1414 A BILL ENTITLED
1515
1616 AN ACT concerning 1
1717
1818 Dams With Hydroelectric Power Plants – Annual Compensation Fee 2
1919
2020 FOR the purpose of requiring the owner of a dam associated with a certain hydroelectric 3
2121 power plant to pay an annual compensation fee to the Department of the 4
2222 Environment for the use of State land and waterways beginning on a certain date; 5
2323 requiring the Public Service Commission to determine the average price of a Tier 2 6
2424 renewable energy credit for certain renewable energy portfolio standard compliance 7
2525 years; prohibiting the owner of the dam from applying to or petitioning the 8
2626 Commission to increase the hydroelectric power plant’s rates as a means of offsetting 9
2727 the cost of the compensation fee; requiring the Department to transfer revenue 10
2828 generated from the compensation fee to the Chesapeake Bay Trust for certain 11
2929 purposes; and generally relating to an annual compensation fee for dams associated 12
3030 with hydroelectric power plants. 13
3131
3232 BY adding to 14
3333 Article – Public Utilities 15
3434 Section 7–217 16
3535 Annotated Code of Maryland 17
3636 (2020 Replacement Volume and 2021 Supplement) 18
3737
3838 SECTION 1. BE IT ENACTED BY THE GENERAL ASSEMBLY OF MARYLAND, 19
3939 That the Laws of Maryland read as follows: 20
4040
4141 Article – Public Utilities 21
4242
4343 7–217. 22
4444
4545 (A) (1) IN THIS SECTION THE F OLLOWING WORDS HAVE THE MEANINGS 23
4646 INDICATED. 24
4747 2 SENATE BILL 902
4848
4949
5050 (2) “RENEWABLE ENERGY CRED IT” HAS THE MEANING STAT ED IN § 1
5151 7–701 OF THIS TITLE. 2
5252
5353 (3) “RENEWABLE ENERGY PORTFOLIO STANDARD ” HAS THE 3
5454 MEANING STATED IN § 7–701 OF THIS TITLE. 4
5555
5656 (4) “TIER 2” MEANS A TIER 2 RENEWABLE SOURCE AS DEFINED IN § 5
5757 7–701 OF THIS TITLE. 6
5858
5959 (B) BEGINNING JANUARY 1, 2023, THE OWNER OF A DAM ASSOC IATED WITH 7
6060 A HYDROELECTRIC POWE R PLANT THAT HAS A GENERATIN G CAPACITY OF AT LEA ST 8
6161 30 MEGAWATTS AND IS CONNECTED WIT H THE ELECTRIC DISTRIBUTION GRID 9
6262 SERVING MARYLAND SHALL PAY AN ANNUAL COMPENSATION FEE TO THE 10
6363 DEPARTMENT OF THE ENVIRONMENT FOR THE USE OF STATE LAND AND 11
6464 WATERWAYS . 12
6565
6666 (C) (1) EXCEPT AS PROVIDED IN PARAGRAPH (3) OF THIS SUBSECTION , 13
6767 THE COMPENSATION FEE SHA LL BE: 14
6868
6969 (I) CALCULATED ON AN ANNU AL BASIS; AND 15
7070
7171 (II) COMPUTED BY MULTIPLYI NG: 16
7272
7373 1. THE MEGAWATT –HOURS OF ELECTRICITY 17
7474 GENERATED BY THE HYD ROELECTRIC POWER PLA NT DURING THE PREVIOUS YEAR ; 18
7575
7676 2. THE AVERAGE PRICE OF A TIER 2 RENEWABLE 19
7777 ENERGY CREDIT FOR THE PREVIOUS RENEWABLE ENERGY POR TFOLIO STANDARD 20
7878 COMPLIANCE YEAR, AS DETERMINED BY THE COMMISSION; AND 21
7979
8080 3. 80%. 22
8181
8282 (2) ON OR BEFORE JANUARY 31, 2023, AND ON OR BEFORE EACH 23
8383 JANUARY 31 THEREAFTER , THE COMMISSION SHALL DETE RMINE THE AVERAGE 24
8484 PRICE OF A TIER 2 RENEWABLE ENERGY CRE DIT FOR THE PREVIOUS RENEWABLE 25
8585 ENERGY PORTFOLIO STANDARD COMPLIANCE YEAR. 26
8686
8787 (3) (I) THE COMPENSATION FEE PAID IN 2023 SHALL INCLUDE A 27
8888 FEE FOR THE USE OF STATE LAND AND WATERW AYS DURING THE 2020 AND 2021 28
8989 CALENDAR YEARS . 29
9090
9191 (II) THE COMPENSATION FEE UNDER SUBPARAGRAPH (I) OF 30
9292 THIS PARAGRAPH SHALL BE COMPUTED BY MULTIPLY ING: 31 SENATE BILL 902 3
9393
9494
9595
9696 1. THE MEGAWATT –HOURS OF ELECTRICITY 1
9797 GENERATED BY THE HYD ROELECTRIC POWER PLA NT DURING 2020 AND 2021, 2
9898 RESPECTIVELY ; 3
9999
100100 2. THE AVERAGE PRICE OF A TIER 2 RENEWABLE 4
101101 ENERGY CREDIT FOR TH E 2020 AND 2021 RENEWABLE ENERGY POR TFOLIO 5
102102 STANDARD COMPLIANCE YEARS, RESPECTIVELY , AS DETERMINED BY THE 6
103103 COMMISSION; AND 7
104104
105105 3. 80%. 8
106106
107107 (III) ON OR BEFORE JANUARY 31, 2023, THE COMMISSION 9
108108 SHALL DETERMINE THE AVERAGE PRICE OF A TIER 2 RENEWABLE ENERGY CRE DIT 10
109109 FOR THE 2020 AND 2021 RENEWABLE ENERGY POR TFOLIO STANDARD COMPLIANCE 11
110110 YEARS. 12
111111
112112 (D) THE OWNER OF A DAM AS SOCIATED WITH A HYDR OELECTRIC POWER 13
113113 PLANT MAY NOT APPLY TO OR PETITION THE COMMISSION TO INCREAS E THE 14
114114 HYDROELECTRIC POWER PLANT’S ELECTRICITY RATES AS A MEANS OF OFFSET TING 15
115115 THE COST OF THE COMP ENSATION FEE IMPOSED UNDER THIS SECTION . 16
116116
117117 (E) THE DEPARTMENT OF THE ENVIRONMENT SHALL TRANSFER REVEN UE 17
118118 GENERATED FROM THE C OMPENSATION FEE UNDE R THIS SECTION TO TH E 18
119119 CHESAPEAKE BAY TRUST TO BE USED AS FOLLOWS: 19
120120
121121 (1) 25% OF THE REVENUE FOR THE ADMINISTRATI ON OF GRANTS FOR 20
122122 AQUATIC SPECIES REST ORATION; AND 21
123123
124124 (2) 75% OF THE REVENUE AS GRANTS TO COUNTY OYSTER 22
125125 COMMITTEES FOR PURCH ASING OR OBTAINING N ATIVE CHESAPEAKE BAY OYSTER 23
126126 SHELLS. 24
127127
128128 (F) THE COMMISSION AND THE DEPARTMENT OF THE ENVIRONMENT 25
129129 JOINTLY SHALL ADOPT REGULATI ONS TO CARRY OUT THI S SECTION. 26