11 1.1 A bill for an act​
22 1.2 relating to environment; modifying provisions for permitting efficiency; amending​
33 1.3 Minnesota Statutes 2024, sections 115.542; 116.03, subdivision 2b; 116.07,​
44 1.4 subdivision 4a.​
55 1.5BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:​
66 1.6 Section 1. Minnesota Statutes 2024, section 115.542, is amended to read:​
77 1.7 115.542 NOTICE REQUIREMENTS FOR PUBLICLY OWNED WASTEWATER​
88 1.8TREATMENT FACILITIES.​
99 1.9 Subdivision 1.Definitions.For the purpose of this section, the following terms have​
1010 1.10the meanings given:​
1111 1.11 (1) "permit" means a national pollutant discharge elimination system (NPDES) permit​
1212 1.12or state disposal system (SDS) permit; and​
1313 1.13 (2) "permit applicant" means a person or entity submitting an application for a new​
1414 1.14permit or renewal, modification, or revocation of an existing permit for a publicly owned​
1515 1.15wastewater treatment facility.​
1616 1.16 Subd. 2.Applicability.This section applies to all draft permits and permits for publicly​
1717 1.17owned wastewater treatment facilities for which the commissioner of the Pollution Control​
1818 1.18Agency makes a preliminary determination whether to issue or deny.​
1919 1.19 Subd. 3.Prepublic notice review requirements.Unless waived by the permit applicant,​
2020 1.20the commissioner of the Pollution Control Agency must provide a permit applicant with a​
2121 1.21copy of the draft permit and any fact sheets required by agency rules at least 30 days before​
2222 1.22the distribution and public notice of the permit application and preliminary determination.​
2323 1​Section 1.​
2424 REVISOR EB/ES 25-00354​01/15/25 ​
2525 State of Minnesota​
2626 This Document can be made available​
2727 in alternative formats upon request​
2828 HOUSE OF REPRESENTATIVES​
2929 H. F. No. 1208​
3030 NINETY-FOURTH SESSION​
3131 Authored by Fischer​02/19/2025​
3232 The bill was read for the first time and referred to the Committee on Environment and Natural Resources Finance and Policy​ 2.1 Subd. 4.Permitting efficiency Public notice requirements.The commissioner must​
3333 2.2prepare and issue a public notice of a completed application and the commissioner's​
3434 2.3preliminary determination as to whether the permit should be issued or denied. The public​
3535 2.4comment period must be at least 60 days for permit applications under this section but may​
3636 2.5be reduced to 30 days if:​
3737 2.6 (1) a request for the reduction is made by the permit applicant; and​
3838 2.7 (2) the commissioner approves the request based on consideration of public or Tribal​
3939 2.8interest in the permit action.​
4040 2.9 Subd. 5.Permitting efficiency.Notwithstanding section 116.03, it is the goal of the​
4141 2.10state that tier 2 permits for publicly owned wastewater treatment facilities be issued or​
4242 2.11denied within 210 days following submission of a permit application.​
4343 2.12 Sec. 2. Minnesota Statutes 2024, section 116.03, subdivision 2b, is amended to read:​
4444 2.13 Subd. 2b.Permitting efficiency.(a) It is the goal of the state that environmental and​
4545 2.14resource management permits be issued or denied within 90 days for tier 1 permits or 150​
4646 2.15days for tier 2 permits following submission of a permit application. The commissioner of​
4747 2.16the Pollution Control Agency shall establish management systems designed to achieve the​
4848 2.17goal. For the purposes of this section, "tier 1 permits" are permits that do not require​
4949 2.18individualized actions or public comment periods, and "tier 2 permits" are permits that​
5050 2.19require individualized actions or public comment periods.​
5151 2.20 (b) The commissioner shall prepare an annual permitting efficiency report that includes​
5252 2.21statistics on meeting the goal in paragraph (a) and the criteria for tier 2 by permit categories.​
5353 2.22The report is due August 1 each year. For permit applications that have not met the goal,​
5454 2.23the report must state the reasons for not meeting the goal. In stating the reasons for not​
5555 2.24meeting the goal, the commissioner shall separately identify delays caused by the​
5656 2.25responsiveness of the proposer, lack of staff, scientific or technical disagreements, or the​
5757 2.26level of public engagement. The report must specify the number of days from initial​
5858 2.27submission of the application to the day of determination that the application is complete.​
5959 2.28The report must aggregate the data for the year and assess whether program or system​
6060 2.29changes are necessary to achieve the goal. The report must be posted on the agency's website​
6161 2.30and submitted to the governor and the chairs and ranking minority members of the house​
6262 2.31of representatives and senate committees having jurisdiction over environment policy and​
6363 2.32finance.​
6464 2​Sec. 2.​
6565 REVISOR EB/ES 25-00354​01/15/25 ​ 3.1 (c) The commissioner shall allow electronic submission of environmental review and​
6666 3.2permit documents to the agency.​
6767 3.3 (d) Within 30 business days of application for a permit subject to paragraph (a), the​
6868 3.4commissioner of the Pollution Control Agency shall notify the permit applicant, in writing,​
6969 3.5whether the application is complete or incomplete. If the commissioner determines that an​
7070 3.6application is incomplete, the notice to the applicant must enumerate all deficiencies, citing​
7171 3.7specific provisions of the applicable rules and statutes, and advise the applicant on how the​
7272 3.8deficiencies can be remedied. If the commissioner determines that the application is complete,​
7373 3.9the notice must confirm the application's tier 1 or tier 2 permit status. If the commissioner​
7474 3.10believes that a complete application for a tier 2 construction permit cannot be issued within​
7575 3.11the 150-day goal, the commissioner must provide notice to the applicant with the​
7676 3.12commissioner's notice that the application is complete and, upon request of the applicant,​
7777 3.13provide the permit applicant with a schedule estimating when the agency will begin drafting​
7878 3.14the permit and issue the public notice of the draft permit. This paragraph does not apply to​
7979 3.15an application for a permit that is subject to a grant or loan agreement under chapter 446A.​
8080 3.16 (e) If, after notifying the permit applicant that the application is complete, the​
8181 3.17commissioner determines that additional information is needed, the commissioner must​
8282 3.18notify the applicant. Upon notice under this paragraph, counting days toward the 90- or​
8383 3.19150-day goal described in paragraph (a) stops until the applicant has responded with the​
8484 3.20additional information. Once the applicant has responded with all the additional information​
8585 3.21required, counting resumes from where it stopped. The applicant has 30 business days to​
8686 3.22provide the additional information to the commissioner, but the commissioner may extend​
8787 3.23the time upon the applicant's request.​
8888 3.24 (e) (f) For purposes of this subdivision, "permit professional" means an individual not​
8989 3.25employed by the Pollution Control Agency who:​
9090 3.26 (1) has a professional license issued by the state of Minnesota in the subject area of the​
9191 3.27permit;​
9292 3.28 (2) has at least ten years of experience in the subject area of the permit; and​
9393 3.29 (3) abides by the duty of candor applicable to employees of the Pollution Control Agency​
9494 3.30under agency rules and complies with all applicable requirements under chapter 326.​
9595 3.31 (f) (g) Upon the agency's request, an applicant relying on a permit professional must​
9696 3.32participate in a meeting with the agency before submitting an application:​
9797 3​Sec. 2.​
9898 REVISOR EB/ES 25-00354​01/15/25 ​ 4.1 (1) at least two weeks prior to the preapplication meeting, the applicant must submit at​
9999 4.2least the following:​
100100 4.3 (i) project description, including, but not limited to, scope of work, primary emissions​
101101 4.4points, discharge outfalls, and water intake points;​
102102 4.5 (ii) location of the project, including county, municipality, and location on the site;​
103103 4.6 (iii) business schedule for project completion; and​
104104 4.7 (iv) other information requested by the agency at least four weeks prior to the scheduled​
105105 4.8meeting; and​
106106 4.9 (2) during the preapplication meeting, the agency shall provide for the applicant at least​
107107 4.10the following:​
108108 4.11 (i) an overview of the permit review program;​
109109 4.12 (ii) a determination of which specific application or applications will be necessary to​
110110 4.13complete the project;​
111111 4.14 (iii) a statement notifying the applicant if the specific permit being sought requires a​
112112 4.15mandatory public hearing or comment period;​
113113 4.16 (iv) a review of the timetable established in the permit review program for the specific​
114114 4.17permit being sought; and​
115115 4.18 (v) a determination of what information must be included in the application, including​
116116 4.19a description of any required modeling or testing.​
117117 4.20 (g) (h) The applicant may select a permit professional to undertake the preparation of​
118118 4.21the permit application and draft permit.​
119119 4.22 (h) (i) If a preapplication meeting was held, the agency shall, within seven business days​
120120 4.23of receipt of an application, notify the applicant and submitting permit professional that the​
121121 4.24application is complete or is denied, specifying the deficiencies of the application.​
122122 4.25 (i) (j) Upon receipt of notice that the application is complete, the permit professional​
123123 4.26shall submit to the agency a timetable for submitting a draft permit. The permit professional​
124124 4.27shall submit a draft permit on or before the date provided in the timetable. Within 60 days​
125125 4.28after the close of the public comment period, the commissioner shall notify the applicant​
126126 4.29whether the permit can be issued.​
127127 4.30 (j) (k) Nothing in this section shall be construed to modify:​
128128 4​Sec. 2.​
129129 REVISOR EB/ES 25-00354​01/15/25 ​ 5.1 (1) any requirement of law that is necessary to retain federal delegation to or assumption​
130130 5.2by the state; or​
131131 5.3 (2) the authority to implement a federal law or program.​
132132 5.4 (k) (l) The permit application and draft permit shall identify or include as an appendix​
133133 5.5all studies and other sources of information used to substantiate the analysis contained in​
134134 5.6the permit application and draft permit. The commissioner shall request additional studies,​
135135 5.7if needed, and the permit applicant shall submit all additional studies and information​
136136 5.8necessary for the commissioner to perform the commissioner's responsibility to review,​
137137 5.9modify, and determine the completeness of the application and approve the draft permit.​
138138 5.10 Sec. 3. Minnesota Statutes 2024, section 116.07, subdivision 4a, is amended to read:​
139139 5.11 Subd. 4a.Permits.(a) The Pollution Control Agency may issue, continue in effect or​
140140 5.12deny permits, under such conditions as it may prescribe for the prevention of pollution, for​
141141 5.13the emission of air contaminants, or for the installation or operation of any emission facility,​
142142 5.14air contaminant treatment facility, treatment facility, potential air contaminant storage​
143143 5.15facility, or storage facility, or any part thereof, or for the sources or emissions of noise​
144144 5.16pollution.​
145145 5.17 (b) The Pollution Control Agency may also issue, continue in effect or deny permits,​
146146 5.18under such conditions as it may prescribe for the prevention of pollution, for the storage,​
147147 5.19collection, transportation, processing, or disposal of waste, or for the installation or operation​
148148 5.20of any system or facility, or any part thereof, related to the storage, collection, transportation,​
149149 5.21processing, or disposal of waste.​
150150 5.22 (c) The agency may not issue a permit to a facility without analyzing and considering​
151151 5.23the cumulative levels and effects of past and current environmental pollution from all sources​
152152 5.24on the environment and residents of the geographic area within which the facility's emissions​
153153 5.25are likely to be deposited, provided that the facility is located in a community in a city of​
154154 5.26the first class in Hennepin County that meets all of the following conditions:​
155155 5.27 (1) is within a half mile of a site designated by the federal government as an EPA​
156156 5.28superfund site due to residential arsenic contamination;​
157157 5.29 (2) a majority of the population are low-income persons of color and American Indians;​
158158 5.30 (3) a disproportionate percent of the children have childhood lead poisoning, asthma,​
159159 5.31or other environmentally related health problems;​
160160 5​Sec. 3.​
161161 REVISOR EB/ES 25-00354​01/15/25 ​ 6.1 (4) is located in a city that has experienced numerous air quality alert days of dangerous​
162162 6.2air quality for sensitive populations between February 2007 and February 2008; and​
163163 6.3 (5) is located near the junctions of several heavily trafficked state and county highways​
164164 6.4and two one-way streets which carry both truck and auto traffic.​
165165 6.5 (d) The Pollution Control Agency may revoke or modify any permit issued under this​
166166 6.6subdivision and section 116.081 whenever it is necessary, in the opinion of the agency, to​
167167 6.7prevent or abate pollution.​
168168 6.8 (e) The Pollution Control Agency has the authority for approval over the siting, expansion,​
169169 6.9or operation of a solid waste facility with regard to environmental issues. However, the​
170170 6.10agency's issuance of a permit does not release the permittee from any liability, penalty, or​
171171 6.11duty imposed by any applicable county ordinances. Nothing in this chapter precludes, or​
172172 6.12shall be construed to preclude, a county from enforcing land use controls, regulations, and​
173173 6.13ordinances existing at the time of the permit application and adopted pursuant to Minnesota​
174174 6.14Statutes 2020, sections 366.10 to 366.181, or sections 394.21 to 394.37, or 462.351 to​
175175 6.15462.365, with regard to the siting, expansion, or operation of a solid waste facility.​
176176 6.16 (f) Except as prohibited by federal law, a person may commence construction,​
177177 6.17reconstruction, replacement, or modification of any facility prior to the issuance of a​
178178 6.18construction permit by the agency.​
179179 6.19 (g) For the purposes of this subdivision, the Pollution Control Agency may require the​
180180 6.20owners and operators of any emission facility, air containment treatment facility, treatment​
181181 6.21facility, potential air containment storage facility, or storage facility, or any part thereof, to​
182182 6.22conduct air dispersion modeling of air contaminants.​
183183 6​Sec. 3.​
184184 REVISOR EB/ES 25-00354​01/15/25 ​