UNOFFICIAL COPY 23 RS HB 4/EN Page 1 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed AN ACT relating to merchant electric generating facilities and making an 1 appropriation therefor. 2 Be it enacted by the General Assembly of the Commonwealth of Kentucky: 3 Section 1. KRS 278.702 is amended to read as follows: 4 (1) There is hereby established the Kentucky State Board on Electric Generation and 5 Transmission Siting. The board shall be composed of seven (7) members as 6 follows: 7 (a) The three (3) members of the Kentucky Public Service Commission; 8 (b) The secretary of the Energy and Environment Cabinet or the secretary's 9 designee; 10 (c) The secretary of the Cabinet for Economic Development or the secretary's 11 designee; 12 (d) 1. If the facility subject to board approval is proposed to be located in one 13 (1) county, two (2) ad hoc public members to be appointed by the 14 Governor from a county where a facility subject to board approval is 15 proposed to be located: 16 a. One (1) of the ad hoc public members shall be the chairman of the 17 planning commission with jurisdiction over an area in which a 18 facility subject to board approval is proposed to be located. If the 19 proposed location is not within a jurisdiction with a planning 20 commission, then the Governor shall appoint either the county 21 judge/executive of a county that contains the proposed location of 22 the facility or the mayor of a city, if the facility is proposed to be 23 within a city; and 24 b. One (1) of the ad hoc public members shall be appointed by the 25 Governor and shall be a resident of the county in which the facility 26 is proposed to be located. 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 2 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed 2. If the facility subject to board approval is proposed to be located in more 1 than one (1) county, two (2) ad hoc public members to be chosen as 2 follows: 3 a. One (1) ad hoc public member shall be the county judge/executive 4 of a county in which the facility is proposed to be located, to be 5 chosen by majority vote of the county judge/executives of the 6 counties in which the facility is proposed to be located; and 7 b. One (1) ad hoc public member shall be a resident of a county in 8 which the facility is proposed to be located, and shall be appointed 9 by the Governor. 10 If a member has not been chosen by majority vote, as provided in 11 subdivision a. of this subparagraph, by thirty (30) days after the filing of 12 the application, the Governor shall directly appoint the member. 13 3. Ad hoc public members appointed to the board shall have no direct 14 financial interest in the facility proposed to be constructed. 15 (2) The term of service for the ad hoc members of the board shall continue until the 16 merchant electric generating facility[board issues a final determination in the 17 proceeding] for which they were appointed has been constructed and begins 18 generating electricity for sale or the construction certificate expires. The 19 remaining members of the board shall be permanent members. 20 (3) The board shall be attached to the Public Service Commission for administrative 21 purposes. The commission staff shall serve as permanent administrative staff for the 22 board. The members of the board identified in subsection (1)(a) to (d) of this 23 section shall promulgate administrative regulations in accordance with KRS 24 Chapter 13A to implement KRS 278.700 to 278.716. 25 (4) No member of the board shall receive any salary or fee for service on the board or 26 shall have any financial interest in any facility the application for which comes 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 3 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed before the board, but each member shall be reimbursed for actual travel and 1 expenses directly related to service on the board. 2 (5) The chairman of the Public Service Commission shall be the chairman of the board. 3 The chairman shall designate one (1) member of the board as vice chairman. A 4 majority of the members of the board shall constitute a quorum for the transaction 5 of business. No vacancy on the board shall impair the right of the remaining 6 members to exercise all of the powers of the board. The board shall convene upon 7 the call of the chairman. 8 Section 2. KRS 278.704 is amended to read as follows: 9 (1) No person shall commence to construct a merchant electric generating facility until 10 that person has applied for and obtained a construction certificate for the facility 11 from the board. The construction certificate shall be valid for a period of three 12 (3)[two (2)] years after the issuance date of the last permit required to be obtained 13 from the Energy and Environment Cabinet after which the certificate shall be void. 14 The certificate shall be conditioned upon the applicant obtaining necessary air, 15 water, and waste permits. If an applicant has not obtained all necessary permits and 16 has not commenced to construct prior to the expiration date of the certificate, the 17 applicant shall be required to obtain a new valid certificate from the board. 18 (2) Except as provided in subsections (3), (4), and (5) of this section, no construction 19 certificate shall be issued to construct a merchant electric generating facility unless 20 the exhaust stack of the proposed facility and any wind turbine is at least one 21 thousand (1,000) feet from the property boundary of any adjoining property owner 22 and all proposed structures or facilities used for generation of electricity are two 23 thousand (2,000) feet from any residential neighborhood, school, hospital, or 24 nursing home facility. For purposes of applications for site compatibility certificates 25 pursuant to KRS 278.216, only the exhaust stack of the proposed facility to be 26 actually used for coal or gas-fired generation or, beginning with applications for site 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 4 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed compatibility certificates filed on or after January 1, 2015, the proposed structure or 1 facility to be actually used for solar or wind generation shall be required to be at 2 least one thousand (1,000) feet from the property boundary of any adjoining 3 property owner and two thousand (2,000) feet from any residential neighborhood, 4 school, hospital, or nursing home facility. 5 (3) If the merchant electric generating facility is proposed to be located in a county or a 6 municipality with planning and zoning, then decommissioning and setback 7 requirements from a property boundary, residential neighborhood, school, hospital, 8 or nursing home facility may be established by the planning and zoning 9 commission. Any decommissioning requirement or setback established by a 10 planning and zoning commission for a facility in an area over which it has 11 jurisdiction shall: 12 (a) Have primacy over the decommissioning requirements in subsection (2)(m) 13 of Section 3 of this Act and the setback requirement in subsections (2) and (5) 14 of this section; and 15 (b) Not be subject to modification or waiver by the board through a request for 16 deviation by the applicant, as provided in subsection (4) of this section or 17 otherwise. 18 (4) The board may grant a deviation from the requirements of subsection (2) of this 19 section on a finding that the proposed facility is designed to and, as located, would 20 meet the goals of KRS 224.10-280, 278.010, 278.212, 278.214, 278.216, 278.218, 21 and 278.700 to 278.716 at a distance closer than those provided in subsection (2) of 22 this section. 23 (5) If the merchant electric generating facility is proposed to be located on a site of a 24 former coal processing plant in the Commonwealth where the electric generating 25 facility will utilize on-site waste coal as a fuel source, then the one thousand (1,000) 26 foot property boundary requirement in subsection (2) of this section shall not be 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 5 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed applicable; however, the applicant shall be required to meet any other setback 1 requirements contained in subsection (2) of this section. 2 (6) If requested, a merchant electric generating entity considering construction of a 3 facility for the generation of electricity or a person acting on behalf of such an 4 entity shall hold a public meeting in any county where acquisition of real estate or 5 any interest in real estate is being considered for the facility. A request for such a 6 meeting may be made by the commission, or by any city or county governmental 7 entity, including a board of commissioners, planning and zoning, fiscal court, 8 mayor, or county judge/executive. The meeting shall be held not more than thirty 9 (30) days from the date of the request. 10 (7) The purpose of the meeting under subsection (6) of this section is to fully inform 11 landowners and other interested parties of the full extent of the project being 12 considered, including the project time line. One (1) or more representatives of the 13 entity with full knowledge of all aspects of the project shall be present and shall 14 answer questions from the public. 15 (8) Notice of the time, subject, and location of the meeting under subsection (6) of this 16 section shall be posted in both a local newspaper, if any, and a newspaper of 17 general circulation in the county. Notice shall also be placed on the websites[Web 18 sites] of the unregulated entity, and any local governmental unit. Owners of real 19 estate known to be included in the project and any person whose property adjoins at 20 any point any property to be included in the project shall be notified personally by 21 mail. All notices must be mailed or posted at least two (2) weeks prior to the 22 meeting. 23 (9) The merchant electric generating entity or a person acting on behalf of a merchant 24 electric generating entity shall, on or before the date of the public meeting held 25 under subsection (6) of this section, provide notice of all research, testing, or any 26 other activities being planned or considered to: 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 6 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed (a) The Energy and Environment Cabinet; 1 (b) The Public Service Commission; 2 (c) The Transportation Cabinet; 3 (d) The Attorney General; and 4 (e) The Office of the Governor. 5 (10) [A person that, on or before April 10, 2014, has started acquiring interests in real 6 estate for a project as described in subsection (6) of this section shall hold a meeting 7 that complies with this section within thirty (30) days of April 10, 2014. 8 (11)] Subsections (6) to (9)[(10)] of this section shall not apply to any facility or project 9 that has already received a certificate of construction from the board. 10 Section 3. KRS 278.706 is amended to read as follows: 11 (1) Any person seeking to obtain a construction certificate from the board to construct a 12 merchant electric generating facility shall file an application at the office of the 13 Public Service Commission. 14 (2) A completed application shall include the following: 15 (a) The name, address, and telephone number of the person proposing to 16 construct and own the merchant electric generating facility; 17 (b) A full description of the proposed site, including a map showing the distance 18 of the proposed site from residential neighborhoods, the nearest residential 19 structures, schools, and public and private parks that are located within a two 20 (2) mile radius of the proposed facility; 21 (c) Evidence of public notice that shall include the location of the proposed site 22 and a general description of the project, state that the proposed construction is 23 subject to approval by the board, and provide the telephone number and 24 address of the Public Service Commission. Public notice shall be given within 25 thirty (30) days immediately preceding the application filing to: 26 1. Landowners whose property borders the proposed site; and 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 7 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed 2. The general public in a newspaper of general circulation in the county or 1 municipality in which the facility is proposed to be located; 2 (d) A statement certifying that the proposed plant will be in compliance with all 3 local ordinances and regulations concerning noise control and with any local 4 planning and zoning ordinances. The statement shall also disclose setback 5 requirements established by the planning and zoning commission as provided 6 under KRS 278.704(3); 7 (e) If the facility is not proposed to be located on a site of a former coal 8 processing plant and the facility will use on-site waste coal as a fuel source or 9 in an area where a planning and zoning commission has established a setback 10 requirement pursuant to KRS 278.704(3), a statement that the exhaust stack of 11 the proposed facility and any wind turbine is at least one thousand (1,000) feet 12 from the property boundary of any adjoining property owner and all proposed 13 structures or facilities used for generation of electricity are two thousand 14 (2,000) feet from any residential neighborhood, school, hospital, or nursing 15 home facility, unless facilities capable of generating ten megawatts (10MW) 16 or more currently exist on the site. If the facility is proposed to be located on a 17 site of a former coal processing plant and the facility will use on-site waste 18 coal as a fuel source, a statement that the proposed site is compatible with the 19 setback requirements provided under KRS 278.704(5). If the facility is 20 proposed to be located in a jurisdiction that has established setback 21 requirements pursuant to KRS 278.704(3), a statement that the proposed site 22 is in compliance with those established setback requirements; 23 (f) A complete report of the applicant's public involvement program activities 24 undertaken prior to the filing of the application, including: 25 1. The scheduling and conducting of a public meeting in the county or 26 counties in which the proposed facility will be constructed at least 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 8 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed ninety (90) days prior to the filing of an application, for the purpose of 1 informing the public of the project being considered and receiving 2 comment on it; 3 2. Evidence that notice of the time, subject, and location of the meeting 4 was published in the newspaper of general circulation in the county, and 5 that individual notice was mailed to all owners of property adjoining the 6 proposed project at least two (2) weeks prior to the meeting; and 7 3. Any use of media coverage, direct mailing, fliers, newsletters, additional 8 public meetings, establishment of a community advisory group, and any 9 other efforts to obtain local involvement in the siting process; 10 (g) A summary of the efforts made by the applicant to locate the proposed facility 11 on a site where existing electric generating facilities are located; 12 (h) Proof of service of a copy of the application upon the chief executive officer 13 of each county and municipal corporation in which the proposed facility is to 14 be located, and upon the chief officer of each public agency charged with the 15 duty of planning land use in the jurisdiction in which the facility is proposed 16 to be located; 17 (i) An analysis of the proposed facility's projected effect on the electricity 18 transmission system in Kentucky; 19 (j) An analysis of the proposed facility's economic impact on the affected region 20 and the state; 21 (k) A detailed listing of all violations by it, or any person with an ownership 22 interest, of federal or state environmental laws, rules, or administrative 23 regulations, whether judicial or administrative, where violations have resulted 24 in criminal convictions or civil or administrative fines exceeding five 25 thousand dollars ($5,000). The status of any pending action, whether judicial 26 or administrative, shall also be submitted;[ and] 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 9 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed (l) A site assessment report as specified in KRS 278.708. The applicant may 1 submit and the board may accept documentation of compliance with the 2 National Environmental Policy Act (NEPA) rather than a site assessment 3 report; and 4 (m) A decommissioning plan that shall describe how the merchant electric 5 generating facility will be decommissioned and dismantled following the 6 end of its useful life. The decommissioning plan shall, at a minimum, 7 include plans to: 8 1. Unless otherwise requested by the landowner, remove all above-9 ground facilities; 10 2. Unless otherwise requested by the landowner, remove any 11 underground components and foundations of above-ground facilities. 12 Facilities removed under this subparagraph shall be removed to a 13 depth of three (3) feet below the surface grade of the land in or on 14 which the component was installed, unless the landowner and the 15 applicant otherwise agree to a different depth; 16 3. Return the land to a substantially similar state as it was prior to the 17 commencement of construction; 18 4. Unless otherwise requested by the landowner, leave any 19 interconnection or other facilities in place for future use at the 20 completion of the decommissioning process; 21 5. Secure a bond or other similar security for the project to assure 22 financial performance of the decommissioning obligation, provided 23 that: 24 a. The amount of the proposed bond or similar security shall be 25 determined by an independent, licensed engineer who is 26 experienced in the decommissioning of solar electric generating 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 10 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed facilities and has no financial interest in either the merchant 1 electric generating facility or any parcel of land upon which the 2 merchant electric generating facility is located. The proposed 3 amount of the bond or similar security shall be either: 4 i. The net present value of the total estimated cost of 5 completing the decommissioning plan, less the current net 6 salvage value of the merchant electric generating facility's 7 components; or 8 ii. The bond amount required by a county or municipal 9 government that has established a decommissioning bond 10 requirement or similar security obligation in the county or 11 municipality where the merchant electric generating 12 facility will be located. If the facility will be located in more 13 than one (1) county or municipality that has established a 14 decommissioning bond or similar security obligation, then 15 the higher amount shall be required for the facility; 16 b. The bond or other similar security names: 17 i. For property that is leased by the applicant, each 18 landowner from whom the applicant leases land and the 19 Energy and Environment Cabinet as the primary co-20 beneficiaries; or 21 ii. For property that is owned by the applicant, the Energy and 22 Environment Cabinet as the primary beneficiary; 23 c. If the merchant electric generating facility is to be located in a 24 county or municipality that has not established a 25 decommissioning bond or other similar security obligation, the 26 bond or other similar security shall name the county or 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 11 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed municipality as a secondary beneficiary with the county's or 1 municipality's consent; 2 d. The bond or other similar security shall be provided by an 3 insurance company or surety that shall at all times maintain at 4 least an "Excellent" rating as measured by the AM Best rating 5 agency or an investment grade credit rating by any national 6 credit rating agency and, if available, shall be noncancelable by 7 the provider or the customer until completion of the 8 decommissioning plan or until a replacement bond is secured; 9 and 10 e. The bond or other similar security shall provide that at least 11 thirty (30) days prior to its cancellation or lapse, the surety shall 12 notify the applicant, its successor or assign, each landowner, the 13 Energy and Environment Cabinet, and the county or city in 14 which the facility is located of the impending cancellation or 15 lapse. The notice shall specify the reason for the cancellation or 16 lapse and provide any of the parties, either jointly or separately, 17 the opportunity to cure the cancellation or lapse prior to it 18 becoming effective. The applicant, its successor, or its assign, 19 shall be responsible for all costs incurred by all parties to cure 20 the cancellation or lapse of the bond. Each landowner, or the 21 Energy and Environment Cabinet with the prior approval of 22 each landowner, may make a demand on the bond and initiate 23 and complete the decommissioning plan. 24 6. Communicate with each affected landowner at the end of the 25 merchant electric generating facility's useful life so that any requests 26 of the landowner that are in addition to the minimum requirements set 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 12 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed forth in this paragraph and in addition to any other requirements 1 specified in the lease with the landowner may, in the sole discretion of 2 the applicant or its successor or assign, be accommodated; and 3 7. Incorporate the requirements of paragraphs (m)1. to 6. of this 4 subsection into the applicant's leases with landowners. 5 (3) Application fees for a construction certificate shall be set by the board and 6 deposited into a trust and agency account to the credit of the commission. 7 (4) Replacement of a merchant electric generating facility with a like facility, or the 8 repair, modification, retrofitting, enhancement, or reconfiguration of a merchant 9 electric generating facility shall not, for the purposes of this section and KRS 10 224.10-280, 278.704, 278.708, 278.710, and 278.712, constitute construction of a 11 merchant electric generating facility. 12 (5) The board shall promulgate administrative regulations prescribing fees to pay 13 expenses associated with its review of applications filed with it pursuant to KRS 14 278.700 to 278.716. All application fees collected by the board shall be deposited in 15 a trust and agency account to the credit of the Public Service Commission. If a 16 majority of the members of the board find that an applicant's initial fees are 17 insufficient to pay the board's expenses associated with the application, including 18 the board's expenses associated with legal review thereof, the board shall assess a 19 supplemental application fee to cover the additional expenses. An applicant's failure 20 to pay a fee assessed pursuant to this subsection shall be grounds for denial of the 21 application. 22 Section 4. KRS 278.708 is amended to read as follows: 23 (1) Any person proposing to construct a merchant electric generating facility shall file a 24 site assessment report with the board as required under KRS 278.706(2)(l). 25 (2) A site assessment report shall be prepared by the applicant or its designee. 26 (3) A completed site assessment report shall include: 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 13 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed (a) A description of the proposed facility that shall include a proposed site 1 development plan that describes: 2 1. Surrounding land uses for residential, commercial, agricultural, and 3 recreational purposes; 4 2. The legal boundaries of the proposed site; 5 3. Proposed access control to the site; 6 4. The location of facility buildings, transmission lines, and other 7 structures; 8 5. Location and use of access ways, internal roads, and railways; 9 6. Existing or proposed utilities to service the facility; 10 7. Compliance with applicable setback requirements as provided under 11 KRS 278.704(2), (3), (4), or (5); and 12 8. Evaluation of the noise levels expected to be produced by the facility; 13 (b) An evaluation of the compatibility of the facility with scenic surroundings; 14 (c) The potential changes in property values and land use resulting from the 15 siting, construction, and operation of the proposed facility for property owners 16 adjacent to the facility; 17 (d) Evaluation of anticipated peak and average noise levels associated with the 18 facility's construction and operation at the property boundary; and 19 (e) The impact of the facility's operation on road and rail traffic to and within the 20 facility, including anticipated levels of fugitive dust created by the traffic and 21 any anticipated degradation of roads and lands in the vicinity of the facility. 22 (4) The site assessment report shall also suggest any mitigating measures to be 23 implemented by the applicant to minimize or avoid adverse effects identified in the 24 site assessment report. 25 (5) The board shall have the authority to hire a consultant to review the site assessment 26 report and provide recommendations concerning the adequacy of the report and 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 14 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed proposed mitigation measures. The board may direct the consultant to prepare a 1 separate site assessment report. Any expenses or fees incurred by the board's hiring 2 of a consultant shall be borne by the applicant. 3 (6) The applicant shall be given the opportunity to present evidence to the board 4 regarding any mitigation measures. As a condition of approval for an application to 5 obtain a construction certificate, the board may require the implementation of any 6 mitigation measures that the board deems appropriate. Ongoing compliance with 7 any mitigation measures that were conditions of construction certificate 8 application approval shall be enforced by the Energy and Environment Cabinet 9 pursuant to subsection (9) of Section 5 of this Act. 10 Section 5. KRS 278.710 is amended to read as follows: 11 (1) Within one hundred twenty (120) days of receipt of an administratively complete 12 application, or within one hundred eighty (180) days of receipt of an 13 administratively complete application if a hearing is requested, the board shall, by 14 majority vote, grant or deny a construction certificate, either in whole or in part, 15 based upon the following criteria: 16 (a) Impact of the facility on scenic surroundings, property values, the pattern and 17 type of development of adjacent property, and surrounding roads; 18 (b) Anticipated noise levels expected as a result of construction and operation of 19 the proposed facility; 20 (c) The economic impact of the facility upon the affected region and the state; 21 (d) Whether the facility is proposed for a site upon which existing generating 22 facilities, capable of generating ten megawatts (10MW) or more of electricity, 23 are currently located; 24 (e) Whether the proposed facility will meet all local planning and zoning 25 requirements that existed on the date the application was filed; 26 (f) Whether the additional load imposed upon the electricity transmission system 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 15 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed by use of the merchant electric generating facility will adversely affect the 1 reliability of service for retail customers of electric utilities regulated by the 2 Public Service Commission; 3 (g) Except where the facility is subject to a statewide setback established by a 4 planning and zoning commission as provided in KRS 278.704(3) and except 5 for a facility proposed to be located on a site of a former coal processing plant 6 and the facility will use on-site waste coal as a fuel source, whether the 7 exhaust stack of the proposed merchant electric generating facility and any 8 wind turbine is at least one thousand (1,000) feet from the property boundary 9 of any adjoining property owner and all proposed structures or facilities used 10 for generation of electricity are two thousand (2,000) feet from any residential 11 neighborhood, school, hospital, or nursing home facility, unless a different 12 setback has been requested and approved under KRS 278.704(4). If a 13 planning and zoning commission has established setback requirements that 14 differ from those under KRS 278.704(2), the applicant shall provide evidence 15 of compliance. If the facility is proposed to be located on site of a former coal 16 processing plant and the facility will use on-site waste coal as a fuel source, 17 the applicant shall provide evidence of compliance with the setback 18 requirements provided in KRS 278.704(5); 19 (h) The efficacy of any proposed measures to mitigate adverse impacts that are 20 identified pursuant to paragraph (a), (b), (e), or (f) of this subsection from the 21 construction or operation of the proposed facility;[ and] 22 (i) Whether the applicant has a good environmental compliance history; and 23 (j) Whether the decommissioning plan is complete and complies with the 24 requirements of subsection (2)(m) of Section 3 of this Act and any other 25 local requirements that may apply. 26 (2) When considering an application for a construction certificate for a merchant 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 16 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed electric generating facility, the board may consider the policy of the General 1 Assembly to encourage the use of coal as a principal fuel for electricity generation 2 as set forth in KRS 152.210, provided that any facility, regardless of fuel choice, 3 shall comply fully with KRS 224.10-280, 278.212, 278.216, and 278.700 to 4 278.716. 5 (3) A person that has received a construction certificate for a merchant electric 6 generating facility shall: 7 (a) File with the Energy and Environment Cabinet the copy of the bond or 8 other similar security that, pursuant to subsection (2)(m)5. of Section 3 of 9 this Act, is required by a county or a municipal government or as part of a 10 decommissioning plan, no later than the date upon which the construction 11 of the merchant generating facility commences, and refile an updated copy 12 at least once every five (5) years thereafter; 13 (b) Not transfer rights and obligation under the certificate without having first 14 applied for and received a board determination that: 15 1.[(a)] The acquirer has a good environmental compliance history; and 16 2.[(b)] The acquirer has the financial, technical, and managerial capacity 17 to meet the obligations imposed by the terms of the approval or has the 18 ability to contract to meet these obligations; 19 (c) File with the Energy and Environment Cabinet a notice of the date that 20 construction is complete and the merchant electric generating facility 21 begins producing electricity for sale; and 22 (d) Following the date the merchant electric generating facility begins 23 producing electricity for sale, file a notice of any transaction involving the 24 transfer or sale of ownership, control, or the right to control the merchant 25 electric generating facility, with lessors of property where the merchant 26 electric generating facility is located, the Energy and Environment Cabinet, 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 17 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed the county judge/executive of a county and, if applicable, the mayor of a 1 municipality in which the merchant electric generating facility is located, 2 within ten (10) days of completing the transaction. The notice shall include 3 the name, street address, telephone number, and e-mail address of the 4 person acquiring ownership, control, or the right to control the merchant 5 electric generating facility. 6 (4) A person that has acquired ownership, control, or the right to control a merchant 7 electric generating facility from the applicant or its successor or assign shall file 8 with the Energy and Environment Cabinet within ten (10) days of completing the 9 acquisition: 10 (a) A written consent to assume the obligations set forth in the 11 decommissioning plan as of the date the acquisition occurred; and 12 (b) A notice of adoption of an existing bond or other similar security previously 13 filed pursuant to subsection (3)(a) of this section or a replacement bond or 14 other similar security that complies with subsection (2)(m)5. of Section 3 of 15 this Act. An existing bond or other similar security shall be adopted, or a 16 replacement bond or other similar security shall be in place, as of the date 17 the acquisition occurs so that there is no lapse in coverage of the 18 decommissioning bond or other similar security. A person making a filing 19 pursuant to this subsection shall file an updated bond or other similar 20 security that complies with subsection (2)(m)5. of Section 3 of this Act at 21 least once every five (5) years. 22 (5) Any person who transfers or sells ownership, control, or the right to control a 23 merchant electric generating facility shall remain liable for all existing 24 decommissioning obligations and bond requirements until the person who 25 acquires ownership, control, or the right to control the merchant electric 26 generating facility files with the Energy and Environment Cabinet the documents 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 18 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed required by subsection (4) of this section and they are accepted as complete by the 1 secretary. 2 (6) Any application approval condition that requires the approval of the transfer of 3 control of a merchant electric generating facility after construction is complete 4 shall be void and unenforceable, but any transfer of control of a merchant 5 electric generating facility shall be subject to compliance with the requirements of 6 subsections (3)(d), (4), and (5) of this section. 7 (7) Notwithstanding any provision of law to the contrary, including any order issued 8 by the board prior to the effective date of this Act, after the board has approved 9 an application for a construction certificate for a merchant electric generating 10 facility under this section, the approved applicant has posted the bond or similar 11 security required under subsection (2)(m)5. of Section 3 of this Act, and the 12 facility is constructed and begins generating electricity for sale, the board's 13 authority to enforce any conditions of the construction certificate, including 14 bonding and decommissioning requirements, shall end and the secretary of the 15 Energy and Environment Cabinet shall monitor and enforce the construction 16 certificate holder's compliance with the requirements of KRS 278.700 to 278.716 17 and the conditions of its construction certificate application approval. 18 (8) In addition to all compliance monitoring and enforcement performed by the 19 secretary of the Energy and Environment Cabinet, and notwithstanding any 20 provision of law to the contrary, the secretary shall also review the 21 decommissioning plan required by subsection (2)(m) of Section 3 of this Act or by 22 local ordinance, license, or permit and the bond or similar security amount 23 required by subsection (2)(m)5. of Section 3 of this Act or by local ordinance, 24 license, or permit as needed, including any time a transfer determination is made 25 under subsection (5) of this section, but in any event at least once every five (5) 26 years. Upon review, the secretary of the Energy and Environment Cabinet shall 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 19 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed require the decommissioning plan to be updated and the bond amount to be 1 changed to match any significant change in circumstances or change to the 2 estimated cost of effectuating the decommissioning plan or to the salvage value of 3 the facility or its components. 4 (9) After the facility for which an application for a construction certificate has been 5 approved is constructed and begins generating electricity for sale, the secretary of 6 the Energy and Environment Cabinet shall ensure ongoing compliance with the 7 mitigation measures that were conditions of the application approval under 8 subsection (6) of Section 4 of this Act and any enforcement by the board of the 9 mitigation measures shall cease. 10 (10) During the period that the merchant electric generating facility is operational, if 11 solar panels are replaced and discarded, the facility owner-operator shall remove 12 discarded solar panels from the site within ninety (90) days of completion of the 13 work. Upon request of the facility owner-operator, the secretary of the Energy 14 and Environment Cabinet may extend the time period under this subsection for 15 removing discarded solar panels. 16 Section 6. KRS 278.718 is amended to read as follows: 17 The provisions of KRS 278.700, 278.704, 278.706, 278.708, and 278.710 shall[ be in 18 addition to, and shall] not supplant, any other state or federal law, including the powers 19 available to local governments under the provisions of home rule under KRS 67.080, 20 67.083, 67.850, 67.922, 67A.060, 67C.101, and 82.082. An ordinance, permit, or license 21 issued by a local government shall have primacy over the provisions and requirements 22 of KRS 278.700 and Sections 2, 3, and 4 of this Act, and any conflict between an order 23 of the board and a local ordinance, permit, or license shall be resolved in favor of the 24 local government's ordinance, permit, or license. 25 Section 7. KRS 224.10-100 is amended to read as follows: 26 In addition to any other powers and duties vested in it by law, the cabinet shall have the 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 20 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed authority, power, and duty to: 1 (1) Exercise general supervision of the administration and enforcement of this chapter, 2 and all rules, regulations, and orders promulgated thereunder; 3 (2) Prepare and develop a comprehensive plan or plans related to the environment of 4 the Commonwealth; 5 (3) Encourage industrial, commercial, residential, and community development which 6 provides the best usage of land areas, maximizes environmental benefits, and 7 minimizes the effects of less desirable environmental conditions; 8 (4) Develop and conduct a comprehensive program for the management of water, land, 9 and air resources to assure their protection and balance utilization consistent with 10 the environmental policy of the Commonwealth; 11 (5) Provide for the prevention, abatement, and control of all water, land, and air 12 pollution, including but not limited to that related to particulates, pesticides, gases, 13 dust, vapors, noise, radiation, odor, nutrients, heated liquid, or other contaminants; 14 (6) Provide for the control and regulation of surface coal mining and reclamation in a 15 manner to accomplish the purposes of KRS Chapter 350; 16 (7) Secure necessary scientific, technical, administrative, and operational services, 17 including laboratory facilities, by contract or otherwise; 18 (8) Collect and disseminate information and conduct educational and training programs 19 relating to the protection of the environment; 20 (9) Appear and participate in proceedings before any federal regulatory agency 21 involving or affecting the purposes of the cabinet; 22 (10) Enter and inspect any property or premises for the purpose of investigating either 23 actual or suspected sources of pollution or contamination or for the purpose of 24 ascertaining compliance or noncompliance with this chapter, or any regulation 25 which may be promulgated thereunder; 26 (11) Conduct investigations and hold hearings and compel the attendance of witnesses 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 21 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed and the production of accounts, books, and records by the issuance of subpoenas; 1 (12) Accept, receive, and administer grants or other funds or gifts from public and 2 private agencies including the federal government for the purpose of carrying out 3 any of the functions of the cabinet. The funds received by the cabinet shall be 4 deposited in the State Treasury to the account of the cabinet; 5 (13) Request and receive the assistance of any state or municipal educational institution, 6 experiment station, laboratory, or other agency when it is deemed necessary or 7 beneficial by the cabinet in the performance of its duties; 8 (14) Advise, consult, and cooperate with other agencies of the Commonwealth, other 9 states, the federal government, and interstate and interlocal agencies, and affected 10 persons, groups, and industries; 11 (15) Formulate guides for measuring presently unidentified environmental values and 12 relationships so they can be given appropriate consideration along with social, 13 economic, and technical considerations in decision making; 14 (16) Monitor the environment to afford more effective and efficient control practices, to 15 identify changes and conditions in ecological systems, and to warn of emergency 16 conditions; 17 (17) Adopt, modify, or repeal with the recommendation of the commission any standard, 18 regulation, or plan; 19 (18) Issue, after hearing, orders abating activities in violation of this chapter, or the 20 provisions of this chapter, or the regulations promulgated pursuant thereto and 21 requiring the adoption of the remedial measures the cabinet deems necessary; 22 (19) Issue, continue in effect, revoke, modify, suspend, or deny under such conditions as 23 the cabinet may prescribe and require that applications be accompanied by plans, 24 specifications, and other information the cabinet deems necessary for the following 25 permits: 26 (a) Permits to discharge into any waters of the Commonwealth, and for the 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 22 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed installation, alteration, expansion, or operation of any sewage system; 1 however, the cabinet may refuse to issue the permits to any person, or any 2 partnership, corporation, etc., of which the person owns more than ten percent 3 (10%) interest, who has improperly constructed, operated, or maintained a 4 sewage system willfully, through negligence, or because of lack of proper 5 knowledge or qualifications until the time that person demonstrates proper 6 qualifications to the cabinet and provides the cabinet with a performance 7 bond; 8 (b) Permits for the installation, alteration, or use of any machine, equipment, 9 device, or other article that may cause or contribute to air pollution or is 10 intended primarily to prevent or control the emission of air pollution; or 11 (c) Permits for the establishment or construction and the operation or 12 maintenance of waste disposal sites and facilities; 13 (20) May establish, by regulation, a fee or schedule of fees for the cost of processing 14 applications for permits authorized by this chapter, and for the cost of processing 15 applications for exemptions or partial exemptions which may include but not be 16 limited to the administrative costs of a hearing held as a result of the exemption 17 application, except that applicants for existing or proposed publicly owned facilities 18 shall be exempt from any charge, other than emissions fees assessed pursuant to 19 KRS 224.20-050, and that certain nonprofit organizations shall be charged lower 20 fees to process water discharge permits under KRS 224.16-050(5); 21 (21) May require for persons discharging into the waters or onto the land of the 22 Commonwealth, by regulation, order, or permit, technological levels of treatment 23 and effluent limitations; 24 (22) Require, by regulation, that any person engaged in any operation regulated pursuant 25 to this chapter install, maintain, and use at such locations and intervals as the 26 cabinet may prescribe any equipment, device, or test and the methodologies and 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 23 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed procedures for the use of the equipment, device, or test to monitor the nature and 1 amount of any substance emitted or discharged into the ambient air or waters or 2 land of the Commonwealth and to provide any information concerning the 3 monitoring to the cabinet in accordance with the provisions of subsection (23) of 4 this section; 5 (23) Require by regulation that any person engaged in any operation regulated pursuant 6 to this chapter file with the cabinet reports containing information as to location, 7 size, height, rate of emission or discharge, and composition of any substance 8 discharged or emitted into the ambient air or into the waters or onto the land of the 9 Commonwealth, and such other information the cabinet may require; 10 (24) Promulgate regulations, guidelines, and standards for waste planning and 11 management activities, approve waste management facilities, develop and publish a 12 comprehensive statewide plan for nonhazardous waste management which shall 13 contain but not be limited to the provisions set forth in KRS 224.43-345, and 14 develop and publish a comprehensive statewide plan for hazardous waste 15 management which shall contain but not be limited to the following: 16 (a) A description of current hazardous waste management practices and costs, 17 including treatment and disposal, within the Commonwealth; 18 (b) An inventory and description of all existing facilities where hazardous waste 19 is being generated, treated, recycled, stored, or disposed of, including an 20 inventory of the deficiencies of present facilities in meeting current hazardous 21 waste management needs and a statement of the ability of present hazardous 22 waste management facilities to comply with state and federal laws relating to 23 hazardous waste; 24 (c) A description of the sources of hazardous waste affecting the Commonwealth 25 including the types and quantities of hazardous waste currently being 26 generated and a projection of such activities as can be expected to continue 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 24 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed for not less than twenty (20) years into the future; and 1 (d) An identification and continuing evaluation of those locations within the 2 Commonwealth which are naturally or may be engineered to be suitable for 3 the establishment of hazardous waste management facilities, and an 4 identification of those general characteristics, values, and attributes which 5 would render a particular location unsuitable, consistent with the policy of 6 minimizing land disposal and encouraging the treatment and recycling of the 7 wastes. 8 The statewide waste management plans shall be developed consistent with state and 9 federal laws relating to waste; 10 (25) Perform other acts necessary to carry out the duties and responsibilities described in 11 this section; 12 (26) Preserve existing clean air resources while ensuring economic growth by issuing 13 regulations, which shall be no more stringent than federal requirements, setting 14 maximum allowable increases from stationary sources over baseline concentrations 15 of air contaminants to prevent significant deterioration in areas meeting the state 16 and national ambient air quality standards; 17 (27) Promulgate regulations concerning the bonding provisions of subsection (19)(a) of 18 this section, setting forth bonding requirements, including but not limited to 19 requirements for the amount, duration, release, and forfeiture of the bonds. All 20 funds from the forfeiture of bonds required pursuant to this section shall be placed 21 in the State Treasury and credited to a special trust and agency account which shall 22 not lapse. The account shall be known as the "sewage treatment system 23 rehabilitation fund" and all moneys placed in the fund shall be used for the 24 elimination of nuisances and hazards created by sewage systems which were 25 improperly built, operated, or maintained, and insofar as practicable be used to 26 correct the problems at the same site for which the bond or other sureties were 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 25 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed originally provided; 1 (28) Promulgate administrative regulations not inconsistent with the provisions of law 2 administered by the cabinet;[ and] 3 (29) Through the secretary or designee of the secretary, enter into, execute, and enforce 4 reciprocal agreements with responsible officers of other states relating to 5 compliance with the requirements of KRS Chapters 350, 351, and 352 and the 6 administrative regulations promulgated under those chapters; 7 (30) Monitor and enforce the compliance of a merchant electric generating entity to 8 which a construction certificate has been issued pursuant to Section 5 of this Act 9 with respect to its obligations under subsections (3), (4), (5), (7), (8), (9) and (10) 10 of Section 5 of this Act; and 11 (31) Draw upon a decommissioning bond or similar security for which it is named as 12 a beneficiary and decommission and dismantle a merchant electric generating 13 facility in accordance with its approved decommissioning plan. 14 Section 8. KRS 224.99-010 is amended to read as follows: 15 (1) Any person who violates KRS 224.10-110(2) or (3), 224.70-110, 224.73-120, 16 224.20-050, 224.20-110, 224.46-580, 224.1-400, or who fails to perform any duties 17 imposed by these sections, or who violates any determination, permit, 18 administrative regulation, or order of the cabinet promulgated pursuant thereto shall 19 be liable for a civil penalty not to exceed the sum of twenty-five thousand dollars 20 ($25,000) for each day during which such violation continues, and in addition, may 21 be concurrently enjoined from any violations as hereinafter provided in this section 22 and KRS 224.99-020. 23 (2) Any person who violates KRS 224.10-110(4) or (5), or KRS 224.40-100, 224.40-24 305, or any provision of this chapter relating to noise, or who fails to perform any 25 determination, permit, administrative regulation, or order of the cabinet 26 promulgated pursuant thereto shall be liable for a civil penalty not to exceed the 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 26 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed sum of five thousand dollars ($5,000) for said violation and an additional civil 1 penalty not to exceed five thousand dollars ($5,000) for each day during which such 2 violation continues, and in addition, may be concurrently enjoined from any 3 violations as hereinafter provided in this section and KRS 224.99-020. 4 (3) (a) Any person who shall knowingly violate any of the provisions of this chapter 5 relating to noise or any determination or order of the cabinet promulgated 6 pursuant to those sections which have become final shall be guilty of a Class 7 A misdemeanor. Each day upon which the violation occurs shall constitute a 8 separate violation. 9 (b) For offenses by motor vehicles, a person shall be guilty of a violation. 10 (4) Any person who knowingly violates KRS 224.70-110, 224.73-120, 224.40-100, 11 224.20-110, 224.20-050, 224.40-305, or 224.10-110(2) or (3), or any determination, 12 permit, administrative regulation, or order of the cabinet promulgated pursuant to 13 those sections which have become final, or who knowingly provides false 14 information in any document filed or required to be maintained under this chapter, 15 or who knowingly renders inaccurate any monitoring device or method, or who 16 tampers with a water supply, water purification plant, or water distribution system 17 so as to knowingly endanger human life, shall be guilty of a Class D felony, and 18 upon conviction thereof, shall be punished by a fine not to exceed twenty-five 19 thousand dollars ($25,000), or by imprisonment for a term of not less than one (1) 20 year and not more than five (5) years, or by both fine and imprisonment, for each 21 separate violation. Each day upon which a violation occurs shall constitute a 22 separate violation. 23 (5) If any person engages in generation, treatment, storage, transportation, or disposal 24 of hazardous waste in violation of the hazardous waste management provisions of 25 this chapter or contrary to a permit, order, or rule issued or promulgated under this 26 chapter, or fails to provide information or to meet reporting requirements required 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 27 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed by terms and conditions of a permit or administrative regulations promulgated 1 pursuant to this chapter, the secretary may issue an order requiring compliance 2 within a specified time period or may commence a civil action in a court of 3 appropriate jurisdiction. The violator shall be liable for a civil penalty not to exceed 4 the sum of twenty-five thousand dollars ($25,000) for each day during which the 5 violation continues, and in addition, may be enjoined from any violations in a court 6 of appropriate jurisdiction. 7 (6) Any person who knowingly is engaged in generation, treatment, storage, 8 transportation, or disposal of hazardous waste in violation of this chapter or 9 contrary to a permit, order, or administrative regulation issued or promulgated 10 under this chapter, or knowingly makes a false statement, representation, or 11 certification in an application for or form pertaining to a permit or in a notice or 12 report required by the terms and conditions of an issued permit, shall be guilty of a 13 Class D felony, and upon conviction thereof, shall be punished by a fine not to 14 exceed twenty-five thousand dollars ($25,000) for each day of violation, or by 15 imprisonment for a term of not less than one (1) year and not more than five (5) 16 years, or by both fine and imprisonment, for each separate violation. Each day upon 17 which a violation occurs shall constitute a separate violation. 18 (7) Nothing contained in subsections (4) or (5) of this section shall abridge the right of 19 any person to recover actual compensatory damages resulting from any violation. 20 (8) Any person who violates any provision of this chapter to which no express penalty 21 provision applies, except as provided in KRS 211.995, or who fails to perform any 22 duties imposed by those sections, or who violates any determination or order of the 23 cabinet promulgated pursuant thereto shall be liable for a civil penalty not to exceed 24 the sum of one thousand dollars ($1,000) for said violation and an additional civil 25 penalty not to exceed one thousand dollars ($1,000) for each day during which the 26 violation continues, and in addition, may be concurrently enjoined from any 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 28 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed violations as hereinafter provided in this section and KRS 224.99-020. 1 (9) The Franklin Circuit Court shall hold concurrent jurisdiction and venue of all civil, 2 criminal, and injunctive actions instituted by the cabinet or by the Attorney General 3 on its behalf for the enforcement of the provisions of this chapter or the orders and 4 administrative regulations of the cabinet promulgated pursuant thereto, except for 5 any actions arising from or related to subsections (3), (4), or (5) of Section 5 of 6 this Act or subsection (16) of this section, which shall be brought in the Circuit 7 Court in any county in which the merchant electric generating facility is located. 8 (10) Any person who deposits leaves, clippings, prunings, garden refuse, or household 9 waste materials in any litter receptacle, except with permission of the owner of the 10 receptacle, or who places litter into a receptacle in such a manner that the litter may 11 be carried away or deposited by the elements upon any property or water not owned 12 by him or her is guilty of a Class B misdemeanor. Penalties imposed under this 13 subsection shall be, when collected, transferred to the county treasurer where the 14 offense occurred and placed into a fund for solid waste cleanup. This subsection 15 shall not be construed to divert any other fines assessed and collected by the cabinet 16 or funds available to the cabinet for the purpose of remediation of open dumps. 17 (11) In addition to or in lieu of the penalties set forth in this section or in KRS Chapters 18 532 and 534, any person found guilty of a second or subsequent offense related to 19 littering may be ordered by the court to pick up litter for not less than four (4) 20 hours. 21 (12) Any person who violates KRS 224.20-300, 224.20-310, any other provision of this 22 chapter, or any determination, permit, administrative regulation, or order of the 23 cabinet relating to the Asbestos Hazard Emergency Response Act of 1986 24 (AHERA), Public Law 99-519, as amended, shall be liable to the Commonwealth 25 of Kentucky for a civil penalty in an amount not to exceed twenty-five thousand 26 dollars ($25,000) for each violation. Each day a violation continues shall, for 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 29 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed purposes of this subsection, constitute a separate violation of provisions of this 1 chapter relating to AHERA. 2 (13) A violation of KRS 224.50-413 shall be subject to a fifty dollar ($50) fine for each 3 day the violation continues. 4 (14) Any person who removes a methamphetamine contamination notice posted under 5 KRS 224.1-410(9) contrary to the administrative regulations governing 6 methamphetamine contamination notice removal shall be guilty of a Class A 7 misdemeanor. 8 (15) Any person who leases, rents, or sells a property that has been determined to be 9 contaminated property under KRS 224.1-410(4) to a lessee, renter, or buyer without 10 giving written notice that the property is a contaminated property pursuant to KRS 11 224.1-410(10) shall be guilty of a Class D felony. 12 (16) Any person who violates subsection (3), (4), or (5) of Section 5 of this Act may be 13 subject to civil penalties not to exceed two thousand five hundred dollars ($2,500) 14 per day. In determining the civil penalty to be imposed under this subsection, the 15 cabinet shall consider all relevant circumstances including but not limited to the 16 extent of harm or potential harm caused by the violation, the nature and duration 17 of the violation, the number of past violations, and any corrective action taken by 18 the merchant electric generating facility owner. If a merchant electric generating 19 facility fails to pay any civil penalty for noncompliance under this subsection for 20 a period of three hundred sixty-five (365) days after a final determination of the 21 assessment of the civil penalty, or fails to post a bond or replacement bond in 22 compliance with subsections (3), (4), or (5) of Section 5 of this Act within ninety 23 (90) days of a final determination that the bond or replacement bond is required, 24 the cabinet may order suspension of its operations until it is brought back into 25 compliance and all civil penalties have been paid or the bond or replacement 26 bond is posted. If after a final determination that the cabinet's order suspending 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 30 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed operations of the facility is valid, and the merchant electric generating facility 1 fails to bring the facility back into compliance by paying all outstanding civil 2 penalties or posting the bond or replacement bond within ninety (90) days of that 3 final determination, the cabinet may order the decommissioning of the facility to 4 commence. 5 SECTION 9. A NEW SECTION OF SUBCHAPTER 10 OF KRS CHAPTER 6 224 IS CREATED TO READ AS FOLLOWS: 7 (1) If the owner of a merchant electric generating facility fails to complete the 8 decommissioning plan within eighteen (18) months of the date that the facility 9 ceases to produce electricity for sale and the secretary has not extended the 10 deadline, the cabinet shall draw upon the decommissioning bond and implement 11 the decommissioning plan. 12 (2) Within ninety (90) days of the effective date of this Act, the cabinet shall 13 promulgate administrative regulations pursuant to KRS Chapter 13A to establish 14 the monitoring and enforcement requirements for the obligations set forth in 15 subsections (3), (4), (5), (7), (8), (9) and (10) of Section 5 of this Act and 16 subsections (30) and (31) of Section 7 of this Act. The cabinet shall establish a fee 17 structure covering the entire useful life of a merchant electric generating facility 18 to be charged to each facility for which the cabinet has monitoring and 19 enforcement responsibilities. The fees collected shall be deposited in the restricted 20 fund established in subsection (3) of this section. 21 (3) (a) There is hereby established in the State Treasury a restricted fund to be 22 known as the merchant electric generating facility monitoring and 23 enforcement fund, which shall be administered by the cabinet and shall 24 consist of the fees collected under subsection (2) of this section and any 25 moneys collected pursuant to enforcement actions taken by the cabinet in 26 the course of performing its monitoring and enforcement responsibilities for 27 UNOFFICIAL COPY 23 RS HB 4/EN Page 31 of 31 HB000420.100 - 900 - XXXX 3/15/2023 8:24 PM Engrossed merchant electric generating facilities. 1 (b) Amounts deposited in the fund shall only be used to defray the costs of the 2 cabinet's monitoring and enforcement responsibilities for merchant electric 3 generating facilities and for no other purpose. 4 (c) Notwithstanding KRS 45.229, fund amounts not expended at the close of the 5 fiscal year shall not lapse, but shall be carried forward into the next fiscal 6 year. 7 (d) Any interest earnings of the fund shall become part of the fund and shall 8 not lapse. 9 (e) Moneys deposited in the fund are hereby appropriated for the purposes set 10 forth in this subsection and shall not be appropriated or transferred by the 11 General Assembly for any other purposes. 12 (4) In carrying out its decommissioning plan and bond adequacy review under 13 subsection (8) of Section 5 of this Act, the cabinet shall have the authority to hire 14 a consulting independent licensed engineer to review the secured 15 decommissioning bond or similar security instrument and decommissioning plan 16 and provide recommendations concerning the adequacy of the security 17 instrument to cover actual costs. The cabinet may direct the independent licensed 18 engineer to prepare an assessment report. Any expenses or fees incurred by the 19 cabinet’s hiring of the independent licensed engineer shall be paid by the owner-20 operator of the merchant electric generating facility. 21