1 | 1 | | |
---|
2 | 2 | | |
---|
3 | 3 | | EXPLANATION: CAPITALS INDICATE MAT TER ADDED TO EXISTIN G LAW. |
---|
4 | 4 | | [Brackets] indicate matter deleted from existing law. |
---|
5 | 5 | | *hb1328* |
---|
6 | 6 | | |
---|
7 | 7 | | HOUSE BILL 1328 |
---|
8 | 8 | | C5, M5, P2 4lr2845 |
---|
9 | 9 | | CF SB 1082 |
---|
10 | 10 | | By: Delegates Ziegler and Crosby |
---|
11 | 11 | | Introduced and read first time: February 9, 2024 |
---|
12 | 12 | | Assigned to: Economic Matters and Appropriations |
---|
13 | 13 | | |
---|
14 | 14 | | A BILL ENTITLED |
---|
15 | 15 | | |
---|
16 | 16 | | AN ACT concerning 1 |
---|
17 | 17 | | |
---|
18 | 18 | | Solar Energy and Energy Storage – Development and State Procurement 2 |
---|
19 | 19 | | |
---|
20 | 20 | | FOR the purpose of authorizing a county to enact a local law creating a conservation and 3 |
---|
21 | 21 | | restoration fund for a certain purpose; establishing the Utility–Scale Solar Design 4 |
---|
22 | 22 | | and Siting Commission in the Power Plant Research Program to provide 5 |
---|
23 | 23 | | recommendations related to solar energy development and land conservation and 6 |
---|
24 | 24 | | preservation; requiring the owner or operator of a certain solar energy generating 7 |
---|
25 | 25 | | station to plant and maintain a certain cover crop on the land on which the station 8 |
---|
26 | 26 | | is located and submit a certain vegetation management plan to a certain entity; 9 |
---|
27 | 27 | | requiring the Public Service Commission, in consultation with certain other entities, 10 |
---|
28 | 28 | | to develop certain model standards for energy storage permitting and fire 11 |
---|
29 | 29 | | suppression; requiring the Department of General Services, in consultation with the 12 |
---|
30 | 30 | | Public Service Commission, to procure a certain amount of solar energy each year 13 |
---|
31 | 31 | | for a certain number of years for a certain purpose; requiring the State to offer for 14 |
---|
32 | 32 | | sale certain energy or associated renewable energy credits under certain 15 |
---|
33 | 33 | | circumstances; exempting the State from certain renewable energy portfolio 16 |
---|
34 | 34 | | standard requirements under certain circumstances; establishing certain labor 17 |
---|
35 | 35 | | requirements for certain solar energy developers; requiring the Maryland Energy 18 |
---|
36 | 36 | | Administration’s Solar Technical Assistance Program to analyze State–owned land 19 |
---|
37 | 37 | | for solar development and create a certain database; requiring each electric company 20 |
---|
38 | 38 | | to submit certain information to the Administration for a certain purpose; requiring 21 |
---|
39 | 39 | | the Maryland Agricultural Land Preservation Foundation to submit a report on 22 |
---|
40 | 40 | | certain property and easements to the Solar Technical Assistance Program and the 23 |
---|
41 | 41 | | General Assembly on or before a certain date; stating the intent of the General 24 |
---|
42 | 42 | | Assembly that a certain number of positions be created in the Department of Natural 25 |
---|
43 | 43 | | Resources for positions that will focus on providing certain support and guidance to 26 |
---|
44 | 44 | | local governments; and generally relating to the development of solar energy and 27 |
---|
45 | 45 | | energy storage technology in the State. 28 |
---|
46 | 46 | | |
---|
47 | 47 | | BY adding to 29 |
---|
48 | 48 | | Article – Local Government 30 2 HOUSE BILL 1328 |
---|
49 | 49 | | |
---|
50 | 50 | | |
---|
51 | 51 | | Section 12–905 1 |
---|
52 | 52 | | Annotated Code of Maryland 2 |
---|
53 | 53 | | (2013 Volume and 2023 Supplement) 3 |
---|
54 | 54 | | |
---|
55 | 55 | | BY adding to 4 |
---|
56 | 56 | | Article – Natural Resources 5 |
---|
57 | 57 | | Section 3–306.2 6 |
---|
58 | 58 | | Annotated Code of Maryland 7 |
---|
59 | 59 | | (2023 Replacement Volume and 2023 Supplement) 8 |
---|
60 | 60 | | |
---|
61 | 61 | | BY adding to 9 |
---|
62 | 62 | | Article – Public Utilities 10 |
---|
63 | 63 | | Section 7–215.1 and 7–216.2 11 |
---|
64 | 64 | | Annotated Code of Maryland 12 |
---|
65 | 65 | | (2020 Replacement Volume and 2023 Supplement) 13 |
---|
66 | 66 | | |
---|
67 | 67 | | BY adding to 14 |
---|
68 | 68 | | Article – State Finance and Procurement 15 |
---|
69 | 69 | | Section 4–325 to be under the new part “Part IV. State Purchase of Solar Energy” 16 |
---|
70 | 70 | | Annotated Code of Maryland 17 |
---|
71 | 71 | | (2021 Replacement Volume and 2023 Supplement) 18 |
---|
72 | 72 | | |
---|
73 | 73 | | BY adding to 19 |
---|
74 | 74 | | Article – State Government 20 |
---|
75 | 75 | | Section 9–2016 21 |
---|
76 | 76 | | Annotated Code of Maryland 22 |
---|
77 | 77 | | (2021 Replacement Volume and 2023 Supplement) 23 |
---|
78 | 78 | | |
---|
79 | 79 | | SECTION 1. BE IT ENACTED BY THE GENERAL ASSEMBLY OF MARYLAND, 24 |
---|
80 | 80 | | That the Laws of Maryland read as follows: 25 |
---|
81 | 81 | | |
---|
82 | 82 | | Article – Local Government 26 |
---|
83 | 83 | | |
---|
84 | 84 | | 12–905. 27 |
---|
85 | 85 | | |
---|
86 | 86 | | (A) IN THIS SECTION, “GENERATING STATION ” HAS THE MEANING STAT ED 28 |
---|
87 | 87 | | IN § 7–207 OF THE PUBLIC UTILITIES ARTICLE. 29 |
---|
88 | 88 | | |
---|
89 | 89 | | (B) THIS SECTION APPLIES TO ALL COUNTIES . 30 |
---|
90 | 90 | | |
---|
91 | 91 | | (C) A COUNTY MAY ENACT A L OCAL LAW TO: 31 |
---|
92 | 92 | | |
---|
93 | 93 | | (1) CREATE A CONSERVATIO N AND RESTORATION FU ND; 32 |
---|
94 | 94 | | |
---|
95 | 95 | | (2) REQUIRE A DEVELOPER OF A SOLAR GENERATIN G STATION TO 33 |
---|
96 | 96 | | PAY A REASONABLE AMO UNT INTO A CONSERVAT ION AND RESTORATION FUND IF 34 HOUSE BILL 1328 3 |
---|
97 | 97 | | |
---|
98 | 98 | | |
---|
99 | 99 | | THE SOLAR GENERATING STATION IS ON LAND Z ONED FOR AGRICULTURA L USE OR 1 |
---|
100 | 100 | | SILVICULTURAL USE ; AND 2 |
---|
101 | 101 | | |
---|
102 | 102 | | (3) REQUIRE THAT THE FUN D UNDER ITEM (1) OF THIS SUBSECTION 3 |
---|
103 | 103 | | BE USED FOR: 4 |
---|
104 | 104 | | |
---|
105 | 105 | | (I) CONSERVATION OR REST ORATION OF AGRICULTU RAL, 5 |
---|
106 | 106 | | ENVIRONMENTAL , OR HISTORICALL Y SENSITIVE AREAS ; AND 6 |
---|
107 | 107 | | |
---|
108 | 108 | | (II) INCENTIVES FOR SOLAR DEVELOPMENT . 7 |
---|
109 | 109 | | |
---|
110 | 110 | | Article – Natural Resources 8 |
---|
111 | 111 | | |
---|
112 | 112 | | 3–306.2. 9 |
---|
113 | 113 | | |
---|
114 | 114 | | (A) (1) IN THIS SECTION THE F OLLOWING WORDS HAVE THE MEANINGS 10 |
---|
115 | 115 | | INDICATED. 11 |
---|
116 | 116 | | |
---|
117 | 117 | | (2) “COMMISSION” MEANS THE UTILITY–SCALE SOLAR DESIGN AND 12 |
---|
118 | 118 | | SITING ADVISORY COMMISSION. 13 |
---|
119 | 119 | | |
---|
120 | 120 | | (3) “GENERATING STATION ” HAS THE MEANING STAT ED IN § 7–207 OF 14 |
---|
121 | 121 | | THE PUBLIC UTILITIES ARTICLE. 15 |
---|
122 | 122 | | |
---|
123 | 123 | | (B) THERE IS A UTILITY–SCALE SOLAR DESIGN AND SITING ADVISORY 16 |
---|
124 | 124 | | COMMISSION IN THE PROGRAM. 17 |
---|
125 | 125 | | |
---|
126 | 126 | | (C) THE COMMISSION CONSISTS O F THE FOLLOWING MEMB ERS: 18 |
---|
127 | 127 | | |
---|
128 | 128 | | (1) ONE REPRESENTATIVE OF A WESTERN COUNTY IN THE STATE 19 |
---|
129 | 129 | | WHO HAS LAND USE EXP ERIENCE, DESIGNATED BY THE MARYLAND ASSOCIATION 20 |
---|
130 | 130 | | OF COUNTIES; 21 |
---|
131 | 131 | | |
---|
132 | 132 | | (2) ONE REPRESENTATIVE OF A SOUTHERN COUNTY IN THE STATE 22 |
---|
133 | 133 | | WHO HAS LAND USE EXP ERIENCE, DESIGNATED BY THE MARYLAND ASSOCIATION 23 |
---|
134 | 134 | | OF COUNTIES; 24 |
---|
135 | 135 | | |
---|
136 | 136 | | (3) ONE REPRESENTATIVE OF A CENTRAL COUNTY IN THE STATE 25 |
---|
137 | 137 | | WHO HAS LAND USE EXP ERIENCE, DESIGNATED BY THE MARYLAND ASSOCIATION 26 |
---|
138 | 138 | | OF COUNTIES; 27 |
---|
139 | 139 | | |
---|
140 | 140 | | (4) ONE REPRESENTATIVE OF AN EASTERN COUNTY IN THE STATE 28 |
---|
141 | 141 | | WHO HAS LAND USE EXP ERIENCE, DESIGNATED BY THE MARYLAND ASSOCIATION 29 |
---|
142 | 142 | | OF COUNTIES; 30 4 HOUSE BILL 1328 |
---|
143 | 143 | | |
---|
144 | 144 | | |
---|
145 | 145 | | |
---|
146 | 146 | | (5) ONE REPRESENTATIVE OF A RURAL MUNICIPALITY IN THE STATE 1 |
---|
147 | 147 | | WHO HAS LAND USE EXP ERIENCE, DESIGNATED BY THE MARYLAND MUNICIPAL 2 |
---|
148 | 148 | | LEAGUE; 3 |
---|
149 | 149 | | |
---|
150 | 150 | | (6) ONE REPRESENTATIVE OF AN URBAN MUNICIPALIT Y IN THE 4 |
---|
151 | 151 | | STATE WITH LAND USE EXPERIENCE , DESIGNATED BY THE MARYLAND MUNICIPAL 5 |
---|
152 | 152 | | LEAGUE; 6 |
---|
153 | 153 | | |
---|
154 | 154 | | (7) ONE REPRESENTATIVE AP POINTED BY THE DEPARTMENT ; 7 |
---|
155 | 155 | | |
---|
156 | 156 | | (8) ONE REPRESENTATIVE AP POINTED BY THE DEPARTMENT OF 8 |
---|
157 | 157 | | AGRICULTURE ; 9 |
---|
158 | 158 | | |
---|
159 | 159 | | (9) ONE REPRESENTATIVE AP POINTED BY THE DEPARTMENT OF 10 |
---|
160 | 160 | | PLANNING; 11 |
---|
161 | 161 | | |
---|
162 | 162 | | (10) ONE REPRESENTATIVE AP POINTED BY THE DEPARTMENT OF THE 12 |
---|
163 | 163 | | ENVIRONMENT ; 13 |
---|
164 | 164 | | |
---|
165 | 165 | | (11) ONE REPRESENTATIVE AP POINTED BY THE MARYLAND ENERGY 14 |
---|
166 | 166 | | ADMINISTRATION ; 15 |
---|
167 | 167 | | |
---|
168 | 168 | | (12) ONE REPRESENTATIVE AP POINTED BY THE CHAIR OF THE PUBLIC 16 |
---|
169 | 169 | | SERVICE COMMISSION; 17 |
---|
170 | 170 | | |
---|
171 | 171 | | (13) THREE REPRESENTATIVES O F THE SOLAR DEVELOPM ENT 18 |
---|
172 | 172 | | INDUSTRY, APPOINTED BY THE MARYLAND ENERGY ADMINISTRATION AS FOL LOWS: 19 |
---|
173 | 173 | | |
---|
174 | 174 | | (I) AT LEAST ONE REPRESEN TATIVE OF THE COMMUN ITY 20 |
---|
175 | 175 | | SOLAR INDUSTRY ; AND 21 |
---|
176 | 176 | | |
---|
177 | 177 | | (II) AT LEAST ONE REPRESEN TATIVE OF THE UTILIT Y–SCALE 22 |
---|
178 | 178 | | SOLAR INDUS TRY; 23 |
---|
179 | 179 | | |
---|
180 | 180 | | (14) ONE REPRESENTATIVE DE SIGNATED BY THE MARYLAND FARM 24 |
---|
181 | 181 | | BUREAU; 25 |
---|
182 | 182 | | |
---|
183 | 183 | | (15) ONE REPRESENTATIVE OF AN ENVIRONMENTAL NON PROFIT 26 |
---|
184 | 184 | | ORGANIZATION IN THE STATE, APPOINTED BY THE DEPARTMENT OF THE 27 |
---|
185 | 185 | | ENVIRONMENT ; 28 |
---|
186 | 186 | | HOUSE BILL 1328 5 |
---|
187 | 187 | | |
---|
188 | 188 | | |
---|
189 | 189 | | (16) ONE REPRESENTATIVE OF AN ENVIRONMENTAL JUS TICE 1 |
---|
190 | 190 | | COMMUNITY , APPOINTED BY THE DEPARTMENT OF THE ENVIRONMENT ; 2 |
---|
191 | 191 | | |
---|
192 | 192 | | (17) ONE REPRESENTATIVE OF A LAND PRESERVATION 3 |
---|
193 | 193 | | ORGANIZATION , APPOINTED BY THE DEPARTMENT ; AND 4 |
---|
194 | 194 | | |
---|
195 | 195 | | (18) THE SECRETARY, OR THE SECRETARY’S DESIGNEE. 5 |
---|
196 | 196 | | |
---|
197 | 197 | | (D) THE SECRETARY, OR THE SECRETARY’S DESIGNEE, SHALL SERVE AS 6 |
---|
198 | 198 | | CHAIR OF THE COMMISSION. 7 |
---|
199 | 199 | | |
---|
200 | 200 | | (E) THE DEPARTMENT SHALL PROV IDE STAFF FOR THE COMMISSION. 8 |
---|
201 | 201 | | |
---|
202 | 202 | | (F) ON OR BEFORE DECEMBER 1, 2024, THE COMMISSION SHALL PROV IDE 9 |
---|
203 | 203 | | TO THE GOVERNOR AND , IN ACCORDANCE WITH § 2–1257 OF THE STATE 10 |
---|
204 | 204 | | GOVERNMENT ARTICLE, THE GENERAL ASSEMBLY RECOMMENDATI ONS ON: 11 |
---|
205 | 205 | | |
---|
206 | 206 | | (1) BALANCING COMPETING G OALS RELATED TO SOLA R ENERGY 12 |
---|
207 | 207 | | DEVELOPMENT AND LAND CONSERVATION AND PRE SERVATION; 13 |
---|
208 | 208 | | |
---|
209 | 209 | | (2) THE APPROPRIATE APPRO ACH FOR SOLAR DEVELO PMENT ON 14 |
---|
210 | 210 | | PRIME AND PRODUCTIVE SOILS THAT: 15 |
---|
211 | 211 | | |
---|
212 | 212 | | (I) DOES NOT INCLUDE SPECIFIC S OIL CLASSIFICATION 16 |
---|
213 | 213 | | PROHIBITIONS; AND 17 |
---|
214 | 214 | | |
---|
215 | 215 | | (II) CONSIDERS THE IMPACT ON LOCAL PROGRAMS OF 18 |
---|
216 | 216 | | AGRICULTURAL LAND PR ESERVATION APPROVED UNDER § 2–512 OF THE 19 |
---|
217 | 217 | | AGRICULTURE ARTICLE; 20 |
---|
218 | 218 | | |
---|
219 | 219 | | (3) SETBACK RANGES AND SC REENING REQUIREMENTS THAT 21 |
---|
220 | 220 | | CONSIDER THE STATE’S GEOGRAPHIC DIVERSI TY, NATIVE VEGETATION , AND 22 |
---|
221 | 221 | | STORMWATER MANAGEMEN T; 23 |
---|
222 | 222 | | |
---|
223 | 223 | | (4) ENCOURAGING THE DEVEL OPMENT OF SOLAR ENER GY 24 |
---|
224 | 224 | | GENERATING STATIONS ON BROWNFIELDS , PARKING LOTS, AND OTHER AREAS ; AND 25 |
---|
225 | 225 | | |
---|
226 | 226 | | (5) PRESERVING FORESTS , SOIL, AND NATURAL RESOURCE S. 26 |
---|
227 | 227 | | |
---|
228 | 228 | | (G) ON OR BEFORE DECEMBER 1, 2025, THE COMMISSION SHALL PROV IDE 27 |
---|
229 | 229 | | TO THE GOVERNOR AND , IN ACCORDANCE WITH § 2–1257 OF THE STATE 28 |
---|
230 | 230 | | GOVERNMENT ARTICLE, THE GENERAL ASSEMBLY RECOMMENDATI ONS ON: 29 |
---|
231 | 231 | | 6 HOUSE BILL 1328 |
---|
232 | 232 | | |
---|
233 | 233 | | |
---|
234 | 234 | | (1) BEST PRACTICES FOR SI TING SOLAR ENERGY GE NERATING 1 |
---|
235 | 235 | | STATIONS WITH A GENERATING CAPA CITY OF 2 MEGAWATTS OR MORE ; 2 |
---|
236 | 236 | | |
---|
237 | 237 | | (2) ESTABLISHING A MODEL POLICY FOR THE DEVEL OPMENT OF 3 |
---|
238 | 238 | | SOLAR ENERGY GENERAT ING STATIONS WITH A GENERATING CAPACITY OF 2 4 |
---|
239 | 239 | | MEGAWATTS OR MORE IN EACH COUNTY TO MEET THE STATE’S SOLAR ENERGY 5 |
---|
240 | 240 | | COMMITMENTS UNDER TITLE 7, SUBTITLE 7 OF THE PUBLIC UTILITIES ARTICLE; 6 |
---|
241 | 241 | | |
---|
242 | 242 | | (3) METHODS BY WHICH A LO CAL JURISDICTION MAY PRIORITIZE 7 |
---|
243 | 243 | | THE DEVELOPMENT OF S OLAR ENERGY WITH OTH ER LOCAL NEEDS ; AND 8 |
---|
244 | 244 | | |
---|
245 | 245 | | (4) DECOMMISSIONING STAND ARDS FOR SOLAR ENERG Y 9 |
---|
246 | 246 | | GENERATING STATIONS . 10 |
---|
247 | 247 | | |
---|
248 | 248 | | (H) THE COMMISSION SHALL CONV ENE AT LEAST ONCE EV ERY 10 YEARS TO 11 |
---|
249 | 249 | | PROVIDE TO THE GOVERNOR AND , IN ACCORDANCE WITH § 2–1257 OF THE STATE 12 |
---|
250 | 250 | | GOVERNMENT ARTICLE, THE GENERAL ASSEMBLY RECOMMENDATI ONS ON: 13 |
---|
251 | 251 | | |
---|
252 | 252 | | (1) BEST PRACTICES FOR SI TING SOLAR ENERGY GE NERATING 14 |
---|
253 | 253 | | STATIONS WITH A GENERATING CAPA CITY OF 2 MEGAWATTS OR MORE ; 15 |
---|
254 | 254 | | |
---|
255 | 255 | | (2) ADAPTING TO CHANGES I N TECHNOLOGY ; 16 |
---|
256 | 256 | | |
---|
257 | 257 | | (3) MEETING STATE ENERGY GOALS ; AND 17 |
---|
258 | 258 | | |
---|
259 | 259 | | (4) ANY OTHER ISSUE THE COMMISSION CONSIDERS APPROPRIATE . 18 |
---|
260 | 260 | | |
---|
261 | 261 | | Article – Public Utilities 19 |
---|
262 | 262 | | |
---|
263 | 263 | | 7–215.1. 20 |
---|
264 | 264 | | |
---|
265 | 265 | | (A) THIS SECTION APPLIES TO A GROUND –MOUNTED SOLAR ENERGY 21 |
---|
266 | 266 | | GENERATING STATION L OCATED IN THE STATE THAT: 22 |
---|
267 | 267 | | |
---|
268 | 268 | | (1) HAS THE CAPACITY TO PRODUCE MORE THAN 2 MEGAWATTS OF 23 |
---|
269 | 269 | | ELECTRICITY; AND 24 |
---|
270 | 270 | | |
---|
271 | 271 | | (2) IS DESIGNED TO PRODU CE ELECTRICITY FOR S ALE ON THE 25 |
---|
272 | 272 | | WHOLESALE MARKET . 26 |
---|
273 | 273 | | |
---|
274 | 274 | | (B) (1) THE OWNER OR O PERATOR OF A GROUND –MOUNTED SOLAR 27 |
---|
275 | 275 | | ENERGY GENERATING ST ATION SHALL: 28 |
---|
276 | 276 | | HOUSE BILL 1328 7 |
---|
277 | 277 | | |
---|
278 | 278 | | |
---|
279 | 279 | | (I) IN CONSULTATION WITH THE UNIVERSITY OF MARYLAND 1 |
---|
280 | 280 | | EXTENSION, PLANT AND MAINTAIN ON THE LAND ON WHICH THE STATION IS 2 |
---|
281 | 281 | | LOCATED A COVER CROP THAT IS BENEFICIAL T O SOIL HEALTH AND RE GENERATION 3 |
---|
282 | 282 | | AND PROVIDES CARBON SEQUESTRATION ; AND 4 |
---|
283 | 283 | | |
---|
284 | 284 | | (II) SUBMIT TO THE UNIVERSITY OF MARYLAND EXTENSION A 5 |
---|
285 | 285 | | VEGETATION MANAGEMEN T PLAN DESIGNED TO M ITIGATE HARM TO NATI VE 6 |
---|
286 | 286 | | VEGETATION AND POLLI NATOR HABITATS . 7 |
---|
287 | 287 | | |
---|
288 | 288 | | (2) THE REQUIREMENT TO PL ANT A COVER CROP UND ER PARAGRAPH 8 |
---|
289 | 289 | | (1)(I) OF THIS SUBSECTION D OES NOT APPLY TO LAN D THAT IS ADJACENT T O THE 9 |
---|
290 | 290 | | LAND ON WHICH THE SO LAR ENERGY GENERATIN G STATION IS LOCATED . 10 |
---|
291 | 291 | | |
---|
292 | 292 | | 7–216.2. 11 |
---|
293 | 293 | | |
---|
294 | 294 | | (A) IN THIS SECTION , “ENERGY STORAGE DEVIC E” HAS THE MEANING 12 |
---|
295 | 295 | | STATED IN § 7–216 OF THIS SUBTITLE. 13 |
---|
296 | 296 | | |
---|
297 | 297 | | (B) THE COMMISSION, IN CONSULTATION WITH THE POWER PLANT 14 |
---|
298 | 298 | | RESEARCH PROGRAM, THE COMMISSION’S ENERGY STORAGE WORKING GROUP, 15 |
---|
299 | 299 | | AND THE STATE FIRE MARSHAL, SHALL DEVELOP FOR AD OPTION BY THE STATE OR 16 |
---|
300 | 300 | | LOCAL GOVERNMENTS : 17 |
---|
301 | 301 | | |
---|
302 | 302 | | (1) MODEL PERMITTING STA NDARDS FOR ENERGY STORAGE 18 |
---|
303 | 303 | | DEVICES; AND 19 |
---|
304 | 304 | | |
---|
305 | 305 | | (2) MODEL FIRE SUPPRESSI ON STANDARDS AND REQ UIREMENTS FOR 20 |
---|
306 | 306 | | ENERGY STORAGE DEVIC ES. 21 |
---|
307 | 307 | | |
---|
308 | 308 | | Article – State Finance and Procurement 22 |
---|
309 | 309 | | |
---|
310 | 310 | | 4–323. RESERVED. 23 |
---|
311 | 311 | | |
---|
312 | 312 | | 4–324. RESERVED. 24 |
---|
313 | 313 | | |
---|
314 | 314 | | PART IV. STATE PURCHASE OF SOLAR ENERGY. 25 |
---|
315 | 315 | | |
---|
316 | 316 | | 4–325. 26 |
---|
317 | 317 | | |
---|
318 | 318 | | (A) ON OR BEFORE DECEMBER 31, 2025, AND EACH DECEMBER 31 27 |
---|
319 | 319 | | THEREAFTER THROUGH 2035, THE DEPARTMENT , IN CONSULTATION WITH THE 28 |
---|
320 | 320 | | PUBLIC SERVICE COMMISSION, SHALL PROCURE 200 MEGAWATTS OF SOLAR 29 |
---|
321 | 321 | | ENERGY TO MEET THE STATE’S ENERGY NEEDS , THE STATE’S RENEWABLE ENERGY 30 8 HOUSE BILL 1328 |
---|
322 | 322 | | |
---|
323 | 323 | | |
---|
324 | 324 | | PORTFOLIO STANDARD , AND THE STATE’S NET–ZERO STATEWIDE GREEN HOUSE GAS 1 |
---|
325 | 325 | | EMISSIONS REDUCTION GOALS. 2 |
---|
326 | 326 | | |
---|
327 | 327 | | (B) THE DEPARTMENT , IN CONSULTATION WITH THE PUBLIC SERVICE 3 |
---|
328 | 328 | | COMMISSION: 4 |
---|
329 | 329 | | |
---|
330 | 330 | | (1) SHALL ISSUE A COMPET ITIVE SEALED PROCURE MENT 5 |
---|
331 | 331 | | SOLICITATION FOR THE SOLAR ENERGY REQUIRED UNDER SUBSE CTION (A) OF THIS 6 |
---|
332 | 332 | | SECTION; AND 7 |
---|
333 | 333 | | |
---|
334 | 334 | | (2) MAY ENTER INTO AT LE AST ONE CONTRACT FOR A POWER 8 |
---|
335 | 335 | | PURCHASE AGREEMENT T O PROCURE SOLAR ENER GY. 9 |
---|
336 | 336 | | |
---|
337 | 337 | | (C) THE STATE SHALL: 10 |
---|
338 | 338 | | |
---|
339 | 339 | | (1) OFFER FOR SALE ANY E NERGY OR RENEWABLE E NERGY CREDITS 11 |
---|
340 | 340 | | REMAINING AFTER THE STATE HAS MET ITS REN EWABLE ENERGY PORTFO LIO 12 |
---|
341 | 341 | | STANDARD REQUIREMENT S UNDER § 7–703 OF THE PUBLIC UTILITIES ARTICLE ON 13 |
---|
342 | 342 | | THE COMPETITIVE WHOL ESALE POWER MARKET O PERATED BY PJM 14 |
---|
343 | 343 | | INTERCONNECTION , THROUGH BILATERAL SA LES TO CREDIT –WORTHY 15 |
---|
344 | 344 | | COUNTERPARTIES , OR INTO RENE WABLE ENERGY CREDIT MARKETS; AND 16 |
---|
345 | 345 | | |
---|
346 | 346 | | (2) BE EXEMPTED FROM THE RENEWABLE ENERGY POR TFOLIO 17 |
---|
347 | 347 | | STANDARD REQUIREMENT S UNDER § 7–703 OF THE PUBLIC UTILITIES ARTICLE IF 18 |
---|
348 | 348 | | THE DEPARTMENT PROCURES 100% OF THE STATE’S ENERGY NEEDS FROM A 19 |
---|
349 | 349 | | POWER PURCHASE AGREE MENT REQUIRED UNDER SUBSECTION (B) OF THIS 20 |
---|
350 | 350 | | SECTION. 21 |
---|
351 | 351 | | |
---|
352 | 352 | | (D) EACH CONTRACT ENTERED INTO UNDER SUBSECTIO N (B) OF THIS 22 |
---|
353 | 353 | | SECTION SHALL : 23 |
---|
354 | 354 | | |
---|
355 | 355 | | (1) INCLUDE A COMMUNITY BENEFIT AGREEMENT FO R A SOLAR 24 |
---|
356 | 356 | | ENERGY DEVELOPER ; AND 25 |
---|
357 | 357 | | |
---|
358 | 358 | | (2) BE SUBJECT TO A PROJ ECT LABOR AGREEMENT FOR A SOLAR 26 |
---|
359 | 359 | | ENERGY DEVELOPER THAT : 27 |
---|
360 | 360 | | |
---|
361 | 361 | | (I) BINDS ALL CONTRACTOR S AND SUBCONTRACTORS ON A 28 |
---|
362 | 362 | | CONTRACT THROUGH THE INCLUSION OF SPECIFI CATIONS IN ALL RELEV ANT 29 |
---|
363 | 363 | | SOLICITATION PROVISI ONS AND CONTRACT DOC UMENTS; 30 |
---|
364 | 364 | | |
---|
365 | 365 | | (II) ALLOWS ALL CONTRACTO RS AND SUBCONTRACTOR S TO 31 |
---|
366 | 366 | | COMPETE FOR CO NTRACTS AND SUBCONTR ACTS ON THE PROJECT WITHOUT 32 HOUSE BILL 1328 9 |
---|
367 | 367 | | |
---|
368 | 368 | | |
---|
369 | 369 | | REGARD TO WHETHER TH EY ARE OTHERWISE PAR TIES TO COLLECTIVE B ARGAINING 1 |
---|
370 | 370 | | AGREEMENTS ; 2 |
---|
371 | 371 | | |
---|
372 | 372 | | (III) ESTABLISHES UNIFORM TERMS AND CONDITIONS OF 3 |
---|
373 | 373 | | EMPLOYMENT FOR ALL C ONSTRUCTION LABOR EM PLOYED ON A PROJECT ; 4 |
---|
374 | 374 | | |
---|
375 | 375 | | (IV) GUARANTEES AGAINST STR IKES, LOCKOUTS, AND SIMILAR 5 |
---|
376 | 376 | | JOB DISRUPTIONS ; 6 |
---|
377 | 377 | | |
---|
378 | 378 | | (V) ESTABLISHES MUTUALLY BINDING PROCEDURES F OR 7 |
---|
379 | 379 | | LABOR DISPUTES ; AND 8 |
---|
380 | 380 | | |
---|
381 | 381 | | (VI) INCLUDES ANY OTHER P ROVISIONS NEGOTIATED BY THE 9 |
---|
382 | 382 | | PARTIES TO PROMOTE S UCCESSFUL DELIVERY O F SOLAR ENERGY . 10 |
---|
383 | 383 | | |
---|
384 | 384 | | Article – State Government 11 |
---|
385 | 385 | | |
---|
386 | 386 | | 9–2016. 12 |
---|
387 | 387 | | |
---|
388 | 388 | | (A) ON OR BEFORE DECEMBER 1, 2025, TO ASSIST THE STATE IN MEETING 13 |
---|
389 | 389 | | ITS SOLAR ENERGY COM MITMENTS UNDER TITLE 7, SUBTITLE 7 OF THE PUBLIC 14 |
---|
390 | 390 | | UTILITIES ARTICLE, THE ADMINISTRATION ’S SOLAR TECHNICAL ASSISTANCE 15 |
---|
391 | 391 | | PROGRAM, IN CONSULTATION WITH THE DEPARTMENT , THE DEPARTMENT OF 16 |
---|
392 | 392 | | NATURAL RESOURCES, AND THE DEPARTMENT OF PLANNING, SHALL: 17 |
---|
393 | 393 | | |
---|
394 | 394 | | (1) ANALYZE LAND IN THE STATE TO IDENTIFY LAN D SUITABLE FOR 18 |
---|
395 | 395 | | SOLAR ENERGY DEVELOP MENT TO ASSIST THE STATE IN MEETING ITS SOLAR 19 |
---|
396 | 396 | | ENERGY COMMITMENTS U NDER TITLE 7, SUBTITLE 7 OF THE PUBLIC UTILITIES 20 |
---|
397 | 397 | | ARTICLE; 21 |
---|
398 | 398 | | |
---|
399 | 399 | | (2) DEVELOP A DATABASE , SORTED BY COUNTY , IDENTIFYING AND 22 |
---|
400 | 400 | | RECOMMENDING STATE LAND SUITABLE F OR SOLAR ENERGY DEVE LOPMENT, 23 |
---|
401 | 401 | | INCLUDING: 24 |
---|
402 | 402 | | |
---|
403 | 403 | | (I) BROWNFIELDS ; 25 |
---|
404 | 404 | | |
---|
405 | 405 | | (II) LANDFILLS; 26 |
---|
406 | 406 | | |
---|
407 | 407 | | (III) PARKING LOTS AND GARAGES ; AND 27 |
---|
408 | 408 | | |
---|
409 | 409 | | (IV) LAND OWNED OR UNDER EASEMENT BY : 28 |
---|
410 | 410 | | |
---|
411 | 411 | | 1. THE MARYLAND AGRICULTURAL LAND 29 |
---|
412 | 412 | | PRESERVATION FOUNDATION; 30 10 HOUSE BILL 1328 |
---|
413 | 413 | | |
---|
414 | 414 | | |
---|
415 | 415 | | |
---|
416 | 416 | | 2. THE DEPARTMENT OF TRANSPORTATION ; AND 1 |
---|
417 | 417 | | |
---|
418 | 418 | | 3. THE DEPARTMENT OF NATURAL RESOURCES; AND 2 |
---|
419 | 419 | | |
---|
420 | 420 | | (3) ESTABLISH A GOAL FOR THE AMOUNT OF STATE LAND THAT MAY 3 |
---|
421 | 421 | | BE USED FOR SOLAR EN ERGY GENERATION TO M EET THE STATE’S RENEWABLE 4 |
---|
422 | 422 | | ENERGY PORTFOLIO STA NDARD GOALS FOR SOLA R ENERGY UNDER TITLE 7, 5 |
---|
423 | 423 | | SUBTITLE 7 OF THE PUBLIC UTILITIES ARTICLE. 6 |
---|
424 | 424 | | |
---|
425 | 425 | | (B) THE DATABASE DEVELOPE D IN ACCORDANCE WITH SUBSECTION (A) OF 7 |
---|
426 | 426 | | THIS SECTION SHALL I NCLUDE: 8 |
---|
427 | 427 | | |
---|
428 | 428 | | (1) THE ACREAGE OF EACH PLOT OF LAND; 9 |
---|
429 | 429 | | |
---|
430 | 430 | | (2) WHETHER THE PLOT OF LAND IS SUBJECT TO C ONSERVATION 10 |
---|
431 | 431 | | EASEMENTS OR ZONING ; AND 11 |
---|
432 | 432 | | |
---|
433 | 433 | | (3) THE ACREAGE THAT A STATE AGENCY OFFERS F OR USE FOR 12 |
---|
434 | 434 | | SOLAR DEVELOPMENT . 13 |
---|
435 | 435 | | |
---|
436 | 436 | | (C) ON OR BEFORE JULY 1, 2025, EACH ELECTRIC COMPAN Y SHALL SUBMIT 14 |
---|
437 | 437 | | TO THE SOLAR TECHNICAL ASSISTANCE PROGRAM INFORMATION T O ASSIST THE 15 |
---|
438 | 438 | | PROGRAM IN ITS ANALYS IS UNDER SUBSECTION (A) OF THIS SECTION, INCLUDING: 16 |
---|
439 | 439 | | |
---|
440 | 440 | | (1) THE LOCATION OF EACH TRANSMISSION AND DIS TRIBUTION 17 |
---|
441 | 441 | | CIRCUIT USED BY THE ELECTRIC COMPANY ; 18 |
---|
442 | 442 | | |
---|
443 | 443 | | (2) THE NUMBER OF SUBSTA TION TRANSFORMERS OW NED BY THE 19 |
---|
444 | 444 | | ELECTRIC COMPANY ; 20 |
---|
445 | 445 | | |
---|
446 | 446 | | (3) THE KILOVOLT –AMPERE RATING OF EAC H SUBSTATION 21 |
---|
447 | 447 | | TRANSFORMER OWNED BY THE ELECTRIC COMPANY ; 22 |
---|
448 | 448 | | |
---|
449 | 449 | | (4) LINE EQUIPMENT FOR E ACH CONDUCTOR OWNE D BY THE 23 |
---|
450 | 450 | | ELECTRIC COMPANY ; 24 |
---|
451 | 451 | | |
---|
452 | 452 | | (5) CONDUCTOR RATINGS FO R EACH CONDUCTOR OWN ED BY THE 25 |
---|
453 | 453 | | ELECTRIC COMPANY ; 26 |
---|
454 | 454 | | |
---|
455 | 455 | | (6) CURRENT AND QUEUED G ENERATION ON CIRCUIT S AND 27 |
---|
456 | 456 | | TRANSFORMERS OWNED B Y THE ELECTRIC COMPA NY, TO BE UPDATED QUARTE RLY; 28 |
---|
457 | 457 | | HOUSE BILL 1328 11 |
---|
458 | 458 | | |
---|
459 | 459 | | |
---|
460 | 460 | | (7) THE LOADS OF EACH CI RCUIT AND SUBSTATION OWNED BY THE 1 |
---|
461 | 461 | | ELECTRIC COMPANY , INCLUDING PEAK AND M INIMUM DAYTIME LOAD ; 2 |
---|
462 | 462 | | |
---|
463 | 463 | | (8) THE STATUS OF CONSTR UCTION FOR NEW LINES AND 3 |
---|
464 | 464 | | SUBSTATIONS OWNED BY THE ELECTRIC COMPANY ; AND 4 |
---|
465 | 465 | | |
---|
466 | 466 | | (9) AVERAGE COSTS TO UPG RADE SUBSTATIONS AND CIRCUITS 5 |
---|
467 | 467 | | OWNED BY THE ELECTRIC COMPANY . 6 |
---|
468 | 468 | | |
---|
469 | 469 | | (D) ON OR BEFORE DECEMBER 1, 2025, THE MARYLAND AGRICULTURAL 7 |
---|
470 | 470 | | LAND PRESERVATION FOUNDATION OF THE MARYLAND DEPARTMENT OF 8 |
---|
471 | 471 | | AGRICULTURE , IN CONSULTATION WITH THE HOWARD HUGHES CENTER FOR 9 |
---|
472 | 472 | | SUSTAINABLE AGRICULTURE , SHALL SUBMIT TO THE SOLAR TECHNICAL 10 |
---|
473 | 473 | | ASSISTANCE PROGRAM AND , IN ACCORDANCE WITH § 2–1257 OF THIS ARTICLE, THE 11 |
---|
474 | 474 | | GENERAL ASSEMBLY A REPORT CON TAINING: 12 |
---|
475 | 475 | | |
---|
476 | 476 | | (1) A LIST OF REAL PROPE RTY OWNED AND CONSER VATION 13 |
---|
477 | 477 | | EASEMENTS HELD BY TH E FOUNDATION; 14 |
---|
478 | 478 | | |
---|
479 | 479 | | (2) THE FUNDS REQUIRED T O RENEW EACH CONSERV ATION 15 |
---|
480 | 480 | | EASEMENT; AND 16 |
---|
481 | 481 | | |
---|
482 | 482 | | (3) RECOMMENDATIONS CONC ERNING REQUIREMENTS FOR THE 17 |
---|
483 | 483 | | STATE TO RETURN LAND HELD BY THE FOUNDATION UNDER A CO NSERVATION 18 |
---|
484 | 484 | | EASEMENT TO ITS ORIG INAL CONDITION . 19 |
---|
485 | 485 | | |
---|
486 | 486 | | SECTION 2. AND BE IT FURTHER ENACTED, That it is the intent of the General 20 |
---|
487 | 487 | | Assembly that two Position Identification Numbers (PINs) be created in the Department of 21 |
---|
488 | 488 | | Natural Resources for full–time positions in the Power Plant Research Program that will 22 |
---|
489 | 489 | | focus on providing support and guidance to local governments on the permitting process for 23 |
---|
490 | 490 | | solar energy development. 24 |
---|
491 | 491 | | |
---|
492 | 492 | | SECTION 3. AND BE IT FURTHER ENACTED, That this Act shall take effect July 25 |
---|
493 | 493 | | 1, 2024. 26 |
---|