Louisiana 2020 Regular Session

Louisiana Senate Bill SB265 Latest Draft

Bill / Introduced Version

                            SLS 20RS-57	ORIGINAL
2020 Regular Session
SENATE BILL NO. 265
BY SENATOR PETERSON 
PUBLIC CONTRACTS.  Provides relative to payments under public contracts. (8/1/20)
1	AN ACT
2 To amend and reenact R.S. 38:2191(C), relative to public contracts; to provide that the
3 payment of attorney fees and interest on amounts due for failure to pay progressive
4 stage or final payments under certain circumstances, may be waived by contract; and
5 to provide for related matters.
6 Be it enacted by the Legislature of Louisiana:
7 Section 1.  R.S. 38:2191(C) is hereby amended and reenacted to read as follows:
8 ยง2191. Payments under contract
9	*          *          *
10	C. The provisions of this Section shall not be subject to waiver by contract.
11	*          *          *
The original instrument and the following digest, which constitutes no part
of the legislative instrument, were prepared by Martha S. Hess.
DIGEST
SB 265 Original 2020 Regular Session	Peterson
Present law provides that public entities shall promptly pay all obligations arising under a
public contract when the obligations are due and payable under the contract. Requires that
if the public entity fails to make any progressive stage payment, without reasonable cause,
within 45 days after receipt of a certified request for payment, the entity is liable for
Page 1 of 2
Coding: Words which are struck through are deletions from existing law;
words in boldface type and underscored are additions. SB NO. 265
SLS 20RS-57	ORIGINAL
reasonable attorney fees and interest charged at 0.5% accumulated daily, not to exceed 15%.
Present law requires that if the public entity fails to make final payment after formal final
acceptance and within 45 days after receipt of a clear lien certificate, the entity is liable for
reasonable attorney fees and interest charged at 0.5% accumulated daily, not to exceed 15%.
Present law provides that any interest paid by public entities on public contracts shall be
disbursed on a prorated basis among the contractors and subcontractors within ten business
days of receipt of the interest payment.
Present law provides that the provisions of present law may not be waived by contract.
Proposed law changes present law to allow the provisions of present law to be waived by
contract.
Effective August 1, 2020.
(Amends R.S. 38:2191(C))
Page 2 of 2
Coding: Words which are struck through are deletions from existing law;
words in boldface type and underscored are additions.