Louisiana 2022 2022 Regular Session

Louisiana House Bill HB703 Engrossed / Bill

                    HLS 22RS-1008	ENGROSSED
2022 Regular Session
HOUSE BILL NO. 703
BY REPRESENTATIVE GREGORY MILLER
CONTRACTS:  Provides relative to repair contracts following a natural disaster
1	AN ACT
2To enact R.S. 9:2784.1, relative to repair contracts following a natural disaster; to provide
3 for venue for disputes arising from the contract; to provide for nullification of certain
4 terms; to provide for rescission of the contract; to provide for notice; to provide for
5 exceptions; and to provide for related matters.
6Be it enacted by the Legislature of Louisiana:
7 Section 1.  R.S. 9:2784.1 is hereby enacted to read as follows: 
8 ยง2784.1.  Repair contracts entered into during a state of emergency; venue;
9	rescission
10	A.(1)  The exclusive venue for any proceeding involving a dispute over a
11 contract for repairs to residential property that was entered into while the property
12 was under a federally declared state of emergency following a natural disaster shall
13 be the parish where the residence is located.  If the property is situated in more than
14 one parish, the action may be brought in any parish where the property is situated.
15	(2)  Notwithstanding any provision of the law to the contrary, any provision,
16 clause, covenant, or agreement contained in, collateral to, or affecting a contract or
17 subcontract for repairs on residential property entered into while the property was
18 under a federally declared state of emergency following a natural disaster which
19 purports to require any proceeding involving a dispute over repairs to be brought in
Page 1 of 4
CODING:  Words in struck through type are deletions from existing law; words underscored
are additions. HLS 22RS-1008	ENGROSSED
HB NO. 703
1 a venue other than a parish provided in Paragraph (1) of this Subsection is contrary
2 to the public policy of this state and is null, void, and unenforceable.
3	B.(1) The owner of residential property who enters into a contract or
4 subcontract for repairs on residential property entered into while the property is
5 under a federally declared state of emergency following a natural disaster may cancel
6 the contract or subcontract within ten days of entering into the contract or
7 subcontract.
8	(2)  If a homeowner elects to cancel a contract or subcontract pursuant to this
9 Subsection, he may do so by hand-delivering notice thereof to the contractor or by
10 mailing notice by United States mail to the contractor at his last known address, or
11 to his agent for service of process.
12	(3)  Cancellation made pursuant to this Subsection shall be without penalty
13 and all payments made by the homeowner before cancellation shall be refunded
14 promptly.  This contractor shall be entitled to payment for the cost of work
15 performed and materials ordered or delivered prior to cancellation, along with
16 reasonable overhead.
17	C.(1)  This Section shall not apply to material suppliers or materialmen for
18 sales to the owner of the affected residential property or deliveries to the affected
19 residential property of materials ordered by a contractor or subcontractor even if the
20 repair contract is cancelled pursuant to Subsection B of this Section.
21	(2)  This Section shall not affect proper venue for an action on an open
22 account, promissory  note, or contract for sales of materials by a material supplier
23 or materialman to the owner of the residential property as provided in Code of Civil
24 Procedure Articles 74.4 and 76.1.
25	D.  Nothing in this Section shall affect the rights of any party provided in
26 R.S. 9:4801 et seq. or R.S. 9:2781.
Page 2 of 4
CODING:  Words in struck through type are deletions from existing law; words underscored
are additions. HLS 22RS-1008	ENGROSSED
HB NO. 703
DIGEST
The digest printed below was prepared by House Legislative Services.  It constitutes no part
of the legislative instrument.  The keyword, one-liner, abstract, and digest do not constitute
part of the law or proof or indicia of legislative intent.  [R.S. 1:13(B) and 24:177(E)]
HB 703 Engrossed 2022 Regular Session Gregory Miller
Abstract:  Provides for the exclusive venue for disputes regarding contracts for repairs to
residential property entered into while the property was under a federally declared
state of emergency following a natural disaster, nullifies any contrary venue
provisions, and permits rescission of such contracts within 10 days of entering the
contract.
Proposed law provides the exclusive venue for any proceeding involving a dispute over a
contract for repairs to residential property that was entered into while the property was under
a federally declared state of emergency following a natural disaster shall be the parish where
the residence is located.  If the property is situated in more than one parish, the action may
be brought in any parish where the property is situated.
Proposed law further provides that any provision, clause, covenant, or agreement contained
in, collateral to, or affecting a contract or subcontract for repairs on residential property
entered into while the property was under a federally declared state of emergency following
a natural disaster which purports to require any proceeding involving a dispute over repairs
to be brought in a venue other than the parish provided in proposed law is contrary to the
public policy of this state and is null, void, and unenforceable.
Proposed law provides that the owner of residential property who enters into a contract or
subcontract for repairs on residential property entered into while the property is under a
federally declared state of emergency following a natural disaster may cancel the contract
or subcontract within 10 days of entering into the contract or subcontract.
Proposed law further provides that if a homeowner elects to cancel a contract or subcontract,
he may do so by hand-delivering notice thereof to the contractor or by mailing notice by U.S.
mail to the contractor at his last known address, or to his agent for service of process.
Proposed law provides that cancellation made pursuant to proposed law shall be without
penalty and all payments made by the homeowner before cancellation shall be refunded
promptly.  Further provides that the contractor shall be entitled to payment for the cost of
work performed and materials ordered or delivered prior to cancellation, along with
reasonable overhead.
Proposed law shall not apply to material suppliers or materialmen for sales to the owner of
the affected residential property or deliveries to the affected residential property of materials
ordered by a contractor or subcontractor even if the repair contract is cancelled.
Proposed law shall not affect proper venue for an action on an open account, promissory 
note, or contract for sales of materials by a material supplier or materialman to the owner of
the residential property.
Page 3 of 4
CODING:  Words in struck through type are deletions from existing law; words underscored
are additions. HLS 22RS-1008	ENGROSSED
HB NO. 703
Proposed law shall not affect the rights of any party provided in present law Private Works
Act and provisions regarding claims on open accounts.
(Adds R.S. 9:2784.1)
Summary of Amendments Adopted by House
The Committee Amendments Proposed by House Committee on Civil Law and
Procedure to the original bill:
1. Provide for bringing a dispute in a venue, rather than a forum or jurisdiction.
2. Provide for consistent use of the phrase "federally declared state of emergency
following a natural disaster".
3. Allow for payment of the cost of work performed and material ordered or
delivered prior to cancellation, along with reasonable overhead.
4. Create exceptions applicable to materialmen.
5. Create an exception for the rights of any party provided by the Private Works Act
and the provision for claims on open accounts.
Page 4 of 4
CODING:  Words in struck through type are deletions from existing law; words underscored
are additions.