Minnesota 2025-2026 Regular Session

Minnesota House Bill HF1234 Latest Draft

Bill / Introduced Version Filed 02/19/2025

                            1.1	A bill for an act​
1.2 relating to state government; requiring payment transparency in public contracts;​
1.3 amending Minnesota Statutes 2024, sections 15.72, subdivision 2, by adding a​
1.4 subdivision; 337.10, subdivision 4.​
1.5BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:​
1.6 Section 1. Minnesota Statutes 2024, section 15.72, subdivision 2, is amended to read:​
1.7 Subd. 2.Retainage.(a) A public contracting agency may reserve as retainage from any​
1.8progress payment on a public contract for a public improvement an amount not to exceed​
1.9five percent of the payment. A public contracting agency may reduce the amount of the​
1.10retainage and may eliminate retainage on any monthly contract payment if, in the agency's​
1.11opinion, the work is progressing satisfactorily.​
1.12 (b) The public contracting agency must release all retainage no later than 60 days after​
1.13substantial completion, subject to the terms of this subdivision. If the public contracting​
1.14agency reduces the amount of retainage, the contractor must reduce retainage for any​
1.15subcontractors at the same rate.​
1.16 (c) A contractor on a public contract for a public improvement must pay all remaining​
1.17retainage to its subcontractors no later than ten days after receiving payment of retainage​
1.18from the public contracting agency, unless there is a dispute about the work under a​
1.19subcontract. If there is a dispute about the work under a subcontract, the contractor must​
1.20pay out retainage to any subcontractor whose work is not involved in the dispute, and must​
1.21provide a written statement detailing the amount and reason for the withholding to the​
1.22affected subcontractor.​
1​Section 1.​
REVISOR SGS/EN 25-02075​02/07/25 ​
State of Minnesota​
This Document can be made available​
in alternative formats upon request​
HOUSE OF REPRESENTATIVES​
H. F. No.  1234​
NINETY-FOURTH SESSION​
Authored by Scott, Hollins and Mekeland​02/20/2025​
The bill was read for the first time and referred to the Committee on State Government Finance and Policy​ 2.1 (d) Upon written request of a subcontractor, the public contracting agency shall notify​
2.2the subcontractor of a progress payment, retainage payment, or final payment made to the​
2.3contractor.​
2.4 (e) After substantial completion, a public contracting agency may withhold no more​
2.5than:​
2.6 (1) 250 percent of the cost to correct or complete work known at the time of substantial​
2.7completion; and​
2.8 (2) one percent of the value of the contract or $500, whichever is greater, pending​
2.9completion and submission of all final paperwork by the contractor or subcontractor. For​
2.10purposes of this subdivision, "final paperwork" means documents required to fulfill​
2.11contractual obligations, including, but not limited to, operation manuals, payroll documents​
2.12for projects subject to prevailing wage requirements, and the withholding exemption​
2.13certificate required by section 270C.66.​
2.14If the public contracting agency withholds payment under this paragraph, the public​
2.15contracting agency must promptly provide a written statement detailing the amount and​
2.16basis of withholding to the contractor. The public contracting agency and contractor must​
2.17provide a copy of this statement to any subcontractor that requests it. Any amounts withheld​
2.18under clause (1) must be paid within 60 days after completion of the work. Any amounts​
2.19withheld under clause (2) must be paid within 60 days after submission of all final paperwork.​
2.20 (f) As used in this subdivision, "substantial completion" shall be determined as provided​
2.21in section 541.051, subdivision 1, paragraph (a). For construction, reconstruction, or​
2.22improvement of streets and highways, including bridges, substantial completion means the​
2.23date when construction-related traffic devices and ongoing inspections are no longer required.​
2.24 (g) Withholding retainage for warranty work is prohibited. This provision does not waive​
2.25any rights for warranty claims.​
2.26 (h) For a project funded with federal or state aid, the public contracting agency is not​
2.27required to pay that portion of the contract funded by federal or state aid until the federal​
2.28or state aid payments have been received.​
2.29 (i) Nothing in this section requires payment for a portion of a contract that is not complete​
2.30or for which an invoice has not been submitted. A contract, management system, or procedure​
2.31that restricts, delays, or prohibits a party from submitting an invoice is contrary to public​
2.32policy and is void and unenforceable.​
2​Section 1.​
REVISOR SGS/EN 25-02075​02/07/25 ​ 3.1 Sec. 2. Minnesota Statutes 2024, section 15.72, is amended by adding a subdivision to​
3.2read:​
3.3 Subd. 4.Notification to contractors and subcontractors of payment.(a) A public​
3.4contracting agency must notify contractors and subcontractors on a public improvement​
3.5project of every tier of any progress payment, retainage payment, final payment, or any​
3.6other payment made by the public contracting agency.​
3.7 (b) The notification must include:​
3.8 (1) the amount of the payment;​
3.9 (2) the date the payment was made;​
3.10 (3) the name and address of the party receiving the payment;​
3.11 (4) at least one of the following items:​
3.12 (i) an identification of the scope of work the payment relates to;​
3.13 (ii) the percentage of overall project completion, the percentage of completion for scope​
3.14of work the payment relates to, and a general description of what work the amount paid​
3.15relates to; or​
3.16 (iii) a copy of a payment application submitted by a contractor or subcontractor that the​
3.17payment issued relates to; and​
3.18 (5) the reasons for withholding of payment and any retainage terms applied to the​
3.19payment.​
3.20 (c) The public contracting agency must provide the notification in this subdivision to​
3.21contractors and subcontractors of every tier within three business days of making the​
3.22payment.​
3.23 (d) No cost or fees shall be charged to the contractor or subcontractor for the notice​
3.24provided to them.​
3.25 Sec. 3. Minnesota Statutes 2024, section 337.10, subdivision 4, is amended to read:​
3.26 Subd. 4.Progress payments and retainages.(a) Unless the building and construction​
3.27contract provides otherwise, the owner or other persons making payments under the contract​
3.28must make progress payments monthly as the work progresses. Payments shall be based​
3.29upon estimates of work completed as approved by the owner or the owner's agent. A progress​
3.30payment shall not be considered acceptance or approval of any work or waiver of any defects​
3.31therein.​
3​Sec. 3.​
REVISOR SGS/EN 25-02075​02/07/25 ​ 4.1 (b) Retainage on a building and construction contract may not exceed five percent. An​
4.2owner or owner's agent may reduce the amount of retainage and may eliminate retainage​
4.3on any monthly contract payment if, in the owner's opinion, the work is progressing​
4.4satisfactorily. If the owner reduces the amount of retainage, the contractor must reduce​
4.5retainage for any subcontractors at the same rate. Nothing in this subdivision is intended to​
4.6require that retainage be withheld in any building or construction contract.​
4.7 (c) The owner or the owner's agent must release all retainage no later than 60 days after​
4.8substantial completion subject to the terms of this subdivision. For purposes of this​
4.9subdivision, "substantial completion" shall be determined as provided in section 541.051,​
4.10subdivision 1, paragraph (a).​
4.11 (d) A contractor must pay all remaining retainage to its subcontractors no later than ten​
4.12days after receiving payment of retainage, unless there is a dispute about the work under a​
4.13subcontract, in which case the contractor must pay out retainage to any party whose work​
4.14is not involved in the dispute. If there is a dispute about the work under a subcontract, the​
4.15contractor must pay out retainage to any subcontractor whose work is not involved in the​
4.16dispute, and must provide a written statement detailing the amount and reason for the​
4.17withholding to the affected subcontractor.​
4.18 (e) After substantial completion, an owner or owner's agent may withhold no more than:​
4.19 (1) 250 percent of the cost to correct or complete work known at the time of substantial​
4.20completion; and​
4.21 (2) one percent of the value of the contract or $500, whichever is greater, pending​
4.22completion and submission of all final paperwork by the contractor or subcontractor. For​
4.23purposes of this subdivision, "final paperwork" means documents required to fulfill​
4.24contractual obligations, including, but not limited to, operation manuals, payroll documents​
4.25for projects subject to prevailing wage requirements, and the withholding exemption​
4.26certificate required by section 270C.66.​
4.27If the owner or the owner's agent withholds payment under this paragraph, the owner or the​
4.28owner's agent must promptly provide a written statement detailing the amount and basis of​
4.29withholding to the contractor. The owner or the owner's agent and the contractor must​
4.30provide a copy of this statement to any subcontractor that requests it. Any amounts withheld​
4.31under clause (1) must be paid within 60 days after completion of the work. Any amounts​
4.32withheld under clause (2) must be paid within 60 days after submission of all final paperwork.​
4.33 (f) Withholding retainage for warranty work is prohibited. This provision does not waive​
4.34any rights for warranty claims.​
4​Sec. 3.​
REVISOR SGS/EN 25-02075​02/07/25 ​ 5.1 (g) This subdivision does not apply to a public agency as defined in section 15.71,​
5.2subdivision 3.​
5.3 (h) This subdivision does not apply to contracts for professional services as defined in​
5.4sections 326.02 to 326.15.​
5.5 (i) Nothing in this section requires payment for a portion of a contract that is not complete​
5.6or for which an invoice has not been submitted. A contract, management system, or procedure​
5.7that restricts, delays, or prohibits a party from submitting an invoice is contrary to public​
5.8policy and is void and unenforceable.​
5​Sec. 3.​
REVISOR SGS/EN 25-02075​02/07/25 ​