDRESS CONDITION OF WENDELL H. FORD WESTERN KY PARKWAY FROM MILEPOINT 52.535 TO MILEPOINT 54.317 WK-9001Muhlenberg PL22163 DN 170,000 NHPM RW UT CN 1,700,000 NHPM Project Cost: 0 0 1,870,000 182 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS SAFETY AND MOBILITY ISSUES AT KY 246 INTERSECTION W ITH KY 176 (2020CCN) KY-246Muhlenberg PL80100 DN RW 400,000 SPP UT 420,000 SPP CN Project Cost: 400,000 0 420,000 ADDRESS SAFETY AND MOBILITY ISSUES AT THE INTERSECTION OF K Y 81 AND KY 181 (2020CCN) KY-181, K Y-81 Muhlenberg PL80101 DN RW 250,000 SPP UT 180,000 SPP CN 400,000 SPP Project Cost: 430,000 400,000 0 T otal for Muhlenberg county PL Total Amounts: CN UT RW DN 220,000 170,000 650,000 1,500,000 180,000 1,420,000 2,662,000 1,700,000 830,000 4,382,000 3,290,000 B ARDSTOWN-LOUISVILLE WIDENING AND ACCESS MANAGEMENT IMPROVEMENTS ON US-31E BETWEEN NAZARETH DRIVE AND KY 509. (2004BOPC) US-31Nelson PL287.5000 DN 2,500,000 SPP RW UT CN Project Cost: 0 2,500,000 0 I MPROVE SAFETY, MOBILITY, AND GEOMETRICS ON US-150 FROM THE BLUEGRASS PARKWAY TO THE NELSON/WASHINGTON COUNTY LINE. (2016BOP)(18CCR)(D-Auth under 4-396) US-150Nelson PL396.1000 DN 1,500,000 STPF RW 4,000,000 STPF UT 2,000,000 STPF CN Project Cost: 0 1,500,000 6,000,000 183 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 WIDEN US-150 FROM KY-49 TO NEAR KY-245/WAL-MART WIDENING. ( 06CCN) us-150Nelson PL8308.1000 DN 1,500,000 STP1 RW 2,210,000 STP1 UT CN Project Cost: 0 1,500,000 2,210,000 N EW ROUTE BETWEEN US 62 AND KY 245 WEST OF BARDSTOWN (2020CCN) US-31Nelson PL8809 DN RW 4,500,000 STPF UT 1,500,000 STPF CN 5,000,000 STPF Project Cost: 4,500,000 1,500,000 5,000,000 B RIDGE PROJECT IN NELSON COUNTY ON (090B00056N) US-62 AT CEDAR CREEK US-62Nelson PL10062 DN 36,000 FBP2 RW UT CN 360,000 FBP2 Project Cost: 0 0 396,000 BRIDGE PROJECT IN NELSON COUNTY ON (090C00037N) KING RD AT E FK COX CR @SPENCER CL CR-1314N elson PL10066 DN 57,000 BRZ RW UT CN 570,000 BRZ Project Cost: 0 627,000 0 I NTERSECTION IMPROVEMENTS AT US 62 AND US 31E. (18CCN) (2020CCR) US-31, US-62Nelson PL80050 DN 300,000 SPP RW 550,000 SPP UT 200,000 SPP CN 1,900,000 SPP Project Cost: 300,000 750,000 1,900,000 184 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS SAFETY AND GEOMETRIC DEFICIENCIES ON KY 52 (MP 1 2.009) AND IMPORVE INTERSECTION AT DEE HEAD ROAD. KY-52Nelson PL80253 DN 150,000 STPF RW 50,000 STPF UT 150,000 STPF CN 650,000 STPF Project Cost: 0 1,000,000 0 IMPROVE CONNECTIVITY WEST OF BARDSTOWN BY CONSTRUCTION N EW ROUTE FROM THE BLUEGRASS PARKWAY BEGINNING WEST OF EXIT 21 TO US 31E NEAR COX'S CREEK PF-9999N elson PL80254 DN 6,000,000 SPP RW UT CN Project Cost: 0 6,000,000 0 I MPROVE MOBILITY AND CONNECTIVITY WEST OF BARDSTOWN FROM KY 245 TO US 31E NEAR COX'S CREEK. PF-9999Nelson PL80255 DN 2,500,000 STPF RW 5,000,000 SPP UT CN Project Cost: 0 2,500,000 5,000,000 T otal for Nelson county PL Total Amounts: CN UT RW DN 300,000 14,207,000 36,000 4,500,000 600,000 11,210,000 1,850,000 2,000,000 1,220,000 7,260,000 4,800,000 17,877,000 20,506,000 I MPROVE THE KY-36/KY-32 INTERSECTION NEAR THE NICHOLAS COUNTY SCHOOL PROPERTY (12CCR)(16CCR)(2020CCR) ky-36Nicholas PL205 DN RW 1,500,000 STP UT CN Project Cost: 0 0 1,500,000 185 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 RECONSTRUCT KY 36/KY 928 INTERSECTION. (14CCN)(16CCR) ( 18CCN) KY-36Nicholas PL8811 DN RW 280,000 SPP UT 220,000 SPP CN 680,000 SPP Project Cost: 0 500,000 680,000 S AFETY IMPROVEMENTS ALONG KY 32 FROM LAKE ROAD (MP 9.5) TO SCRUBGRASS CREEK (MP 12.5) TO CORRECT HORIZONTAL, VERTICAL, PAVEMENT WITH DEFICIENCIES. (14CCN)(18CCN) KY-32Nicholas PL 230,000 SPP8812 DN RW UT CN Project Cost: 0 0 230,000 B RIDGE PROJECT IN NICHOLAS COUNTY ON (091B00012N) KY-32 AT FLEMING CREEK KY-32Nicholas PL10094 DN 173,000 BRX RW UT CN 1,730,000 BRX Project Cost: 0 173,000 1,730,000 T otal for Nicholas county PL Total Amounts: CN UT RW DN 230,000 173,000 280,000 1,500,000 220,000 2,410,000 0 673,000 4,140,000 I NSTALL GUARDRAIL ON KY-69 IN OHIO COUNTYKY-69Ohio PL4302 DN RW UT CN 32,000 GR Project Cost: 32,000 0 0 186 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-69 IN OHIO COUNTYK Y-69Ohio PL4303 DN RW UT CN 43,000 GR Project Cost: 43,000 0 0 I NSTALL GUARDRAIL ON US-62 IN OHIO COUNTYUS-62Ohio PL4315 DN RW UT CN 8,000 GR Project Cost: 0 0 8,000 R EPLACE, IMPROVE ALIGNMENTS AND APPROACHES, AND ADDRESS SAFETY ISSUES WITH BRIDGES ON KY-136 IN MCLEAN COUNTY FROM KY-56 TO OHIO COUNTY LINE. (075B00034N, 075B00011N, 075B00009N, 075B00010N) ky-136Ohio PL8812 DN RW UT CN 3,000,000 STP2 Project Cost: 0 0 3,000,000 R EPLACE, IMPROVE ALIGNMENTS AND APPROACHES, AND ADDRESS SAFETY ISSUES WITH BRIDGES ON KY-136 IN OHIO COUNTY FROM THE MCLEAN COUNTY LINE TO US-231. KY-136Ohio PL8812.2000 DN RW 240,000 STPF UT 1,000,000 STPF CN Project Cost: 1,240,000 0 0 I MPROVE SAFETY ON KY 54 BY UPGRADING MP 7.0 TO MP 8.0 TO THREE LANES INCLUDING CURB AND GUTTER AND ADDRESSING TWO SHARP TURNS. (16CCN)(18CCN) (2020CCR) KY-54Ohio PL8951 DN RW 1,750,000 SPP UT CN Project Cost: 0 1,750,000 0 187 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN OHIO COUNTY ON (092B00072L) WESTERN K ENTUCKY P AT NATCHER PARKWAY WK-9001Ohio PL10126 DN 136,000 FBP RW UT CN 1,360,000 FBP Project Cost: 1,496,000 0 0 B RIDGE PROJECT IN OHIO COUNTY ON (092B00085N) KY-136 AT BARNETT CREEK KY-136Ohio PL10127 DN 238,000 FBP RW UT CN 2,380,000 FBP Project Cost: 238,000 2,380,000 0 B RIDGE PROJECT IN OHIO COUNTY ON (092B00136N) KY-2712 AT WESTERN KENTUCKY PARKWAY KY-2712Ohio PL10130 DN 157,000 FBP2 RW UT CN 1,570,000 FBP2 Project Cost: 1,727,000 0 0 T otal for Ohio county PL Total Amounts: CN UT RW DN 531,000 240,000 1,750,000 1,000,000 3,005,000 2,380,000 3,008,000 4,776,000 4,130,000 3,008,000 K Y-393 RECONSTRUCT FROM 140FEET SOUTH OF RAILROAD CROSSING (CSX) EXTENDING NORTHWEST TOWARDS KY 146 ENDING AT STATION 12+00 (DESIGN UNDER 5-230.00). (CONSTRUCTION SEQ.#2) (2020CCN) KY-146, KY-393 Oldham PL234 DN RW UT CN 14,500,000 STPF Project Cost: 14,500,000 0 0 188 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Railroad crossing safety project on KY 329 in Crestwood.K Y-329Oldham PL477 DN 90,000 SPP RW 120,000 SPP UT 150,000 SPP CN 870,000 SPP Project Cost: 90,000 270,000 870,000 W IDEN I-71 FROM FOUR TO SIX LANES FROM KY-329 (MP 14.1) TO KY-393 (MP 18.0). I -71Oldham PL483.1000 DN RW 1,900,000 NH UT 1,800,000 NH CN 12,000,000 NH Project Cost: 3,700,000 0 12,000,000 W IDEN I-71 FROM FOUR TO SIX LANES FROM KY-393 (MP 18.0) TO KY-53 (MP 22.4). (16CCN) I -71Oldham PL483.2000 DN 5,500,000 NH RW UT CN Project Cost: 0 5,500,000 0 C ONSTRUCT NEW I-71 INTERCHANGE BETWEEN KY-393 AND KY-53 TO RELIEVE CONGESTION IN LAGRANGE. (2020CCR) I -71Oldham PL483.3000 DN RW UT CN 12,000,000 NH Project Cost: 12,000,000 0 0 I NSTALL GUARDRAIL ON KY-362 IN OLDHAM COUNTYKY-362Oldham PL4308 DN RW UT CN 49,000 GR Project Cost: 0 0 49,000 189 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 DESIGN FOR IMPROVING KY-53 FROM ZHALE SMITH ROAD TO KY-22 ( TOTAL 3.2 MILES). (14CCN)(18CCN) KY-53Oldham PL8852 DN 2,000,000 STPF RW UT CN Project Cost: 2,000,000 0 0 ADDRESS CONDITION OF I-71 FROM MILEPOINT 14.49 TO MILEPOINT 2 2.3 I-71Ol dham PL22098 DN 1,700,000 NHPM RW UT CN 17,000,000 NHPM Project Cost: 0 18,700,000 0 I MPROVE THE INTERCHANGE OF I 71 AND KY 329. (18CCN) (2020CCR) (DESIGNED UNDER 5-483.10) I -71Oldham PL80005 DN 370,000 NH RW UT CN Project Cost: 370,000 0 0 C ONSTRUCT A TURN LANE ON KY 329 BYPASS AT DOVEFIELD DRIVE.(18CCN) (2020CCR) KY-329Oldham PL80050 DN RW UT CN 360,000 SPP Project Cost: 360,000 0 0 I mprove safety and reduce congestion on KY 53 from I-71 to Zhale Smith Road. Includes consideration of a five lane widening and bike/ped accommodations. KY-53Oldham PL80209 DN 1,600,000 STPF RW UT CN Project Cost: 0 0 1,600,000 190 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Improve safety and reduce congestion on KY 146 (LaGrange Road) f rom KY 329B (KY 329 Bypass) to KY 393. Includes consideration of a four lane widening and bike/ped accommodations. KY-146Oldham PL 240,000 STPF80210 DN RW UT CN Project Cost: 0 0 240,000 L andslide repair on Westport Road (KY-524) from JCT. US-42 West, north 1.0 mile. (2002BOPC)(NOT REQUIRED) KY-524Oldham PL80211 DN 600,000 SPP RW UT CN Project Cost: 0 0 600,000 T otal for Oldham county PL Total Amounts: CN UT RW DN 240,000 2,460,000 7,200,000 2,200,000 1,900,000 120,000 1,800,000 150,000 26,860,000 17,000,000 12,919,000 33,020,000 24,470,000 15,359,000 I MPROVE SAFETY ON KY-22 FROM KY-227 TO KY-845. (06CCR) (08CCN)(12CCR)(14CCR) (2020CCR) KY-22Owen PL198 DN RW UT CN 5,200,000 SPP Project Cost: 5,200,000 0 0 A DDRESS DEFICIENCIES OF BRIDGE OVER CEDAR CREEK ON SAWDRIDGE CREEK W ROAD (CR 1214) 0.2 MI N OF US 127 (094C00011N) CR-1214Owen PL1088 DN RW UT CN 750,000 BRX Project Cost: 750,000 0 0 191 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Total for Owen county P L Total Amounts: CN UT RW DN 5,950,000 5,950,000 0 0 R eplace bridge over Moores Fork and realign roadway.KY-708Owsley PL173 DN 350,000 BRX RW UT CN Project Cost: 0 0 350,000 R ECONSTRUCT THE INTERSECTION OF KY 11 AND KY 846 (2020CCN)KY-11Owsley PL80105 DN 210,000 SPP RW 220,000 SPP UT CN Project Cost: 0 210,000 220,000 T otal for Owsley county PL Total Amounts: CN UT RW DN 210,000 350,000 220,000 0 210,000 570,000 A ddress roadway slide on KY 7 from MP 9.8 to MP 10.0.KY-7Perry PL178 DN 650,000 PROT RW 150,000 PROT UT 2,300,000 PROT CN Project Cost: 0 650,000 2,450,000 192 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE KY-476 FROM KY-15X IN WALKERTOWN TO NORTH OF W ALKER CORNETT ROAD IN WABACO. KY-476Perry PL209 DN RW 525,000 STP2 UT CN Project Cost: 0 0 525,000 R ECONSTRUCTION OF KY 15 FROM BONNYMAN TO NEAR KY 28. (14CCN) (2020CCN) KY-15Perry PL269.2000 DN 2,000,000 SPP RW UT CN Project Cost: 0 2,000,000 0 N EW INTERCHANGE OFF OF A NEW EXIT 55 HAL ROGERS PARKWAY. (16CCN)(18CCN) HR-9006Perry PL8903 DN RW 1,260,000 NH UT 350,000 NH CN Project Cost: 0 1,260,000 350,000 S AFETY IMPROVEMENTS ON KY-80 FROM LESLIE COUNTY LINE TO KY-451 (16CCN) ky-80Perry PL8906 DN RW UT CN 2,810,000 NH Project Cost: 0 0 2,810,000 N EW IMPROVED ACCESS TO WENDALL FORD AIRPORT (2020CCN)CR-1365Perry PL80100 DN RW 1,350,000 SPP UT 300,000 SPP CN 3,000,000 SPP Project Cost: 1,650,000 0 3,000,000 T otal for Perry county PL Total Amounts: CN UT RW DN 2,650,000 1,350,000 1,260,000 675,000 300,000 2,650,000 5,810,000 1,650,000 3,910,000 9,135,000 193 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 MITIGATE OR ELIMINATE ROCKFALL HAZARDS AND IMPROVE R OADWAY FOR BETTER FLOW AND EFFICIENCY IN ORDER TO HANDLE THE EXPECTED CONGESTION ARISING FROM EVENTS AT THE EXPO CENTER. IDENTIFIED IN THE 1999 PIKEVILLE URBAN STUDY, FROM BILL KING RD. TO US 119. (2020CCR) KY-1426P ike PL147 DN 1,670,000 PROT RW 870,000 PROT UT CN Project Cost: 0 1,670,000 870,000 I MPROVE KY 194 FROM US 119 RAMP NEAR SMITH FARMS BOTTOM (CR 1458) TO NEAR DESKINS BRANCH CULVERT. (18CCR) (2020CCR) KY-194Pike PL198 DN RW UT 2,050,000 STPF CN Project Cost: 0 0 2,050,000 P IKEVILLE TO VA. STATE LINE; US-460/KY-80 FROM KY-195 TO DUNLEARY HOLLOW. (SURFACING FOR SECTIONS 6A & 6B) (2000BOP)(14CCN) PF-9999Pike PL263.6900 DN RW UT CN 5,000,000 APD Project Cost: 0 0 5,000,000 K Y-199 SPOT IMPROVEMENT; RELOCATE PORTIONS OF KY-199 ALONG OLD NORFOLK SOUTHERN RAILROAD BED @ STONE. (2002BOPC)(08CCR) KY-199Pike PL298.4000 DN RW UT CN 3,050,000 SPP Project Cost: 0 3,050,000 0 I MPROVE SAFETY AND REDUCE CONGESTION AT THE US-460 AND KY-1460 INTERSECTION. (2020CCR) US-460Pike PL346 DN 240,000 NH RW 400,000 NH UT 160,000 NH CN Project Cost: 0 800,000 0 194 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 PLANNING STUDY TO EVALUATE REPLACING OLD NOLAN TOLL B RIDGE AT KY 292 JUST SW OF KY 468 INTERSECTION. (2020CCR) CO-0Pike PL1129 DN 250,000 SPP RW UT CN Project Cost: 0 250,000 0 I NSTALL GUARDRAIL ON KY-194 IN PIKE COUNTYKY-194Pike PL4314 DN RW UT CN 23,000 GR Project Cost: 23,000 0 0 I NSTALL GUARDRAIL ON KY-194 IN PIKE COUNTYKY-194Pike PL4319 DN RW UT CN 74,000 GR Project Cost: 74,000 0 0 I NSTALL GUARDRAIL ON KY-194 IN PIKE COUNTYKY-194Pike PL4350 DN RW UT CN 41,000 GR Project Cost: 0 41,000 0 I NSTALL GUARDRAIL ON KY-194 IN PIKE COUNTYKY-194Pike PL4351 DN RW UT CN 83,000 GR Project Cost: 0 83,000 0 195 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-194 IN PIKE COUNTYK Y-194Pike PL4352 DN RW UT CN 44,000 GR Project Cost: 0 44,000 0 I NSTALL GUARDRAIL ON KY-194 IN PIKE COUNTYKY-194Pike PL4353 DN RW UT CN 72,000 GR Project Cost: 0 72,000 0 I NSTALL GUARDRAIL ON KY-122 IN PIKE COUNTYKY-122Pike PL4363 DN RW UT CN 34,000 GR Project Cost: 0 0 34,000 I NSTALL GUARDRAIL ON KY-194 IN PIKE COUNTYKY-194Pike PL4364 DN RW UT CN 45,000 GR Project Cost: 0 0 45,000 I NSTALL GUARDRAIL ON KY-194 IN PIKE COUNTYKY-194Pike PL4365 DN RW UT CN 43,000 GR Project Cost: 0 0 43,000 196 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-194 IN PIKE COUNTYK Y-194Pike PL4366 DN RW UT CN 36,000 GR Project Cost: 0 0 36,000 I NSTALL GUARDRAIL ON KY-194 IN PIKE COUNTYKY-194Pike PL4367 DN RW UT CN 70,000 GR Project Cost: 0 0 70,000 I NSTALL GUARDRAIL ON KY-194 IN PIKE COUNTYKY-194Pike PL4368 DN RW UT CN 68,000 GR Project Cost: 0 0 68,000 I NSTALL GUARDRAIL ON KY-611 IN PIKE COUNTYKY-611Pike PL4369 DN RW UT CN 121,000 GR Project Cost: 0 0 121,000 I NSTALL GUARDRAIL ON KY-611 IN PIKE COUNTYKY-611Pike PL4370 DN RW UT CN 90,000 GR Project Cost: 0 0 90,000 197 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-122 IN PIKE COUNTYK Y-122Pike PL4383 DN RW UT CN 24,000 GR Project Cost: 0 0 24,000 I NSTALL GUARDRAIL ON KY-1441 IN PIKE COUNTYKY-1441Pike PL4384 DN RW UT CN 131,000 GR Project Cost: 0 0 131,000 IMPROVE CONNECTIVITY BETWEEN THOMPSON ROAD AND US-23 AT S TONECOAL.(12CCN)(14CCR)(16CCR) CS-1215P ike PL8705 DN RW UT 730,000 SPP CN Project Cost: 0 0 730,000 B RIDGE PROJECT IN PIKE COUNTY ON (098B00013N) KY-1426 AT Bent Branch KY-1426Pike PL10132 DN 90,000 BRX RW UT CN 900,000 BRX Project Cost: 0 90,000 900,000 B RIDGE PROJECT IN PIKE COUNTY ON (098B00072N) KY-610 AT SHELBY CREEK KY-610Pike PL10136 DN 77,000 FBP2 RW UT CN 770,000 FBP2 Project Cost: 0 0 847,000 198 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN PIKE COUNTY ON (098B00135N) KY-1441 AT R accoon Creek KY-1441Pike PL10137 DN 40,000 FBP2 RW UT CN 400,000 FBP2 Project Cost: 0 0 440,000 B RIDGE PROJECT IN PIKE COUNTY ON (098B00235N) KY-1441 AT RACCOON CREEK KY-1441Pike PL10139 DN 125,000 FBP RW UT CN Project Cost: 0 0 125,000 B RIDGE PROJECT IN PIKE COUNTY ON (098C00123N) GIN FRK AT LFT.FK-BRUSH FK-JOHNS CK CR-1393Pike PL10143 DN 21,000 BRZ RW UT CN 210,000 BRZ Project Cost: 0 231,000 0 T otal for Pike county PL Total Amounts: CN UT RW DN 2,271,000 242,000 400,000 870,000 160,000 2,780,000 97,000 3,500,000 7,732,000 97,000 6,331,000 11,624,000 I MPROVE SAFETY, UPGRADE GEOMETRICS, AND ADDRESS CAPACITY ISSUES FOR KY 213 FROM KY 615 TO BOTTOM OF MOUNTAIN. (PRIORITY SECTION 2)(2018BOP) ky-213Powell PL163.2000 DN 1,000,000 STP RW UT CN Project Cost: 0 1,000,000 0 199 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Correct flooding issues on KY 613 at Bowen from KY 11 to Bridge o ver Red River in Powell County. KY-613Powell PL174 DN 400,000 PROT RW 100,000 PROT UT 50,000 PROT CN Project Cost: 0 400,000 150,000 M inor widening to improve redundancy of Regional Travel.KY-15Powell PL176 DN 750,000 PROT RW UT CN Project Cost: 0 0 750,000 A DDRESS CONDITION OF BERT T. COMBS MOUNTAIN PARKWAY FROM MILEPOINT 32.787 TO MILEPOINT 35.28 ky-9000Powell PL20008 DN 200,000 NHPM RW UT CN 2,000,000 NHPM Project Cost: 0 0 2,200,000 C ONSTRUCT THE HAL ROGERS PARKWAY BRIDGE ON KY 11 (CAMPTON ROAD) MP 3.4 TO 3.85 ky-11Powell PL 3,000,000 SPP80250 DN RW UT CN Project Cost: 0 3,000,000 0 T otal for Powell county PL Total Amounts: CN UT RW DN 3,000,000 1,400,000 950,000 100,000 50,000 2,000,000 0 4,400,000 3,100,000 200 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ACCESS IMPROVEMENTS TO ACCOMMODATE BURNSIDE E LEMENTARY SCHOOL pf-9999Pulaski PL174 DN RW UT CN 3,100,000 STPF Project Cost: 0 3,100,000 0 I NSTALL GUARDRAIL ON KY-196 IN PULASKI COUNTYKY-196Pulaski PL4310 DN RW UT CN 35,000 GR Project Cost: 35,000 0 0 I NSTALL GUARDRAIL ON KY-804 IN PULASKI COUNTYKY-804Pulaski PL4312 DN RW UT CN 53,000 GR Project Cost: 0 53,000 0 I NSTALL GUARDRAIL ON KY-769 IN PULASKI COUNTYKY-769Pulaski PL4313 DN RW UT CN 14,000 GR Project Cost: 0 0 14,000 S AFETY PROJECT TO RECONSTRUCT KY 635 TO ELIMINATE AT GRADE RAILROAD CROSSING AND REPLACE WITH RAILROAD SEPARATION CROSSING AT SCIENCE HILL, KENTUCKY IN PULASKI COUNTY. (2016BOP) (2020CCR) KY-635Pulaski PL9010 DN RW UT CN 3,300,000 STPF Project Cost: 0 0 3,300,000 201 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN PULASKI COUNTY ON (100B00029N) KY-80 AT Fi shing Creek KY-80Pulaski PL10064 DN 657,000 BRX RW UT CN 2,000,000 BRX Project Cost: 0 657,000 2,000,000 B RIDGE PROJECT IN PULASKI COUNTY ON (100B00093N) KY-3260 AT PITTMAN CREEK KY-3260Pulaski PL10067 DN 84,000 FBP2 RW UT CN 840,000 FBP2 Project Cost: 0 924,000 0 B RIDGE PROJECT IN PULASKI COUNTY ON (100B00096N) KY-3267 AT BEE LICK CREEK KY-3267Pulaski PL10068 DN 39,000 FBP2 RW UT CN 390,000 FBP2 Project Cost: 0 429,000 0 C ONSTRUCT CONNECTOR BETWEEN NORTH MIDDLE SCHOOL AND PULASKI COUNTY HIGH SCHOOL (2020CCN) PF-9999Pulaski PL80100 DN 75,000 SPP RW 50,000 SPP UT 95,000 SPP CN Project Cost: 75,000 145,000 0 R EDUCE CONGESTION AND IMPROVE SAFETY, CAPACITY AND MOBILIITY ALONG KY 90 BETWEEN WAYNE COUNTY LINE AND NEW CUMBERLAND RIVER BRIDGE (2020CCN) KY-90Pulaski PL80104 DN RW 7,000,000 SPP UT CN Project Cost: 0 7,000,000 0 202 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 UPGRADE THE CUMBERLAND PARKWAY (EXPRESSWAY) FOR E NTRY INTO THE FEDERAL HIGHWAY SYSTEM AS A SPUR OF I 65 (2020CCN) LN-9008Pulaski PL 500,000 SPP80109 DN RW UT CN Project Cost: 500,000 0 0 T otal for Pulaski county PL Total Amounts: CN UT RW DN 500,000 75,000 780,000 7,050,000 95,000 35,000 4,383,000 5,314,000 610,000 12,308,000 5,314,000 I MPROVE CURVE ON KY 616 AND IMPROVE ROADWAY FROM THE NEW ROBERTSON COUNTY SCHOOL TO MT OLIVET. (12CCN) (14CCR)(18CCN) (2020CCR) KY-616Robertson PL8711 DN RW 270,000 SPP UT 210,000 SPP CN Project Cost: 270,000 210,000 0 WIDEN THE BRIDGE ON US 62 OVER N. BRANCH CEDAR CREEK NEAR K ENTONTOWN TO IMPROVE SAFETY AND MOBILITY. (2020CCN) US-62R obertson PL80151 DN RW 115,000 FBP UT 115,000 FBP CN 1,255,000 FBP Project Cost: 0 0 1,485,000 T otal for Robertson county PL Total Amounts: CN UT RW DN 270,000 115,000 210,000 115,000 1,255,000 270,000 210,000 1,485,000 203 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-1229 IN ROCKCASTLE COUNTYK Y-1229Rockcastle PL4314 DN RW UT CN 102,000 GR Project Cost: 0 0 102,000 I MPROVE KY-461 FROM US-150 TO THE EXISTING FOUR LANE APPROACH AT US-25.(16CCN)(18CCR) (2020CCR) KY-461Rockcastle PL8952 DN RW UT 3,350,000 NH CN 5,000,000 5,000,000 NH Project Cost: 3,350,000 5,000,000 5,000,000 B RIDGE PROJECT IN ROCKCASTLE COUNTY ON (102B00034N) KY-1787 AT CLEAR CREEK KY-1787Rockcastle PL10070 DN 103,000 FBP2 RW UT CN 1,030,000 FBP2 Project Cost: 0 1,133,000 0 A DDRESS SAFETY, MOBILITY, AND CONGESTION WITH ACCESS AMANGEMENT ALONG US-25 (RICHMOND ST) FROM THE US 25/US 461 INTERSECTION TO I 75 (2020CCN) US-25Rockcastle PL80106 DN 1,100,000 SPP RW 250,000 SPP UT CN Project Cost: 0 1,100,000 250,000 U S 25 FROM I 75 EXIT 62 NORTHERLY TO MP 17.3 - PLANNING STUDY TO ADDRESS ECONOMIC DEVELOPMENT (2020CCN) US-25Rockcastle PL 300,000 SPP80107 DN RW UT CN Project Cost: 0 300,000 0 T otal for Rockcastle county PL Total Amounts: CN UT RW DN 300,000 1,203,000 250,000 3,350,000 6,030,000 5,102,000 3,350,000 7,533,000 5,352,000 204 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE KY-32 FROM PARK HILLS DRIVE TO VIKING DRIVE NORTH. ( 12CCR)(18CCR) (2020CCR) KY-32Rowan PL204 DN RW UT CN 5,000,000 SPP Project Cost: 0 0 5,000,000 I NSTALL GUARDRAIL ON US-60 IN ROWAN COUNTYUS-60Rowan PL4312 DN RW UT CN 3,000 GR Project Cost: 0 3,000 0 I NSTALL GUARDRAIL ON US-60 IN ROWAN COUNTYUS-60Rowan PL4315 DN RW UT CN 76,000 GR Project Cost: 0 0 76,000 I NSTALL GUARDRAIL ON KY-3319 IN ROWAN COUNTYKY-3319Rowan PL4319 DN RW UT CN 50,000 GR Project Cost: 0 0 50,000 I NSTALL GUARDRAIL ON US-60 IN ROWAN COUNTYUS-60Rowan PL4320 DN RW UT CN 3,000 GR Project Cost: 0 0 3,000 205 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON US-60 IN ROWAN COUNTYU S-60Rowan PL4321 DN RW UT CN 32,000 GR Project Cost: 0 0 32,000 I MPROVE SAFETY AND CONNECTIVITY AND REDUCE CONGESTION ON KY-377 FROM KY-32 TO NORTH OF KY-799. (08CCN)(10CCR) (16CCR)(18CCR) (2020CCR) KY-377Rowan PL8406 DN RW UT 2,000,000 NH CN Project Cost: 0 0 2,000,000 A DDRESS CONDITION OF I-64 FROM MILEPOINT 128.955 TO MILEPOINT 134.75 I-64Rowan PL20012 DN 500,000 NHPM RW UT CN 5,000,000 NHPM Project Cost: 0 0 5,500,000 ADDRESS CONDITION OF I-64 FROM MILEPOINT 141.5 TO MILEPOINT 1 47.94 I-64R owan PL20014 DN 550,000 NHPM RW UT CN 5,000,000 NHPM Project Cost: 0 0 5,550,000 A DDRESS DEFICIENCIES ON CIMMARON RD BRIDGE (2020CCN)CR-1317Rowan PL80100 DN 370,000 BRZ RW 10,000 FBP UT 40,000 FBP CN 400,000 BRZ Project Cost: 370,000 50,000 400,000 206 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 WIDEN AND SOFTEN CURVE ON CR 1391 (BRATTON BRANCH RD) AT W ALMART (2020CCN) CR-1391R owan PL80108 DN RW UT CN 150,000 SPP Project Cost: 150,000 0 0 T otal for Rowan county PL Total Amounts: CN UT RW DN 370,000 1,050,000 10,000 40,000 2,000,000 150,000 3,000 15,561,000 520,000 53,000 18,611,000 R ELOCATE US-127 FROM EAST OF THE KY-1730 AND MANNTOWN RD INTERSECTION, AND EXTENDING NORTHERLY TO NORTH BANK OF CUMBERLAND RIVER (SEE 8-108&8-115 FOR PE/PH.2)(12CCR) (14CCR) US-127Russell PL8601.2100 DN RW UT CN 10,000,000 20,000,000 NH Project Cost: 0 10,000,000 20,000,000 I MPROVE CONGESTION AND SAFETY ALONG US 127 AT KY 1381 (VOILS ROAD) AND SK LANE IN RUSSELL SPRINGS (MILEPOINT 17.2 TO MILEPOINT 17.45) KY-127Russell PL80250 DN 200,000 SPP RW 50,000 SPP UT 685,000 SPP CN 960,000 SPP Project Cost: 0 935,000 960,000 T otal for Russell county PL Total Amounts: CN UT RW DN 200,000 50,000 685,000 10,000,000 20,960,000 0 10,935,000 20,960,000 207 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN SCOTT COUNTY ON (105R00607N) FIELDS RD at N S (CNO&TP) SYSTEM CR-1022S cott PL1139 DN 9,000 BRZ RW UT CN 90,000 BRZ Project Cost: 0 99,000 0 I NSTALL GUARDRAIL ON KY-32 IN SCOTT COUNTYKY-32Scott PL4307 DN RW UT CN 148,000 GR Project Cost: 148,000 0 0 BRIDGE PROJECT IN SCOTT COUNTY ON (105C00112N) LEMONS MILL R D AT NS (CNO&TP) SYSTEM CS-1010S cott PL10006 DN RW UT CN 1,520,000 BRZ Project Cost: 0 1,520,000 0 B RIDGE PROJECT IN SCOTT COUNTY ON (105R00605N) HINTON RD AT NS (CNO&TP) SYSTEM CR-1020Scott PL10013 DN 160,000 BRZ RW UT CN Project Cost: 0 160,000 0 B RIDGE PROJECT IN SCOTT COUNTY ON (105B00082N) CANE RUN RD AT I 64 I -64Scott PL10059 DN RW UT CN 3,000,000 FBP Project Cost: 0 3,000,000 0 208 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS CONDITION OF I-75 FROM MILEPOINT 138.424 TO M ILEPOINT 143.239 i-75Scott PL20021 DN 550,000 NHPM RW UT CN 5,500,000 NHPM Project Cost: 0 6,050,000 0 A DDRESS CONDITION OF I-75 FROM MILEPOINT 138.424 TO MILEPOINT 143.239 I-75Scott PL22118 DN 1,700,000 NHPM RW UT CN 17,000,000 NHPM Project Cost: 0 0 18,700,000 I MPROVE CAPACITY AND ACCESS ON KY 2906 FROM US 460 TO US 62 (2020CCN) KY-2906Scott PL80102 DN RW 1,158,000 STP1 UT 1,406,000 STP1 CN Project Cost: 1,158,000 1,406,000 0 T otal for Scott county PL Total Amounts: CN UT RW DN 719,000 1,700,000 1,158,000 1,406,000 148,000 10,110,000 17,000,000 1,306,000 12,235,000 18,700,000 W IDEN I-64 TO 6-LANES FROM 0.458 MILE EAST OF THE KY-55 INTERCHANGE TO THE KY-1790 UNDERPASS. I -64Shelby PL65.4000 DN RW UT CN 20,000,000 20,000,000 NH Project Cost: 0 20,000,000 20,000,000 209 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 EXPAND TRUCK PARKING AT I-64 EB WELCOME CENTER.I -64Shelby PL579 DN RW UT CN 1,000,000 NH Project Cost: 0 0 1,000,000 CONSTRUCT A THIRD LANE ON US-60 FROM THE MASONIC HOME TO R OCKET LANE. (12CCN)(14CCR)(2020CCR) US-60S helby PL8713 DN RW UT CN 2,870,000 SPP Project Cost: 0 2,870,000 0 A DDRESS DEFICIENCIES OF MOODY PIKE BRIDGE OVER FOX RUN CREEK. (106C00004N) CR-1007Shelby PL10024 DN 60,000 FBP RW UT CN 310,000 FBP Project Cost: 0 370,000 0 B RIDGE PROJECT IN SHELBY COUNTY ON (106B00007R) US 60 EB AT CLEAR CREEK US-60Shelby PL10086 DN 315,000 FBP RW UT CN 3,150,000 FBP Project Cost: 3,465,000 0 0 ADDRESS CONDITION OF I-64 FROM MILEPOINT 23.974 TO MILEPOINT 2 7.91 I-64S helby PL22027 DN 1,300,000 NHPM RW UT CN 13,000,000 NHPM Project Cost: 0 0 14,300,000 210 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 FOUR RIGHT TURNING LANES AT THE INTERSECTION OF KY 55X AND K Y 43 AND TWO LEFT TURNING LANES FROM KY 55X ONTO KY 43. (18CCN) (2020CCR) KY-55S helby PL80004 DN RW 30,000 SPP UT 30,000 SPP CN 520,000 SPP Project Cost: 60,000 520,000 0 B RIDGE PROJECT IN SHELBY COUNTY ON (106B00069N) KY 12 AT RJ CORMAN RAILROAD KY-12Shelby PL80104 DN 60,000 BRX RW UT CN 600,000 BRX Project Cost: 0 60,000 600,000 T otal for Shelby county PL Total Amounts: CN UT RW DN 315,000 120,000 1,300,000 30,000 30,000 3,150,000 23,700,000 34,600,000 3,525,000 23,820,000 35,900,000 I MPROVE KY-1008 FROM KY-73 TO NORTH FRANKLIN STREET. (14CCN) KY-1008Simpson PL8855 DN RW 1,700,000 SPP UT CN Project Cost: 0 1,700,000 0 A DD A TURN LANE AT THE INTERSECTION OF KY 1008 AND US 31W (2020CCN) KY-1008Simpson PL80106 DN RW 350,000 SPP UT 300,000 SPP CN 950,000 SPP Project Cost: 0 650,000 950,000 211 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 SUPPLEMENTAL MOA FOR INDUSTRIAL ACCESS ROADS FOR S TONE-GIVENS PARK Simpson PL80202 DN RW UT CN 300,000 SPP Project Cost: 0 300,000 0 T otal for Simpson county PL Total Amounts: CN UT RW DN 2,050,000 300,000 300,000 950,000 0 2,650,000 950,000 IMPROVE SAFETY AND ADDRESS GEOMETRIC DEFICIENCIES ALONG K Y-44 NEAR DUTCHMAN CREEK ROAD. (16CCN) (2020CCR) KY-44S pencer PL8955 DN RW 230,000 SPP UT 210,000 SPP CN 1,270,000 SPP Project Cost: 0 0 1,710,000 B RIDGE PROJECT IN SPENCER COUNTY ON (108B00015N) KY 1060 AT PLUM CREEK KY-1060Spencer PL10095 DN 212,000 BRX RW UT CN 2,120,000 BRX Project Cost: 0 2,332,000 0 BRIDGE PROJECT IN SPENCER COUNTY ON (108B00042N) KY 1319 at P LUM CREEK KY-1319S pencer PL80150 DN 189,000 BRX RW UT CN 1,890,000 BRX Project Cost: 0 189,000 1,890,000 212 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 REDUCE CONGESTION, IMPROVE SAFETY, AND ENHANCE MOBILITY O N KY 55 FROM KY 44 TO INDUSTRIAL DR. (MP 6.610 TO MP 6.838) KY-55S pencer PL80213 DN 220,000 SPP RW UT 30,000 SPP CN 570,000 SPP Project Cost: 0 220,000 600,000 IMPROVE CAPACITY, RELIEVE CONGESTION, AND IMPROVE SAFETY A LONG KY 44 FROM COXS LANE (CR 1087) NEAR THE BULLITT/SPENCER CO LINE TO GOOSE CREEK ROAD (CR 1121) (MILEPOINT 0 TO MILEPOINT 1.202). KY-44S pencer PL80255 DN 1,580,000 SPP RW UT CN Project Cost: 0 1,580,000 0 I MPROVE SAFETY AND TRAFFIC OPERATIONS ON KY 55 FROM KY 44 IN TAYLORSVILLE TO KY 1169 (NORMANDY ROAD) BY PROVIDING ADDITIONAL TURNING AND PASSING OPPORTUNITIES (2+1 ROAD BY ADDING A TURN LANE THAT CAN SERVE AS AN ALTERNATING PASSING LANE). KY-55Spencer PL80256 DN 1,590,000 SPP RW UT CN Project Cost: 0 0 1,590,000 T otal for Spencer county PL Total Amounts: CN UT RW DN 2,201,000 1,590,000 230,000 240,000 2,120,000 3,730,000 0 4,321,000 5,790,000 I NSTALL GUARDRAIL ON KY-3098 IN TAYLOR COUNTYKY-3098Taylor PL4309 DN RW UT CN 55,000 GR Project Cost: 55,000 0 0 213 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN TAYLOR COUNTY ON (109C00042N) SOUTH C OLUMBIA AVE AT BUCKHORN CREEK CS-1343Taylor PL10067 DN 48,000 BRZ RW UT CN 480,000 BRZ Project Cost: 0 48,000 480,000 A DDRESS SAFETY AND GEOMETRIC DEFICIENCIES ALONG KY 70 FROM 0. MILES EAST OF ROBERTS RD (NEAR ELKHORN BAPTIST CHURCH) TO NEAR KY 76 (MILEPOINT 3.1 TO MILEPOINT 4.1) KY-70Taylor PL80256 DN 600,000 SPP RW UT CN Project Cost: 0 600,000 0 E XTEND KY 3350 (CAMPBELLSVILLE BYPASS) FROM ky 289 TO US 68 ON THE EAST SIDE OF CAMPBELLSVILLE. PF-9999Taylor PL80257 DN 1,250,000 SPP RW UT CN Project Cost: 0 1,250,000 0 T otal for Taylor county PL Total Amounts: CN UT RW DN 1,898,000 55,000 480,000 55,000 1,898,000 480,000 U pgrade connection for new industrial site on KY 848 (Haddensville Road). KY-848Todd PL170 DN RW UT CN 4,500,000 SPP Project Cost: 0 0 4,500,000 214 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 RECONSTRUCT KY-181 (ELKTON ROAD) FROM US-79 (MP 0.000) TO N ORTH OF INTERSECTION WITH US-41 (MP 0.214) TO INCLUDE A NEW INTERSECTION WITH KY-294. (MP 0.000-0.400) (14CCN)(18CCN) KY-181T odd PL8811 DN RW 280,000 STP2 UT 730,000 STP2 CN 2,820,000 STP2 Project Cost: 280,000 730,000 2,820,000 REDUCE CONGESTION AND IMPROVE MOBILITY ON US 79 FROM MP 0 TO 3 (2020BOP) US-79T odd PL 80001.1000 DN R W UT 3,435,000 NH CN 4,600,000 NH Project Cost: 0 3,435,000 4,600,000 R eplace and Widen the bridge over CSX Railroad and realign the KY 346 intersection. (2020BOP)(BUILD)(TO BE LET WITH 3-10010 & 3-80100) US-79Todd PL 80001.2000 DN R W UT CN 5,500,000 BRZ Project Cost: 0 0 5,500,000 W IDEN CR 1128 BY 1 FOOT FROM MP .333 TO KY 848 AND EXTEND 3 LANE ROAD FROM MP .129 TO MP .333 CR-1128Todd PL80215 DN RW UT CN 1,100,000 SPP Project Cost: 0 0 1,100,000 T otal for Todd county PL Total Amounts: CN UT RW DN 280,000 4,165,000 18,520,000 280,000 4,165,000 18,520,000 215 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 REALIGN KY 124 APPROACH TO KY 139 TO IMPROVE INTERSECTION A NGLE AND SIGHT DISTANCE. (16CCN)(18CCN) (2020CCR) KY-139T rigg PL8951 DN RW UT CN 500,000 STP2 Project Cost: 0 500,000 0 B RIDGE PROJECT IN TRIGG COUNTY ON (111B00031N) KY-525 AT UNNAMED STREAM KY-525Trigg PL10183 DN 70,000 FBP RW UT CN 700,000 FBP Project Cost: 70,000 700,000 0 T otal for Trigg county PL Total Amounts: CN UT RW DN 70,000 1,200,000 70,000 1,200,000 0 A DDRESS SAFETY ISSUES AND ACCESS AT THE INTERSECTION OF US-421/KY-1226 AT MP 11.5. (12CCR) (2020CCR) US-421Trimble PL905 DN RW 690,000 STP2 UT 550,000 STP2 CN Project Cost: 0 1,240,000 0 C ONSTRUCT TURN LANES INTO TRIMBLE COUNTY HIGH SCHOOL. (12CCN) US-421Trimble PL8712 DN RW 400,000 SPP UT CN 750,000 SPP Project Cost: 400,000 750,000 0 216 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS CONDITION OF I-71 FROM MILEPOINT 38.086 TO MILEPOINT 3 8.808 I-71T rimble PL22100 DN 160,000 NHPM RW UT CN 1,600,000 NHPM Project Cost: 0 1,760,000 0 T otal for Trimble county PL Total Amounts: CN UT RW DN 160,000 400,000 690,000 550,000 2,350,000 400,000 3,750,000 0 A DDRESS SAFETY, CONDITION AND SERVICE CONCERN FROM KY 109 TO WEST OF KY 360 TO ESTABLISH TRUCK NETWORK CONNECTION TO SHAWNEETOWN BRIDGE.(14CCR) (SAME AS ITEM NO. 2-310.20 IN 2014 SYP) (2020CCR) KY-56Union PL310.2100 DN RW UT CN 10,000,000 STPF Project Cost: 0 0 10,000,000 A ddress safety and service concerns of US-60 from the KY-950 to KY-492. us-60Union PL80202 DN 1,500,000 STP2 RW UT CN Project Cost: 0 0 1,500,000 A ddress the service, safety and condition of KY 56 from Morganfield to KY 141. ky-56Union PL80203 DN 2,800,000 STP1 RW UT CN Project Cost: 0 0 2,800,000 217 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Total for Union county P L Total Amounts: CN UT RW DN 4,300,000 10,000,000 0 0 14,300,000 IMPROVE KY 185 FROM 0.24 MILES SOUTH OF PRUITT ROAD TO 0.16 M ILES SOUTH OF KY 1320. (2018BOP) KY-185W arren PL110.3000 DN RW UT CN 4,000,000 STP1 Project Cost: 0 0 4,000,000 C onstruct left and right turn lanes from US 68/KY 80 onto Fred Madison Road at approximately the 17.1 milepoint. (2020BOP) US-68Warren PL166 DN RW UT CN 1,600,000 STPF Project Cost: 0 1,600,000 0 R ECONSTRUCT KY 622 (PLANO RD) TO ELIMINATE TWO RIGHT-ANGLE CURVES. KY-622Warren PL182 DN 310,000 SPP RW 260,000 SPP UT 380,000 SPP CN Project Cost: 310,000 640,000 0 I NSTALL GUARDRAIL ON KY-234 IN WARREN COUNTYKY-234Warren PL4307 DN RW UT CN 25,000 GR Project Cost: 25,000 0 0 218 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 THREE SPRINGS ROAD EXTENSION FROM FLEALAND TO THE N ATCHER PARKWAY INCLUDING BRIDGE OVER PARKWAY. (14CCN) (18CCN) (2020CCR) KY-884Warren PL8818 DN RW 2,310,000 SPP UT 4,900,000 SPP CN Project Cost: 2,310,000 0 4,900,000 W IDEN US-31W FROM WARREN/SIMPSON COUNTY LINE TO BUCHANON PARK. (14CCN) (2020CCN) US-31Warren PL8853 DN RW 1,540,000 SPP UT 4,290,000 SPP CN Project Cost: 1,540,000 0 4,290,000 MAJOR WIDENING/RECONSTRUCTION OF CEMETERY ROAD (KY-234) F ROM FOUNTAIN TRACE TO ROGER PORTER ROAD (MP 7.878 TO MP 9.625).(14CCN) (2020CCN) KY-234W arren PL8854 DN 1,000,000 SPP RW 3,150,000 SPP UT CN Project Cost: 1,000,000 0 3,150,000 I MPROVE US-31W FROM CAMPBELL LANE (US-231) TO UNIVERSITY BOULEVARD (US-231X). (14CCN)(16CCR)(18CCR) (2020CCR) US-31Warren PL8857 DN RW UT 3,000,000 SPP CN Project Cost: 0 0 3,000,000 I MPROVE MOBILITY AND REDUCE CONGESTION ON US-31W FROM US-68 TO MIZPAH. (16CCN) (2020CCR) US-31Warren PL8905 DN RW UT CN 2,760,000 STP1 Project Cost: 0 0 2,760,000 219 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADD LEFT TURNING LANE ON KY 242 INTO RICHPOND ELEMENTARY S CHOOL AT MP 3.8 TO 3.95(18CCN) KY-242Warren PL80005 DN RW UT CN 280,000 SPP Project Cost: 280,000 0 0 SAFETY IMPROVEMENTS AND REHABILITATION ON KY-3225. KEEP E XISTING FOOTPRINT BY REPLACING CURBLINE IN SAME LOCATION FROM MP 0 TO MP 1(18CCN) KY-3225W arren PL80051 DN RW 1,230,000 SPP UT 110,000 SPP CN Project Cost: 0 1,340,000 0 WIDEN KY-234 FROM MP 11.9 TO 12.4. IMPROVEMENTS MAY I NCLUDE A ROUNDABOUT, TURN LANE, AND A SIGNAL AT HAMPTON DR. (18CCN) KY-234W arren PL80052 DN 290,000 SPP RW 220,000 SPP UT CN Project Cost: 0 290,000 220,000 R educe congestion and increase safety on Cave Mill Road/Dishman Lane from the end of the three-lane section near Raintree Drive (MP 0.570) just eat of Grider Pond Road. cs-1432Warren PL80201 DN 1,860,000 SPP RW UT CN Project Cost: 0 1,860,000 0 I mprove mobility and reduce congestion on US-31W from Mizpah Road to Freeport Road US-31Warren PL80203 DN 1,000,000 NH RW 2,000,000 NH UT 1,000,000 NH CN Project Cost: 0 1,000,000 3,000,000 220 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Improve connectivity to Transpark.C R-1060Warren PL80204 DN 200,000 SPP RW 600,000 SPP UT CN 6,900,000 SPP Project Cost: 0 7,700,000 0 R EDUCE CONGESTION AND INCREASE SAFETY AND MOBILITY ON DISHMAN LANE EXT. (CS-6010) FROM MP 0.570 TO JUST EAST OF GRIDER POND ROAD ON CAVE MILL ROAD (CS-1432) CR-1704Warren PL80212 DN 1,860,000 SPP RW UT CN Project Cost: 0 1,860,000 0 C onstruct a two-lane roundabout at the intersection of KY 101 and the I-65 southbound entrance and exit ramps in Smiths Grove. Widen the existing I-65 southbound exit ramp to two lanes and extend the beginning point if the ramp approximately five-hundred to one-thousand feet north. Widen approximately five hundred feet of KY-101Warren PL80214 DN 750,000 STP2 RW UT CN Project Cost: 0 0 750,000 T otal for Warren county PL Total Amounts: CN UT RW DN 1,310,000 5,210,000 750,000 3,850,000 2,090,000 5,370,000 490,000 13,190,000 305,000 8,500,000 6,760,000 5,465,000 16,290,000 26,070,000 I MPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY CORRIDOR FROM US 150X (MP 0.00) TO KY 53 (MP 8.7) KY-555Washington PL164.1000 DN 1,300,000 STPF RW 500,000 STPF UT 1,300,000 STPF CN 5,000,000 STPF Project Cost: 0 1,800,000 6,300,000 221 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE MOBILITY ON THE KY 555 HEARTLAND PARKWAY C ORRIDOR FROM KY 53 TO BLUEGRASS PARKWAY KY-555Washington PL164.2000 DN 1,500,000 STPF RW UT CN Project Cost: 0 0 1,500,000 I MPROVE SAFETY, MOBILITY, AND GEOMETRICS ALONG US-150 FROM WEST OF OLD FREDERICKTOWN-BARDSTOWN ROAD (KY-1872) THROUGH GRUNDY HOME CURVE TO MAYFIELD LN (CR-1336). (2016BOP) (2020CCR)(D-Auth under 4-396) US-150Washington PL396.2000 DN RW UT 1,500,000 STPF CN Project Cost: 0 0 1,500,000 A DDRESS SAFETY, MOBILITY, AND GEOMETRIC ISSUES ALONG US 150 IN WASHINGTON COUNTY FROM 0.7 MILES EAST OF GRUNDY HOME ROAD (MILEPOINT 2.50) TO US 150X (MP 6.557) AT THE OLD ST. CATHERINE'S COLLEGE. (2016BOP) US-150Washington PL396.3000 DN 750,000 STPF RW 1,000,000 STPF UT CN Project Cost: 0 750,000 1,000,000 BRIDGE PROJECT IN WASHINGTON COUNTY ON (115B00004N) KY-53 A T CHAPLIN RIVER KY-53W ashington PL10068 DN 410,000 BRX RW UT CN 2,000,000 BRX Project Cost: 0 410,000 2,000,000 B RIDGE PROJECT IN WASHINGTON COUNTY ON (115B00019N) KY-152 AT CARTWRIGHT CREEK KY-152Washington PL10070 DN 175,000 BRX RW 10,000 BRX UT 10,000 BRZ CN 1,295,000 BRZ Project Cost: 0 195,000 1,295,000 222 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE PROJECT IN WASHINGTON COUNTY ON (115B00045N) K Y-458 AT BEECH FORK OF SALT RIVER KY-458Washington PL10072 DN 211,000 FBP2 RW UT CN 2,110,000 FBP2 Project Cost: 2,321,000 0 0 B RIDGE PROJECT IN WASHINGTON COUNTY ON (115C00065N) Armory Hill AT Road Run Creek CS-1041Washington PL10074 DN 57,000 BRZ RW UT CN 570,000 BRZ Project Cost: 0 627,000 0 A DDRESS CONDITION OF MARTHA LANE COLLINS BLUEGRASS PARKWAY FROM MILEPOINT 39.267 TO MILEPOINT 42 BG-9002Washington PL22177 DN 200,000 NHPM RW UT CN 2,000,000 NHPM Project Cost: 0 0 2,200,000 A DDRESS CONDITION OF MARTHA LANE COLLINS BLUEGRASS PARKWAY FROM MILEPOINT 42 TO MILEPOINT 44.807 BG-9002Washington PL22178 DN 200,000 NHPM RW UT CN 2,000,000 NHPM Project Cost: 0 2,200,000 0 T otal for Washington county PL Total Amounts: CN UT RW DN 211,000 2,892,000 1,700,000 510,000 1,000,000 10,000 2,800,000 2,110,000 2,570,000 10,295,000 2,321,000 5,982,000 15,795,000 223 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-789 IN WAYNE COUNTYK Y-789Wayne PL4311 DN RW UT CN 64,000 GR Project Cost: 0 64,000 0 B RIDGE PROJECT IN WAYNE COUNTY ON (116C00042N) EAST RALEIGH CREEK AT RALEIGH CREEK CR-1006Wayne PL10073 DN 41,000 BRZ RW UT CN 410,000 BRZ Project Cost: 0 41,000 410,000 I MPROVE CURVE ON KY 1275 AT KY 833/ROGERS GROVE ROAD AND RESURFACE FROM KY 1275 FROM BELL LANE TO KY 833/ROGERS GROVE ROAD(18CCN) (2020CCR) KY-1275Wayne PL80005 DN RW 3,500 SPP UT 60,000 SPP CN 200,000 SPP Project Cost: 63,500 200,000 0 R educe congestion and improve safety, capacity, and mobility along KY 1275, including sidewalks, from KY 90 to Bell Lane. (18CCN) (2020CCR) KY-1275Wayne PL80006 DN 490,000 STP2 RW 200,000 STP2 UT 500,000 STP2 CN Project Cost: 490,000 700,000 0 R EDUCE CONGESTION AND IMPROVES SAFETY, CAPACITY AND MOBILITY OF KY 90 BETWEEN KY 90X/KY 1275 AND KY 3106 (2020CCN) KY-90Wayne PL80105 DN RW 6,078,000 SPP UT CN Project Cost: 0 6,078,000 0 224 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 ADDRESS SAFETY, MOBILITY, AND CONNECTIVITY BY RELOCATING A LONG KY 92 IN MONTICELLO BETWEEN LOCUST ST AND ELK SPRINGS CREEK RD (2020CCN) KY-90, KY-92Wayne PL80108 DN RW 1,100,000 SPP UT 500,000 SPP CN Project Cost: 0 1,100,000 500,000 T otal for Wayne county PL Total Amounts: CN UT RW DN 490,000 41,000 3,500 7,378,000 60,000 500,000 500,000 264,000 410,000 553,500 8,183,000 910,000 RECONSTRUCT BETWEEN KY 120 AND RR BRIDGE AT SLAUGHTERS TO ALLEVIATE FLOODING. (12CCR)(18CCN) (2020CCR) KY-138W ebster PL228 DN 200,000 SPP RW 110,000 SPP UT 260,000 SPP CN Project Cost: 200,000 370,000 0 B RIDGE PROJECT IN WEBSTER COUNTY ON (117B00012N) KY-56 AT GREEN RIVER KY-56Webster PL10135 DN 890,000 FBP RW UT CN 8,900,000 FBP Project Cost: 9,790,000 0 0 T otal for Webster county PL Total Amounts: CN UT RW DN 1,090,000 110,000 260,000 8,900,000 9,990,000 370,000 0 225 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 DESIGN STUDY FOR WIDENING OF 1-75 TO 6 LANES IN WHITLEY C OUNTY FROM THE KENTUCKY/TENNESSEE STATE LINE MP 0 TO MP 20 I-75W hitley PL1 DN 2,000,000 NH RW UT CN Project Cost: 0 2,000,000 0 IMPROVE FREIGHT MOBILITY AND REDUCE CONGESTION ON US-25W F ROM KY-727 TO KY-3041 (12CCR)(16CCR)(2020CCR) (BUILD-$15.05M) us-25W hitley PL186 DN RW UT CN 16,820,000 NH Project Cost: 16,820,000 0 0 I NSTALL GUARDRAIL ON KY-1064 IN WHITLEY COUNTYKY-1064Whitley PL4311 DN RW UT CN 67,000 GR Project Cost: 67,000 0 0 I NSTALL GUARDRAIL ON KY-1064 IN WHITLEY COUNTYKY-1064Whitley PL4312 DN RW UT CN 87,000 GR Project Cost: 87,000 0 0 I NSTALL GUARDRAIL ON KY-779 IN WHITLEY COUNTYKY-779Whitley PL4313 DN RW UT CN 71,000 GR Project Cost: 71,000 0 0 226 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-26 IN WHITLEY COUNTYK Y-26Whitley PL4321 DN RW UT CN 20,000 GR Project Cost: 20,000 0 0 I NSTALL GUARDRAIL ON KY-856 IN WHITLEY COUNTYKY-856Whitley PL4322 DN RW UT CN 129,000 GR Project Cost: 129,000 0 0 I NSTALL GUARDRAIL ON KY-727 IN WHITLEY COUNTYKY-727Whitley PL4327 DN RW UT CN 15,000 GR Project Cost: 15,000 0 0 I NSTALL GUARDRAIL ON KY-312 IN WHITLEY COUNTYKY-312Whitley PL4328 DN RW UT CN 6,000 GR Project Cost: 0 6,000 0 I NSTALL GUARDRAIL ON KY-312 IN WHITLEY COUNTYKY-312Whitley PL4329 DN RW UT CN 5,000 GR Project Cost: 0 5,000 0 227 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-856 IN WHITLEY COUNTYK Y-856Whitley PL4330 DN RW UT CN 54,000 GR Project Cost: 0 54,000 0 I NSTALL GUARDRAIL ON KY-1064 IN WHITLEY COUNTYKY-1064Whitley PL4335 DN RW UT CN 121,000 GR Project Cost: 0 121,000 0 I NSTALL GUARDRAIL ON KY-727 IN WHITLEY COUNTYKY-727Whitley PL4336 DN RW UT CN 9,000 GR Project Cost: 0 9,000 0 I NSTALL GUARDRAIL ON KY-727 IN WHITLEY COUNTYKY-727Whitley PL4337 DN RW UT CN 13,000 GR Project Cost: 0 13,000 0 I NSTALL GUARDRAIL ON KY-779 IN WHITLEY COUNTYKY-779Whitley PL4338 DN RW UT CN 51,000 GR Project Cost: 0 51,000 0 228 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-779 IN WHITLEY COUNTYK Y-779Whitley PL4339 DN RW UT CN 19,000 GR Project Cost: 0 19,000 0 I NSTALL GUARDRAIL ON KY-779 IN WHITLEY COUNTYKY-779Whitley PL4340 DN RW UT CN 24,000 GR Project Cost: 0 24,000 0 I NSTALL GUARDRAIL ON KY-836 IN WHITLEY COUNTYKY-836Whitley PL4341 DN RW UT CN 59,000 GR Project Cost: 0 59,000 0 I NSTALL GUARDRAIL ON KY-1064 IN WHITLEY COUNTYKY-1064Whitley PL4346 DN RW UT CN 40,000 GR Project Cost: 0 0 40,000 I NSTALL GUARDRAIL ON KY-779 IN WHITLEY COUNTYKY-779Whitley PL4347 DN RW UT CN 25,000 GR Project Cost: 0 0 25,000 229 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-779 IN WHITLEY COUNTYK Y-779Whitley PL4348 DN RW UT CN 8,000 GR Project Cost: 0 0 8,000 I NSTALL GUARDRAIL ON KY-1064 IN WHITLEY COUNTYKY-1064Whitley PL4358 DN RW UT CN 9,000 GR Project Cost: 0 0 9,000 I NSTALL GUARDRAIL ON KY-204 IN WHITLEY COUNTYKY-204Whitley PL4359 DN RW UT CN 11,000 GR Project Cost: 0 0 11,000 I NSTALL GUARDRAIL ON KY-312 IN WHITLEY COUNTYKY-312Whitley PL4361 DN RW UT CN 5,000 GR Project Cost: 0 0 5,000 I NSTALL GUARDRAIL ON KY-727 IN WHITLEY COUNTYKY-727Whitley PL4362 DN RW UT CN 16,000 GR Project Cost: 0 0 16,000 230 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 INSTALL GUARDRAIL ON KY-836 IN WHITLEY COUNTYK Y-836Whitley PL4363 DN RW UT CN 10,000 GR Project Cost: 0 0 10,000 I NSTALL GUARDRAIL ON KY-856 IN WHITLEY COUNTYKY-856Whitley PL4364 DN RW UT CN 41,000 GR Project Cost: 0 0 41,000 B RIDGE PROJECT IN WHITLEY COUNTY ON (118B00084N) KY-204 at YOUNGS CREEK KY-204Whitley PL10034 DN 79,000 BRX RW UT CN 790,000 BRX Project Cost: 0 79,000 790,000 ADDRESS CONDITION OF I-75 FROM MILEPOINT 20.045 TO MILEPOINT 2 5.4 (24.645 CARDINAL) I-75W hitley PL20018 DN 400,000 NHPM RW UT CN 4,000,000 NHPM Project Cost: 0 0 4,400,000 I MPROVE SAFETY AND MOBILITY ON US 25W (MILEPOINT 13.3 TO MILEPOINT 14.6) INCLUDED IN THIS RECONSTRUCTION WILL BE APPROXIMATELY 1.3 MILES OF ROADWAY TO BE WIDENED/IMPROVED, AN APPROXIMATELY 250' BRIDGE REPLACEMENT OVER WATTS CREEK, AN APPROXIMATELY 150' us-25Whitley PL80107 DN RW 1,000,000 BRO UT 500,000 BRO CN Project Cost: 0 1,000,000 500,000 231 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 WIDEN BLACK DIAMOND ROAD (2020CCN)C R-1088Whitley PL80112 DN RW UT CN 260,000 SPP Project Cost: 260,000 0 0 RECONFIGURE EXISTING INTERSECTION OF KY 92 AND PENNY LANE TO IMPROVE SAFETY ALONG AT INTERSECTION. CONSTRUCT NEW CONNECTOR ROAD BETWEEN KY 92 AND PENNY LANE. RECONFIGURE TRAFFIC OPERATION ALONG PENNY LANE BETWEEN KY 92 AND NEW CONNECTOR ROAD ky-92W hitley PL80264 DN 150,000 SPP RW 1,000,000 SPP UT 90,000 SPP CN 1,300,000 SPP Project Cost: 0 150,000 2,390,000 T otal for Whitley county PL Total Amounts: CN UT RW DN 2,229,000 400,000 1,000,000 1,000,000 590,000 17,469,000 361,000 6,255,000 17,469,000 3,590,000 8,245,000 MOUNTAIN PARKWAY CORRIDOR: WIDEN THE MTN PKY TO 4 LANES F ROM 0.6 MI W OF KY 191 OVERPASS TO 0.45 MI W OF KY 205 INTERCHANGE. (US DOT providing $55.2 million of INFRA Grant funding to be used in conjunction with the $55.2 million of federal NH funding.) KY-9009W olfe PL168 DN RW UT CN 55,200,000 NH Project Cost: 55,200,000 0 0 M inor widening to improve redundancy of Regional travel.KY-15Wolfe PL177 DN 750,000 PROT RW UT CN Project Cost: 0 0 750,000 232 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 IMPROVE THE KY-191 AND KY-1812 INTERSECTION.K Y-191Wolfe PL212 DN 260,000 STP2 RW 110,000 STP2 UT 110,000 STP2 CN Project Cost: 0 260,000 220,000 T otal for Wolfe county PL Total Amounts: CN UT RW DN 260,000 750,000 110,000 110,000 55,200,000 55,200,000 260,000 970,000 I MPROVE US 60 (VERSAILLES ROAD) FROM THE BLUEGRASS PARKWAY/HUNTERTOWN PIKE TO PISGAH PIKE. US-60Woodford PL117 DN 1,000,000 NH RW UT CN Project Cost: 0 1,000,000 0 ACCESS MANAGEMENT IMPROVEMENTS ON US 60 FROM LEXINGTON R OAD AT WOODFORD FEED TO MARSAILLES DRIVE (MP 9.38 TO MP 9.70).(16CCN)(18CCN) US-60W oodford PL8905 DN RW 1,000,000 SPP UT 780,000 SPP CN Project Cost: 0 1,780,000 0 A DDRESS CONDITION OF MARTHA LANE COLLINS BLUEGRASS PARKWAY CARDINAL DIRECTION FROM MILEPOINT 70.727 TO MILEPOINT 71.134 BG-9002Woodford PL22184 DN 25,000 NHPM RW UT CN 250,000 NHPM Project Cost: 0 275,000 0 233 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 Reconstruct McCracken Pike (KY-1659) on a new horizontal alignment t o minimize pedestrian and vehicle conflicts near Woodford Reserve Distillery (ROW to be provided by County) ky-1659Woodford PL80200 DN 225,000 SPP RW UT 120,000 SPP CN 850,000 SPP Project Cost: 225,000 120,000 850,000 T otal for Woodford county PL Total Amounts: CN UT RW DN 225,000 1,025,000 1,000,000 900,000 250,000 850,000 225,000 3,175,000 850,000 B RIDGE REPAIRS ON VARIOUS BRIDGES FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL65.1900 DN RW UT CN 5,000,000 5,000,000 5,000,000 BRO Project Cost: 5,000,000 5,000,000 5,000,000 B RIDGE REPAIRS ON VARIOUS BRIDGES FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL65.2000 DN RW UT CN 3,000,000 3,000,000 3,000,000 BRX Project Cost: 3,000,000 3,000,000 3,000,000 B RIDGE REPAIRS ON VARIOUS OFF SYSTEM BRIDGES FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL65.2100 DN RW UT CN 2,000,000 2,000,000 2,000,000 BRZ Project Cost: 2,000,000 2,000,000 2,000,000 234 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 BRIDGE REPAIRS ON VARIOUS BRIDGES FOR FY 2022-2028. (FBP P ROGRAM) CO-0ZVarious PL65.2200 DN RW UT CN 5,000,000 5,000,000 FBP Project Cost: 5,000,000 5,000,000 0 B RIDGE REPAIRS ON VARIOUS BRIDGES FOR FY 2022-2028. (FBP2 PROGRAM) CO-0ZVarious PL65.2300 DN RW UT CN 8,000,000 6,500,000 8,000,000 FBP2 Project Cost: 8,000,000 6,500,000 8,000,000 ' ITS' AND 'TSMO' ACTIVITIES ON VARIOUS NHS ROUTES IN KENTUCKY FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL66.1900 DN RW UT CN 5,000,000 5,000,000 5,000,000 NH Project Cost: 5,000,000 5,000,000 5,000,000 T ransportation Systems Management and Operations (TSMO) activities on various routes for FY-2022 through FY 2028. CO-0ZVarious PL66.2100 DN RW UT CN 2,000,000 2,000,000 2,000,000 SPP Project Cost: 2,000,000 2,000,000 2,000,000 S TATEWIDE TRANSPORTATION ALTERNATIVES PROGRAM FOR FY 2022 THROUGH FY 2028 CO-0ZVarious PL195.1600 DN RW UT CN 11,386,503 11,614,233 11,846,518 TAP Project Cost: 11,386,503 11,614,233 11,846,518 235 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 NON-ATTAINMENT AREAS STATEWIDE CMAQ FUNDED PROJECTS FO R FY 2022 THROUGH FY 2028. CO-0ZVarious PL219.1800 DN RW UT CN 14,926,634 15,225,167 15,529,670 CM Project Cost: 14,926,634 15,225,167 15,529,670 P AVEMENT REHAB ON STATE (NON RS) SYSTEM ROUTES IN KENTUCKY FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL224.1400 DN RW UT CN 5,000,000 5,000,000 5,000,000 STP5 Project Cost: 5,000,000 5,000,000 5,000,000 P ROMOTING RESILIENT OPERATIONS FOR TRANSFORMATIVE, EFFICIENT, AND COST SAVING TRANSPORTATION (PROTECT) PROGRAM FORMULA FUNDS. CO-0ZVarious PL239 DN RW UT CN 30,560,000 19,559,000 25,060,000 PROT Project Cost: 30,560,000 19,559,000 25,060,000 S TATEWIDE CARBON REDUCTION PROGRAM.CO-0ZVarious PL244 DN RW UT CN 26,860,000 29,410,000 27,960,000 CARB Project Cost: 26,860,000 29,410,000 27,960,000 S TATEWIDE ELECTRIC VEHICLE CHARGING STATION PROGRAMCO-0ZVarious PL247 DN RW UT CN 13,800,000 13,800,000 13,800,000 EV Project Cost: 13,800,000 13,800,000 13,800,000 236 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 STATEWIDE BRIDGE INSPECTION FOR FY 2022 THROUGH FY 2028.C O-0ZVarious PL327.1600 DN RW UT CN 5,000,000 5,000,000 5,000,000 BRX Project Cost: 5,000,000 5,000,000 5,000,000 S TATEWIDE I-STATE ROUTES FOR FY 2022 THROUGH FY 2028.CO-0ZVarious PL337.1500 DN RW UT CN 5,000,000 5,000,000 5,000,000 NHPM Project Cost: 5,000,000 5,000,000 5,000,000 S TATEWIDE OFF-SYSTEM BRIDGE INSPECTION FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL346.1600 DN RW UT CN 3,000,000 3,000,000 3,000,000 BRZ Project Cost: 3,000,000 3,000,000 3,000,000 R AILWAY-HIGHWAY CROSSINGS PROGRAM ON VARIOUS ROUTES FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL352.1600 DN RW UT CN 4,000,000 4,000,000 4,000,000 RRP Project Cost: 4,000,000 4,000,000 4,000,000 P AVEMENT REHABILITATION FOR VARIOUS NHS ROUTES IN KENTUCKY FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL369.1000 DN RW UT CN 5,000,000 5,000,000 5,000,000 NHPM Project Cost: 5,000,000 5,000,000 5,000,000 237 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 OHIO RIVER BRIDGES FRACTURE CRITICAL FOR FY 2022 THROGH FY 2 028. CO-0Z Various PL388.1000 DN RW UT CN 4,000,000 4,000,000 4,000,000 BRX Project Cost: 4,000,000 4,000,000 4,000,000 S TATEWIDE HIGHWAY PROJECT DESIGN ACTIVITIES FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL391.0600 DN 1,000,000 1,000,000 1,000,000 STPF RW UT CN Project Cost: 1,000,000 1,000,000 1,000,000 S TATEWIDE HIGHWAY PROJECT DESIGN ACTIVITIES FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL391.0700 DN 5,000,000 5,000,000 5,000,000 SPP RW UT CN Project Cost: 5,000,000 5,000,000 5,000,000 U PGRADE NAVIGATIONAL LIGHTING FOR BRIDGES OVER MAJOR STREAMS AND WATERWAYS FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL400.0700 DN RW UT CN 500,000 500,000 500,000 BRX Project Cost: 500,000 500,000 500,000 H ONORING BORDER STATES COMMITMENTS FOR EXISTING BRIDGES(CANNOT BE MOVED) FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL510.0500 DN RW UT CN 2,000,000 2,000,000 2,000,000 BRX Project Cost: 2,000,000 2,000,000 2,000,000 238 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 STATEWIDE CORRECTIONS OF ROCK FALL OR EMBANKMENT S TABILIZATION FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL511.0400 DN RW UT CN 1,000,000 1,000,000 1,000,000 SPP Project Cost: 1,000,000 1,000,000 1,000,000 P REVENTATIVE MAINTENANCE FOR BRIDGE STRUCTURES FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL514.0100 DN RW UT CN 2,500,000 2,500,000 2,500,000 BRX Project Cost: 2,500,000 2,500,000 2,500,000 S TATEWIDE CORRECTIONS OF ROCKFALL OR EMBANKMENT STABILIZATION ON NH ROUTES FOR FY 2020. (2020CCR) CO-0ZVarious PL518.0100 DN RW UT CN 5,000,000 5,000,000 5,000,000 NH Project Cost: 5,000,000 5,000,000 5,000,000 S TATEWIDE CORRECTIONS OF ROCKFALL OR EMBANKMENT STABILIZATION ON NON NH ROUTES FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL518.0300 DN RW UT CN 5,000,000 5,000,000 3,000,000 STPF Project Cost: 5,000,000 5,000,000 3,000,000 S TATEWIDE SAFETY PROGRAM FOR FY 2022 THROUGH FY 2028. (HSIP) CO-0ZVarious PL911.0900 DN RW UT CN 52,277,904 53,403,157 54,550,914 SAF Project Cost: 52,277,904 53,403,157 54,550,914 239 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 STATEWIDE SAFETY FUNDING TO BE USED ALONGSIDE FEDERAL H SIP FUNDING TO ENHANCE ROADWAY SAFETY, AND SCHOOL SAFETY PROJECTS IN KENTUCKY. CO-0ZVarious PL911.5000 DN RW UT CN 11,500,000 11,500,000 11,500,000 SPP Project Cost: 11,500,000 11,500,000 11,500,000 S TATEWIDE UNDERWATER BRIDGE INSPECTION FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL1063.1600 DN RW UT CN 1,000,000 1,000,000 1,000,000 BRX Project Cost: 1,000,000 1,000,000 1,000,000 S TATEWIDE PROGRAM TO FUND BRIDGE SCOUR COUNTER-MEASURES FOR STATE-MAINTAINED BRIDGES FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL1071.0800 DN RW UT CN 3,000,000 3,000,000 3,000,000 BRX Project Cost: 3,000,000 3,000,000 3,000,000 S TATEWIDE BRIDGE REPLACEMENT PROGRAM FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL1074.0800 DN RW UT CN 3,000,000 3,000,000 3,000,000 BRX Project Cost: 3,000,000 3,000,000 3,000,000 P AVEMENT PREVENTATIVE MAINTENANCE PROGRAM FOR FY 2022 THROUGH FY 2028 STP5 FUNDING. CO-0ZVarious PL2700.1400 DN RW UT CN 2,000,000 2,000,000 2,000,000 STP5 Project Cost: 2,000,000 2,000,000 2,000,000 240 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 AMERICANS WITH DISABILITIES ACT (ADA) TRANSITION PLAN I MPLEMENTATION PROJECTS FY 2022 THROUGH FY 2028. CO-0ZVarious PL3011.0100 DN RW UT CN 1,000,000 1,000,000 1,000,000 STPF Project Cost: 1,000,000 1,000,000 1,000,000 S CHOOL TURN LANE PROJECTS FOR NEW SCHOOLS FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL8500.1600 DN RW UT CN 2,500,000 2,500,000 2,500,000 SPP Project Cost: 2,500,000 2,500,000 2,500,000 W estern KY DECEMBER 2021 Tornado Relief Funding POOL FOR THE LAST DOLLAR (UNCOVERED BY FEMA OR INSURANCE) RECONCTRUCTION OF EXISTING ROADS. CO-0ZVarious PL8600 DN RW UT CN 10,000,000 10,000,000 SPP Project Cost: 0 10,000,000 10,000,000 A DVANCE CONSTRUCTION COMMITMENTS FOR I-MOVE, I-69 AND OTHER ACTIVE DESIGN/BUILD PROJECTS. CO-0ZVarious PL8601 DN RW UT CN 89,000,000 89,000,000 NH Project Cost: 0 89,000,000 89,000,000 U S 68/KY 80 LAKE BARKLEY AND KENTUCKY LAKE GARVEE BOND DEBT SERVICE FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL9068.6100 DN RW UT CN 9,100,000 9,100,000 21,000,000 GAR Project Cost: 9,100,000 9,100,000 21,000,000 241 County FundPhaseDescriptionRouteItem No. 2022-2 FY2022 FY2023 FY2024 US 68/KY 80 LAKE BARKLEY AND KENTUCKY LAKE GARVEE BOND D EBT SERVICE (STP) FOR FY 2022 THROUGH FY 2028. CO-0ZVarious PL9068.6600 DN RW UT CN 9,100,000 9,100,000 21,000,000 GAR Project Cost: 9,100,000 9,100,000 21,000,000 G ARVEE BOND DEBT SERVICE FOR LOUISVILLE BRIDGES PROJECT FOR FY 2022 THROUGH FY 2025 "NH" FUNDING. CO-0ZVarious PL9659.2300 DN RW UT CN 62,800,000 30,000,000 30,000,000 GAR Project Cost: 62,800,000 30,000,000 30,000,000 T otal for ZVarious county PL Total Amounts: CN UT RW DN 6,000,000 6,000,000 6,000,000 331,811,041 389,711,557 413,747,102 337,811,041 395,711,557 419,747,102 242 2022-2 Biennium Fund Summary Fund D FY 2023 FY 2024 Total APD FEDERAL APPALACHIAN DEVELOPMENT HIGHWAYS 0 5,000,000 5,000,000 BRO FEDERAL BRIDGE REPLACEMENT - ON SYSTEM 94,925,000 87,051,000 181,976,000 BRX FEDERAL BRIDGE REPLACEMENT - ON/OFF SYSTEM 69,233,000 61,920,000 131,153,000 BRZ FEDERAL BRIDGE REPLACEMENT - OFF SYSTEM 26,517,000 23,656,500 50,173,500 CARB CARBON REDUCTION PROGRAM 29,410,000 27,960,000 57,370,000 CM FEDERAL CONGESTION MITIGATION FUNDS 15,225,167 15,529,670 30,754,837 EV ELECTRIC VEHICLE CHARGING STATION FUNDS 13,800,000 13,800,000 27,600,000 FBP FEDERAL BRIDGE PROGRAM 59,206,000 59,520,000 118,726,000 FBP2 FEDERAL BRIDGE PROGRAM - OFF SYSTEM 59,502,000 57,847,000 117,349,000 GAR BIENNIAL GARVEE BOND FUNDS DESIGNATED FOR LSIORB 48,200,000 72,000,000 120,200,000 GR GUARD RAIL INSTALLATION 3,653,000 4,024,000 7,677,000 IF INNOVATIVE FINANCING 440,000,000 355,000,000 795,000,000 NH FEDERAL NATIONAL HIGHWAY SYSTEM FUNDS 291,315,800 392,805,000 684,120,800 NHPM NATIONAL HIGHWAYS SYSTEM FUNDS FOR PAVEMENT 193,684,590 234,846,902 428,531,492 PROT PROTECT FORMULA PROGRAM 32,670,000 31,800,000 64,470,000 RRP SAFETY-RAILROAD PROTECTION 4,000,000 4,000,000 8,000,000 SAF FEDERAL SAFETY FUNDS 53,403,157 54,550,914 107,954,071 SAH FEDERAL STP FUNDS DEDICATED TO ASHLAND 1,718,828 1,753,205 3,472,033 SHN FEDERAL STP FUNDS DEDICATED TO HENDERSON 868,100 885,462 1,753,562 SLO FEDERAL STP FUNDS DEDICATED TO LOUISVILLE 25,279,952 25,785,551 51,065,503 SLX FEDERAL STP FUNDS DEDICATED TO LEXINGTON 7,417,834 7,566,191 14,984,025 SNK FEDERAL STP FUNDS DEDICATED TO NORTHERN KENTUCKY 8,072,447 8,233,896 16,306,343 SPP STATE CONSTRUCTION HIGH PRIORITY PROJECTS 294,960,700 299,108,470 594,069,170 STP FEDERAL STATEWIDE TRANSPORTATION PROGRAM FUNDS 44,530,000 30,020,000 74,550,000 STP1 SURFACE TRANSPORTATION (5-200K POP) 23,581,000 54,291,000 77,872,000 STP2 SURFACE TRANSPORTATION (<5K POP) 57,123,200 64,666,600 121,789,800 STP3 SURFACE TRANSPORTATION (5-200K POP) FOR PAVEMENT 5,000,000 5,500,000 10,500,000 STP4 SURFACE TRANSPORTATION (<5K POP) FOR PAVEMENT 2,000,000 0 2,000,000 STP5 SURFACE TRANSPORTATION FLEX FUNDING FOR PAVEMENT 10,440,000 7,225,000 17,665,000 STPF SURFACE TRANSPORTATION FLEX FUNDING 78,610,000 172,682,500 251,292,500 TAP FEDERAL TRANSPORTATION ALTERNATIVES PROGRAM 11,614,233 11,846,518 23,460,751 Total Amount 2,005,961,008 2,190,875,379 4,196,836,387 243 2022-2 Fund Summary Fund D FY 2022 FY 2023 FY 2024 Total APD FEDERAL APPALACHIAN DEVELOPMENT HIGHWAYS 0 0 5,000,000 5,000,000 BRO FEDERAL BRIDGE REPLACEMENT - ON SYSTEM 25,250,000 94,925,000 87,051,000 207,226,000 BRX FEDERAL BRIDGE REPLACEMENT - ON/OFF SYSTEM 35,323,000 69,233,000 61,920,000 166,476,000 BRZ FEDERAL BRIDGE REPLACEMENT - OFF SYSTEM 11,126,000 26,517,000 23,656,500 61,299,500 CARB CARBON REDUCTION PROGRAM 26,860,000 29,410,000 27,960,000 84,230,000 CM FEDERAL CONGESTION MITIGATION FUNDS 14,926,634 15,225,167 15,529,670 45,681,471 EV ELECTRIC VEHICLE CHARGING STATION FUNDS 13,800,000 13,800,000 13,800,000 41,400,000 FBP FEDERAL BRIDGE PROGRAM 52,333,000 59,206,000 59,520,000 171,059,000 FBP2 FEDERAL BRIDGE PROGRAM - OFF SYSTEM 57,641,000 59,502,000 57,847,000 174,990,000 GAR BIENNIAL GARVEE BOND FUNDS DESIGNATED FOR LSIORB 81,000,000 48,200,000 72,000,000 201,200,000 GR GUARD RAIL INSTALLATION 4,708,000 3,653,000 4,024,000 12,385,000 IF INNOVATIVE FINANCING 0 440,000,000 355,000,000 795,000,000 NH FEDERAL NATIONAL HIGHWAY SYSTEM FUNDS 173,510,000 291,315,800 392,805,000 857,630,800 NHPM NATIONAL HIGHWAYS SYSTEM FUNDS FOR PAVEMENT 88,865,000 193,684,590 234,846,902 517,396,492 PROT PROTECT FORMULA PROGRAM 30,560,000 32,670,000 31,800,000 95,030,000 RRP SAFETY-RAILROAD PROTECTION 4,000,000 4,000,000 4,000,000 12,000,000 SAF FEDERAL SAFETY FUNDS 52,277,904 53,403,157 54,550,914 160,231,975 SAH FEDERAL STP FUNDS DEDICATED TO ASHLAND 1,685,126 1,718,828 1,753,205 5,157,159 SHN FEDERAL STP FUNDS DEDICATED TO HENDERSON 851,078 868,100 885,462 2,604,640 SLO FEDERAL STP FUNDS DEDICATED TO LOUISVILLE 24,784,266 25,279,952 25,785,551 75,849,769 SLX FEDERAL STP FUNDS DEDICATED TO LEXINGTON 7,272,387 7,417,834 7,566,191 22,256,412 SNK FEDERAL STP FUNDS DEDICATED TO NORTHERN KENTUCKY 7,914,163 8,072,447 8,233,896 24,220,506 SPP STATE CONSTRUCTION HIGH PRIORITY PROJECTS 93,424,750 294,960,700 299,108,470 687,493,920 STP FEDERAL STATEWIDE TRANSPORTATION PROGRAM FUNDS 5,500,000 44,530,000 30,020,000 80,050,000 STP1 SURFACE TRANSPORTATION (5-200K POP) 18,298,000 23,581,000 54,291,000 96,170,000 STP2 SURFACE TRANSPORTATION (<5K POP) 21,140,000 57,123,200 64,666,600 142,929,800 STP3 SURFACE TRANSPORTATION (5-200K POP) FOR PAVEMENT 0 5,000,000 5,500,000 10,500,000 STP4 SURFACE TRANSPORTATION (<5K POP) FOR PAVEMENT 365,000 2,000,000 0 2,365,000 STP5 SURFACE TRANSPORTATION FLEX FUNDING FOR PAVEMENT 7,000,000 10,440,000 7,225,000 24,665,000 STPF SURFACE TRANSPORTATION FLEX FUNDING 58,500,400 78,610,000 172,682,500 309,792,900 TAP FEDERAL TRANSPORTATION ALTERNATIVES PROGRAM 11,386,503 11,614,233 11,846,518 34,847,254 Total Amount 930,302,211 2,005,961,008 2,190,875,379 5,127,138,598 244