1 | 1 | | |
---|
2 | 2 | | |
---|
3 | 3 | | EXPLANATION: CAPITALS INDICATE MAT TER ADDED TO EXISTIN G LAW. |
---|
4 | 4 | | [Brackets] indicate matter deleted from existing law. |
---|
5 | 5 | | *sb1025* |
---|
6 | 6 | | |
---|
7 | 7 | | SENATE BILL 1025 |
---|
8 | 8 | | C5 4lr2338 |
---|
9 | 9 | | CF 4lr2212 |
---|
10 | 10 | | By: Senator Brooks |
---|
11 | 11 | | Introduced and read first time: February 2, 2024 |
---|
12 | 12 | | Assigned to: Education, Energy, and the Environment |
---|
13 | 13 | | |
---|
14 | 14 | | A BILL ENTITLED |
---|
15 | 15 | | |
---|
16 | 16 | | AN ACT concerning 1 |
---|
17 | 17 | | |
---|
18 | 18 | | Public Utilities – Distributed Generation Certificate of Public Convenience and 2 |
---|
19 | 19 | | Necessity 3 |
---|
20 | 20 | | |
---|
21 | 21 | | FOR the purpose of establishing a distributed generation certificate of public convenience 4 |
---|
22 | 22 | | and necessity to authorize the construction and operation of a certain distributed 5 |
---|
23 | 23 | | solar energy generating system; requiring the Power Plant Research Program to 6 |
---|
24 | 24 | | develop and submit to the Public Service Commission proposed siting and design 7 |
---|
25 | 25 | | requirements and licensing conditions; prohibiting a person from being required to 8 |
---|
26 | 26 | | obtain a distributed generation certificate of public convenience and necessity until 9 |
---|
27 | 27 | | certain regulations have been adopted; prohibiting a person from beginning 10 |
---|
28 | 28 | | construction of a distributed solar energy generating system unless a distributed 11 |
---|
29 | 29 | | generation certificate of public convenience and necessity is first obtained from the 12 |
---|
30 | 30 | | Commission; requiring the Program to make a certain determination regarding a 13 |
---|
31 | 31 | | proposed distributed solar energy generating system within a certain period of time; 14 |
---|
32 | 32 | | establishing a process by which the Commission may grant a distributed generation 15 |
---|
33 | 33 | | certificate of public convenience and necessity; providing the applications of certain 16 |
---|
34 | 34 | | provisions; and generally relating to a distributed generation certificate of public 17 |
---|
35 | 35 | | convenience and necessity. 18 |
---|
36 | 36 | | |
---|
37 | 37 | | BY repealing and reenacting, with amendments, 19 |
---|
38 | 38 | | Article – Natural Resources 20 |
---|
39 | 39 | | Section 3–306(a)(1) 21 |
---|
40 | 40 | | Annotated Code of Maryland 22 |
---|
41 | 41 | | (2023 Replacement Volume and 2023 Supplement) 23 |
---|
42 | 42 | | |
---|
43 | 43 | | BY repealing and reenacting, with amendments, 24 |
---|
44 | 44 | | Article – Public Utilities 25 |
---|
45 | 45 | | Section 7–207(b)(1)(i) and (ii) and 7–207.1(c)(1) 26 |
---|
46 | 46 | | Annotated Code of Maryland 27 |
---|
47 | 47 | | (2020 Replacement Volume and 2023 Supplement) 28 |
---|
48 | 48 | | 2 SENATE BILL 1025 |
---|
49 | 49 | | |
---|
50 | 50 | | |
---|
51 | 51 | | BY adding to 1 |
---|
52 | 52 | | Article – Public Utilities 2 |
---|
53 | 53 | | Section 7–207.3 3 |
---|
54 | 54 | | Annotated Code of Maryland 4 |
---|
55 | 55 | | (2020 Replacement Volume and 2023 Supplement) 5 |
---|
56 | 56 | | |
---|
57 | 57 | | Preamble 6 |
---|
58 | 58 | | |
---|
59 | 59 | | WHEREAS, The State has set aggressive minimum renewable energy requirements, 7 |
---|
60 | 60 | | recognizing that a shift towards sustainable energy sources is crucial for the health of our 8 |
---|
61 | 61 | | planet and the well–being of future generations; and 9 |
---|
62 | 62 | | |
---|
63 | 63 | | WHEREAS, The State has committed to reducing greenhouse gas emissions by 60% 10 |
---|
64 | 64 | | from 2006 levels, reflecting a proactive stance in the global effort to combat climate change; 11 |
---|
65 | 65 | | and 12 |
---|
66 | 66 | | |
---|
67 | 67 | | WHEREAS, Distributed solar generation is an essential component of meeting these 13 |
---|
68 | 68 | | aggressive policies, offering both economic opportunities and environmental benefits; and 14 |
---|
69 | 69 | | |
---|
70 | 70 | | WHEREAS, The General Assembly finds that an efficient permitting process for 15 |
---|
71 | 71 | | distributed solar energy generating stations with consistency across jurisdictions is 16 |
---|
72 | 72 | | necessary to meet the State’s renewable energy and greenhouse gas reduction 17 |
---|
73 | 73 | | commitments and can be structured to preserve farmland and forests; now, therefore, 18 |
---|
74 | 74 | | |
---|
75 | 75 | | SECTION 1. BE IT ENACTED BY THE GENERAL ASSEMBLY OF MARYLAND, 19 |
---|
76 | 76 | | That the Laws of Maryland read as follows: 20 |
---|
77 | 77 | | |
---|
78 | 78 | | Article – Natural Resources 21 |
---|
79 | 79 | | |
---|
80 | 80 | | 3–306. 22 |
---|
81 | 81 | | |
---|
82 | 82 | | (a) (1) Notwithstanding anything to the contrary in this article or the Public 23 |
---|
83 | 83 | | Utilities Article, on application to the Public Service Commission for a certificate of public 24 |
---|
84 | 84 | | convenience and necessity associated with power plant construction IN ACCORDANCE 25 |
---|
85 | 85 | | WITH § 7–207 OF THE PUBLIC UTILITIES ARTICLE, the Commission shall notify 26 |
---|
86 | 86 | | immediately the Department [of Natural Resources] and the Department of the 27 |
---|
87 | 87 | | Environment of the application. 28 |
---|
88 | 88 | | |
---|
89 | 89 | | Article – Public Utilities 29 |
---|
90 | 90 | | |
---|
91 | 91 | | 7–207. 30 |
---|
92 | 92 | | |
---|
93 | 93 | | (b) (1) (i) [Unless] EXCEPT AS PROVIDED IN SUBPARAGRAPH (II) OF 31 |
---|
94 | 94 | | THIS PARAGRAPH , UNLESS a certificate of public convenience and necessity for the 32 |
---|
95 | 95 | | construction is first obtained from the Commission, a person may not begin construction in 33 |
---|
96 | 96 | | the State of: 34 |
---|
97 | 97 | | SENATE BILL 1025 3 |
---|
98 | 98 | | |
---|
99 | 99 | | |
---|
100 | 100 | | 1. a generating station; or 1 |
---|
101 | 101 | | |
---|
102 | 102 | | 2. a qualified generator lead line. 2 |
---|
103 | 103 | | |
---|
104 | 104 | | (ii) [If a person obtains Commission approval for construction under 3 |
---|
105 | 105 | | § 7–207.1 of this subtitle, the Commission shall exempt a person from the requirement to 4 |
---|
106 | 106 | | obtain a certificate of public convenience and necessity under this section.] A PERSON IS 5 |
---|
107 | 107 | | NOT REQUIRED TO OBTA IN A CERTIFICATE OF PUBLIC CONVENIENCE A ND 6 |
---|
108 | 108 | | NECESSITY UNDER THIS SECTION IF THE PERSO N OBTAINS: 7 |
---|
109 | 109 | | |
---|
110 | 110 | | 1. COMMISSION APP ROVAL FOR CONSTRUCTI ON UNDER 8 |
---|
111 | 111 | | § 7–207.1 OF THIS SUBTITLE; OR 9 |
---|
112 | 112 | | |
---|
113 | 113 | | 2. A DISTRIBUTED GENERA TION CERTIFICATE OF 10 |
---|
114 | 114 | | PUBLIC CONVENIENCE A ND NECESSITY UNDER § 7–207.3 OF THIS SUBTITLE. 11 |
---|
115 | 115 | | |
---|
116 | 116 | | 7–207.1. 12 |
---|
117 | 117 | | |
---|
118 | 118 | | (c) (1) The Commission shall require a person that is exempted from the 13 |
---|
119 | 119 | | requirement to obtain a certificate of public convenience and necessity UNDER § 14 |
---|
120 | 120 | | 7–207(B)(1)(II)1 OF THIS SUBTITLE to obtain approval from the Commission under this 15 |
---|
121 | 121 | | section before the person may construct a generating station described in subsection (b) of 16 |
---|
122 | 122 | | this section. 17 |
---|
123 | 123 | | |
---|
124 | 124 | | 7–207.3. 18 |
---|
125 | 125 | | |
---|
126 | 126 | | (A) (1) IN THIS SECTION THE F OLLOWING WORDS HAVE THE MEANINGS 19 |
---|
127 | 127 | | INDICATED. 20 |
---|
128 | 128 | | |
---|
129 | 129 | | (2) “DISTRIBUTED GENERATIO N CERTIFICATE OF PUB LIC 21 |
---|
130 | 130 | | CONVENIENCE AND NECE SSITY” OR “DGCPCN” MEANS A CERTIFICATE ISSUED BY 22 |
---|
131 | 131 | | THE COMMISSION UNDER THIS SECTION THAT AUTHORI ZES THE CONSTRUCTION 23 |
---|
132 | 132 | | AND OPERATION OF A D ISTRIBUTED SOLAR ENE RGY GENERATING SYSTE M. 24 |
---|
133 | 133 | | |
---|
134 | 134 | | (3) “DISTRIBUTED SOLAR ENE RGY GENERATING SYSTE M” MEANS A 25 |
---|
135 | 135 | | COMMUNITY SOLAR ENER GY GENERATING SY STEM, AS DEFINED IN § 7–306.2 OF 26 |
---|
136 | 136 | | THIS TITLE, THAT: 27 |
---|
137 | 137 | | |
---|
138 | 138 | | (I) HAS A CAPACITY TO PR ODUCE MORE THAN 2 MEGAWATTS 28 |
---|
139 | 139 | | BUT NOT MORE THAN 5 MEGAWATTS OF ALTERNA TING CURRENT ; AND 29 |
---|
140 | 140 | | |
---|
141 | 141 | | (II) IS NOT LOCATED WITHI N A MUNICIPAL CORPOR ATION. 30 |
---|
142 | 142 | | |
---|
143 | 143 | | (4) “POWER PLANT RESEARCH PROGRAM” MEANS THE PROGRAM 31 4 SENATE BILL 1025 |
---|
144 | 144 | | |
---|
145 | 145 | | |
---|
146 | 146 | | WITHIN THE DEPARTMENT OF NATURAL RESOURCES UNDER TITLE 3, SUBTITLE 3 1 |
---|
147 | 147 | | OF THE NATURAL RESOURCES ARTICLE. 2 |
---|
148 | 148 | | |
---|
149 | 149 | | (B) (1) ON OR BEFORE JANUARY 1, 2025, THE POWER PLANT RESEARCH 3 |
---|
150 | 150 | | PROGRAM, AFTER GIVING NOTICE AND OPPORTUNITY FOR PUBLIC COMMENT , 4 |
---|
151 | 151 | | SHALL DEVELOP AND SUBM IT TO THE COMMISSION PROPOSED S TANDARD SITING 5 |
---|
152 | 152 | | AND DESIGN REQUIREME NTS AND PROPOSED STA NDARD LICENSING COND ITIONS 6 |
---|
153 | 153 | | FOR THE ISSUANCE OF A DGCPCN. 7 |
---|
154 | 154 | | |
---|
155 | 155 | | (2) IN DEVELOPING THE PRO POSED STANDARD SITIN G AND DESIGN 8 |
---|
156 | 156 | | REQUIREMENTS AND THE PROPOSED ST ANDARD LICENSING CON DITIONS, THE 9 |
---|
157 | 157 | | POWER PLANT RESEARCH PROGRAM SHALL CONSIDE R: 10 |
---|
158 | 158 | | |
---|
159 | 159 | | (I) ACHIEVEMENT OF THE STATE’S CLIMATE AND RENEWA BLE 11 |
---|
160 | 160 | | ENERGY COMMITMENTS ; 12 |
---|
161 | 161 | | |
---|
162 | 162 | | (II) REASONABLE SETBACKS AND LANDSCAPE SCREEN ING 13 |
---|
163 | 163 | | REQUIREMENTS ; 14 |
---|
164 | 164 | | |
---|
165 | 165 | | (III) ENVIRONMENTAL PRESER VATION, INCLUDING FOREST 15 |
---|
166 | 166 | | CONSERVATION EXCEPT WHERE NECESSARY TO : 16 |
---|
167 | 167 | | |
---|
168 | 168 | | 1. REDUCE SOLAR PANEL S HADING; 17 |
---|
169 | 169 | | |
---|
170 | 170 | | 2. FACILITATE INTERCONN ECTION INFRASTRUCTUR E; 18 |
---|
171 | 171 | | AND 19 |
---|
172 | 172 | | |
---|
173 | 173 | | 3. ENSURE ADEQUATE SITE ACCESS; 20 |
---|
174 | 174 | | |
---|
175 | 175 | | (IV) STORMWATER MANAGEMEN T, EROSION AND SEDIMENT 21 |
---|
176 | 176 | | CONTROL, AND SITE STABILIZATION ; 22 |
---|
177 | 177 | | |
---|
178 | 178 | | (V) MINIMIZATION AND MIT IGATION OF EFFECTS O N HISTORIC 23 |
---|
179 | 179 | | SITES; 24 |
---|
180 | 180 | | |
---|
181 | 181 | | (VI) PUBLIC SAFETY; 25 |
---|
182 | 182 | | |
---|
183 | 183 | | (VII) INDUSTRY BEST PRACTI CES; AND 26 |
---|
184 | 184 | | |
---|
185 | 185 | | (VIII) LICENSING CONDITIONS PREVIOUSLY ADOPTED B Y THE 27 |
---|
186 | 186 | | COMMISSION FOR SOLAR ENERGY GENERATING SY STEMS. 28 |
---|
187 | 187 | | |
---|
188 | 188 | | (C) (1) ON OR BEFORE JULY 1, 2025, THE COMMISSION SHALL ADOP T 29 SENATE BILL 1025 5 |
---|
189 | 189 | | |
---|
190 | 190 | | |
---|
191 | 191 | | REGULATIONS TO : 1 |
---|
192 | 192 | | |
---|
193 | 193 | | (I) IMPLEMENT STANDARD S ITING AND DESIGN 2 |
---|
194 | 194 | | REQUIREMENTS AND STA NDARD LICENSING COND ITIONS FOR A DGCPCN; 3 |
---|
195 | 195 | | |
---|
196 | 196 | | (II) SPECIFY THE FORM OF THE APPLICATION FOR A 4 |
---|
197 | 197 | | DISTRIBUTED SOLAR E NERGY GENERATING SYS TEM TO RECEIVE A DGCPCN; AND 5 |
---|
198 | 198 | | |
---|
199 | 199 | | (III) SPECIFY THE COMMISSION’S PROCEDURE FOR PROC ESSING 6 |
---|
200 | 200 | | AN APPLICATION FOR A DGCPCN, WHICH MAY INCLUDE AN EXPEDITED HEARING 7 |
---|
201 | 201 | | BEFORE A PUBLIC UTIL ITY LAW JUDGE. 8 |
---|
202 | 202 | | |
---|
203 | 203 | | (2) THE COMMISSION SHALL CONS IDER THE PRO POSED STANDARD 9 |
---|
204 | 204 | | SITING AND DESIGN RE QUIREMENTS AND THE P ROPOSED STANDARD LIC ENSING 10 |
---|
205 | 205 | | CONDITIONS DEVELOPED BY THE POWER PLANT RESEARCH PROGRAM IN 11 |
---|
206 | 206 | | ADOPTING THE REGULAT IONS UNDER THIS SUBS ECTION. 12 |
---|
207 | 207 | | |
---|
208 | 208 | | (D) NOTWITHSTANDING SUBSE CTION (E) OF THIS SECTION, A PERSON MAY 13 |
---|
209 | 209 | | NOT BE REQUIRED TO O BTAIN A DGCPCN UNDER THIS SECTION U NTIL THE 14 |
---|
210 | 210 | | COMMISSION ADOPTS THE REGULATIONS REQUIRED UNDER SUBSECTION (C) OF 15 |
---|
211 | 211 | | THIS SECTION. 16 |
---|
212 | 212 | | |
---|
213 | 213 | | (E) (1) UNLESS A DGCPCN IS FIRST OBTAINED FR OM THE COMMISSION 17 |
---|
214 | 214 | | IN ACCORDANCE WITH T HIS SECTION, A PERSON MAY NOT BEG IN CONSTRUCTION IN 18 |
---|
215 | 215 | | THE STATE OF A DISTRIBUTE D SOLAR ENERGY GENER ATING SYSTEM. 19 |
---|
216 | 216 | | |
---|
217 | 217 | | (2) WHEN A PERSON SUBMITS AN APPLICATION FOR A DGCPCN TO 20 |
---|
218 | 218 | | THE COMMISSION, THE PERSON SHALL SUB MIT A COPY OF THE APPLICATION TO : 21 |
---|
219 | 219 | | |
---|
220 | 220 | | (I) THE POWER PLANT RESEARCH PROGRAM; AND 22 |
---|
221 | 221 | | |
---|
222 | 222 | | (II) THE GOVERNING BODY O F THE COUNTY WHERE T HE 23 |
---|
223 | 223 | | DISTRIBUTED SOLAR EN ERGY GENERATING SYST EM IS PROPOSED TO BE LOCATED. 24 |
---|
224 | 224 | | |
---|
225 | 225 | | (F) (1) THE COMMISSION SHALL PROV IDE AN OPPORTUNITY F OR PUBLIC 25 |
---|
226 | 226 | | COMMENT AND HOLD A PUBLI C HEARING ON AN APPL ICATION FOR A DGCPCN IN 26 |
---|
227 | 227 | | EACH COUNTY IN WHICH ANY PORTION OF THE C ONSTRUCTION OF THE 27 |
---|
228 | 228 | | DISTRIBUTED SOLAR EN ERGY GENERATING SYST EM IS PROPOSED TO BE LOCATED. 28 |
---|
229 | 229 | | |
---|
230 | 230 | | (2) THE COMMISSION MAY HOLD T HE PUBLIC HEARING VI RTUALLY 29 |
---|
231 | 231 | | RATHER THAN IN PERSON IF THE COMMISSION PROVIDES A COMPARABLE 30 |
---|
232 | 232 | | OPPORTUNITY FOR PUBL IC COMMENT AND PARTI CIPATION IN THE HEAR ING. 31 |
---|
233 | 233 | | 6 SENATE BILL 1025 |
---|
234 | 234 | | |
---|
235 | 235 | | |
---|
236 | 236 | | (G) (1) WITHIN 90 DAYS AFTER THE DATE AN APPLICATION FOR A 1 |
---|
237 | 237 | | DGCPCN IS FILED WITH THE COMMISSION, THE POWER PLANT RESEARCH 2 |
---|
238 | 238 | | PROGRAM SHALL: 3 |
---|
239 | 239 | | |
---|
240 | 240 | | (I) DETERMINE WHETHER TH E DISTRIBUTED SOLAR ENERGY 4 |
---|
241 | 241 | | GENERATING SYSTEM SA TISFIES THE STANDARD SITING AND DESIGN 5 |
---|
242 | 242 | | REQUIREMENTS AND STA NDARD LICENSING COND ITIONS FOR THE DGCPCN; AND 6 |
---|
243 | 243 | | |
---|
244 | 244 | | (II) NOTIFY THE COMMISSION IN WRITING AS TO THE 7 |
---|
245 | 245 | | DETERMINATION MA DE UNDER ITEM (I) OF THIS PARAGRAPH , INCLUDING HOW AN 8 |
---|
246 | 246 | | APPLICATION THAT IS DETERMINED NOT TO SA TISFY THE STANDARD S ITING AND 9 |
---|
247 | 247 | | DESIGN REQUIREMENTS AND STANDARD LICENSI NG CONDITIONS CAN CU RE THE 10 |
---|
248 | 248 | | DEFICIENCY. 11 |
---|
249 | 249 | | |
---|
250 | 250 | | (2) IN MAKING A DETERMINA TION UNDER PARAGRAPH (1) OF THIS 12 |
---|
251 | 251 | | SUBSECTION, THE POWER PLANT RESEARCH PROGRAM SHALL CONSIDE R PUBLIC 13 |
---|
252 | 252 | | COMMENTS RECEIVED BY THE COMMISSION. 14 |
---|
253 | 253 | | |
---|
254 | 254 | | (H) (1) WITHIN 45 DAYS AFTER THE POWER PLANT RESEARCH 15 |
---|
255 | 255 | | PROGRAM MAKES ITS DET ERMINATION UNDER SUB SECTION (G)(1) OF THIS 16 |
---|
256 | 256 | | SECTION, THE COMMISSION SHALL SCHEDULE AN AD MINISTRATIVE MEETING OR AN 17 |
---|
257 | 257 | | EXPEDITED HEARING BE FORE A PUBLIC UTILIT Y LAW JUDGE TO CONSI DER THE 18 |
---|
258 | 258 | | APPLICATION FOR A DGCPCN. 19 |
---|
259 | 259 | | |
---|
260 | 260 | | (2) AT THE ADMINISTRATIVE MEETING OR EXPEDITED HEARING 20 |
---|
261 | 261 | | UNDER PARAGRAPH (1) OF THIS SUBSECTION , THE COMMISSION OR PUBLIC UTILITY 21 |
---|
262 | 262 | | LAW JUDGE SHALL DETE RMINE WHETHER THE PR OPOSED DISTRIBUTED S OLAR 22 |
---|
263 | 263 | | ENERGY GENERATING SY STEM SATISFIES THE S TANDARD SITING AND D ESIGN 23 |
---|
264 | 264 | | REQUIREMENTS AND : 24 |
---|
265 | 265 | | |
---|
266 | 266 | | (I) IF THE COMMISSION OR PUBLIC UTILITY LAW JUDGE 25 |
---|
267 | 267 | | DETERMINES THE PROPO SED DISTRIBUTED S OLAR ENERGY GENERATI NG SYSTEM 26 |
---|
268 | 268 | | SATISFIES THE STANDA RD SITING AND DESIGN REQUIREMENTS , THE COMMISSION 27 |
---|
269 | 269 | | SHALL GRANT A DGCPCN TO THE APPLICANT TO CONSTRUCT THE PROPOS ED 28 |
---|
270 | 270 | | DISTRIBUTED SOLAR GE NERATING STATION SUB JECT TO THE STANDARD LICENSING 29 |
---|
271 | 271 | | CONDITIONS; OR 30 |
---|
272 | 272 | | |
---|
273 | 273 | | (II) IF THE COMMISSION OR PUBLIC UTILITY LAW JUDGE 31 |
---|
274 | 274 | | DETERMINES THE PROPO SED DISTRIBUTED SOLA R ENERGY GENERATING SYSTEM 32 |
---|
275 | 275 | | DOES NOT SATISFY THE STANDARD SITING AND DESIGN REQUIREMENTS , THE 33 |
---|
276 | 276 | | COMMISSION SHALL GIVE THE APPLICANT A WRIT TEN EXPLANATION OF W HY THE 34 |
---|
277 | 277 | | DISTRIBUTED SOLAR ENERG Y GENERATING SYSTEM DOES NOT SATISFY THE 35 |
---|
278 | 278 | | STANDARD SITING AND DESIGN REQUIREMENTS AND HOW THE APPLICAN T CAN 36 SENATE BILL 1025 7 |
---|
279 | 279 | | |
---|
280 | 280 | | |
---|
281 | 281 | | CURE THE DEFICIENCY . 1 |
---|
282 | 282 | | |
---|
283 | 283 | | SECTION 2. AND BE IT FURTHER ENACTED, That this Act may not be applied 2 |
---|
284 | 284 | | or interpreted to have any effect on or application to the construction or modification of any 3 |
---|
285 | 285 | | solar energy generating system for which a certificate of public convenience and necessity 4 |
---|
286 | 286 | | or other required approval was obtained before the effective date of the regulations adopted 5 |
---|
287 | 287 | | by the Public Service Commission under § 7–207.3(c) of the Public Utilities Article, as 6 |
---|
288 | 288 | | enacted by Section 1 of this Act. 7 |
---|
289 | 289 | | |
---|
290 | 290 | | SECTION 3. AND BE IT FURTHER ENACTED, That, this Act shall take effect July 8 |
---|
291 | 291 | | 1, 2024. 9 |
---|
292 | 292 | | |
---|