1 | 1 | | |
---|
2 | 2 | | |
---|
3 | 3 | | EXPLANATION: CAPITALS INDICATE MAT TER ADDED TO EXISTING LAW . |
---|
4 | 4 | | [Brackets] indicate matter deleted from existing law. |
---|
5 | 5 | | *hb0976* |
---|
6 | 6 | | |
---|
7 | 7 | | HOUSE BILL 976 |
---|
8 | 8 | | M3 5lr2977 |
---|
9 | 9 | | CF SB 637 |
---|
10 | 10 | | By: Delegates Arentz, Ghrist, and Jacobs |
---|
11 | 11 | | Introduced and read first time: January 31, 2025 |
---|
12 | 12 | | Assigned to: Environment and Transportation |
---|
13 | 13 | | |
---|
14 | 14 | | A BILL ENTITLED |
---|
15 | 15 | | |
---|
16 | 16 | | AN ACT concerning 1 |
---|
17 | 17 | | |
---|
18 | 18 | | State and Private Wetlands – Nonwater–Dependent Project – Definition 2 |
---|
19 | 19 | | |
---|
20 | 20 | | FOR the purpose of establishing that a certain vessel is not a nonwater–dependent project 3 |
---|
21 | 21 | | for the purpose of certain provisions of law regarding construction on State or private 4 |
---|
22 | 22 | | wetlands; and generally relating to State and private wetlands. 5 |
---|
23 | 23 | | |
---|
24 | 24 | | BY repealing and reenacting, without amendments, 6 |
---|
25 | 25 | | Article – Environment 7 |
---|
26 | 26 | | Section 16–101(a) and 16–104(b) and (c) 8 |
---|
27 | 27 | | Annotated Code of Maryland 9 |
---|
28 | 28 | | (2014 Replacement Volume and 2024 Supplement) 10 |
---|
29 | 29 | | |
---|
30 | 30 | | BY repealing and reenacting, with amendments, 11 |
---|
31 | 31 | | Article – Environment 12 |
---|
32 | 32 | | Section 16–101(i) 13 |
---|
33 | 33 | | Annotated Code of Maryland 14 |
---|
34 | 34 | | (2014 Replacement Volume and 2024 Supplement) 15 |
---|
35 | 35 | | |
---|
36 | 36 | | SECTION 1. BE IT ENACTED BY THE GENERAL ASSEMBLY OF MARYLAND, 16 |
---|
37 | 37 | | That the Laws of Maryland read as follows: 17 |
---|
38 | 38 | | |
---|
39 | 39 | | Article – Environment 18 |
---|
40 | 40 | | |
---|
41 | 41 | | 16–101. 19 |
---|
42 | 42 | | |
---|
43 | 43 | | (a) In this title the following words have the meanings indicated. 20 |
---|
44 | 44 | | |
---|
45 | 45 | | (i) (1) “Nonwater–dependent project” means a temporary or permanent 21 |
---|
46 | 46 | | structure that, by reason of its intrinsic nature, use, or operation, does not require location 22 |
---|
47 | 47 | | in, on, or over State or private wetlands. 23 |
---|
48 | 48 | | 2 HOUSE BILL 976 |
---|
49 | 49 | | |
---|
50 | 50 | | |
---|
51 | 51 | | (2) “Nonwater–dependent project” includes: 1 |
---|
52 | 52 | | |
---|
53 | 53 | | (i) A dwelling unit on a pier; 2 |
---|
54 | 54 | | |
---|
55 | 55 | | (ii) A restaurant, a shop, an office, or any other commercial building 3 |
---|
56 | 56 | | or use on a pier; 4 |
---|
57 | 57 | | |
---|
58 | 58 | | (iii) A temporary or permanent roof or covering on a pier; 5 |
---|
59 | 59 | | |
---|
60 | 60 | | (iv) A pier used to support a nonwater–dependent use; and 6 |
---|
61 | 61 | | |
---|
62 | 62 | | (v) A small–scale renewable energy system on a pier, including: 7 |
---|
63 | 63 | | |
---|
64 | 64 | | 1. A solar energy system and its photovoltaic cells, solar 8 |
---|
65 | 65 | | panels, or other necessary equipment; 9 |
---|
66 | 66 | | |
---|
67 | 67 | | 2. A geothermal energy system and its geothermal heat 10 |
---|
68 | 68 | | exchanger or other necessary equipment; and 11 |
---|
69 | 69 | | |
---|
70 | 70 | | 3. A wind energy system and its wind turbine, tower, base, 12 |
---|
71 | 71 | | or other necessary equipment. 13 |
---|
72 | 72 | | |
---|
73 | 73 | | (3) “Nonwater–dependent project” does not include: 14 |
---|
74 | 74 | | |
---|
75 | 75 | | (i) A fuel pump or other fuel–dispensing equipment on a pier; 15 |
---|
76 | 76 | | |
---|
77 | 77 | | (ii) A sanitary sewage pump or other wastewater removal equipment 16 |
---|
78 | 78 | | on a pier; 17 |
---|
79 | 79 | | |
---|
80 | 80 | | (iii) A pump, a pipe, or any other equipment attached to a pier and 18 |
---|
81 | 81 | | associated with a shellfish nursery operation under a permit issued by the Department of 19 |
---|
82 | 82 | | Natural Resources under § 4–11A–23 of the Natural Resources Article; [or] 20 |
---|
83 | 83 | | |
---|
84 | 84 | | (iv) An office on a pier for managing marina operations, including 21 |
---|
85 | 85 | | monitoring vessel traffic, registering vessels, providing docking services, and housing 22 |
---|
86 | 86 | | electrical or emergency equipment related to marina operations; OR 23 |
---|
87 | 87 | | |
---|
88 | 88 | | (V) A VESSEL REGISTERED UNDER TITLE 8, SUBTITLE 7 OF THE 24 |
---|
89 | 89 | | NATURAL RESOURCES ARTICLE, REGARDLESS OF HOW TH E VESSEL IS USED OR 25 |
---|
90 | 90 | | OPERATED. 26 |
---|
91 | 91 | | |
---|
92 | 92 | | 16–104. 27 |
---|
93 | 93 | | |
---|
94 | 94 | | (b) (1) Except as provided in paragraphs (2) and (3) of this subsection and 28 |
---|
95 | 95 | | notwithstanding any other provision of law, the Board of Public Works may not issue a 29 |
---|
96 | 96 | | license to authorize a nonwater–dependent project located on State wetlands. 30 HOUSE BILL 976 3 |
---|
97 | 97 | | |
---|
98 | 98 | | |
---|
99 | 99 | | |
---|
100 | 100 | | (2) The Board of Public Works may issue a license to authorize a 1 |
---|
101 | 101 | | nonwater–dependent project located on State wetlands if the project: 2 |
---|
102 | 102 | | |
---|
103 | 103 | | (i) 1. Involves a commercial activity that is permitted as a 3 |
---|
104 | 104 | | secondary or accessory use to a permitted primary commercial use; 4 |
---|
105 | 105 | | |
---|
106 | 106 | | 2. Is not located on a pier that is attached to residentially, 5 |
---|
107 | 107 | | institutionally, or industrially used property; 6 |
---|
108 | 108 | | |
---|
109 | 109 | | 3. Avoids and minimizes impacts to State or private 7 |
---|
110 | 110 | | wetlands and other aquatic resources; 8 |
---|
111 | 111 | | |
---|
112 | 112 | | 4. Is located in: 9 |
---|
113 | 113 | | |
---|
114 | 114 | | A. An intensely developed area and the project is authorized 10 |
---|
115 | 115 | | under a program amendment to a local jurisdiction’s critical area program approved on or 11 |
---|
116 | 116 | | after July 1, 2013, if the approved program amendment includes necessary changes to the 12 |
---|
117 | 117 | | local jurisdiction’s zoning, subdivision, and other ordinances so as to be consistent with or 13 |
---|
118 | 118 | | more restrictive than the requirements provided under this paragraph; or 14 |
---|
119 | 119 | | |
---|
120 | 120 | | B. An area that has been excluded from a local critical area 15 |
---|
121 | 121 | | program if the exclusion has been adopted or approved by the Critical Area Commission for 16 |
---|
122 | 122 | | the Chesapeake and Atlantic Coastal Bays; 17 |
---|
123 | 123 | | |
---|
124 | 124 | | 5. Is approved by the local planning and zoning authorities 18 |
---|
125 | 125 | | after the local jurisdiction’s program amendment under item 4A of this item, if applicable, 19 |
---|
126 | 126 | | has been approved; 20 |
---|
127 | 127 | | |
---|
128 | 128 | | 6. Allows or enhances public access to State wetlands; 21 |
---|
129 | 129 | | |
---|
130 | 130 | | 7. Does not expand beyond the length, width, or channelward 22 |
---|
131 | 131 | | encroachment of the pier on which the project is constructed; 23 |
---|
132 | 132 | | |
---|
133 | 133 | | 8. Has a height of up to 18 feet unless the project is located 24 |
---|
134 | 134 | | at a marina and the Secretary recommends additional height; 25 |
---|
135 | 135 | | |
---|
136 | 136 | | 9. Is up to 1,000 square feet in total area; 26 |
---|
137 | 137 | | |
---|
138 | 138 | | 10. Is not located in, on, or over vegetated tidal wetlands, 27 |
---|
139 | 139 | | submerged aquatic vegetation, a natural oyster bar, a public shellfish fishery area, a Yates 28 |
---|
140 | 140 | | Bar, or an area with rare, threatened, or endangered species or species in need of 29 |
---|
141 | 141 | | conservation; and 30 |
---|
142 | 142 | | |
---|
143 | 143 | | 11. Does not adversely impact a fish spawning or nursery area 31 |
---|
144 | 144 | | or an historic waterfowl staging area; or 32 |
---|
145 | 145 | | 4 HOUSE BILL 976 |
---|
146 | 146 | | |
---|
147 | 147 | | |
---|
148 | 148 | | (ii) 1. Is located on a pier that was in existence on or before 1 |
---|
149 | 149 | | December 31, 2012; 2 |
---|
150 | 150 | | |
---|
151 | 151 | | 2. Satisfies all of the requirements under item (i)1 through 8 3 |
---|
152 | 152 | | of this paragraph; and 4 |
---|
153 | 153 | | |
---|
154 | 154 | | 3. If applicable, has a temporary or permanent roof or 5 |
---|
155 | 155 | | covering that is up to 1,000 square feet in total area. 6 |
---|
156 | 156 | | |
---|
157 | 157 | | (3) (i) The Board of Public Works may issue a license to authorize a 7 |
---|
158 | 158 | | nonwater–dependent project for a small–scale renewable energy system on a pier located 8 |
---|
159 | 159 | | on State wetlands if the project: 9 |
---|
160 | 160 | | |
---|
161 | 161 | | 1. Involves the installation or placement of a small–scale 10 |
---|
162 | 162 | | renewable energy system that is permitted as a secondary or accessory use on a pier that 11 |
---|
163 | 163 | | is authorized under this title; 12 |
---|
164 | 164 | | |
---|
165 | 165 | | 2. Avoids and minimizes impacts to State or private 13 |
---|
166 | 166 | | wetlands and other aquatic resources; 14 |
---|
167 | 167 | | |
---|
168 | 168 | | 3. Is located in: 15 |
---|
169 | 169 | | |
---|
170 | 170 | | A. The Chesapeake and Atlantic Coastal Bays Critical Area 16 |
---|
171 | 171 | | and the project is authorized under a program amendment to a local jurisdiction’s critical 17 |
---|
172 | 172 | | area program approved on or after July 1, 2013, if the approved program amendment 18 |
---|
173 | 173 | | includes necessary changes to the local jurisdiction’s zoning, subdivision, and other 19 |
---|
174 | 174 | | ordinances so as to be consistent with or more restrictive than the requirements provided 20 |
---|
175 | 175 | | under this paragraph; or 21 |
---|
176 | 176 | | |
---|
177 | 177 | | B. An area that has been excluded from a local critical area 22 |
---|
178 | 178 | | program if the exclusion has been adopted or approved by the Critical Area Commission for 23 |
---|
179 | 179 | | the Chesapeake and Atlantic Coastal Bays; 24 |
---|
180 | 180 | | |
---|
181 | 181 | | 4. Is approved by the local planning and zoning authorities 25 |
---|
182 | 182 | | after the local jurisdiction’s program amendment under item 3A of this subparagraph, if 26 |
---|
183 | 183 | | applicable, has been approved; 27 |
---|
184 | 184 | | |
---|
185 | 185 | | 5. Is not located in, on, or over vegetated tidal wetlands, 28 |
---|
186 | 186 | | submerged aquatic vegetation, a natural oyster bar, a public shellfish fishery area, a Yates 29 |
---|
187 | 187 | | Bar, or an area with rare, threatened, or endangered species or species in need of 30 |
---|
188 | 188 | | conservation; and 31 |
---|
189 | 189 | | |
---|
190 | 190 | | 6. Does not adversely impact a fish spawning or nursery area 32 |
---|
191 | 191 | | or an historic waterfowl staging area. 33 |
---|
192 | 192 | | |
---|
193 | 193 | | (ii) A license issued under subparagraph (i) of this paragraph may 34 |
---|
194 | 194 | | include the installation or placement of: 35 HOUSE BILL 976 5 |
---|
195 | 195 | | |
---|
196 | 196 | | |
---|
197 | 197 | | |
---|
198 | 198 | | 1. A solar energy system attached to a pier if the device or 1 |
---|
199 | 199 | | equipment associated with that system does not extend more than: 2 |
---|
200 | 200 | | |
---|
201 | 201 | | A. 4 feet above or 18 inches below the deck of the pier; or 3 |
---|
202 | 202 | | |
---|
203 | 203 | | B. 1 foot beyond the length or width of the pier; 4 |
---|
204 | 204 | | |
---|
205 | 205 | | 2. A solar energy system attached to a piling if there is only 5 |
---|
206 | 206 | | one solar panel per boat slip; 6 |
---|
207 | 207 | | |
---|
208 | 208 | | 3. A solar energy system attached to a boathouse roof if the 7 |
---|
209 | 209 | | device or equipment associated with that system does not extend beyond the length, width, 8 |
---|
210 | 210 | | or height of the boathouse roof; 9 |
---|
211 | 211 | | |
---|
212 | 212 | | 4. A closed–loop geothermal heat exchanger under a pier if 10 |
---|
213 | 213 | | the geothermal heat exchanger or any associated devices or equipment do not: 11 |
---|
214 | 214 | | |
---|
215 | 215 | | A. Extend beyond the length, width, or channelward 12 |
---|
216 | 216 | | encroachment of the pier; 13 |
---|
217 | 217 | | |
---|
218 | 218 | | B. Deleteriously alter long shore drift; or 14 |
---|
219 | 219 | | |
---|
220 | 220 | | C. Cause significant individual or cumulative thermal 15 |
---|
221 | 221 | | impacts to aquatic resources; or 16 |
---|
222 | 222 | | |
---|
223 | 223 | | 5. A wind energy system attached to a pier if there is only 17 |
---|
224 | 224 | | one wind energy system per pier for which: 18 |
---|
225 | 225 | | |
---|
226 | 226 | | A. The height from the deck of the pier to the blade extended 19 |
---|
227 | 227 | | at its highest point is up to 12 feet; 20 |
---|
228 | 228 | | |
---|
229 | 229 | | B. The rotor diameter of the wind turbine is up to 4 feet; and 21 |
---|
230 | 230 | | |
---|
231 | 231 | | C. The setbacks of the wind energy system from the nearest 22 |
---|
232 | 232 | | property line and from the channelward edge of the pier to which that system is attached 23 |
---|
233 | 233 | | are at least 1.5 times the total height of the system from its base to the blade extended at 24 |
---|
234 | 234 | | its highest point. 25 |
---|
235 | 235 | | |
---|
236 | 236 | | (c) (1) Except as provided in paragraph (2) of this subsection and 26 |
---|
237 | 237 | | notwithstanding any other provision of law, the Secretary may not issue a permit to 27 |
---|
238 | 238 | | authorize a nonwater–dependent project located on private wetlands. 28 |
---|
239 | 239 | | |
---|
240 | 240 | | (2) Except for the public access requirement under subsection (b)(2)(i)6 of 29 |
---|
241 | 241 | | this section, the Secretary may issue a permit to authorize a nonwater–dependent project 30 |
---|
242 | 242 | | located on private wetlands if the project satisfies all of the requirements under subsection 31 |
---|
243 | 243 | | (b)(2) or (3) of this section. 32 6 HOUSE BILL 976 |
---|
244 | 244 | | |
---|
245 | 245 | | |
---|
246 | 246 | | |
---|
247 | 247 | | SECTION 2. AND BE IT FURTHER ENACTED, That this Act shall take effect July 1 |
---|
248 | 248 | | 1, 2025. 2 |
---|